User manual

Copyright

©2007 by Xuzhou Hirschmann Electronics Co., Ltd


This document contains propriety information which is protected by copyright law. All
rights reserved. No part of this document may be photocopied, reproduced or
translated without the previous written consent of Hirschmann.
User manual of Xuzhou Hirschmann HC4900 LMI Series
2nd edition, May, 2008

Notice

Xuzhou Hirschmann makes guarantee that the description and guidance of HC4900
LMI Series user manual is correct after examine and verify. The information in this
document is subject to change without notice. Hirschmann shall not be liable for
errors contained herein or for incidental or consequential damages in connection
with the furnishing, performance, or use of this manual.

Xuzhou Hirschmann Electronics Co., Ltd.


No.11 South Pantaoshan Road of Xuzhou Economic Development Zone, Jiangsu
Province, PRC
Tel: +86 516 87885799、87885700
Fax:+86 516 87793971
Post code: 221001
Web site:Http://www.hirschmann-js.com
Email:infoecs@hirschmann-js.com

-1-
User manual

Catalogue

1. GENERAL INFORMATION ..................................................................... - 4 -

2. WARNINGS ................................................................................................. - 4 -

3. SYSTEM DESCRIPTION .......................................................................... - 5 -

4. SYSTEM STRUCTURE ............................................................................. - 5 -

5. OPERATION DESCRIPTION .................................................................. - 6 -

6. FUNCTION AND OPERATING METHODS .......................................... - 8 -

6.1DISPLAY CONTENT .................................................................................... - 8 -


6.2 OPERATION METHOD .............................................................................. - 10 -
6.2.1 Switchover between Chinese and English ..................................... - 10 -
6.2.2 Switchover between metric unit and Imperial unit......................... - 11 -
6.2.3 OM setting ..................................................................................... - 12 -
6.2.4 Reeving setting ............................................................................... - 14 -
6.2.5 Error checking ................................................................................ - 15 -
6.2.6 Time and date setting ..................................................................... - 16 -
6.2.7 CAN communication status checking ............................................ - 18 -
6.2.8 OM checking .................................................................................. - 19 -
6.3 ANGLE UPPER AND LOWER LIMIT SETTING .............................................. - 20 -
6.3.1 Angle upper limit setting ................................................................ - 21 -
6.3.2 Angle lower limit setting ................................................................ - 21 -
6.3.3 Cancel angle limit .......................................................................... - 22 -
6.4 BUZZ STOPPING ...................................................................................... - 22 -

-2-
User manual

6.5 INDICATING LIGHT DESCRIPTION ............................................................ - 23 -


6.5.1 A2B Indicating light ....................................................................... - 23 -
6.5.2 Pre-warning light............................................................................ - 23 -
6.5.3 Overload alarm light ...................................................................... - 23 -

7. HC4900 SYSTEM FUNCTION ............................................................... - 24 -

8. DAILY MAINTENANCE AND ADJUSTMENT METHOD ................ - 25 -

8.1 MAINTENANCE ....................................................................................... - 25 -


8.2 LENGTH SENSOR ADJUSTMENT ............................................................... - 25 -
8.3 ANGLE SENSOR ADJUSTMENT ................................................................. - 26 -
8.4 BUZZING ALARM .................................................................................... - 27 -
8.5 THE CABLE OF REEL RETRACT NOT SMOOTHLY ....................................... - 27 -

9. ERROR INFORMATION AND MALFUNCTION SOLVED .............. - 28 -

10. HC4900 CABLE CONNECTION DIAGRAM ..................................... - 37 -

11. OM LIST .................................................................................................. - 38 -

-3-
User manual

1. General information
The Xuzhou Hirschmann load moment indicator (ab. LMI) HC4900 has been designed
to provide the crane operator with the effective information required to enable the
machine to be used within its design parameters.
Using various sensing devices, the load moment indicator monitors crane’s various
work functions and provide the operator with a continuous reading of the crane’s
capacity. The readings continuously change as the crane executes different work.
The LMI provides the operator with information regarding the length and angle of the
boom, tip height, working radius, rated load and the total calculated weight being
lifted by the crane.
If no permitted conditions are approached, the HC4900 Load Moment Indicator will
warn the operator by sounding an audible alarm, lighting a warning light and locking
out those functions that may aggravate the crane’s condition.

2. Warnings
The LMI is an operational aid which warns crane operator of approaching overload
conditions and also warns of over-hoist conditions which could cause damage to
equipment and personnel.
The device is not, and shall not be a substitute for good operator’s judgment,
experience and use of accepted safe crane operating procedures.
The responsibility for the safe operation of the crane shall remain with the crane
operator who shall ensure that all warnings and instructions supplied are fully
understood and observed.

Notice
If the program of LMI and the load chart is correct and the OM set correct,
the display content will help a lot for the operator. To prevent property damage or
serious bodily injury or death to personnel, ensure the LMI is properly
programmed before the LMI to be installed.

-4-
User manual

Proper operation is dependent upon proper daily inspection and observations of the
operating instructions set forth in this manual.

3. System description
The HC4900 LMI system can be installed on various kinds of cranes to measure the
load moment and judge whether it is overload to protect the crane from dangerous
operation.
Because of the load moment value is not easy to measure and even to inspect by eyes,
it can result in the operator’s wrong judgment. While HC4900 system can monitor the
real-time status of crane operation that enables the operation to keep in safety ranges.
The HC4900 system can monitor the crane information such as boom length, boom
angle, max hoist height, working radius, rated capacity and actual load, etc. The LMI
calculated the load moment value from the force component’s measuring data. When
the operation exceed the allowed safety range the LMI will send warning signal to the
LCD Graphic screen and send control signal to the central unit to warn the operator to
stop the illegal operation.
The following chapters will describe the characteristics, functions, operation methods
and notices about HC4900 LMI.

4. System structure
1. Central unit (Mentor)
2. CAN signal junction box
3. LCD Graphic Display
4. Pressure transducer
5. Length/Angle sensor
6. Anti-Two-Block switch and weight

-5-
User manual

HC4900 LMI structure

5. Operation description
After the proper adjustment, the LMI system can start work automatically. So the
crane operator should be very familiar with the LMI operation and operate the crane
after proper adjustment.

-6-
User manual

Power on

Self test of LMI


system
Yes Look up the error
Error? code and debar it
No
Is the showed OM the No Set correct OM
same as the actual
one?
Yes
Is the showed Reev No Set correct Reeving
the same as the actual
one?
Yes
Is the showed Length No Adjust the Main boom
the same as the actual Length potentiometer
one?
Yes
Is the showed Radius No Adjust the Main boom Angle
the same as the actual to make them to be the same
one?
Yes
Need set the upper and No Set the upper and
lower Limit Angle lower limit angle
No
Operate the crane again

-7-
User manual

6. Function and operating methods

6.1Display content

Picture 1 Main interface

-8-
User manual

1. A2B light 2. Pre-warning Light 3. Overload warning Light


A. Bar graph (load moment percentage)
B. OM display (display the operation mode)
C. Reeving display(display the steel wire’s number of hook)
D. Main Boom length display
E. The largest lifting height at the current position
F. Main boom angle display
G. Working radius display
H. Rated load capacity
I. Actual load
J. Level data display
K. Display the number of the balance weight
L. Wind sensor data display
M. Time display
N. Function key
O. OM setting button
P. Reeving setting button
Q. Error inquire button
R. Buzzing stop button
S. Outrigger display(1/2:half-extended,2/2:full-extended)
Note:The number keys on the LMI display are used for setting.

-9-
User manual

6.2 Operation method

6.2.1 Switchover between Chinese and English

The IC4600 displays used for HC4900 series can switchover language between
Chinese and English.
The default language is Chinese. The English display can be set following the below
operation:

Press the function key on the main interface as the picture 1(as N refer to)to

enter into the function interface as picture 2.

Pic 2. Interface of function setting

Press the button on picture 2 interface to switchover language between Chinese

and English. If the current Chinese interface needs to be changed to English interface,

- 10 -
User manual

please press the button to switch to the picture 3 interface. While if you want to

return back to Chinese interface, please repeat the operation of pressing the

button on picture 3 interface to accomplish it.

The switchover function has memory function. If operator switchover Chinese


interface to English interface, system will display following operation in English while
system will display following operation in Chinese after switch to Chinese language.
The Interface after switchover to English as follow:

Pic 3. English interface of function setting

6.2.2 Switchover between metric unit and Imperial unit

In order to satisfy the requirement of export, we set the switchover function of metric
unit and English unit on display.
The metric unit is default when leaving the factory. Please follow the operation if the

- 11 -
User manual

Imperial unit is needed:

Press the button on the interface to switch the metric unit to English unit.

While if you want to return back to metric unit, please repeat the operation of pressing

the button on picture 4 interface to accomplish it.

As the switchover between Chinese and English, this switchover function also has
memory function.

Pic 4. English unit setting interface

6.2.3 OM setting

The OM setting is used for adjusting the LMI parameter according to the actual
crane’s condition. When operate the crane please make sure the displayed operation
mode is the same as the actual operation mode.
Before operating the crane, please check the corresponding OM code according to
your crane type and actual mode and adjust the OM to be the same as the actual OM.

- 12 -
User manual

Warning

The correct setting is of utmost importance for the proper function of the system
and the crane. Therefore only operators who are thoroughly familiar with use
and operation of the system shall set this function.

Correct method for OM setting :

Press the button on the main interface as picture 1 to enter into the OM
setting interface as picture 5.

Pic 5 OM setting interface


Press the number key and function key on this interface to set the display OM same as

the actual operation. For example, press the button and then press number key 1

to make the new OM to be 1. After pressing the button to confirm the setting

- 13 -
User manual
and return back to main interface, the whole process of setting OM 1 is accomplished.

Press the button and then press number key 2 and key 1 to make the new OM to

be 21. After pressing the button to confirm the setting and return back to main
interface, the whole process of setting OM 21 is accomplished. If new OM is not

needed on this interface, please press button to return back.


See specific information about OM on 6.2.8 OM checking

6.2.4 Reeving setting

This function is for setting the number of the steel rope for LMI system. Before
operate the crane the operator is asked to adjust the displayed reeving to be same with
the actual one.
The relationship between the actual reeving and displayed one is as following:
Displayed reeving number: 1----------16
Number of the actual steel wire ropes: 1----------16

Press the number button on the main interface as picture 1 to enter into the
reeving setting interface as picture 5.

- 14 -
User manual

Pic 6. Reeving setting interface

The operation method of this interface is same as the OM setting.

6.2.5 Error checking

Press the button of error inquire on the main interface as picture 1 to enter
into the error inquire interface as picture 6. This interface can provide meanings of
the error codes and offer convenient for using and maintenance.

- 15 -
User manual

Pic 7. Error code checking interface

The button and are used for checking the former and next code while

the button is to return back to the main interface as picture 1.

6.2.6 Time and date setting

Press the number key 1 on the function setting interface as picture 2 to enter into the
time setting interface.

- 16 -
User manual

Pic 8. Time setting interface


When the operator enters into the interface the first time, there will be green point
lighting at the default place. The year, month, hour and second are all displaying as 00
(as the above picture shows). If the displayed time or date is incorrect, please press

the button and to change the place of the green point and then the item
where the green point is will be activated to set. The number keys are used for setting
date and time. For example, if the date and time is 18:30, May 1 st , 2008, at first please

press the number 0 and 8 at the year item where the green point is , press button

to switch to month item and then press number 0 and 5, press button to switch

to date item and then press number 0 and 1, press button to switch to hour item

- 17 -
User manual

and then press number 1 and 8, press button to switch to second item and then

press number 3 and 0, after all the above operation, please press button to
confirm the setting . The interface will be displayed as following.

Pic 9. Time setting interface


Note:The default second setting starts from 0.

6.2.7 CAN communication status checking

Operator can get direct knowledge about the working status of every part through the
CAN communication status checking.
Press the number key 2 as the item CAN communication status checking on the
function interface to enter into the CAN bus status checking interface.
The standard configuration of HC4900 system contains the following parts. When the
part is green, it means the part works normally, when the part is yellow, it means the

- 18 -
User manual

part hasn’t been activated. When the part is red, it means the part is broken or can’t
work normally.

Pic 10. CAN communication status checking interface

Press the button on this interface to return back to the main interface as

picture 1.

6.2.8 OM checking

OM represents different working status during crane operation, such as main boom
OM, jib boom OM and boom head pulley. The parameter about crane rated capacity,
working radius can only been displayed after setting the correct OM.
Press the number key 3 on the function interface as the picture 2 to enter into the OM
checking interface.

- 19 -
User manual

Press the button and to check different OM while press the button

to return back to the main interface.

Pic 11. OM checking interface

6.3 Angle upper and lower limit setting

The system has the function to limit the boom angle in order to remind the operator of

extreme caution under dangerous operation condition: buildings, bridges, high-voltage

wire etc.

- 20 -
User manual

Notice
This limit function is only for warning user without control function. For
each time restart the LMI system, operator needs to reset the limit value.

6.3.1 Angle upper limit setting

Luff up the boom to maximal safe position according to actual operation situation and

then press the button on the function interface as picture 2. The upper angle

limit value will be displayed at the left side of icon . The displayed angle value
will be recorded as the upper limit angle. When this limit value is exceeded, the

STOP
“ ” indication light will light up and send audible alarm sound to warn the
operator to take extreme operation.
Note:The upper limit angle shall not be smaller than the lower limit angle

6.3.2 Angle lower limit setting

Luff down the boom to minimal safe position according to actual operation situation

and then and then press the button on the function interface. The upper angle

limit value will be displayed at the left side of icon . The displayed angle value
will be recorded as the lower limit angle. When the angle is lower than this limit value

STOP
the “ ” indication light will light up and send out audible alarm sound to warn
the operator to take extreme operation.

- 21 -
User manual

Note:the lower limit angle shall not be larger than the upper limit angle.

For example, if the upper limit angle is 75°the lower limit angle60°, the interface after

setting is as following:

Pic 12. Angle upper and lower limit setting interface

6.3.3 Cancel angle limit

On function interface, press the number key 0 to cancel all the angle limit value.

6.4 Buzz stopping

HC4900 system buzzer will sent out warning under follow condition:
—— overload the largest rated moment
—— hook is near the limit height
—— exceed operation range
—— LMI system error
—— wrong operation

- 22 -
User manual

Press the button on the main interface to close the buzz warning 20S

6.5 Indicating light description

6.5.1 A2B Indicating light

The red warning light will light up as soon as the anti-two-block Switch contact open,
indicating that a two-blocking condition is approaching. At the same time the audible
alarm will sound. The following crane movements will be stopped subsequently: hoist
up, telescope out, boom down. In order to avoid any injury to people or crane, please
check the A2B system by following methods before operating the crane.
Checking method:
a. lifting the weight of A2B switch manually. The light will light up and the buzz
will sound.
b. Slowly raise the hook or lower the boom or extend the boom to create a
potential two-block condition, when the hook lifts the weight, the audible alarm
sound, the anti two-block alarm light will light and the crane movement such as
hoist up, boom down, telescope out will be stopped.
c. If the light and audible alarm does not function as described and the crane
movements are not stopped, the system is not working properly. The malfunction
shall be corrected before operating the crane.

6.5.2 Pre-warning light

The yellow load moment pre-warning Light will light up when the load on the crane
reaches to the pre-warning area 90%~100% of the rated capacity, thus indicating that
an overload condition is approaching. This means the operator shall continue his crane
operation with extreme caution.

6.5.3 Overload alarm light

The red warning light will light up and the buzz sends out audible sound when the load
- 23 -
User manual
on the crane reaches to 100% of the rated moment. The light will light up when the
system has error situation and the operation of lifting hook, extended boom and
downward luffing will be stopped. This status will be canceled along with dropping
the weight or upward luffing.

7. HC4900 system function


1. warning:
——overload
——over-tip

——malfunction

Under any above conditions, HC4900 system will light up and send out alarm for

warning.

2. Prohibited
Cooperating with crane electrics system, LMI system will send alarm warning and any
of the following crane’s movements will be prohibited:
——Boom luffing down
——Telescope out
——Hoist up
At this moment only the movements toward safe direction is allowed:
——Boom luffing up

——Boom retract

——Hoist down

The LMI system has cut-off function however the operation toward dangerous
direction is not allowed when overload, anti-two-block limit or system error condition

- 24 -
User manual

happens (Alarm at the same time). Because this cut-off device is an interacted system,
in case of any error it may cause big danger.

Notice
When the cut-off device is activated this cut-off signal will always keep be out.
Functions such as “dangerous direction operation is not allowed”, “only safe
direction operation is allowed” is realized by cooperating with the crane’s
electronics system which including “ safe direction inspect switch”, “safe
overflow solenoid valve” etc. The LMI system cannot judge the operation is
safe or dangerous itself.
8. Daily maintenance and adjustment method

Please maintain and adjust according to the following content. If you have any
problem please contact us.

8.1 Maintenance

1. Check all the cable connection of the system. Damaged cables shall to be replaced
immediately.
2. Check the insulating layer of the length sensor, A2B switch cable and the cable
guides. If the insulating layer or the wire inside damaged, you should replace them
immediately.
3. Inspection of the anti-two block switch as to easy running.。
4. Check the cable reel as to sufficient tight or not.
5. Check the pressure transducers at the luffing cylinder and the connection hoses as to
oil leakage.

8.2 Length sensor adjustment

When the displayed boom length is not correct (exceeds the permitted error range),
- 25 -
User manual

please adjust it:


Retract the boom to the basic boom condition and check the pre-stressing force of the
cable reel (cable must be tight) and then open the cover of the length/angle sensor and
turn the axle of the length potentiometer slowly ( as the arrow marks, increase follow
clockwise and decrease counter-clockwise) till the displayed value to be the same with
the actual length.

Length sensor adjustment(as the arrow show)

8.3 Angle sensor adjustment

The angle and length sensor are installed in the same housing.
First withdraw the lifting boom to basic length boom and the displaying boom length
shall be the same as the actual boom length while checking. Use the angle indicator to
measure when the actual angle is between 0°and 70°whether same as the displayed
value or not. Also could use a tape to measure the working radius if the displayed
value or radius is not the same with the actual value, you should adjust the angle
sensor. Please loosen the three bolts(as the arrow pointing)and then slowly turn the
angle sensor till the displayed value accord with the actual one. After that, please tight
the three bolts again.

- 26 -
User manual

Angle sensor adjustment(as the arrow show)

8.4 Buzzing alarm

After start the system it displays without any malfunction or error code but the buzzer

keep sound alarm, in this case please check if any disconnection or water inside the

connection between length cable and A2B switch.

8.5 The cable of reel retract not smoothly

Sometimes when retract the boom it happens that the length cable cannot return to the

original position naturally or retract not smoothly. It is because of the coil-spring’s

pre-tight is too low or the length cable in the cable reel fall off.

Please pre-tighten the length cable several circles to solve the problem:

1. Retract the boom and put it on the rack


2. Draw back the tip of the cable from the tip of the boom and retract to the cable
reel
3. Pre-tight the cable reel 3 to 5 circles, to make the cable can be pulled out and
retracted smoothly (please pay attention that the cable shall be rotate together with

- 27 -
User manual

cable reel when rotate the cable reel).

4. Pull out the cable and fix it on the tip of the boom again

5. After pre-tight the cable reel the display of the boom length will be affected, so

at this moment please adjust the length sensor till the displayed value the same with

the actual length.

Notice
The operator shall be careful the above calibration. The crane
can only be operated under correct adjustment and confirmation
after adjustment.

9. Error information and malfunction solved method


In case of a system malfunction or fault operation, an error code to identify the error
source will be displayed on the LCD. The code numbers listed in the malfunction table
identify various malfunctions that might occur in the LMI system which may cause by
operating faults of the crane operator or by exceeding preset areas.
Following are the explanation of the OM, which will provide convenient for usage and
maintenance.

Important Notice
If there is any Error Code displayed on the console which is not listed in the
Malfunctions Table you shall call us by:
Tel:0516-87885700 Fax:0516-87793971

- 28 -
User manual

Error Error Cause Elimination


Code
E01 Fallen below  Fallen below the minimum  Luff down the
radius range radius or gone past the boom to a radius or
or angle range maximum angle specified in angle specified in
exceeded the respective load chart due the load chart.
to luffing up the boom too
far
E02 Radius range  Gone past the maximum  Luff up the boom to
exceeded or radius or fallen below the a radius or angle
fallen below minimum angle specified in specified in the load
angle range the respective load chart due chart.
to luffing down the boom
too far
E04 Operating  A non existing operating  Set the correct
mode not mode has been selected operating mode for
acknowledged  The boom is in a the operating state
or non non-permitted slewing zone in question
permitted  Slew the boom to a
slewing zone permitted area.

E05 Prohibited  Boom has been extended  Extend/retract


length range either too far or not far boom to the
enough, e.g. if it is correct length
prohibited to go beyond a  Retract boom.
certain maximum boom Check the prestress
length or with load curves of the cable reel
for jibs where the main (cable must be
boom has to be extended taut). Open the
to a certain length length sensor and
 Length sensor adjustment carefully turn the
has changed, e.g. the cable length sensor pot
slid off the length sensor counterclockwise
reel. until the detent by
means of a screw
driver

- 29 -
User manual

Error Error Cause Elimination


Code
E06 Radius range  Maximum radius as  Luff the jib to a
specified in the load radius or angle
exceeded or fallen
chart exceeded or specified in the
below angle range fallen below load chart.
with luffing jib minimum angle due
operation to luffing down the
luffing jib too far
E11 Fallen below  Length potentiometer  Replace length
lower limit value is defective potentiometer
 PDB variable for  Setup of correct
for measuring analog value not PDB variable for
channel "length supported analog value in
main boom"  Electronic component DGA6.i.3
in the measuring  Replace sensor
channel is defective unit

E12 Fallen below  Pressure transducer is  Replace pressure


the lower limit defective. transducer
 PDB variable for  Setup of correct
value in the analog value not PDB variable for
measuring channel supported analog value in
"pressure piston  Electronic component DGA6.i.3
in the measuring  Replace sensor
side"
channel is defective. unit

E13 Fallen below  Refer to E12  Refer to E12


lower limit value
in the measuring
channel "pressure
rod side"

- 30 -
User manual

Error Error Cause Elimination


Code
E15 Fallen below lower  Angle  Replace angle
limit value in measuring potentiometer sensor
defective  Setup of correct
channel "angle main  PDB variable for PDB variable for
boom" analog value not analog value in
supported DGA6.i.3
 Electronic  Replace sensor
component in unit
the measuring
channel
defective.
E21 Upper limit value  Refer to E12  Refer to E12
in measuring channel
"main boom length" has
been exceeded.
E22 Upper limit value  Refer to E12  Refer to E12
in measuring channel
"pressure piston side"
has been exceeded
E23 Upper limit value  Refer to E12  Refer to E12
in measuring channel
"pressure rod side" has
been exceeded.
E24 Upper limit value  Refer to E12  Refer to E12
in measuring channel
"force" has been
exceeded.

- 31 -
User manual

Error Error Cause Elimination


Code
E25 Upper limit value  Refer to E12  Refer to E12
in measuring
channel "main
boom angle" has
been exceeded.
E32 Error in the  +UB System not  +UB System and
power supply present at the system +UB Power must be
start wired separately:
 +UB System not +UB System
present at the system connected direct with
finish the crane battery.
 Contact problems at +UB Power for
+UB switch off/on switch on/off
 +UB switch off/on
again
E37 Error in the  System program file  Upload valid system
logical program is defective software
 Flash-EPROM  Replace central unit
flow defective
E38 System program  The system program  Upload valid system
and crane data in the LMI does not program file or the
match to the valid crane data file
file do not match. programming in the
crane data file
E39 System program  The system program  Upload valid system
and load chart in the LMI and the program file or the
programming in the valid load chart file
file do not match load chart file do not
match.
E43 Error in the  Write/read memory  Replace central unit
write/read (RAM) or central
unit defective.
memory, (RAM)

- 32 -
User manual

Error Error Cause Elimination


Code
E47 Error in the  The CRC sign of the  Restart the LMI
monitored write/ monitored write/read  Replace buffer
memory is wrong battery on the
read memory.  The buffer battery is central unit.
The CRC decharged (< 2V at  Replace central unit
verification of the 1kOhm).
 Central unit
monitored
defective.
write/read memory
provides an
incoherent result
E51 Error in the crane  No valid data in the  Upload valid crane
data file crane data file. data file
 Flash-EPROM  Replace central unit
defective
E52 Error in load chart  No valid data in the  Upload valid load
file. load chart file chart file
 Flash-EPROM  Replace central unit
defective
E53 Wrong setup of  Analog input not  Setup correct Flag
min. analog inputs supported in DGA 6.i.2
length1, angle1,
pressure1
E56 Error in crane data  No valid data in the  Restore or upload
file. crane data file valid crane data file
during calibration.  Replace central unit
 Flash-EPROM
defective
E57 Error in serial  Calibration data file  Upload calibration
crane data file. does not contain data file by
valid data. changing data (OM,
 Flash-EPROM limits) and save
defective  Replace central unit

- 33 -
User manual

Error Error Cause Elimination


Code
E61 Error in the  CAN Bus cable  Check the
CAN bus data between the central connection
unit and the sensor between the
transfer for all CAN unit defective or not central unit and
units connected. the sensor units
 Can bus port in the  Replace the
central unit central unit
defective  Replace Can Bus
 Short circuit in a cable
CAN Bus cable
E62 Error in the can  Cable between the  Check the cable to
bus data transfer of central unit and the the sensor unit
sensor unit  Replace the
the pressure defective. central unit
transducer sensor  Can bus port in the  Replace the sensor
unit central unit unit
defective
 Can bus port in the
sensor unit is
defective
E63 Error in the can bus  The analog values of  Replace the sensor
pressure transducer the sensor unit are unit
invalid
sensor unit
E64 Error in the can  See E62  See E62
bus data transfer of
the length/angle
sensor unit
E84 Wrong rigging  The selected rigging  Select another
condition. condition is not rigging condition
contained in the
crane data file.  Check the
programming in
the crane data file.

- 34 -
User manual

Error Error Cause Elimination


Code
E85 Error in  The computed radius  Check the
the radius is too small (negative programming in the
deflection) crane data file.
determination
E89 Operating  The operating mode  Select operating
mode on the console has mode without load on
been switched over the boom
switchover with with the boom loaded.
load.
E98 LMI watchdog  LMI processing time  Reset system
activated limit exceeded  Connect PC terminal
and watch error
messages
E80 Short circuit in  Short circuit in the  Replace A2B switch
the A2B switch A2B switch  Replace cable to the
 Short circuit in the A2B switch
circuit cable to the A2B
(not with radio switch
A2B)
EAC A2B  Disconnected cable in  Connect or replace
switch circuit the A2B switch cable in the A2B
 Disconnected cable to switch
disconnected the A2B switch  Connect or replace
(not with radio cable to the A2B
A2B) switch
EAD No valid  Sensor wrong  Replace A2B switch
A2B switch function  Replace cable to the
 CAN bus delay A2B switch
status  Radio telegram delay  Replace battery of
module (radio A2B) radio module (radio
 Radio telegram ID is A2B)
invalid  Setup ID in DGA12.9

- 35 -
User manual

Error Error Cause Elimination


Code
EDB Datalogger  Setup of the  transfer data and
setup error datalogger is cleared setup datalogger
(ser. crane data file or again
battery buffered
RAM)
EDC Datalogger  datalogger processing  Reset system
time limit exceeded  Connect PC terminal
watchdog and watch error
activated messages

EDD Battery  Battery check  change battery, after


detected a low voltage this setup of RTC
empty of the battery

- 36 -
User manual

10. HC4900 cable connection diagram

- 37 -
User manual

11. OM list
OM
Crane Main Lateral rear district Front district
OM explanation Full Half Full Half
Type OM
Extended Extended Extended Extended
outrigger outrigger outrigger outrigger
Main boom 0001 0001 1001 0101 1101

QY16K Main +jib 0° 0021 0021 1021 0121 1121


QY25K
Main +jib 15° 0022 0022 1022 0122 1122
QY25K5
QY30K5 Main +jib 30° 0023 0023 1023 0123 1123

Head sheave 0024 0024 1024 0124 1124

Main boom 0001 0001 1001 0101 1101

Main+1st jib 0° 0011 0011 1011 0111 1111


QY30K
Main+1st jib 15° 0012 0012 1012 0112 1112
QY35K
QY35K5 Main+1st jib 30° 0013 0013 1013 0113 1113
QY40K
QY50K Main+2 jibs 0° 0021 0021 1021 0121 1121
QY60K
Main+2 jibs 15° 0022 0022 1022 0122 1122
Qy70K
Main+2 jibs 30° 0023 0023 1023 0123 1123

Head sheave 0031 0031 1031 0131 1131

DIN0――white wire,the rear and front detection switch or the fifth outrigger, the
positive is the lateral rear and the second place of the corresponding OM equals to 0.
DIN1――brown wire,extended and half extended outrigger detection switch, the
positive is extended and the first place of the corresponding OM equals to 0.

- 38 -

You might also like