Professional Documents
Culture Documents
PT Indocement Tunggal Prakarsa Tbk. has three factory complexes, which in total include 12
factories. The Citeureup factory complex in Bogor, West Java, which operates 9 factories, is
one of the largest cement plant complexes in the world. Two other factory complexes are
located in Palimanan, Cirebon, West Java and in Tarjun, Kotabaru, South Kalimantan, with
one factory. Total installed production capacity 25.5 million tons.
Cement
Capacities
Location Factory
(million ton)
Citeureup, Bogor, Jawa Barat 9 11,9 million
Palimanan, Cirebon, Jawa Barat 2 4,1 million
Tarjun, Kotabaru, Kalimantan
1 2,6 million
Selatan
Total 12 18,6 million
Citeureup Plants
Cirebon Plants
QCC Profile
QCC Quantum was formed on July 14, 2009 in the organizational structure including the
Mechanical Department, Operation Plant Division of PT. Indocement Tunggal Prakarsa, Tbk.
Tarjun Village – Kotabaru, South Kalimantan.
Nama Gugus GKM Quantum Jumlah Pertemuan 54 Kali
Ketua Bayu Prianto,ST. % Kehadiran 100%
Sekretaris Hasan Bisri Lama Pertemuan 2 Jam
Anggota Suparto Waktu Pertemuan 13:00 - 15:00
Dibentuk pada 14 Juli 2009 Tema ke 9 (Sembilan )
Fasilitator Bilter Sinaga Usia tertua 45
TQM Project Suryana,SE,MM. Usia Termuda 27
Pendidikan SLTA – S2
Suryana
(Facilitator)
Bilter Sinaga
Operation Plant
DIVISION
QCC
QUANTU
M
I. THEME SELECTION
Period : Week I – IV of February 2021
Summary:
From data and diagram about, it is known that in Januari 2021 there is parameter in KPM
namely down time index that face poor performance as 50 so the performance is red.
In January 2021 one of indicator from KPM namely down time index that face poor
performance due to high downtime mechanical, This will results Mean Time Between Failure
(MTBF) index is low, with the following data:
Standard Actual
Summary:
Based on data and graphic above, it is known that MTBF in January 2021 where is consist of
3 production process area that one of them has index value below standard that is very far
from expectation, as known that the lower of MTBF the higher department down time, due to
equipment failure on production process. This will result KPM mechanical department will be
red, so the Mechanical Department Head instructing to facilitator to solve down time
problems immediately through Quality Control Circle.
1.2. Determining Theme
By following up the instruction from Department Head, QCC QUANTUM doing analyze to
Down time problem. The QCC analysis results that down time problems is high due to
equipment failure on production process. Next is QCC doing problems inventarization based
on location by classifying the data according to how much the disturbances (frequency), how
long the disturbances (duration), lost product and loss value (IDR).
Pareto Analysis:
1. From data sheet and pareto diagram on down time frequency based on work area
above, it seems that raw mill area face the most down time as much as 12 times or
29.27 % for a month.
So that Raw Mill down time is priority issue, and QCC QUANTUM agreed to set the theme:
1. From data sheet and pareto diagram on down time frequency above, it seems that
Mechanical Equipment is a disturbance source on raw mill with the most frequency as much
as 8 time for a month.
2. From data sheet and pareto diagram on downtime duration above, it seems that Mechanical
Equipment is a disturbance type on raw mill with the most duration as much as 310,50 hours
for a month.
3. From data sheet and pareto diagram on raw mill lost product, it seems that Mechanical
Equipment is a disturbance type that can affect to raw mill prodcution loss as much as
152,515,24 Ton or 90,78% for a month.
4. From data sheet and pareto diagram on lost product’s loss value, it seems that Mechanical
Equipment is a disturbance type that can affect to cement production income lost as much as
So that Mechanical Equipment
Rp.70.157.012.195,- or 90,78% are
for apriority
month.issues, and QCC QUANTUM agreed to
set the title:
310.5
350
300 100%
250
200
150 0
100
50
0
Before Repair Initial Goal
1. Target from Mechanical Department is to prevent raw mill downtime due to mechanical
equipment failure.
2. Experience and optimism from QCC members
3. There are full supports from management
2.3. Repair Benefit:
Tangible:
Intangible:
1. Reducing employee work accident risk
2. Increase the employee work motivation
3. Increase good relations between management and subordinate
Ten dominant suspected cause factors above then we’ll evaluate by correlation analysis
on the next steps.
INFLUENCING FACTORS
Period: 1st Week of April s/d 4th Weeks of May 2021
3.1. Hypothesis test
3.1.1.Cause of range between ECS Bin Chute with 361 WF1 Belt is too close.
Testing Purpose : To find out the relationship among range between chute to belt
with squeezed Raw material
X Indicator : Range between chute to belt (Cm)
Y Indicator : Equipment failure duration (hours)
Testing Date : 03 - 15 Apr 2021
N = 11
R = -0.770
R2 = 0.593
59.30%
Summary:
From data and scatter diagram, it’s known that there is strong positive correlation between
how much scrapper liner claw loose with how long the equipment disturbance, that the more
scrapper liner claw loose, so the longer equipment’s failure that resulting stop on raw mill
production process with r value = 0.889 dan r 2 = 0.790 with correlation strength as much as
79.03% . then this cause will be follow up for repair in the next step.
Summary:
From data and scatter diagram above, it’s known that there is strong positive correlation between
how much the harrow teeth loose with how long the equipment’s disturbance, the more harrow
teeth loose, the longer the equipment’s disturbance that resulting stop on raw mill production
process with r value = 0.975 and r2 = 0.952 with correlation strength as much as 95.17% . then this
cause will be follow up for repair in the next step.
3.1.4. Cause of 391 CV 1 – 4 tension shaft moved.
Testing Purpose : To find out the relationship between bearing shaft loose
frequency
With how long the equipment’s disturbance
X Indicator : Bearing shaft loose frequency (times)
Y Indicator : Equipment disturbance duration (hours)
Testing Date : 10 - 24 Apr 2021
Method : Observation & Record
Observation Object : Bearing Shaft
Data Collector : Bayu
Summary:
From data and scatter diagram above, it’s known that there is a strong positive correlation between
bearing loose frequency with equipment disturbance duration that the more often bearing shaft broken,
the more longer the equipment disturbance that resulting stop on raw mill production process, with r
value = 0.988 dan r2 = 0.976 with correlation strength as much as 97.6 % . then this cause will be
follow up for repair in the next step.
3.1.5. Cause of 361RM1 Damring is not high enough.
Testing Purpose : To find out the relationship between material spills frequency
with
How long the equipment disturbance
X Indicator : Material spills frequency (times)
Y Indicator : Equipment disturbance duration (hours)
Testing Date : 01 - 15 May 2021
Method : Observation & Record
Observation Object : Meal Material
Data Collector : Hasan Bisri
From data and scatter diagram above, it’s known that there is a strong positive correlation between
material spills frequency with equipment disturbance duration, that the more material spills, the
longer the equipment disturbance that resulting stop on raw mill production process with r value =
0.960 and r2 = 0.922 with correlation strength as much as 92.16% . then this cause will be follow up
for repair in the next step.
From data and scatter diagram above, it is known that there is a strong positive correlation between
spilage jumping frequency with how long the equipment disturbance duration, which is the more often
spilage jumping, the longer the equipment disturbance that resulting stop on raw mill production
process with r value = 0.948 and r 2 = 0.898 with correlation strength as much as 89.80%. then this
cause will be follow up for repair in the next step.
3.1.7. 361 HD 1 & 2 Wood Pipe Clamp is not strong enough.
Testing Purpose : To find out the relationship between damaged wood clamp
frequency
With how long the equiment disturbance
X Indicator : Damaged Wood Clamp frequency (times)
Y Indicator : Equipment disturbance duration (hours)
Testing Date : 01 - 30 May 2021
Method : Observation & Record
Observation Object : Wood Clamp
Data Collector : Suparto
From data and scatter diagram above, it is known that there is a strong positive correlation
between damaged wood clamp frequency with how long the equipment disturbance that the
more often wood clamp damaged, the longer the equipment disturbance that resulting stop on
raw mill production process with r value = 0.943 and r 2 = 0.889 with correlation strength as
much as 88.92 %. then this cause will be follow up for repair in the next step.
3.1.8. Cause of Shaft Output Stick to Apron Feeder .
Testing Purpose : To find out the relationship between installation & remove
duration
With how long the equipment disturbance
X Indicator : Planetary Gear installation & remove duration (hours)
Y Indicator : Equipment disturbance duration (hours)
Testing Date : 15 - 24 May 2021
Method : Observation & Record
Observation Object : Spilage
Data Collector : Bayu
Based on data and diagram above, it is known that there is a strrong positive correlation
between planetary gear installation & remove duration to equipment disturbance on raw mill.
The longer installation & remove process of planetary gear, The longer the equipment
duration that resulting stop on raw mill production process with r value = 0.952 and r2 = 0.906
with correlation strength as much as 90.63 % . then this cause will be follow up for repair in
the next step.
3.1.9. Cause of Patroller is not Mechanic.
Testing Purpose : To find out the relationship between total of fastened bolts with
Total of broken bolts
X Indicator : Total of fastened bolts (Pcs)
Y Indicator : Total of broken bolts (Pcs)
Testing Date : 15 - 24 May 2021
Method : Observation & Record
Observation Object : Scrapper Bolt
Data Collector : Hasan Bisri
From data and scatter diagram above, it is known that there is a strong positive correlation between
fastened bolts with broken bolts. correlation said that the more bolts is tight, the more bolts is
broken so resulting stop on equipment and production process, with r value = 0.954 and r2 = 0.910
with correlation strength as much as 91.01%. then this cause will be follow up for repair in the next
step.
From scatter diagram data above, it is known that there is strong negative correlation between
the frequency with which the bolts are tightened with bolt age duration that The more often the
bolt is tightened, the faster the bolt will break that can result the scrapper fell and the
production process stopped, with correlation strength as much as 63.20 5 supported by r value
= - 0.795 and r2 value = 0.632, then this cause will be follow up for repair in the next step.
Sequence Number of 3
Dominant Cause
Dominant Cause 361 RM1 Damring is not high enough
Why (Why 361 RM1 Damring that So that the material does not spill
not high enough must be
repaired?)
What (What is the form of repair?) Increase the damring height
Where (Where the repair be Above 361 RM1 table
done?)
When (When the repair be done?) 19 – 30 Jun 2021
Who (Who is in charge?) Bayu Prianto
How (How the steps?) Steps of activities:
1. Prepare equipment and materials (welding machine,
cable roll, hand grinder, welding wire, angle iron and iron
plate)
2. Lock out the equipment
3. Prepare the materials
4 Cut the plate bar sized 30 X 30 mm 600mm length
4. Plat on +/- R2500 rol.
5. Weld the plate bar on the table.
6. Repair results monitoring.
Sequence Number of 5
Dominant Cause
Dominant Cause Shaft Output stick on Apron Feeder
Why (Why shaft Output stick on So that the planetary gear is not cut
apron feeder must be repaired?)
What (What is the form of repair?) Manufacture planetary gear system coupling
Sequence Number of 6
Dominant Cause
Dominant Cause 341 SX2 Sprocket spilled by material
Why (Why the 341 SX2 sprocket
that spilled by material must be To Keep Scrapper Load Low
repaired?)
What (What is the form of repair?) Manufacture a Cannopy
Where (Where the repair be 341 SX2
done?)
When (When the repair be done?) 10 - 18 Jul 2021
Who (Who is in charge?) Hasan Bisri
How (How the steps?) Steps of Activities:
1. Prepare Tools.
2. Prepare the materials.
3. Lock Out process.
4. 5 mm plate 4 rectangular 800X600mm sized.
5. Manufacture support cannopy from iron plate
size 1.5 inc.
6. Do the welding.
How Much (How much the % 100 %
success to be achieved?)
Sequence Number of 8
Dominant Cause
Dominant Cause 311 RE1 Liner Scrapper is easy to bent
Why (Why 311RE1 linner
scrapper that easy to bent must So that the Roller guide does not fall.
be repaired?)
What (What is the form of repair?) Manufacture linner scrapper support
Where (Where the repair be done?)
311 RE1
When (When the repair be done?) 1 - 9 Aug 2021
Who (Who is in charge?) Suparto
How (How the steps?) Steps of Activities:
1. Prepare equipment and materials (welding
machine, cable)
roll, hand grinder, welding wire, elbow iron
and iron plate etc)
2. Equipment Lock out ( PTW )
3. Conveyor spilage floor cleaning
4. Position the scrapper on the tail
5. Cut plate 80 mm x 300 x = 2 pcs
6. Install the plate between the plates that
have been installed (plates that rub against
the scrapper rail)
Sequence Number of 9
Dominant Cause
Dominant Cause There is no bolt tightness frequency monitoring
Why (Why There is no bolt tightness
So that there is a record of the frequency of bolt
frequency monitoring? ) tightening
What (What is the form of repair?)
Monitoring bolt tightness
Where (Where the repair be done?)
311 RE 1
When (When the repair be done?)
1 – 12 Aug 2021
Who(Who is in charge?) Hasan Bisri
Who (Who is in charge?) Steps of Activities:
1. Made monitoring draft.
2. Monitoring print.
3. Monitoring socialization.
4. Monitoring implementation.
How Much (How much the % 100 %
success to be achieved?)
INTERMEDIATE TARGET
310.5
350
300
250
200
100% 100%
150
100
0 0
50
0
Before Repair Initial Goal Intermediate Target
Management comment:
Management approval:
0.9
0.8
Summary:
0.7 Based on the results of monitoring or
0.6 monitoring after repairs have been carried out
QCC QUANTUM – MECHANICAL DEPARTMENT that
0.5
P. 12during
TARJUN KOTABARU-
7 days of monitoring there are no
41
0.4
0
4 5 6 7 8 9 10
1.1.2. Manufacture a Brace / Support on Harrow Teeth 311 RE1.
0.9
After repairs were manufacture by
0.8
increasing the height of the damring by
0.7
0.5 meters, we monitored the condition
QCC QUANTUM
0.6
– MECHANICAL DEPARTMENT P.after
12 TARJUN KOTABARU-
the repair for 8 days with the result
KALSEL
43
0.5
that there was no more vibration at raw
0.4
mill so that no more spilled material and
0.3
the raw mill could operate, which means
0.2
that the production process can run well.
0.1
21 22 23 24 27 28 29 30
Summary:
After the repair was carried out by
Broken Scrapper Bolt Monitoring on 10 - 30 Jun 2021
1
socializing the tightness of the bolts to the
0.9 patrollers and continued with monitoring
0.8 the tightness of the bolts on the scrapper
0.7 for 19 days with the results of monitoring
0.6 that there were no more broken bolts
0.5 because the tightness was according to
0.4
the 411N/M standard so that there were no
0.3
more broken bolts so that the scrapper
0.2
QCC QUANTUM – MECHANICAL DEPARTMENT P. does not fallKOTABARU-
12 TARJUN and the raw mill can still
0.1
operate smoothly. This
KALSEL 0
10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 27 28 29 30
SUCCESSFUL.
44 fix is
4.1.5. Manufacture Planetary Gear System Coupling in 211 AF 1.
Manufacture process
0.1
0
4 5 6 7 8 9 10 11
0.2
0.1
0
12 13 14 15 16 17 18
0
21 22 23 24 25 26 27
0
3 4 5 6 7 8 9
Summary:
Bolt Tightened Frequency Monitoring > 3 Times
03 - 09 August 2021
1
After repairs are manufacture by
0.9 monitoring the frequency of bolt
0.8 tightness, the patroller knows the
0.7 level of frequency of bolt tightness
0.6 and no longer exceeds 3 times in one
0.5 bolt so that there are no more broken
0.4 bolts. This is evidenced by the results
0.3 of monitoring the frequency with
0.2 which the bolts are tightened. Thus
0.1 this repair is declared SUCCESSFUL.
0
3 4 5 6 7 8 9
Before After
Date Bearing Shaft Date Bearing Shaft
Release Release
Frequency Frequency
10-04-2021 1 04-06-2021 0
QCC QUANTUM – MECHANICAL DEPARTMENT P. 12 TARJUN KOTABARU-
KALSEL
51
11-04-2021 0 05-06-2021 0
12-04-2021 4 06-06-2021 0
13-04-2021 1 07-06-2021 0
14-04-2021 1 08-06-2021 0
15-04-2021 0 09-06-2021 0
16-04-2021 0 10-06-2021 0
17-04-2021 3
18-04-2021 1
19-04-2021 2
20-04-2021 2
21-04-2021 3
22-04-2021 1
23-04-2021 1
24-04-2021 2
Total 22 0
Before After
Date Number of Horrow Date Number of Horrow
Teeth Released Teeth Released
( Pcs ) ( Pcs )
01-04-2021 2 12-06-2021 0
02-04-2021 2 13-06-2021 0
03-04-2021 4 14-06-2021 0
04-04-2021 2 15-06-2021 0
05-04-2021 0 16-06-2021 0
06-04-2021 1 17-06-2021 0
07-04-2021 1 18-06-2021 0
QCC QUANTUM – MECHANICAL DEPARTMENT P. 12 TARJUN KOTABARU-
KALSEL
52
08-04-2021 4 19-06-2021
09-04-2021 2
10-04-2021 2
11-04-2021 0
12-04-2021 0
13-04-2021 6
14-04-2021 1
15-04-2021 2
Total 29 0
30
25
20
15
10 0
5
0
Before After
Summary: There is a change in the condition of the cause of the 311 RE1 harrow
teeth not being strong, before the repair there were 29 pcs of harrow teeth loose,
while after the repair there were no more horrow teeth loose. It can be concluded that
the idea of Manufacture braces / support is the right improvement from QCC
Quantum.
1.1.3. Cause of 361 RM1 Damring is not high enough.
Before After
Date Frequency of Date Frequency of
Spilled Material Spilled Material
( Times ) ( Times )
01-05-2021 2 21-06-2021 0
02-05-2021 2 22-06-2021 0
03-05-2021 4 23-06-2021 0
04-05-2021 2 24-06-2021 0
05-05-2021 0 27-06-2021 0
06-05-2021 1 28-06-2021 0
07-05-2021 1 29-06-2021 0
32
35
30
25
20
0
15
10
0
Before After
Summary: There is a change in conditions to the cause of Damring 361 RM1 not
being high enough, before the repair there were 32 times the material was spilled,
while after the repair was carried out there was no more spilled material. It can be
concluded that the idea of increasing the height of the damring is the right
improvement from QCC Quantum.
1.1.4. Cause of Patroller is not from Mechanic.
50
40
30
20
0
10
0
Before After
Before After
Date Equipment Date Equipment
Disturbance Disturbance
(hours) (hours)
15-05-2021 2 04-07-2021 0
16-05-2021 2 05-07-2021 0
17-05-2021 4 06-07-2021 0
18-05-2021 1 07-07-2021 0
19-05-2021 0 08-07-2021 0
20-05-2021 0 09-07-2021 0
21-05-2021 2 10-07-2021 0
22-05-2021 1 11-07-2021 0
QCC QUANTUM – MECHANICAL DEPARTMENT P. 12 TARJUN KOTABARU-
KALSEL
55
23-05-2021 1
24-05-2021 2
Total 15 0
15
16
14
12
10
8
6
4
0
2
0
Before After
Summary: There is a change in conditions to the cause of the output shaft being
attached to the apron feeder, before the repair there were 15 hours of equipment
disturbance, while after the repair was carried out there was no more equipment
disturbance from this cause, so it can be concluded that the idea of Manufacture a
planetary gear coupling system is the right improvement from QCC Quantum.
1.1.6. Cause of 341 SX2 Sprocket spilled by materials.
Before After
Date Spillage Jumping Date Spillage Jumping
Frequency (times) Frequency (times)
01-05-2021 4 12-07-2021 0
02-05-2021 2 13-07-2021 0
03-05-2021 2 14-07-2021 0
04-05-2021 2 15-07-2021 0
05-05-2021 3 16-07-2021 0
06-05-2021 1 17-07-2021 0
07-05-2021 1 18-07-2021 0
08-05-2021 2
09-05-2021 4
10-05-2021 2
QCC QUANTUM – MECHANICAL DEPARTMENT P. 12 TARJUN KOTABARU-
KALSEL
56
Total 23 0
23
25
20
15
10
0
5
0
Before After
Summary: There was a change in conditions that caused material spillage of the 341
SX2 sprocket, before the repair there were 23 spillage jumping, while after the repair
was carried out there was no more spillage jumping, so it can be concluded that the
idea of Manufacture a cannopy on the 341 SX2 is the right improvement from QCC
Quantum.
Before After
Date Fracture Clamp Date Fracture Clamp
Frequency( times ) Frequency( times )
1st week of May 4 21-07-2021 0
2021
2nd week of May 2 22-07-2021 0
2021
3rd week of May 2 23-07-2021 0
2021
4th week of May 3 24-07-2021 0
2021
25-07-2021 0
26-07-2021 0
27-07-2021 0
QCC QUANTUM – MECHANICAL DEPARTMENT P. 12 TARJUN KOTABARU-
KALSEL
57
Total 11 0
11
12
10
4 0
2
0
Before After
Summary: There was a change in conditions that caused the HD pipe wood clamp
to be not strong, before repair there were 11 broken clamps, while after the repair
was carried out there were no more broken clamps, so it can be concluded that the
idea of Manufacture iron clamps from cannal iron is the right improvement from QCC
Quantum.
Before After
Date Number of Loose Date Number of Loose
Scrapper Linner Scrapper Linner
Claws (Pcs) Claws (Pcs)
03-04-2021 4 03-08-2021 0
04-04-2021 4 04-08-2021 0
05-04-2021 1 05-08-2021 0
06-04-2021 0 06-08-2021 0
07-04-2021 1 07-08-2021 0
10-04-2021 4 08-08-2021 0
11-04-2021 2 09-08-2021 0
12-04-2021 2
13-04-2021 0
14-04-2021 1
QCC QUANTUM – MECHANICAL DEPARTMENT P. 12 TARJUN KOTABARU-
KALSEL
58
15-04-2021 2
16-04-2021 3
17-04-2021 2
18-04-2021 4
19-04-2021 3
Total 33 0
30
25
20
15
10
0
5
0
Before After
Summary: There was a change in conditions that caused the 311RE1 liner scrapper
to bend easily, before the repair there were 33 loose linner scrapper nails, while after
the repair was carried out there were no more loose linner scrapper nails, so it can
be concluded that the idea of Manufacture a support liner scrapper is the right
improvement from QCC Quantum.
1.1.9. Cause of no bolt tightness monitoring.
1.1.10. Cause of Distance Between ECS Bin and Belt 361WF1 Too Close.
Before After
Date Equipment Date Equipment
Disturbance Disturbance
(hours) (hours)
03-04-2021 5 16-08-2021 0
04-04-2021 5 17-08-2021 0
05-04-2021 47.5 18-08-2021 0
06-04-2021 4 19-08-2021 0
07-04-2021 4 20-08-2021 0
10-04-2021 3 21-08-2021 0
11-04-2021 2 22-08-2021 0
12-04-2021 2.5 23-08-2021 0
13-04-2021 1 24-08-2021 0
14-04-2021 0 25-08-2021 0
15-04-2021 0 26-08-2021 0
27-08-2021 0
QCC QUANTUM – MECHANICAL DEPARTMENT P. 12 TARJUN KOTABARU-
KALSEL
60
28-08-2021 0
29-08-2021 0
30-08-2021 0
31-08-2021 0
Total 31.25 0
31.25
35
30
25
20
0
15
10
0
Before After
Summary: There was a change in conditions causing the distance between the ECS
bin and the 361 WF1 belt to be too tight, before the repair there were 31.25 hours of
equipment disruption in the bin, while after the repairs were carried out there were no
more equipment disturbances in the bin, so it can be concluded that the idea of
widening the chute angle is a good improvement. right from QCC Quantum.
1.2. Comparative Analysis of Results Against Title
Total Total
3
100 % 100 % 100 %
2
1
0 0 0
0
Before Initia Goal Intermediate Target After
After Repairs
QCC QUANTUM – MECHANICAL DEPARTMENT P. 12 TARJUN KOTABARU-
KALSEL
68
Summary:
Based on the data above, QCC QUANTUM has succeeded in reducing down time in raw
mills, both from the number of disturbances, the duration of the disturbance, raw mill lost
product, clinker lost product, cement lost product, as well as the loss value of lost benefit
production..
Comparison of Results Against KPM Mechanical Department:
Intangible:
1. Reducing the risk of employee accidents
2. Increase employee motivation, knowledge and work experience
3. Improve the relationship between superiors and subordinates as well as
between QCC members.
Efforts Manufacture:
1. Socialization of improvement results to other QCC.
2. Socialization of the results of improvements to the production employees of the Raw
Mill
Negative Impact:
1. The location/position of the spillage disintegrator above the apron feeder hopper is
in an open condition so it is very dangerous for the spillage motor inspector
because the disintegrator rotates continuously.
2. The sound emitted by the big blaster/air canon is so loud that it can cause a shock
to field officers.
Efforts Eliminating Negtive Impact : :
V. STANDARDIZATION
Period : Week I – IV October 2021
1. Standard Procedure
1.1. Standard procedure for Manufacturing & Maintenance of Raw Mill
Mechanical Equipment according to P12/OPD-PR/K3/01
procedures
1.1.1.1 Modify the apron mix rail and shaft sprocket mount
1.1.1.2 Modify the shape of the disintegrator blade
1.1.1.3 Manufacture a canopy sprocket chain spillage conveyor apron mix
1.2.1.1. Perform operations using apron mix rails and shaft sprocket mounts
1.2.1.2. Perform the operation of the new disintegrator blade
1.2.1.3. Perform the operation of the lip elevation chute weight feeder raw mix
1.2.1.4. Carry out the principle operation of the chute weight feeder limestone lip
elevation
1.2.1.5. Perform the operation of using the lip casing chute raw mix with a round bar.
1.2.1.6. Perform the operation of the chute limestone casing lip with a round bar.
1.2.1.7. Perform the operation of the 341SX2 spillage scrapper operation
1.2.1.8. Carry out the principal operation of the air cannon in the silica bin.
1.2.1.9. Carry out the operation using the automatic air cannon start stop panel in the
silica bin
6.1.3.1. Perform maintenance on the apron mix rails and shaft sprocket mounts.
6.1.3.2. Perform new disintegrator blade maintenance
6.1.3.3. Perform maintenance on canopy sprocket chain spillage conveyor apron mix
6.1.3.4. Do lip elevation treatment chute weight feeder raw mix.
6.1.3.5. Do lip elevation treatment of chute weight feeder limestone.
6.1.3.6. Take care rawmix chute casing lip with round bar
6.1.3.7. Do the casing chute limestone lip treatment with a round bar
6.1.3.8. Perform 341SX2 spillage maintenance
6.1.3.9. Do water cannon treatment in silica bin
6.1.3.10. Perform maintenance on the automatic air cannon start stop panel in the silica
bin
6.1.3.11. Take care of the anti-sticky (kalen) material on the casing in the silica bin
6.1.3.12. Take care of the anti-sticky (kalen) material on the casing in the laterite bin
2. Result Standard
By consistently carrying out the above procedures, the Mechanical Equipment
down time in Raw Mill Plant 12 is a maximum of 0 times in one month
Monitor and maintain the standard of results that have been achieved in the
previous step.
3.3. Manufacture braces / support for harrow teeth is not only applied to
311RE1 but also to 331 RE1 & RE2. The similarity between 311 RE1 and
3311RE1 & RE2 is that it is a reclaimer tool for scratching or leveling
materials. The difference is the type of material in 311 RE1 is Limestone,
while the type of material in 331 RE1 & 2 is gypsum. Brace/uspport
installation at 331 RE1 & RE2 will be held on 22 & 23 October 2021.
6
(Kali)
5
5
4
4
Frekuensi gangguan
3
3
0
Raw Mill Finish Mill 1 & 2 Kiln
Pareto Analysis:
1. From the data sheet and bar chart on the down time frequency based on the work area
above, it can be seen that the Raw mill area experiences the most down time 5 times in
one month.
2. From the data sheet and bar chart on the duration of down time based on the work area
above, it can be seen that the Raw Mill area experienced the longest down time of 13.66
hours in one month.
3. From the data sheet and bar chart on the potential Raw Mill lost product above, it can be
seen that Raw mill down time has the biggest influence on the loss of Raw Meal production
of 7,922.80 Tons or 58.15% in one month.
4. From the data sheet and bar chart on Cement lost product above, it can be seen that Raw
mill down time has the biggest influence on the loss of cement production of 6,709.69 tons
or 87.17% in one month.
5. From the data sheet and bar chart on the value of lost product losses above, it can be seen
that Raw mill down time has the biggest influence on the loss of cement production
revenue of Rp. 3,086.456,639.57, - or 87.17% in one month.
Thus, Raw Mill down time is a priority issue, and QCC Quantum agreed to set the theme:
“Eliminate Raw Mill Down Time in Plant 12 Tarjun ”
Schedule of Action Plans for 2022
Bilter Sinaga.
Facilitator