Republic of the Philippines

DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS


Region X
OFFICE OF THE DISTRICT ENGINEER
Lanao del Norte 1st District Engineering Office
0054 Seminary Drive, Del Carmen, Iligan City, Lanao del Norte

Title/Description:

COORDINATION MEETING WITH THE PROJECT ENGINEERS, PROJECT INSPECTOR AND CONTRACTORS

Date: Started: Adjourned: Venue:


14/09/2022 10:00 PM 12:00 NN DPWH- LNED I Conference Room

Meeting attended by:

Refer attached attendance sheet

Agenda: Refer attached notice of meeting.

1.Discussion of negative accomplishments.


2. Problems on-site
3. Other Matters

PERSON RESPONSIBLE/
AGENDA Session Highlights and Discussion
ACTION TAKEN

Mocamadali Pundogar, Admin. Chief Mocamadali Pundogar


Admin. Chief called the attention of DE Sultan to offically opened the Admin. Chief
meeting.
Hadji Khalil D. Sultan
disseminated a notice for a coordination meeting due to a lot of
MPA, ASEAN Eng.
negative accomplihsments of the prior and current projects.
District Engineer

Project engineers and the contrators must follow on what was stipulated
in the contract, contractors must follow/ implement. ADE Mitmug
Saidale M. Mitmug, MPA,
observed a lot of lapses of the contract. He also added that if the
ASEAN Eng.
office's state has not an outstanding performance, it means that the
Assistant District Engineer
implementation of the contractor does not follow the contract/ site
instruction.

Agenda 1.Discussion
of negative Announces to have the mechanics during the meeting to discuss the Mocamadali Pundogar
accomplishments. matter properly. Admin. Chief

The contractor has a completed project with the institution but opened
some problems regarding the current implementation of a project inside
the jurisdiction of the Lanao 1st District. He stated that in a project in
Contractor
Bacolod-Liangan Road Widening, he almost got into a serious accident
due to the lacking of early warning devices/ signages that the road is
still under construction.

Supporting to what the contractor 's claim about the incident and
Maria Liza E. Pomicpic
instructed the contractors to follow the standards to avoid hazards on-
Chief of Construction
site. And reminding the contractor to incorporate the contract with the
Section
ongoing implementation on-site.

Informed everyone about the on-going road widening projects along


Linamon to Zamboanga road which is under the supervision of the
Regional Office that the Lanao 1st District have no control with.
Agenda 1.Discussion
of negative
accomplishments. Mocamadali Pundogar
Admin. Chief
Encouraged the stakeholders/ contractors to give feedbacks. And,
reminded everyone that discussion should be inline with the meeting's
agenda, that other matters should be discussed at the end of the
meeting. Admin Chief scheduled every Friday as feedback day for the
projects.

One of the contractor said that the institution and the constractor
should have a harmonious relationship to avoid conflict.

Some of the problems on-site: location of the project has been


validated, project has a confirmed budget. CONTRACTOR

The project plan has been followed but due to the lacking budget, plan
was changed. The contractor was confused whether what to follow,
General(master plan) or the generated plan.

Agenda 1. Discussion
Cited an example with athe same situation as what the contractor said
of negative
during the meeting. A project for DEPED, C.Y 2017, implented 2018.
accomplishments.
The standard plan was followed as per joint coordination in Binoni. But,
Maria Liza E. Pomicpic
the school principal requested to transfer the building into the lower
Chief of Construction
location compared to the plan as the school principal had another plans
Section
for the original location of the project. The project was completed
physically, but was delayed to accept by the end-user, the DEPED
supervisor.

Instructed the Project Engineers to never change the original plan just
because of the end-user's request. But, if the end-user insisted the Hadji Khalil Sultan, MPA,
request, project engineer and the end-user should have a written ASEAN Eng.
agreement about the request. With the presence of the written District Engineer
agreement, conflicts in receiving the completed projects can be avoided.

1 of 5
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
Region X
OFFICE OF THE DISTRICT ENGINEER
Lanao del Norte 1st District Engineering Office
0054 Seminary Drive, Del Carmen, Iligan City, Lanao del Norte

Title/Description:

Adding the DE's advice, that if the project engineers cannot decide the
Mocamadali Pundogar
policy-detemining problems on-site, one must consult with the higher
Admin. Chief
ups.

Reminded everyone that the institution must meet the target for the
Maria Liza E. Pomicpic
prior and current project. For the month of September 2022, the target
Chief of Construction
is 94%, 85 million for variation order. 45% needs to have 100 million to
Section
meet the 45%

Agenda 1.Discussion
of negative Warned the Project engineers noting that when the office receives 5%
accomplishments. of negative accomplishments, Project engineers should send a letter to
the contractor / inform the ontractor about the status of the project. If
the contractor will not reply of recognize/ follow the site instruction,
send a letter of termination. He also added to always give site Hadji Khalil Sultan, MPA,
instruction. ASEAN Eng.
District Engineer

Asked the RROW head Unit, Engr. Rachid Mudag, to what intervention
the RROW Unit did?

One of the contractor also opened up about one of the reasons why the
project has been delayed lately. No. 1 : delayed delivery of materials
Contractor
on-site due to the national price escalation. Sudden rise of fuel,
materials and increase of labor demand.

Price escalation is a national problem. The contractors organization can Hadji Khalil Sultan, MPA,
request a letter stating the price escalation problem and asked for a ASEAN Eng.
remedial solution for the problem. District Engineer

RROW Unit Head, Rachid Mudag said that not all the project for C.Y
2022 has RROW component. If the constituent affected by the RROW
component that doesn’t have any documents supporting the claim of Engr. Rachid Mudag
the lot location, the RROW Unit will not grant the constituents RROW Unit Head
compensation request, thus the RROW Unit will seek advice or
assistance form the higher ups if the problem still exist.

Project Engineer James Capangpangan ask for more suspension order Engr. James
to aid the delay of the implementation. Capangpangan

Hadji Khalil Sultan, MPA,


If the suspension order is still on process, continue the on-site
ASEAN Eng.
construction to avoid negative slippage of the project.
District Engineer

Project Engineers should always secure and send site instruction to the Mocamadali Pundogar,
contractor and should always follow the bluebook. Admin. Chief
Agenda 2: Problems Project Engineer Batabor reported that all CY 2022 project that is under
on-site. his supervision were still on-going, except for 1 project. The delay was
due to an excuse by the contractor that the equipment were unavailable Engr. Norodin Batabor
or defective. He also added that he already sent a site instruction but
the contractor involved did not reply.

Hadji Khalil Sultan, MPA,


The equipments should be the technical working group's job. Cutting of
ASEAN Eng.
the trees should be the project engineer's job.
District Engineer

The construction section chief announced the following prior projects


that has an on-going problem. 21KF0046, 21KF0056, 21KF0057,
21KF0061, 21KF0066, 21KF0071, 21KF0072, 21KF0079, 21KF0081, Maria Liza E. Pomicpic
21KF0090, 21KF0092, 21KF0094, 21KF0097, 21KF0099, 21KF0100, Chief of Construction
21KF0101, 21KF0104, 21KF0105, 21KF0106, 21KF0107, 21KF0108, Section
21KF0110, 21KF0112, 21KF0113, 21KF0115, 21KF0120, 21KF0135,
21KF0136. She instructed the contractors to update these prior projects.

Documents that has lacked of attachements will not be signed. He also Hadji Khalil D. Sultan,
reminded one of the project engineers to check the project/ site if it was MPA, ASEAN Eng.
cleaned before leaving. District Engineer

Project engineers should set a meeting every week that concerns the
discussion about the current RROW problems of the project. He also
added to always give site instruction all the time, and check field Saidale M. Mitmug, MPA,
personnel. If the contractor does not abide or follow the site instruction, ASEAN Eng.
execute calibrated action or send a notice of termination. Another Assistant District Engineer
reminder from ADE Mitmug for the contracctors and Project Engineers
to arrange lacking documents attached to contracts.

The contractors representative opened up about the DOLE


requirements. He said that the DOLE application requirments has been
Other Matters delaye due to a lot of processes online. The contractors already finished Contractor
the following requirements, but the DOLE added another set of
requirements, namely: NC II for the workers and contract.

Comply the lacking pertinent documents for the Notice of Award to Saidale M. Mitmug, MPA,
avoid delay. Requiring all contractor's workforce to have NC II ASEAN Eng.
certification. Assistant District Engineer
Contractors also opened about the Bureu of Internal Revenue of the
percentage that they will get from the total budget for the project.
Contractor
Presenting the percentage of 1.3% aggregates and 1% of the total
contract amount.

Send a letter to his office discussing the Revenues, addressed from the Mocamodali Pundogar
contractor to administrative office. Admin. Chief

2 of 5
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
Region X
OFFICE OF THE DISTRICT ENGINEER
Lanao del Norte 1st District Engineering Office
0054 Seminary Drive, Del Carmen, Iligan City, Lanao del Norte

Title/Description:

Hadji Khalil D. Sultan,


Acknowledged everyone's presence and thanked them for the active
MPA, ASEAN Eng.
participation.
District Engineer

Meeting Adjourned

Assignments to be validated in the next meeting:


Status (to be
Item Assignment Person-in-Charge accomplished in the next
meeting)
1. Agenda
Weekly coordination
1.Discussion of
meeting with Project Project Engineers and Engr. Rachid Mudag To be accomplished.
negative
Engineers and RROW Unit
accomplishments.
Review and Confirmation:
Prepared by: Reviewed by: Approved by:

SHERLYN P. BERTULFO ALDYN R. QUINTO MARIA LIZA E. POMICPIC


Admin Aide I Assistant Chief, Construction Section Chief, Construction Section
NOTED :

3 of 5
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
Region X
OFFICE OF THE DISTRICT ENGINEER
Lanao del Norte 2nd District Engineering Office
0054 Seminary Drive, Del Carmen, Iligan City, Lanao del Norte

Title/Description:

TECHNICAL MEETING

Date: Started: Adjourned: Venue:

10-Jan-22 1:30 PM DPWH-LNED II Conference Room

ATTENDANCE SHEET
NAME OFFICE CONTACT NUMBER SIGNATURE
AIVEEN C. SINAHON CONSTRUCTION SECTION 9979501304

EDMON SAMSON CONSTRUCTION SECTION 9758854594

SHAIMAH B. AMEROL CONSTRUCTION SECTION 9177112764

MHARX B. PALAMINE CONSTRUCTION SECTION 9173073352

JEANIE ROSE A. CONSTRUCTION SECTION 9759150725

ABDUL GAFFAR PANDAPATAN CONSTRUCTION SECTION 9174400460

FAIROZAH R. TABUACAR CONSTRUCTION SECTION 9151386040

ARSAD P. CADER CONSTRUCTION SECTION 9174475666

ALDYN R. QUINTO CONSTRUCTION SECTION 9168236042

JAMES R. CAPANGPANGAN CONSTRUCTION SECTION 9174406690

LORENA O. ANOR CONSTRUCTION SECTION 9359949534

NOR-HAINA S. ALAWI CONSTRUCTION SECTION 9171009167

JOHN CHRISTIAN G. NIAGA CONSTRUCTION SECTION 9951573945

NAIDAH B. SATA QUALITY ASSURANCE SECTION

SHEREEN EVE MAAGAD MAINTENANCE SECTION 9051089805

ELEANOR CABALUNA CONSTRUCTION SECTION 9664119800

MOHAMMAD SAMIN MINDALANO MAINTENANCE SECTION 9059631789

MOHAMMAD ALI U. MALA MAINTENANCE SECTION 9703574624

YUSUF M. MACADINDANG MAINTENANCE SECTION 9352566950

H. D SANGUILA MAINTENANCE SECTION 9053508290

CABIB ALI JR. MAINTENANCE SECTION 9369537924

MARJAN P. BANSARA CONSTRUCTION SECTION 9750449859

AL MUJIB R. PUNDOGAIR CONSTRUCTION SECTION 9977262365

SITTIE NORHAYDA R. MACARAMBON MAINTENANCE SECTION 9369194275

JOHN MAIKO N. SALLY MAINTENANCE SECTION 9760100729

ARSAD P. CADER COSNTRUCTIONS ECTION 9174475666

MOHAMMAD S. MACALABA MAINTENANCE SECTION 9355506897

FERDINAND V. YABAN QUALITY ASSURANCE SECTION 9352542875

NOLITO B. BAJOLO CONSTRUCTION SECTION 9773909821

MAPANDI, NISAN MAINTENANCE SECTION 9971281702


Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
Region X
OFFICE OF THE DISTRICT ENGINEER
Lanao del Norte 2nd District Engineering Office
0054 Seminary Drive, Del Carmen, Iligan City, Lanao del Norte

Title/Description:

RADIALAOT, SAMSODIN D. QUALITY ASSURANCE SECTION 9128376600

OPEÑA, PAUL BRIAN PLANNIGN AND DESIGN SECTION 9778143335

MARIA B. MONTEJO PLANNING AND DESIGN SECTION

TASMEEN G. MACAPATO CONSTRUCTION SECTION 9270063250