Professional Documents
Culture Documents
Latest Questionnaire - Fahim
Latest Questionnaire - Fahim
I am Muhamad Fahim Hizami Bin Azmi a final year student of EC220- Bachelor of Civil
Engineering (Hons.) of UiTM Shah Alam, Selangor. I am Conducting a survey on the
impacts and prospects of construction project during COVID-19 in Malaysia.
* Required
1. Email *
2. Role in organzation
Project Manager
Engineer
Site Supervisor
Other:
3. Academic qualification
Certificate
Diploma
Degree
Master
PhD
https://docs.google.com/forms/d/1GlohlQ2TBsGnMkdQ5Fyvlt9nXLVH70I7_NKNBnUkzac/edit 1/11
5/5/2021 COVID 19 PANDEMIC: THE IMPACTS AND PROSPECTS OF MALAYSIAN CONSTRUCTION PROJECT
1 year to 5 years
5 years to 10 years
Residential
Building
Commercial / Industrial
Highway
6. The construction project has been delay during COVID-19 because it could not
be running during lockdown
1 2 3 4 5
https://docs.google.com/forms/d/1GlohlQ2TBsGnMkdQ5Fyvlt9nXLVH70I7_NKNBnUkzac/edit 2/11
5/5/2021 COVID 19 PANDEMIC: THE IMPACTS AND PROSPECTS OF MALAYSIAN CONSTRUCTION PROJECT
7. The construction project activities have been delay during COVID-19 because
the activities have been postponed
1 2 3 4 5
1 2 3 4 5
1 2 3 4 5
10. Construction project delay because workers could not attend to the workplace
during lockdown
1 2 3 4 5
https://docs.google.com/forms/d/1GlohlQ2TBsGnMkdQ5Fyvlt9nXLVH70I7_NKNBnUkzac/edit 3/11
5/5/2021 COVID 19 PANDEMIC: THE IMPACTS AND PROSPECTS OF MALAYSIAN CONSTRUCTION PROJECT
11. The worker has been reduced to control the spreading of COVID-19 on the
construction project that lead to delay
1 2 3 4 5
12. COVID-19 pandemic causes the shortage of raw material that leads to delay of
construction project
1 2 3 4 5
13. The production of raw materials has been reduced during the COVID-19
pandemic that leads to project delay
1 2 3 4 5
14. Construction materials could not be delivered on time during MCO that leads
project to delay
1 2 3 4 5
https://docs.google.com/forms/d/1GlohlQ2TBsGnMkdQ5Fyvlt9nXLVH70I7_NKNBnUkzac/edit 4/11
5/5/2021 COVID 19 PANDEMIC: THE IMPACTS AND PROSPECTS OF MALAYSIAN CONSTRUCTION PROJECT
1 2 3 4 5
16. Some modification such as design and method of construction during COVID-
19 pandemic causes cost overrun
1 2 3 4 5
17. The increasing cost of construction materials and transportation are the factor
of overbudget to a construction project during the COVID-19 pandemic
1 2 3 4 5
18. Less profit for construction project because of low income in COVID-19
pandemic
1 2 3 4 5
https://docs.google.com/forms/d/1GlohlQ2TBsGnMkdQ5Fyvlt9nXLVH70I7_NKNBnUkzac/edit 5/11
5/5/2021 COVID 19 PANDEMIC: THE IMPACTS AND PROSPECTS OF MALAYSIAN CONSTRUCTION PROJECT
19. The contractor could not claim payment from the client for the construction
project because of work stoppage during COVID-19
1 2 3 4 5
20. Additional expenses on the COVID-19 screening test and Personal Protective
Equipment (PPE) for workers (following the SOP by the Malaysian government)
has reduced the construction project's profit and income
1 2 3 4 5
1 2 3 4 5
https://docs.google.com/forms/d/1GlohlQ2TBsGnMkdQ5Fyvlt9nXLVH70I7_NKNBnUkzac/edit 6/11
5/5/2021 COVID 19 PANDEMIC: THE IMPACTS AND PROSPECTS OF MALAYSIAN CONSTRUCTION PROJECT
1 2 3 4 5
1 2 3 4 5
24. COVID-19 would increase the use of Artificial Intelligence in future construction
project
1 2 3 4 5
1 2 3 4 5
https://docs.google.com/forms/d/1GlohlQ2TBsGnMkdQ5Fyvlt9nXLVH70I7_NKNBnUkzac/edit 7/11
5/5/2021 COVID 19 PANDEMIC: THE IMPACTS AND PROSPECTS OF MALAYSIAN CONSTRUCTION PROJECT
1 2 3 4 5
27. The local worker would take over the foreign worker in the construction project
post-COVID-19
1 2 3 4 5
28. An incentive program from the government could attract local workers to
involve in construction project post-COVID-19
1 2 3 4 5
29. The pandemic of COVID-19 for construction project could lead to Force Majeure
claims
1 2 3 4 5
https://docs.google.com/forms/d/1GlohlQ2TBsGnMkdQ5Fyvlt9nXLVH70I7_NKNBnUkzac/edit 8/11
5/5/2021 COVID 19 PANDEMIC: THE IMPACTS AND PROSPECTS OF MALAYSIAN CONSTRUCTION PROJECT
30. Many contractors would claims for an extension of time because of project
delay caused by the COVID-19 pandemic
1 2 3 4 5
1 2 3 4 5
32. All machines used for the construction project must be sanitized as a
prevention measure
1 2 3 4 5
33. The contractor provides all Personal Protective Equipment (PPE) to workers
involved in the construction project
1 2 3 4 5
https://docs.google.com/forms/d/1GlohlQ2TBsGnMkdQ5Fyvlt9nXLVH70I7_NKNBnUkzac/edit 9/11
5/5/2021 COVID 19 PANDEMIC: THE IMPACTS AND PROSPECTS OF MALAYSIAN CONSTRUCTION PROJECT
34. Proper planning such as re-estimate cost, increase safety measure, and improve
transportation network could overcome the expected situation
1 2 3 4 5
35. Rearrange the schedule of work on a construction project that has cause delay
could avoid an unexpected situation such as the COVID-19 pandemic
1 2 3 4 5
36. Planning on the budget for a construction project that causes cost overrun
could avoid an unexpected situation such as the COVID-19 pandemic
1 2 3 4 5
1 2 3 4 5
https://docs.google.com/forms/d/1GlohlQ2TBsGnMkdQ5Fyvlt9nXLVH70I7_NKNBnUkzac/edit 10/11
5/5/2021 COVID 19 PANDEMIC: THE IMPACTS AND PROSPECTS OF MALAYSIAN CONSTRUCTION PROJECT
38. Financial support such as grants, funding, and loans could help contractors on
project operations to avoid an unexpected situation such as the COVID-19
pandemic
1 2 3 4 5
Forms
https://docs.google.com/forms/d/1GlohlQ2TBsGnMkdQ5Fyvlt9nXLVH70I7_NKNBnUkzac/edit 11/11