NATIONAL ECONOMICS UNIVERSITY

INTERNATIONAL SCHOOL OF MANAGEMENT AND ECONOMICS

HIGHER NATIONALS
BTEC HIGHER NATIONAL DIPLOMA IN BUSINESS (RQF)

Unit Code, Number and Title


D/508/0491 – Unit 6: Managing a Successful Business Project

Semester and Academic Year Semester 2, Academic year 2021-2022

Unit Assessor(s) Ms. Pham Tran Minh Trang; Mr. Nguyen Van Dai
Ms. Pham Thu Van; Ms. Phan Thu Trang

Assignment Number and Title MSBP: Managing a Research Project (Assignment 1 of 1)


Logbook 2

Submission Date 5.00pm 16/03/2022

Student Name Nguyen Le Minh Anh

NEU Student ID 10200539 Pearson ID


Plagiarism is a particular form of cheating. Plagiarism must be avoided at all costs and students who
break the rules, however innocently, may be penalised. It is your responsibility to ensure that you
understand correct referencing practices. As a university level student, you are expected to use
appropriate references throughout and keep carefully detailed notes of all your sources of materials
for material you have used in your work, including any material downloaded from the Internet. Please
consult the relevant unit lecturer or your course tutor if you need any further advice.
I certify that the assignment submission is entirely my own work and
Student declaration I fully understand the consequences of plagiarism. I understand that
making a false declaration is a form of malpractice.

Student name / Signature Anh Date:


Logbook 2
Project Management Plan

Please provide the draft work of your PMP with suggested format below:

1. Research Aim and Objectives (at least 3 objectives, research aim must align with research
question)
- Research Aim:
+ To explore work-life balance to create a flexible, supportive work environment to engage
employees and maximize human resource performance in the banking sector.
- Research objective:
+ Research objective 1: Discuss the working environment in the digital transformation
period of the financial - banking industry in general and Vietnamese banks in particular.
+ Research objective 2: Analyze employee performance in the digital era in the banking
sector.
+ Research objective 3: Propose work-life balance arrangements to improve the
performance of human resources to match the current digital transformation trend of banks.

2. WBS and GANTT charts


WBS needs to have at least 4 levels (parent – child relationship)
 Level 1: Project Purpose
 Level 2: Project Objectives
 Level 3: Activities
 Level 4: Tasks

WBS:

GANTT:
Milestones:

Phase Starting Date Ending date


Introduction 1/3/2022 8/3/2022
Literature review 8/3/2022 30/3/2022
Research methodology 30/3/2022 6/4/2022
Data collection 6/4/2022 13/4/2022
Data analysis 13/4/2022 28/4/2022
Dicussion 28/4/2022 14/5/2022

WBS and GANTT chart must be consistent (include Milestones)

(Project Libre for GANTT chart)


3. Resource and Cost Management Plan
Resource Expected Costs
Internal Resource

Human: me

Knowledge that
lecturers and tutors
teach.

Books,articles,reports
which was found in
google scholar

External Resource
200.00-VND-300.000VND: to friends who help me providing the
Human: Participants survey to participants.
who take part in the
research, My parents 29.000 VND/gasoline litre

Gasoline money for 200.000VND: to pay for meals


transport
slightly 3.000 VND a minutes to call
Fee for meal

Fee for calling


4. Risk Management Plan
Risks Likelihood Impact Weight = Risk Note
(negative) (Low/Medium/High) (Low/Medium/High) Likelihood x Response
Comments (1-2-3-4-5) Impact Plan
(0.25/0.5/0.75)

Cannot connect 0.5 3 1.5 Mitigate Make a


with participants meeting
appointment
ahead of
time.

Send email
or call to
notify
participants
2-3 days
before data
collection
period
Lose Wifi 0.5 2 1 Accept Use 4G
network
service
instead

Use public
wifi or wifi in
bars,
restaurants.
The data is not 0.5 5 2.5 Mitigate Search data
accredited or on sources
proved such as
google
scholar,
academic
websites, ...
Forget to save the 0.25 5 1.25 Avoid Made on
report Google Docs,
has auto-
save mode
Late submission of 0.25 3 0.75 Avoid Remember
reports the
submission
deadline and
complete the
report early
to
to upload
one day
ahead of
time to avoid
system
errors,
network
errors,...

5. Quality Management Plan


Project Deliverables Deliverable Quality Standards/ Criteria Quality Control Activity
Literature review - Update data (from 2 years ago to - Check the date books,
present) reports were created and
- Consult books, articles, reports made published
and published in the last 5-10 years. - Search for recognized
- Data sources must be authoritative, data sources
factual. - The writer has enough
knowledge about the
research topic
Methodlogy - Use quantitative methods - Contacting participants
- Using indirect measurement by to ensure the number of
survey questionnaire survey takers
- Limited to 100 participants

Questionare - Ask questions that are relevant to - Create a questionnaire


the purpose of the study - Collect answers from
- The questions are designed to participants
achieve understandable goals for - Provide accurate
respondents, thereby exploiting data information necessary
for research

6. Stakeholder Management Plan


Stakeholder Area of influence/ Project Engagement Type of Frequency
interest/role phase approach information
required
Mr.Dai - Guide logbooks All phase Lecture’s class - Logbook 1- Weekly
(Lecture) - Provide Email 5
knowledge and M.Teams - PMP
feedbacks - Final Reprt
- Support in the
process of making
research report.
- Give mark
Ms.Van - Guide logbooks All phase Tutor’s class - Logbook 1- Weekly
(Tutor) - Provide Email 5
knowledge and M.Teams - PMP
feedbacks - Final Reprt
- Support in the
process of making
research report.
- Give mark
Parents -Assisting with Data Phone number The Sometimes
participant contact collection Zalo, message, background
call information
about
participants

Readers -Consult the Final reprt Email Topic of the Based on


research Phone number research redear’s
Zalo, message, times.
call