Professional Documents
Culture Documents
MALAYSIA
HOSPITAL MELAKA
MONTHLY
ENERGY MANAGEMENT REPORT
For
Name : Mohamad Izhan Bin Name: Mohamad Azan Bin Name: Ghafar bin Jenal
Kamaruzaman Fazil Designation:Facility Manager
Designation : Energy Designation: Registered
Engineer Electrical Energy Manager
HOSPITAL MELAKA
DOCUMENT MONTHLY ENERGY MANAGEMENT REPORT VERSION 2.0
TYPE NUMBER
REPORT 28/2/17 Page 2 of 53
PERIOD
Table of Content
LIST OF ABBREVIATIONS..............................................................................3
1.0 EXECUTIVE SUMMARY........................................................................4
2.0 HOSPITAL PROFILE.............................................................................5
3.0 HOSPITAL INFORMATION.....................................................................6
4.0 ENERGY POLICY.................................................................................9
5.0 ENERGY MANAGEMENT COMMITTEE..................................................10
6.0 ENERGY MANAGEMENT MATRIX.........................................................11
7.1 BUILDING ENERGY INDEX AND ENERGY EFFICIENCY INDEX (EEI).............................14
7.2 ENERGY CONSUMPTION BY EACH EAC...............................................................18
7.3 ENERGY PURCHASING HISTORY........................................................................25
7.4 INDEPENDENT ENERGY VARIABLE AND STATIC FACTORS......................................34
7.4.1 LIST OF STATIC FACTORS..............................................................................38
7.5 BASELINE AND ADJUSTED BASELINE.................................................................42
8.0 PART B – ENERGY CONSERVATION MEASURES...........................................46
8.1 PROPOSED ENERGY CONSERVATION MEASURES...................................................46
8.2 LIST OF ENERGY CONSERVATION MEASURES (ECMS) ACTIVITIES / PROJECTS..............49
8.3 LIST OF TRAINING ACTIVITIES................................................................................50
9.0 PART C – ECMS FINANCIAL AND PURCHASING STATUS................................51
10.0 PART D – IMPROVEMENT ACTIONS..........................................................52
10.0 CONCLUSION.......................................................................................53
ATTACHMENT...........................................................................................55
2|Page
HOSPITAL MELAKA
DOCUMENT MONTHLY ENERGY MANAGEMENT REPORT VERSION 2.0
TYPE NUMBER
REPORT 28/2/17 Page 3 of 53
PERIOD
LIST OF ABBREVIATIONS
3|Page
HOSPITAL MELAKA
DOCUMENT MONTHLY ENERGY MANAGEMENT REPORT VERSION 2.0
TYPE NUMBER
REPORT 28/2/17 Page 4 of 53
PERIOD
Justification
Energy saving for the current month is 2.54% which mean that the actual BEI is lower than
the BEI baseline by 2.54%.
4|Page
HOSPITAL MELAKA
DOCUMENT MONTHLY ENERGY MANAGEMENT REPORT VERSION 2.0
TYPE NUMBER
REPORT 28/2/17 Page 5 of 53
PERIOD
Table 1.0 below shows the summary on the Hospital Melaka profile based on the format
5|Page
HOSPITAL MELAKA
DOCUMENT MONTHLY ENERGY MANAGEMENT REPORT VERSION 2.0
TYPE NUMBER
REPORT 28/2/17 Page 6 of 53
PERIOD
Hospital Melaka was built in the early 1930s with the construction of the Straits
Settlement costs totaled $ 2.5 million and was inaugurated by Sir Cecil Clementi , the Straits
Governor on 12th February 1934. The opening ceremony was also attended by Andrew
Caldecott (British Colonial Secretary) , Major General Lewin (Commanding Officer) , Dr RD
Fitzgerald (Director of Medical Treatment and Health) , N.W. Millington (Resident
Counselor) and distinguished guests including 700 people of Malacca .
Currently, there are 8 Energy Account Center (EAC) that has been established for
Hospital Melaka. The information for each EAC are as follow:
7|Page
HOSPITAL MELAKA
DOCUMENT MONTHLY ENERGY MANAGEMENT REPORT VERSION 2.0
TYPE NUMBER
REPORT 28/2/17 Page 8 of 53
PERIOD
8|Page
HOSPITAL MELAKA
DOCUMENT MONTHLY ENERGY MANAGEMENT REPORT VERSION 2.0
TYPE NUMBER
REPORT 28/2/17 Page 9 of 53
PERIOD
9|Page
HOSPITAL MELAKA
DOCUMENT MONTHLY ENERGY MANAGEMENT REPORT VERSION 2.0
TYPE NUMBER
REPORT 28/2/17 Page 10 of 53
PERIOD
10 | P a g e
HOSPITAL MELAKA
DOCUMENT MONTHLY ENERGY MANAGEMENT REPORT VERSION 2.0
TYPE NUMBER
REPORT 28/2/17 Page 11 of 53
PERIOD
Target
Actual
11 | P a g e
HOSPITAL MELAKA
DOCUMENT MONTHLY ENERGY MANAGEMENT REPORT VERSION 2.0
TYPE NUMBER
REPORT 28/2/17 Page 12 of 53
PERIOD
Referring to Table 3.0 Energy Management Matrix, based on the assessment done
during preliminary audit, it is found that Hospital Besar Melaka is on level two for four
categories. The energy policy has been signed by the Hospital Director. Besides, the Energy
Manager in post reporting to ad-hoc committee but the line management and authority are
unclear. In term of energy information system, the monitoring and targeting reports is based
Hospital Melaka scores about two in motivation and investment. Therefore, this
from the top management and formulate the strategy to develop a committee to execute the
energy program and monitor the result. In marketing aspect, the level had increase from level
one to level two. An awareness campaign had been done on 25th April 2016. This campaign
is to train the hospital staff about energy management. A person in charge need to be
The table of Energy Management Matrix score will be revised base on agreement
12 | P a g e
HOSPITAL MELAKA
DOCUMENT MONTHLY ENERGY MANAGEMENT REPORT VERSION 2.0
TYPE NUMBER
REPORT 28/2/17 Page 13 of 53
PERIOD
13 | P a g e
HOSPITAL MELAKA
DOCUMENT MONTHLY ENERGY MANAGEMENT REPORT VERSION 2.0
TYPE NUMBER
REPORT 28/2/17 Page 14 of 53
PERIOD
The Gross Floor Area (GFA) is being used as a factor for the calculation of Building
Energy Index and Energy Efficiency Index (EEI). The graph below shows the trending for the
the BEI and Energy Efficiency Index over the period of one year. The formula that has been
14 | P a g e
HOSPITAL MELAKA
DOCUMENT MONTHLY ENERGY MANAGEMENT REPORT VERSION 2.0
TYPE NUMBER
REPORT 28/2/17 Page 15 of 53
PERIOD
152.00
151.00
150.00
149.00
148.00
Jan-16 Feb-16Mar-16 Apr-16May-16 Jun-16 Jul-16 Aug-16Sep-16 Oct-16 Nov-16 Dec-16 Jan-17
Months
Figure 4.1: Graph trend for BEI Monthly from January 2016 to February 2017
11.64
11.20 EEI Baseline: 12.56kWh/sqm
10.50
MONTHS
EEI (kWh/sqm)
Figure 4.2: Graph trend for EEI January 2016 to January 2017
15 | P a g e
HOSPITAL MELAKA
DOCUMENT MONTHLY ENERGY MANAGEMENT REPORT VERSION 2.0
TYPE NUMBER
REPORT 28/2/17 Page 16 of 53
PERIOD
As showed in figure 4.0 the value of building energy index(BEI) for 2014, 2015 and
2016 is 148 kWh/sqm/yr, 151 kWh/sqm/yr and 151 kWh/sqm/yr respectively, from those
value it can be concluded that the trend is increasing from year 2014 to 2015. Comparing BEI
for 2015 and 2016 the value of BEI is constant. It can tell us that starting from 2016 the
energy consumption for hospital Melaka is being controlled by the building owner even
though there are increase value of Cooling Degree Days which reflect that Air Conditioning
From the graph in Fig. 4.1, the overall monthly Building Energy Index (BEI) for
Hospital Melaka show a fluctuation trend from January 2016 until January 2017. The baseline
for the monthly BEI are taken from July 2014 until June 2015. The baseline value is 155.01
kWh/m². On January 2017, the BEI show some decrement from December 2016, 151.33
kWh/m² to 151.07 kWh/m². From January 2016 to January 2017, all the BEI are lower than
the baseline value. Month July 2016 still holds the lowest BEI value which is 150.95 kWh/m²
and month March 2016 is the highest BEI value recorded which 151.93kWh/m².
From the graph in Fig. 4.2, the overall Energy Efficiency Index (EEI) shows a
fluctuation trend from January 2016 until January 2017 for Hospital Melaka. The baseline for
the EEI are taken from January 2015 to December 2015. The baseline value is 12.56 kWh/m².
On January 2017, the EEI maintain same with December 2016, 12.55 kWh/m 2 which is still
lower than the baseline. From January 2016 to January 2017, there are 7 months where the
value is lower than the baseline which is on February 2016, June 2016, July 2016, September
2016, November 2016, December 2016 and January 2017. Month February 2016 still holds
the lowest EEI value which is 11.64 kWh/m 2 but then soar up to 13.4 kWh/m 2 on the
following month. Lowest value of EEI is on February 2016 is due to lowest billing days in the
16 | P a g e
HOSPITAL MELAKA
DOCUMENT MONTHLY ENERGY MANAGEMENT REPORT VERSION 2.0
TYPE NUMBER
REPORT 28/2/17 Page 17 of 53
PERIOD
electricity bill which is 29 days. On March 2016, the EEI value is the highest value ever
recorded which 13.40 kWh/m2 this is due the highest value of Cooling Degree Days that
17 | P a g e
HOSPITAL MELAKA
DOCUMENT MONTHLY ENERGY MANAGEMENT REPORT VERSION 2.0
TYPE NUMBER
REPORT 28/2/17 Page 18 of 53
PERIOD
EAC 1
9000 6,752
7,826
8000 6,768 6,653
7,031 7,041
7000
6000
5000
kWh/Day
4000
3000
2000
1000
0
16 16 r-16 r-16 16 16 l-16 16 16 t-16 16 16 17
a n- e b- a p a y- un- J u ug- e p- c ov- e c- a n-
J F M A M J A S O N D J
Month
Figure 5.1 Energy Consumption for Administration Block, Cafeteria, & Komplek Ilmu
From figure show the energy consumption per day from January 2016 until January 2017.
The trend show some fluctuated on the energy consumption. The consumption trend we can
see it decreasing from month of October 2016 to January 2017. The decrement can be assume
due to the total of outpatient trend that show decreasing from 35,218 for October 2016 to
23,327 for January 2017. It indirectly reduces the energy consumption on this area. There are
some data losses and meter offline on April 2016 to October 2016 due to the damage of
18 | P a g e
HOSPITAL MELAKA
DOCUMENT MONTHLY ENERGY MANAGEMENT REPORT VERSION 2.0
TYPE NUMBER
REPORT 28/2/17 Page 19 of 53
PERIOD
EAC 2
6,360
6,656 6,356 6,251
7000 6,356
6,048
6000
5000
4000
kWh/day
3000
2000
1000
0
16 16 r-16 r-16 -1
6 16 l-16 16 16 t-16 16 16 17
n- b- a p ay n- u g- p- c ov- e c- n-
Ja Fe M A M J u J Au S e O N D J a
Months
For figure above, the energy consumption for EAC 2 are show decreasing trend from month
of December 2016 to January 2017. The decrement is by 3,265.25 kWh or 1.66 %. This
decrement can be assumed due to the BOR that show some decrement from 82.27% on
December 2016 to 79.47% in the January 2017. Indirectly it contributes to the decrease of
energy consumption. There are some data losses and meter offline on April 2016 to October
19 | P a g e
HOSPITAL MELAKA
DOCUMENT MONTHLY ENERGY MANAGEMENT REPORT VERSION 2.0
TYPE NUMBER
REPORT 28/2/17 Page 20 of 53
PERIOD
EAC 3
700 626 594
600 570 559
506 504
500
400
kWh/Day
300
200
100
0
16 16 16 16 16 16 16 16 16 16 16 16 17
a n- eb- ar- pr- ay- un- Jul- ug- ep- ct- ov- ec- an-
J F M A M J A S O N D J
Month
Energy consumption for EAC 3 which cover area of Pump House and VVIP ward from
months December 2016 and January 2017. There are some data losses and meter offline on
April 2016 to October 2016 due to the damage of dongle and it intermittent in Wi-Fi signal.
EAC 4
12000 11,098
10000 8,449 8,945
8000
kWh/Day
6000
4000
2000
0
Nov-16 Dec-16 Jan-17
Month
Figure 5.4 Energy Consumption for EAC 4(Chillers at Main Plant Room)
Above figure the energy consumption for EAC 4. As we can see, the trend is fluctuated.
There are some increasing on the energy consumption for months of December 2016 until
January 2017. The increasing of the chillers consumption due to the increment of
20 | P a g e
HOSPITAL MELAKA
DOCUMENT MONTHLY ENERGY MANAGEMENT REPORT VERSION 2.0
TYPE NUMBER
REPORT 28/2/17 Page 21 of 53
PERIOD
consumption at Air Handling Unit (AHU). As we can see the services of cooling tower that
was started in Dec 2016 contribute to lower energy consumption following by the next month.
EAC 5
14400 14,252
14200
14000
13800
kWh/Day
13600 13,467
13400 13,335
13200
13000
12800
Nov-16 Dec-16 Jan-17
Month
Above figure shows energy consumption for EAC 5, which cover main wards and critical unit
in Wad Aras that are OT, ICU, CCU, MRI, DC, Hospimart, MSB2A-AHU,KTC,SCN, LAB,
Blood Bank, Labour Room, Dental, Farmasi, Unit Hasil, PABX, Specialist Clinic, A&E and
also X-Ray department or in other word covers New Block except for Wad Aras and Forensic
Department. The trend of energy consumption are decreasing from November 2016 to
January 2017. This is because of the total operation at Operation Theatres that had been done
show some reduction from 3108 cases in November 2016 to 2859 cases in December. It
reduce to1354 cases in January 2017. From the figure above number of OT cases give
21 | P a g e
HOSPITAL MELAKA
DOCUMENT MONTHLY ENERGY MANAGEMENT REPORT VERSION 2.0
TYPE NUMBER
REPORT 28/2/17 Page 22 of 53
PERIOD
EAC 6
1700
1650
1600 1,571
kWh/day
1550 1,537
1,516
1500
1450
1400
Nov-16 Dec-16 Jan-17
Month
EAC 6 as figure above is the energy consumption for Air Handling Unit that covers
AHU room in Hospital Melaka. We can see that the trend is increasing about from December
2016 to January 2017. Although the surrounding temperature (CDD) on January 2017 is
decrease from 290ºC to 280ºC but number in patient are increase compare to December 2016.
The number in patient in December are 6,169 while in January are 26,877. With the increase
of number in patient, it indirectly also increase the usage of air conditioning system to operate
in order to get the comfort level and setting temperature. Increment in January 2017 compared
to December 2016 is by 3.6%. Proposal of installation of timer at the Specialist Clinics can
22 | P a g e
HOSPITAL MELAKA
DOCUMENT MONTHLY ENERGY MANAGEMENT REPORT VERSION 2.0
TYPE NUMBER
REPORT 28/2/17 Page 23 of 53
PERIOD
EAC 7
900
800 748 767
700 631
600
kWh/day
500
400
300
200
100
0
Nov-16 Dec-16 Jan-17
Month
Figure 7.2.7 covers energy consumption for Pathology department in Hospital Melaka as we
can see the trend is increasing from month of December 2016 to January 2017. The increasing
is due to the total of lab test are increase compare to December. The total lab test for the
December are 92,684 while total lab test for January are 253,348.
EAC 8
160 148
138
140
120 115
100
kWh/day
80
60
40
20
0
Nov-16 Dec-16 Jan-17
Month
23 | P a g e
HOSPITAL MELAKA
DOCUMENT MONTHLY ENERGY MANAGEMENT REPORT VERSION 2.0
TYPE NUMBER
REPORT 28/2/17 Page 24 of 53
PERIOD
EAC 8 covering the area of CSSD (Central Sterile Service Department) as in the
above figure there is decrement from December 2016 to January 2017. This reflect with the
number of operation on January 2017 that show some decrement compare to the number of
operation on December 2016. So, the equipment that need undergo sterile is less compare to
previous month.
24 | P a g e
HOSPITAL MELAKA
DOCUMENT MONTHLY ENERGY MANAGEMENT REPORT VERSION 2.0
TYPE NUMBER
REPORT 28/2/17 Page 25 of 53
PERIOD
Table 4.0 below shows the power purchasing history for the year 2015 while table 4.1 shows the power purchasing from January 2016
until December 2016. The graph bar in Fig. 6.1 and Fig. 6.2 was plotted to analyze the electrical energy consumption and the total purchase cost
Table 4.1: Power purchasing history from January 2016 until December 2016.
HOSPITAL MELAKA
DOCUMENT MONTHLY ENERGY MANAGEMENT REPORT VERSION 2.0
TYPE NUMBER
REPORT 28/2/17 Page 27 of 53
PERIOD
27 | P a g e
HOSPITAL MELAKA
DOCUMENT MONTHLY ENERGY MANAGEMENT REPORT VERSION 2.0
TYPE NUMBER
REPORT 28/2/17 Page 28 of 53
PERIOD
Figure 6.1: Bar graph for electrical energy consumption for 2015
28 | P a g e
HOSPITAL MELAKA
DOCUMENT MONTHLY ENERGY MANAGEMENT REPORT VERSION 2.0
TYPE NUMBER
REPORT 28/2/17 Page 29 of 53
PERIOD
Figure 6.2: Bar graph for electrical energy consumption from January 2016 to January 2017
29 | P a g e
HOSPITAL MELAKA
DOCUMENT MONTHLY ENERGY MANAGEMENT REPORT VERSION 2.0
TYPE NUMBER
REPORT 28/2/17 Page 30 of 53
PERIOD
1,600,000
1,400,000
1,200,000
1,000,000
kWh
800,000
600,000
400,000
200,000
0
January February March April May June July August September October November December
Months
Figure 6.3: Bar graph of Monthly Energy Comparison from 2015 until February 2017
30 | P a g e
HOSPITAL MELAKA
DOCUMENT MONTHLY ENERGY MANAGEMENT REPORT VERSION 2.0
TYPE NUMBER
REPORT 28/2/17 Page 31 of 53
PERIOD
750,000.00
Monthly Energy Cost for 2015, 2016 and 2017
700,000.00
650,000.00
600,000.00
550,000.00
RM
500,000.00
450,000.00
400,000.00
350,000.00
300,000.00
January February March April May June July August September October November December
Months
Figure 6.4: Bar graph of total purchase cost in 2015 until February 2017
31 | P a g e
HOSPITAL MELAKA
DOCUMENT MONTHLY ENERGY MANAGEMENT REPORT VERSION 2.0
TYPE NUMBER
REPORT 28/2/17 Page 32 of 53
PERIOD
Figure 6.5: Bar graph of Maximum Demand in 2015 until February 2017
From the figure above it can be seen that energy demand trend is increasing by comparing the reading from 2015 to January 2017.
32 | P a g e
From Fig. 6.1 and 6.2, shows the usage of energy consumption for Off peak and On
peak for 2015 and 2016 include Januari 2017, the time for On Peak is from 8:00am until
10:00pm and from 10:00pm until 8:00am for Off peak. The highest recorded of energy
consumption during Off peak in 2015 is on May 2015 which is 611,605kWh, and for 2016 is
December 2016 which is from 1,580,396 kWh to 1,580,510 kWh, it is 114kWh or 0.007%. In
term of cost, the increment is RM 166.01. Besides that, some variable factors such as
surrounding temperature or ambient temperature, number of laboratory test and number of in-
From Fig.6.5, the highest Maximum Demand (MD) was recorded in May 2016 which
is 3,110 kW. While for January 2017, the Maximum Demand (MD) recorded was 3,044 kW.
There is increment in maximum demand (MD) from December 2016 to January 2017 which is
from 3,042 kW to 3,044 kW increment by 0.07%. By comparing January 2016 and January
33 | P a g e
7.4 INDEPENDENT ENERGY VARIABLE AND STATIC FACTORS
Table 7.1 and 7.2 below shows the Independent Energy Variable for year 2015 and year 2016.
34 | P a g e
Energy Variables Table No.
Plant: Year 2016
Name of Variables
Month OT Maternity In Patient Out Patient Laboratory CDD Working Day Public Holiday School Holiday In Patient In Patient
No. of Operation No. of Delivery BOR % No. of Patient No. of Test °C Day Day Day No. of Patient Patient Days
January 3,568 956 83.74 36,088 96206 324 31 1 3 6,912 28,321
February 2,916 846 79.84 34,131 92007 288 29 2 0 6,289 25,260
March 3,054 871 83.39 38,753 123415 353 31 0 9 6,943 28,202
April 3,199 931 82.05 35,962 102625 350 30 1 0 6,284 26,855
May 3,069 873 82.05 37,031 96456 337 31 3 4 6,440 27,751
June 3,058 991 81.09 36,349 94246 309 30 2 12 6,253 26,540
July 3,075 1,008 80.72 33,949 94276 312 31 2 0 6,695 27,302
August 3,561 1,000 86.34 40,262 102504 329 31 1 0 6,998 29,202
September 3,292 973 85.56 36,356 90491 309 30 2 9 6,415 28,005
October 2800 966 82.55 35218 85092 319 31 3 0 6,362 27,919
November 3108 967 83.34 36559 87449 279 30 0 5 6,195 27,277
December 2859 912 82.27 35945 92684 290 31 2 31 6,169 27,825
35 | P a g e
HOSPITAL MELAKA
DOCUMENT VERSION
MONTHLY ENERGY MANAGEMENT REPORT 2.0
TYPE NUMBER
REPORT
31/01/17 Page 36 of 53
PERIOD
36 | P a g e
Table 7.1, 7.2 and 7.3 shows the value for each independent energy variables for 2015,
2016 and January 2017. The data was obtained from several departments to be analyse and
justifying the relationship it with the monthly electrical energy consumption in this hospital.
On January 2017, the number of operation in operating theater decrease from 2,859 to 1,354
of cases, it is a decrement by 52.64%. The number of maternity was also decrease from 912 to
869 or in other words decrease by 4.71%. The BOR percentage also decrease from 83.34% to
79.47% in other words it is a decreases by 3.87% . The Cooling Degree Days (CDD)
definition is a daily cumulative sum value of different for average ambient temperature
and base temperature or the number of degrees that a day's average temperature is
above 65o Fahrenheit@18DegC and people start to use air conditioning to cool their
buildings. Cooling Degree days comparing from December 2016 and January 2017 it is
290degC and 280degC respectively it is a decrement by 3.45%.
37 | P a g e
HOSPITAL MELAKA
DOCUMENT VERSION
MONTHLY ENERGY MANAGEMENT REPORT 2.0
TYPE NUMBER
REPORT
PERIOD
31/01/17 Page 38 of 53
Table 7.4: List of electrical appliances registered from August 2015 to June 2016
38 | P a g e
Table 7.5: List of electrical appliances registered from August 2015 – June 2016
Table 7.6: List of electrical appliances registered from August 2015 – June 2016
39 | P a g e
Table 7.7: List of electrical appliances registered from July 2016 – September 2016
Table 7.8: List of electrical appliances registered from July 2016 – September 2016
40 | P a g e
Table 7.4 until table 7.8 respectively shows the list of asset that had been registered /
installed from July 2015 till June 2016. While Table 5.7 and Table 5.8 shows the list of asset
that were registered / installed from July 2016 till September 2016. These list of electrical
applianes that were installed after the period of baseline are known as Static Data or Static
Factor. The total power consumption for the asset that had been registered / installed from
August 2015 till June 2016 are 37,468 kWh per month. While the additional power
consumption for the asset that had been registered / installed from July 2016 to September
2016 are 13,230 kWh per month. These values (Static Factor) must to be considered during
calculating the energy saving every month.
Energy Savings (kWh) =Adjusted Baseline + Static Data – Actual Energy Consumption
41 | P a g e
7.5 BASELINE AND ADJUSTED BASELINE
The period of the baseline was selected from July 2014 until June 2015 (12 months) to cater for all possible variations of energy variables
during the baseline period. The baseline and adjusted baseline as per below.
42 | P a g e
HOSPITAL MELAKA
DOCUMENT VERSION
MONTHLY ENERGY MANAGEMENT REPORT 2.0
TYPE NUMBER
REPORT
PERIOD
31/01/17 Page 43 of 53
1,637,596.0
Jul-2015 31 125913.21 1,637,596.00 155.01 149.62 139.51 3.47%
0
1,619,602.0
Aug-2015 31 125913.21 1,619,602.00 155.01 149.82 139.51 3.35%
0
1,582,662.0
Sep-2015 30 125913.21 1,582,662.00 155.01 149.94 139.51 3.27%
0
1,573,529.0
Oct-2015 31 125913.21 1,573,529.00 155.01 150.47 139.51 2.93%
0
1,522,919.0
Nov-2015 30 125913.21 1,522,919.00 155.01 150.18 139.51 3.12%
0
1,578,161.0
Dec-2015 31 125913.21 1,578,161.00 155.01 150.70 139.51 2.78%
0
1,612,850.0
Jan-2016 31 125913.21 1,612,850.00 155.01 151.24 139.51 2.43%
0
1,465,539.0
Feb-2016 29 125913.21 1,465,539.00 155.01 151.77 139.51 2.09%
0
1,686,962.0
Mar-2016 31 125913.21 1,686,962.00 155.01 152.25 139.51 1.78%
0
1,588,430.0
Apr-2016 30 125913.21 1,588,430.00 155.01 152.16 139.51 1.84%
0
1,653,525.0
May-2016 31 125913.21 1,653,525.00 155.01 151.93 139.51 1.99%
0
1,548,981.0
Jun-2016 30 125913.21 1,548,981.00 155.01 151.46 139.51 2.29%
0
1,573,594.0
Jul-2016 31 125913.21 1,573,594.00 155.01 150.95 139.51 2.62%
0
1,630,369.0
Aug-2016 31 125913.21 1,630,369.00 155.01 151.04 139.51 2.56%
0
1,570,472.0
Sep-2016 30 125913.21 1,570,472.00 155.01 150.94 139.51 2.62%
0
1,597,914.0
Oct-2016 31 125913.21 1,597,914.00 155.01 151.13 139.51 2.50%
0
43 | P a g e
HOSPITAL MELAKA
DOCUMENT VERSION
MONTHLY ENERGY MANAGEMENT REPORT 2.0
TYPE NUMBER
REPORT
PERIOD
31/01/17 Page 44 of 53
1,545,339.0
Nov-2016 30 125913.21 1,545,339.00 155.01 151.31 139.51 2.39%
0
1,580,396.0
Dec-2016 31 125913.21 1,580,396.00 155.01 151.33 139.51 2.37%
0
1,580,510.0
Jan-2017 31 125913.21 1,580,510.00 155.01 151.07 139.51 2.54%
0
44 | P a g e
Building Energy Index (BEI)
180.00
135.00
90.00
45.00
0.00
Dec-2013 Feb-2014 May-2014 Aug-2014 Oct-2014 Jan-2015 Apr-2015 Jun-2015 Sep-2015 Nov-2015 Feb-2016 May-2016 Jul-2016 Oct-2016 Jan-2017
45 | P a g e
HOSPITAL MELAKA
DOCUMENT VERSION
MONTHLY ENERGY MANAGEMENT REPORT 2.0
TYPE NUMBER
REPORT
PERIOD
31/01/17 Page 46 of 53
Table 6.0 show the energy consumption and adjusted baseline during the baseline
period which is from July 2014 to June 2015. While the table 6.1 show the adjusted baseline
and BEI saving that has been achieved every month.
Refer to the table 6.1, comparing with the BEI baseline, the BEI for January 2017
decrease from 155.01 kWh/m² to 151.07 kWh/m². From that decrement, the saving is
calculated and get 2.54% saving for January 2017.
46 | P a g e
HOSPITAL MELAKA
DOCUMENT ENERGY SAVING PROPOSAL – INSTALLATION OF VERSION 1.0
TYPE TIMER FOR AHU NUMBER
REPORT 2017 Page 47 of 55
PERIOD
8.1.1 Installation of Solar Hot Water at Block A New Building Hospital Melaka
8.1.1.1 Intoduction of Solar Hot Water and Working Principles of Centralized Solar Hot
Water System
Unlike conventional electric boiler that consumes a huge of amount of electricity to heat up
the water, the Centralized Solar Hot Water System capitalized on the free solar energy using
the high efficiency and high temperature evacuated tube solar collectors to produce the
heating effect.The construction of the evacuated tube solar collectors consists of a 2.5mm
thick borosilicate glass tube vacuum condition beneath the glass tube, aluminum absorber fin
coated with selective sputtering aluminum nitrate, and the copper heat pipe with the
protruding condenser as shown in Figure 8 below.
47 | P a g e
HOSPITAL MELAKA
DOCUMENT ENERGY SAVING PROPOSAL – INSTALLATION OF VERSION 1.0
TYPE TIMER FOR AHU NUMBER
REPORT 2017 Page 48 of 55
PERIOD
With vacuum condition, these solar collectors guarantee high efficiencies with minimum or
almost no heat loss. Vacuum serve as the best insulation that eliminates the heat transfer via
conduction and convection. Heat transfer can only happen via radiation coming from the solar
energy to the selective coating of the absorber, which best in absorbing the radiation energy.
Figure 8: Construction of Heat Pipe Evacuated Tube Solar Collectors
The construction of these solar collectors also guarantees a fast heat transfer rate whenever
there is solar radiation. Inside the heat pipe, it is charged with a little bit of water and
condition is also evacuated until the water can boil at 20°C. When there is solar radiation
shining upon the absorber fin, it has enough energy to boil the water. When water turns to
vapor, it rises up to the condenser tip. As we continuous to have sun radiation, the condition at
the condenser tip becomes superheated, where the temperature can go very high. When we
have cold water at about 26°C passing by the condenser tip, a high rate of heat transfer occurs
as the difference in temperature is very big. Should the evacuated tube solar collectors is
placed under the sun without any water passing by to remove the heat, the temperature at the
condenser tip may go up to 247°C. Figure 2 illustrates on how the heat transfer happens from
these evacuated tube solar collectors.
These type of solar collectors also guarantees easy installation with their plug in / plug out
construction.
There are no water flowing into the evacuated tubes, thus minimizes the possibility of water
leakage problem. The condenser tip is only fit in the heat transfer pocket in the manifold
header.
7
Return of Investment (Years)((Solar -Electric)/savings) - 9.38
Carbon Footprint Reduction CO2 Reduction per year (kg) (based on kWh
savings per year –1 MWh = 600kg CO2 emission) Nil 144,764
Trees Planted (assumed each tree absorbs 22 kg CO2 each year over its
lifespan of 40 years)
Nil 6,580
Actual
Target Status (Proposed/In
Name of Implementation ECM cost Target Savin Actual
Saving Progress/Completed/
ECM Plan (RM) ROI g ROI
(RM) Delay)
(RM)
Digital
Power Meter Install at SS1 108,521.18 N/A N/A N/A N/A Completed
(DPM)
Digital Install at SS3
Completed
Power Meter and Chiller N/A N/A N/A N/A N/A
(November 2016)
(DPM) (1,2,3)
1st Meeting
Sustainability Proposed
for
Program N/A N/A N/A N/A N/A
Sustainabilit (Early April 2017)
progress 2017
y Program
Energy Awareness Proposed (March
N/A N/A N/A N/A N/A
walkthrough briefing 2017)
2nd Meeting
Sustainability In-progress
for
Program N/A N/A N/A N/A N/A (expected early
Sustainabilit
progress 2017 August 2017)
y Program
Digital Install at
Power Meter Multilevel TBA N/A N/A N/A N/A Proposed
(DPM) parking
Install at AHU
Klinik
Timer for pakar,AHU Unit 36,147.60 0.72 (9
14,310 N/A N/A Proposed
AHU Rekod and AHU per year months)
Seminar Rumah
Mayat
Proposed
Installation
installation at
of Solar Hot 1.106M 88,063 9.38 N/A N/A Proposed
Block A of New
Water
Block
No. of
Training Programme Trainer Date Venue Remark
Participants
DPM survey & Data Mohd 13/9/2015 Hospital 4 Done
Gathering Hassaidi Melaka
Purchasing Status
Payment Status
No. Name of ECM Order
Request No. PO Amount (Pending/Done)
No.
DPM installation MKA/SP/15010 - RM Paid
1. 108,521.18
(3 units)
DPM installation TBA - RM Paid
2. 100,915.43
(9 units)
CEM Report (December) MKA/SP/EM/ - RM 6360.00 Paid
3.
17001
Some improvement activities already made on 2016. It start with repair and service all
chillers. Repair and service focused on shell and tube cleaning, overhaul the chiller and
replacement the worn parts. Repairing the cooling tower is the second phase. A new motor
and bearing had been replace the old motor and bearing at cooling tower number 1 and 3.
Besides that, the infill also replace with the new infill. All these repair and servicing to ensure
that the HVAC system is in optimize condition where the CDW input temperature and CHW
output temperature can be achieve with low consumption. Besides that, system AHU, FCU &
Package unit in wards and departments also been repairs and services. The scope of works is
to do the chemical cleaning, major overhaul, and replacing the worn parts. With this activities,
perhaps that the centralize air conditioning system can work as per design and it will directly
reduce the usage of split unit air conditioner. The preliminary audit already done and the
report already submitted to Hospital. The purpose of this audit is to study the energy profile &
Energy Management System level for Hospital Melaka.
53 | P a g e
HOSPITAL MELAKA
DOCUMENT ENERGY SAVING PROPOSAL – INSTALLATION OF VERSION 1.0
TYPE TIMER FOR AHU NUMBER
REPORT 2017 Page 54 of 55
PERIOD
10.0 CONCLUSION
From the Building Energy Index (BEI) graph from figure 4.0 the trend from year of
2014 and 2015 is increasing, comparing the BEI for 2015 and 2016 the trend is not much
different. As showed above BEI trend, the energy consumption on the building is under
control although there is generally increases in Cooling Degree Days and additional of
electrical equipment as in table 5.7 until 5.8 in 2016. EEI for January 2017 maintain same
with December 2016 which is 12.55 kWh/m². The highest EEI was recorded on March 2016
which is 13.40 kWh/m2. From Figure 6.3, the lowest energy consumption was in February
2015 that is 1,398,632 kWh and the highest energy consumption was on March 2016 which is
1,686,962 kWh. Refer Figure 6.3, on January 2017 the energy consumption slightly increase
compare to December 2016 which is 1,580,396 kWh to 1,580,510 kWh. The increment in
energy consumption is about 0.007% or equivalent to 114 kWh. Refer to Figure 6.4, the total
purchase cost for month of January 2017 had increase about 0.027% or equivalent to RM
166.01.
Refer to the table 6.1, comparing with the BEI baseline, the BEI for January 2017
decrease from 155.01 kWh/m² to 151.07 kWh/m². From that decrement, the saving is
Besides the surrounding temperature (CDD) that contribute to the increasing energy
consumption, have others factor that contribute to increasing the energy consumption is from
54 | P a g e
HOSPITAL MELAKA
DOCUMENT ENERGY SAVING PROPOSAL – INSTALLATION OF VERSION 1.0
TYPE TIMER FOR AHU NUMBER
REPORT 2017 Page 55 of 55
PERIOD
usage of air conditioning system. Although the CDD on January 2017 is decrease from 290ºC
to 280ºC but number in patient are increase compare to December 2016. Indirectly, this also
We can see that the electrical energy consumption trend fluctuates every month but
after the adjusted baseline was calculated, the actual energy consumption is lower than
adjusted baseline. The comprehensive awareness on energy efficiency and what does staffs of
the hospital can contribute need to be done in order to increase the awareness among the user
so that can reduce the energy consumption and avoid energy wastage .
ATTACHMENT
Attachment 1 – Monthly TNB Bill
56 | P a g e