Professional Documents
Culture Documents
SHAHID ALI
CSWIP 3.1 (Instructor)
Cell#: 00966-599-807084
Cell#: 0092-334-7497876
Email: ss_aakash@yahoo.com
Web: www.qctrainer.com
What is QA/QC?
Quality Assurance is the system of action and planning needed to
provide maximum confidence for quality requirements.
Quality Control is the operational techniques i.e (Inspection, Testing & Examination) that are used to
fulfill requirement for quality.
What is ITPs?
ITP: ITP means Inspection and Test Plan.
Details of work scope and required types of inspections
Hold point (H) is the level of inspection that client inspection must required through RFI and cannot be
proceeded until inspection is done by client.
Witness point (W) is the level of inspection that inspection activity can be proceeded without client
inspection or if client is not available as per RFI timing.
What is schedule Q?
Schedule Q is an attachment to the contract, which is the provision of quality assurance and control,
Inspection and test plan.
What is WPS?
WPS is Welding Procedure Specification, It is a written document that provides direction to the
welder or welding operator for making production welds.
What is standard?
A Standard can be defined as a set of technical definitions and guidelines that function as instructions for
designers, manufacturers, operators, or users of equipment. Ex ASME31.3 is a standard for process piping.
What is code?
A standard becomes a Code when it has been adopted by one or more governmental bodies and is
enforceable by law, or when it has been incorporated into a business contract.
What is specification?
Specifications clearly and accurately describe the technical requirements of any given product or process
and are used heavily by purchasing departments for controlling the quality of incoming materials. Ex
API5L
For NDT
SAEP-1141 (RPP)
SAEP-1143 (RT)
SAEP-1144 (MT)
SAEP-1145 (PT)
SAEP-1146 (UT)
SAEP-1150 Inspection Coverage on Projects
After Two Contactor Internal NCR for Same Violation: Escalate to raise the ARAMCO NCR
ARAMCO NCR Mean Log Book Entry
Before getting MCC should be close the all open NCRs.
Material Arrival
NDT Coordinator
(Selection of Weld as per ITP, Drawing
10%, 100%)
IF Repair
(Repair Procedure (PQP), MT, Pre Heat, RT)
If Specified
(PWHT, Chart, Procedure)
Send to (NTI)
Sand Blasting, Paining & Coating
Final Inspection
Site Release (IRC)
Only 300 series SS brushes are used on austenitic & nickel alloys.
Where tape is used for back purging, the tape uses an adhesive with a water soluble chloride
content not exceeding 50-ppm. Gray duct tape is prohibited (chlorides)
Austenitic & nickel alloy material fabrication areas are separated from CS areas (upwind to
prevent cross contamination).
Wind velocity in the weld area for GTAW, GMAW, or gas shielded FCAW shall not exceed 8 kph
(2.2 m/s)
Oil, moisture, scale, rust, paint (except approved weld-able primers), metallic coatings (e.g. zinc)
or other foreign matter, has been removed from weld surfaces at least 25mm adjacent to weld
joint.
Back Purging:
Purging is applied on P-5 and Greater materials, For process GTAW & GMAW root passes single
sided grove welds, Purging shall be maintained until at least 10mm of the weld deposit thickness has
been completed.
Not use of Nitrogen as purging gas in Austenitic Stainless steel.
The purge shall achieve actual oxygen levels inside or exiting the joint (via the vent) never greater
than 50 ppm O2 (maximum 0.005%) prior to and during welding, as measured with an O2 analyzer
with low-level read-out capability. (ppm=Parts Per Millions)
12 ppm O2 = No oxide tint ... ACCEPTABLE
Hand Held Spectrometer is used for performing PMI PMI by XRF Metal Analyzer X-MET8000
Methods
The instruments and methods used for PMI testing shall be suitable for identifying the material by
quantitative measurement of the major alloying elements required in the applicable material
specification or welding procedure specification.
The primary acceptable method is X-ray emission analysis, also known as X-ray fluorescence (XRF)
analysis with a calibrated portable instrument
An optical emission spectrograph may be used to check for all the required elements, including
carbon. A hot work permit may be required before using this equipment. Any burn damage resulting
from the usage of the emission spectrograph shall be removed by grinding.
It is noted that some newer XRF analysers can analyze elements such Mg, Al, Si, P, S which are lighter
than sulfur (S),
Lot: Same batch of particular components -- the same supplier, type of component, size, rating, material,
etc., and from the same shipment. Material Specifications: ASME SEC II, Parts
Acceptance Criteria
10.1 For acceptance, it must be demonstrated that materials contain the amounts of alloying elements
shown in the material specification. Alloys shall be acceptable if the alloying elements are each within
10% of the specified range of values.
10.2 Welds with consumables that match, or nearly match, the base metal composition shall be within
±12.5% of the ranges allowed in ASME SEC IIC for each element.
Results showing Copper Content greater than 0.7% indicate unacceptable "cross contamination".
INSTRUCTIONS:
DO NOT USE ELECTRODE OR FILLER MAT'L "LOTS" on SA Projects for production welding until PMI tests
verify composition.
At the latest, test the first production weld. Test consumables immediately after receipt to avoid
"surprise" of "bad batches". Specs requiring PMI at SA are:
ASME SEC II C - Specification for Welding rods, Electrodes & Filler metals
CHEMICAL ANALYSIS (PMI ... "BUTTON"):
Details vary per Spec. Refer to Fig. 1 - Pad for Chemical Analyses of Undiluted Weld Metal
ER70S-2 & 3:
Filler metals are used extensively to produce high quality; high toughness welds with the GTAW
Process. These filler metals are also well suited for use in single side, melt through welding without a
protective root shielding gas on the backside of the joint.
Because: Maximum hardness for P-1 after heat treatment should be less than or equal to:
Sweet Service = 225 BHN Sour Services = 200BHN
Welding Consumables shall have a SAP ID number to show their purchase from an approved vendor
for specific consumable.
Drying & Re-Drying
A 5.1 A 5.5
Low Hydrogen Electrode Low Hydrogen Electrode
60XX 70XX & 80XX
Dried: 260-430 For 2-Hrs Dried: 370-430 For 2-Hrs
The drying step may be deleted if the electrodes are supplied in the dried condition in a hermetically
sealed metal can with a positive indication of seal integrity or vacuum sealed package.
Exposure Limitation:-
A 5.1 A 5.5
Alloy Low Hydrogen Electrode Alloy Low Hydrogen Electrode
60XX 70XX & 80XX
Not be exposed if:- Not be exposed if:-
4-Hr Open in Atmosphere 2-Hr Open in Atmosphere
8-Hr in Portable Oven minimum 65oC 4-Hr in Portable Oven minimum 65oC
Re-Conditioning:
Electrodes exposed to the atmosphere for less than the permitted time period may be returned to a
holding oven maintained at 120°C minimum; after a minimum holding period of 4-hours at 120°C
minimum the electrodes may be reissued.
Contractor shall assure electrode issue control follows a "First In, First Out" Rule.
Check E6010 storage closely.
Zirconated (Brown) or Pure (Green) Use for AC (Cooper / Alloy, Mg, Mi, Plain Carbon, SS)
Thoriated (Red) Use for DC-ve (Steel & Most Metals)
Note: Ceriated (Orange) and Lanthanated (Gold) can be used in place of Thoriated.
Cutting and grinding contaminated and or oxidized tungsten electrode tips using the common
unacceptable practice of silicon carbide grinding wheels spreads contamination and does not produce
quality GTAW welds because of a tendency for tip fracturing & splintering & thus the need for
frequent redressing
Properly prepare new tungsten with diamond type cutting equipment specifically designed for
Tungsten (Tungsten Sharpener Model-Piranha, etc)
Welding Sequence & Pipe Handling meets SA workmanship requirements. Prevent any associated
NDE penalty (RT) with the process:
• For pipelines greater than 16 inch, two welders are used, operating simultaneously and in
opposite quadrants
• Second or hot pass is added ASAP after completing root pass.
• Time shall not exceed 5 minutes (Vertical down, Cellulose electrode)
• Time shall not exceed 15 minutes for vertical up welding.
• Hot pass was made while pipe was fully supported (tractor, etc)
• The pipe shall not be lifted or moved during welding.
• Partially welded joints shall not be lifted or lowered into the ditch.
• The weld joint shall be completed within 24 hours of starting.
Weld Each weld is marked with the welder's identification and is identified in accordance with
identification drawing/weld map
Ensure welds are suitable for all NDT (profile, cleanness etc)-
Weld appearance
Visually inspect welds and sentence in accordance with Code
Dimensional survey Check dimensions are in accordance with drawing/Code
Drawings Ensure any modifications are included on as-built drawings
NDT Ensure all NDT is complete and reports are available for records
Repairs Monitor in accordance with the Procedure
PWHT (if required) Monitor for compliance with Procedure (check chart record)
test (if required) Ensure test equipment is calibrated Monitor test to ensure compliance
Pressure/load
with Procedure/Code. Ensure reports/records are available
Documentation Ensure all reports/records are completed and collated as required
Records
As per ASME Sec-IX: All weld passes thickness less then <13mm
Weld Bead Thickness: 3-Times of Dia of filler wire or Electrode
A – Numbers are used to identify the weld metal chemical composition of ferrous metals.
ANALYSIS
A.
Types of weld deposit C Cr Mo Ni Mn Si
NO.
1 Mild steel 0.20 --- --- --- 1.60 1.00
2 Carbon-Molybdenum 0.15 0.50 0.4-0.65 --- 1.60 1.00
3 Chrome (0.4% to 2%)-Mo 0.15 0.4-2.0 0.4-0.65 --- 1.60 1.00
4 Chrome (2% to 6%)-Mo 0.15 2.0 –6.0 0.4-1.50 --- 1.60 2.00
5 Chrome (6% to 10.5%)-Mo 0.15 6.0-10.5 0.4-1.50 --- 1.20 2.00
6 Chrome-Martensitic 0.15 11-15 0.70 --- 2.0 1.00
7 Chrome-Ferritic 0.15 11-30 1.0 --- 1.0 3.00
8 Chrome-Nickle 0.15 14.5-30 4.0 7.5-15 2.50 1.00
9 Chrome-Nickle 0.30 25-30 4.0 15-37 2.50 1.00
10 Nickle to 4% 0.15 --- 0.55 0.80-4.0 1.70 1.00
11 Mn-Mo 0.17 --- 0.25-0.75 0.85 1.25-2.25 1.00
12 Ni-Cr-Mo 0.15 1.50 0.25-0.80 1.25-2.80 0.75-2.25 1.00
F – Numbers:
F – Numbers are used for filler metal designation & grouping of electrodes & welding rods.
It is based essentially on their usability characteristics.
The main purpose of F – Numbers grouping is to reduce the number of welding procedure and performance
qualifications, where this can logically be done.
P – Numbers:-
To reduce the number of welding procedure qualification required, BASE METALS have been assigned P –
Numbers. Weld ability and Mechanical properties. (P No.2 is not applied)
CSA-53 to SS-304L
13 mm>
Pll -
o 704°C to 760°
A335-P-11 P-11 = 150 C 260°C
Alloy o High Alloy
A335-P-22 P-22=149 C P22 -
730°C to
300°C
790°C
Aluminum
SB 241 Gr 5083
P No.21 to
25
Welder Qualification:-
ASME Sec-IX & SAEP-324 must be qualified
JCC's shall be returned to PID when contractor welder goes on home leave or is terminated from the
project. NOTE: Contractor welders that return to work within three months from home leave (to the
same project) may be reinstated without retesting.
QW-452.3
Groove Weld Diameter Limits
OD Qualified, in (mm)
OD of Test Coupon in (mm)
Min Max
½" ½" Welded Test Unlimited
¾" ¾" Welded Test Unlimited
1" to 2⅞ " (73mm) 1" Unlimited
2⅞ " (73mm) to above 2⅞ " (73mm) Unlimited
OD Qualified, in (mm)
Test Coupon in (mm)
Min Max
<10mm 1.5 mm 2 T Deposit Thickness
>10mm to <13mm 1/2 t 2 T Deposit Thickness
>13mm 1/2 t Unlimited
Minimum thickness that applies to welders qualified is it 1/2 t thickness. If the coupon's thickness is
more than 13mm and he deposits a minimum of 3 layers, he is qualified unlimited.
Position Qualification:
A. 0 - 0.2% Level A
B. >0.2% - 0.4% Level B
C. >0.4% - 0.5% Level C
D. > 0.5% Level D, Revoke
In all cases, Welder performance should target “A” Classification results with the lowest possible Linear &
Joint Repair Rates achievable.
Continuing Process Improvement, Cost Effectiveness is acceptable for Cat. A & B welders.
Cat. C welders are not cost effective and require close supervision)
8. Level D Welders
Welders may exceed the 7.5% joint WRR weekly for a maximum period of 2-3 weeks with close
surveillance on all repairs.
Additional supervision / additional NDT (to 100%) is required until consistent results of 7.5% WRR or less
(joint repair rate) are achieved.
If WRR target is not achieved within 2-3 weeks, the options are: (i) welder may be considered candidate
for re-training and retesting or (ii) revoke qualification and remove from production work.
An example of a complete piping line class designator is "3CS1P11". This designator specifies an
ASME pressure class 300, carbon steel piping system with 1.6 mm corrosion allowance designed for
general process service & fifth field is optional Project Specific requirements.
Exceptions, modification, or additions may be made to the base piping line class to meet specific
requirements through the use of the fifth field location, i.e., modification suffix. Line classes with listed
fields shall be approved the Chairman of the Piping Standards Committee.
A (Air). H (Hydrogen).
BBD (Boiler Blow down). HCL (Hydrochloric Acid).
BD (Blow Down). HO (Hydraulic Oil).
BFW (Boiler Feed Water). HSG (Hydrogen Sulfide Gas).
C (Chemical). IA (Instrument Air).
CA (Caustic). LO (Lube Oil).
CAS (Caustic sewer). PA (Process Air).
CS (Chemical Sewer). RL (Relief Line).
CW (Chilled Water). RW (Raw Water).
CWR (Cooling water return) S (Steam).
CWS (Cooling water supply) SA (Sulfuric Acid).
DMW (Dematerialized Water) SF (Sulfur).
DSW (Distilled water). SR (Sewer Storm).
DW (Drinking water). SW (Salt Water).
EIA (Emergency Instrument Air) SWS (Sanitary Sewer).
FG (Fuel Gas). TW (Treated Water).
HGH (High Pressure Fuel Gas) UA (Utility Air).
FGL (Low Pressure Fuel Gas). UW (Utility Water).
FLO (Flushing Oil). W (Water).
FW (Fire Water). WW (Waste Water).
Tack Weld:
Thickness = 3.2 to 4.8
Length = 12.5 to 25.4
For field welding, remote Current controls shall be used if welding is more than 30 m from welding
power source or when welders are working in "remote" locations (e.g., on an elevated pipe-rack).
Surface Porosity, uneven Profile and undercut remove by grinding.
Inert gas flow time over an extinguishing arc follows the "15 second rule" = Zero Contamination
Note: 15* seconds cooling under gas flow will result in zero oxidation
PWHT
Code exemptions for PWHT for P-No. 7 & P-No. 8 materials are not allowed at Saudi Aramco.
PWHT all P-No. 4 & P-No. 5 mat'l welds & pressure boundary attachments when Sour Service exists
or nominal chrome content is above 1.5%.
Note: P No. 7 (High Alloy Ferritic stainless steel) & 8 (Austenitic stainless steel.) Not Done PWHT
Example:
19mm
19/25 for Convert in Inch : 0.76
0.76 x 222 = 168.72 oC/Hr
Insulation shall be applied a minimum of 300 mm on either side of the weld that is to be PWHTed. The
insulation shall not be removed before the temperature has cooled to below 150°C. The ends of open lines
shall be closed off in order to eliminate drafts or air circulation that could lower the temperature on the
inside surface of the joint unless the internal surface is also insulated.
Socket Welding:
Gap Control Procedure & Inspection
Check all Individual Axial gaps on socket-welded joints before welding.
Fit-up follows an approved Gap Control procedure!
Pre-Welding = 1.5 - 3 mm gap exists
SA CSD recommends 3 mm target gap on fit-ups.
After welding: Maximum gap of 50% engagement is acceptable.
Note: At a minimum, 50% engagement is obtained, this easily verified
If SMAW welding is used for socket welding, the largest size of electrode permitted is 3.2mm Dia.
The axial gap between male and female component, shall be maximum of 3 mm and minimum of 1.5
mm. This gap is required prior to welding. (It does not apply to piping already installed and welding
was completed successfully)
NOTE: Internal tapering (ASME B31.3) by machining, back welding, or a combination may be used
to correct any misalignment. If external surfaces of the components are not aligned, the weld shall be
tapered between them. [ASME B31.3, Para. 328.4.3 (2).
Welding Procedure used is approved & socket weld 2-pass minimum welding sequence (tacking
method, root pass, weld profile/form detail) is available to provide the welder adequate instruction in
the field.
Welder has been qualified for socket welding by passing RT on the first three production welds.
Full penetration groove joint included angles < 30 degrees, except portions of compound bevels, shall
not be used without approval.
Minimum distance between parallel butt welds shall be 25 mm or three times the wall thickness of the
joint, whichever is greater.
A tie-in welds is a weld that connects the pipeline string to another or the pipeline under construction or
to an anchor. The segment of the pipeline between the tie-in points remains fully restrained at the
tie-in temp., if shrinkage of the segment is prevented by adequate anchorage at both ends. For normal daily
temp., variations during construction, one of the following will provide adequate:
The pipes to be tied-in shall be kept near to each other. During the peak temperature of the day, the pipe
shall be marked and cut. The bevel end shall be brought together and aligned using an external clamp. The
joint shall be welded using dolly mix procedure.
The pipe string shall not be lifted to take the slack in the string. The tie-in temperature shall be equal to or
greater than the highest mean temperature of the previous three days.
Notice of inspection shall be issued to Project Inspection 24 hours in advance for witnessing tie-ins.
Detailed Tie-in Procedure will be submitted to Company Representative, Tie-in Package shall be
submitted for approval by Saudi Aramco PMT and Project Inspection.
What is the thumb rule to calculate spanner size for given bolt? Answer:
1.5 x diameter of Bolt
What is the thumb rule to calculate Current required for Welding? Answer:
Current (Amp) = [Diameter of Electrode (mm) X 40] + 20