Title/Description:
COORDINATION MEETING WITH THE PROJECT ENGINEERS, PROJECT INSPECTOR AND CONTRACTORS
PERSON RESPONSIBLE/
AGENDA Session Highlights and Discussion
ACTION TAKEN
Project engineers and the contrators must follow on what was stipulated
in the contract, contractors must follow/ implement. ADE Mitmug
Saidale M. Mitmug, MPA,
observed a lot of lapses of the contract. He also added that if the
ASEAN Eng.
office's state has not an outstanding performance, it means that the
Assistant District Engineer
implementation of the contractor does not follow the contract/ site
instruction.
Agenda 1.Discussion
of negative Announces to have the mechanics during the meeting to discuss the Mocamadali Pundogar
accomplishments. matter properly. Admin. Chief
The contractor has a completed project with the institution but opened
some problems regarding the current implementation of a project inside
the jurisdiction of the Lanao 1st District. He stated that in a project in
Contractor
Bacolod-Liangan Road Widening, he almost got into a serious accident
due to the lacking of early warning devices/ signages that the road is
still under construction.
Supporting to what the contractor 's claim about the incident and
Maria Liza E. Pomicpic
instructed the contractors to follow the standards to avoid hazards on-
Chief of Construction
site. And reminding the contractor to incorporate the contract with the
Section
ongoing implementation on-site.
One of the contractor said that the institution and the constractor
should have a harmonious relationship to avoid conflict.
The project plan has been followed but due to the lacking budget, plan
was changed. The contractor was confused whether what to follow,
General(master plan) or the generated plan.
Agenda 1. Discussion
Cited an example with athe same situation as what the contractor said
of negative
during the meeting. A project for DEPED, C.Y 2017, implented 2018.
accomplishments.
The standard plan was followed as per joint coordination in Binoni. But,
Maria Liza E. Pomicpic
the school principal requested to transfer the building into the lower
Chief of Construction
location compared to the plan as the school principal had another plans
Section
for the original location of the project. The project was completed
physically, but was delayed to accept by the end-user, the DEPED
supervisor.
Instructed the Project Engineers to never change the original plan just
because of the end-user's request. But, if the end-user insisted the Hadji Khalil Sultan, MPA,
request, project engineer and the end-user should have a written ASEAN Eng.
agreement about the request. With the presence of the written District Engineer
agreement, conflicts in receiving the completed projects can be avoided.
1 of 5
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
Region X
OFFICE OF THE DISTRICT ENGINEER
Lanao del Norte 1st District Engineering Office
0054 Seminary Drive, Del Carmen, Iligan City, Lanao del Norte
Title/Description:
Adding the DE's advice, that if the project engineers cannot decide the
Mocamadali Pundogar
policy-detemining problems on-site, one must consult with the higher
Admin. Chief
ups.
Reminded everyone that the institution must meet the target for the
Maria Liza E. Pomicpic
prior and current project. For the month of September 2022, the target
Chief of Construction
is 94%, 85 million for variation order. 45% needs to have 100 million to
Section
meet the 45%
Agenda 1.Discussion
of negative Warned the Project engineers noting that when the office receives 5%
accomplishments. of negative accomplishments, Project engineers should send a letter to
the contractor / inform the ontractor about the status of the project. If
the contractor will not reply of recognize/ follow the site instruction,
send a letter of termination. He also added to always give site Hadji Khalil Sultan, MPA,
instruction. ASEAN Eng.
District Engineer
Asked the RROW head Unit, Engr. Rachid Mudag, to what intervention
the RROW Unit did?
One of the contractor also opened up about one of the reasons why the
project has been delayed lately. No. 1 : delayed delivery of materials
Contractor
on-site due to the national price escalation. Sudden rise of fuel,
materials and increase of labor demand.
Price escalation is a national problem. The contractors organization can Hadji Khalil Sultan, MPA,
request a letter stating the price escalation problem and asked for a ASEAN Eng.
remedial solution for the problem. District Engineer
RROW Unit Head, Rachid Mudag said that not all the project for C.Y
2022 has RROW component. If the constituent affected by the RROW
component that doesn’t have any documents supporting the claim of Engr. Rachid Mudag
the lot location, the RROW Unit will not grant the constituents RROW Unit Head
compensation request, thus the RROW Unit will seek advice or
assistance form the higher ups if the problem still exist.
Project Engineer James Capangpangan ask for more suspension order Engr. James
to aid the delay of the implementation. Capangpangan
Project Engineers should always secure and send site instruction to the Mocamadali Pundogar,
contractor and should always follow the bluebook. Admin. Chief
Agenda 2: Problems Project Engineer Batabor reported that all CY 2022 project that is under
on-site. his supervision were still on-going, except for 1 project. The delay was
due to an excuse by the contractor that the equipment were unavailable Engr. Norodin Batabor
or defective. He also added that he already sent a site instruction but
the contractor involved did not reply.
Documents that has lacked of attachements will not be signed. He also Hadji Khalil D. Sultan,
reminded one of the project engineers to check the project/ site if it was MPA, ASEAN Eng.
cleaned before leaving. District Engineer
Project engineers should set a meeting every week that concerns the
discussion about the current RROW problems of the project. He also
added to always give site instruction all the time, and check field Saidale M. Mitmug, MPA,
personnel. If the contractor does not abide or follow the site instruction, ASEAN Eng.
execute calibrated action or send a notice of termination. Another Assistant District Engineer
reminder from ADE Mitmug for the contracctors and Project Engineers
to arrange lacking documents attached to contracts.
Comply the lacking pertinent documents for the Notice of Award to Saidale M. Mitmug, MPA,
avoid delay. Requiring all contractor's workforce to have NC II ASEAN Eng.
certification. Assistant District Engineer
Contractors also opened about the Bureu of Internal Revenue of the
percentage that they will get from the total budget for the project.
Contractor
Presenting the percentage of 1.3% aggregates and 1% of the total
contract amount.
Send a letter to his office discussing the Revenues, addressed from the Mocamodali Pundogar
contractor to administrative office. Admin. Chief
2 of 5
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
Region X
OFFICE OF THE DISTRICT ENGINEER
Lanao del Norte 1st District Engineering Office
0054 Seminary Drive, Del Carmen, Iligan City, Lanao del Norte
Title/Description:
Meeting Adjourned
3 of 5
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
Region X
OFFICE OF THE DISTRICT ENGINEER
Lanao del Norte 2nd District Engineering Office
0054 Seminary Drive, Del Carmen, Iligan City, Lanao del Norte
Title/Description:
TECHNICAL MEETING
ATTENDANCE SHEET
NAME OFFICE CONTACT NUMBER SIGNATURE
AIVEEN C. SINAHON CONSTRUCTION SECTION 9979501304
Title/Description: