You are on page 1of 56

MINISTRY OF HEALTH

MALAYSIA

HOSPITAL MELAKA
MONTHLY
ENERGY MANAGEMENT REPORT

For

Month of FEBRUARY 2017

Prepared by : Check by : Verified by:

Name : Mohamad Izhan Bin Name: Mohamad Azan Bin Name: Ghafar bin Jenal
Kamaruzaman Fazil Designation:Facility Manager
Designation : Energy Designation: Registered
Engineer Electrical Energy Manager
HOSPITAL MELAKA
DOCUMENT MONTHLY ENERGY MANAGEMENT REPORT VERSION 2.0
TYPE NUMBER
REPORT 28/2/17 Page 2 of 53
PERIOD

Table of Content

LIST OF ABBREVIATIONS..............................................................................3
1.0 EXECUTIVE SUMMARY........................................................................4
2.0 HOSPITAL PROFILE.............................................................................5
3.0 HOSPITAL INFORMATION.....................................................................6
4.0 ENERGY POLICY.................................................................................9
5.0 ENERGY MANAGEMENT COMMITTEE..................................................10
6.0 ENERGY MANAGEMENT MATRIX.........................................................11
7.1 BUILDING ENERGY INDEX AND ENERGY EFFICIENCY INDEX (EEI).............................14
7.2 ENERGY CONSUMPTION BY EACH EAC...............................................................18
7.3 ENERGY PURCHASING HISTORY........................................................................25
7.4 INDEPENDENT ENERGY VARIABLE AND STATIC FACTORS......................................34
7.4.1 LIST OF STATIC FACTORS..............................................................................38
7.5 BASELINE AND ADJUSTED BASELINE.................................................................42
8.0 PART B – ENERGY CONSERVATION MEASURES...........................................46
8.1 PROPOSED ENERGY CONSERVATION MEASURES...................................................46
8.2 LIST OF ENERGY CONSERVATION MEASURES (ECMS) ACTIVITIES / PROJECTS..............49
8.3 LIST OF TRAINING ACTIVITIES................................................................................50
9.0 PART C – ECMS FINANCIAL AND PURCHASING STATUS................................51
10.0 PART D – IMPROVEMENT ACTIONS..........................................................52
10.0 CONCLUSION.......................................................................................53
ATTACHMENT...........................................................................................55

2|Page
HOSPITAL MELAKA
DOCUMENT MONTHLY ENERGY MANAGEMENT REPORT VERSION 2.0
TYPE NUMBER
REPORT 28/2/17 Page 3 of 53
PERIOD

LIST OF ABBREVIATIONS

ACA Air Conditioning Area


ACSU Air Cooled Split Unit
AEMAS ASEAN Energy Management Scheme
AHU Air Handling Unit
ASIS Asset and Services Information System
BEI Building Energy Index
BOR Bed Occupancy Rate
CEM Certified Energy Manager
CFL Compact Fluorescent Lamp
EEI Energy Efficiency Index
EMEER Efficient Management of Electrical Energy Regulation
EMGS Energy Management Gold Standard
EnMS Energy Management System
FCU Fan Coil Unit
GFA Gross Floor Area
HSS Hospital Support Services
HT High Tension
HVAC Heating, Ventilation and Air Conditioning
LPG Liquefied Petroleum Gas
LV Low Voltage
MOH Ministry of Health
MSB Main Switch Board
MVAC Mechanical Ventilation Air Conditioning
REEM Registered Electrical Energy Manager
TNB Tenaga Nasional Berhad
TBA To Be Announce

3|Page
HOSPITAL MELAKA
DOCUMENT MONTHLY ENERGY MANAGEMENT REPORT VERSION 2.0
TYPE NUMBER
REPORT 28/2/17 Page 4 of 53
PERIOD

1.0 EXECUTIVE SUMMARY


Hospital Melaka is classified as High Energy Consumption (HEC) and is required to
comply with Efficient Management of Electrical Energy Regulation (EMEER 2008). This
report provides a trending of hospital electrical energy consumption for the month January
2016.

The ultimate objective of the Energy Management in Ministry of Health, Malaysia, is


to ensure the energy is used efficiently and to achieve 10% energy savings within the first two
(2) years of the concession period without affecting the operation of the hospital. On top of
that, comfort, safety of staff and patients as well as general public as main priorities. The long
term objective is to help to fulfil government commitment in reducing the carbon dioxide
emission intensity up to 40% in relation to the Gross Domestic Product (GDP) by year 2020
as compared to the emission in 2005.

Summary of Energy Consumption

Highest Energy Usage 1,686,962 kWh – March 2016

Energy Saving for Current Month 2.54%

Justification

Energy saving for the current month is 2.54% which mean that the actual BEI is lower than
the BEI baseline by 2.54%.

4|Page
HOSPITAL MELAKA
DOCUMENT MONTHLY ENERGY MANAGEMENT REPORT VERSION 2.0
TYPE NUMBER
REPORT 28/2/17 Page 5 of 53
PERIOD

2.0 HOSPITAL PROFILE

Table 1.0 below shows the summary on the Hospital Melaka profile based on the format

required by the Energy Commission Malaysia.

Hospital Name : Hospital Besar Melaka, Jalan Mufti


Address : Haji Khalil, 75400, Melaka.
Name of Hospital Director : Datuk Dr Za’aba Bin Baba
Designation : Hospital Director
Telephone, fax no & email : 06-289 2222
drzaaba@moh.gov.my
Name of CEM : Mohd Syafiq Bin Mohd Sabri
Telephone, fax no. and email : 019-266 0836
mohd.syafiq@medivest.com.my
Name of Registered Electrical Energy Manager : Mohamad Azan Bin Fazil
Telephone, fax no. and email : 018-982 6894 / 013-205 0160
muhamad.azan@medivest.com.my
Type of Sector/Industry Hospital

No. of Bed 1091

Operating hours (day, week, month) 24 hours / 7 days

Electricity Tariff Category C2

Date of Report 28/02/2017

Table 1.0: Summary on Hospital Melaka profile

5|Page
HOSPITAL MELAKA
DOCUMENT MONTHLY ENERGY MANAGEMENT REPORT VERSION 2.0
TYPE NUMBER
REPORT 28/2/17 Page 6 of 53
PERIOD

3.0 HOSPITAL INFORMATION

Hospital Melaka was built in the early 1930s with the construction of the Straits
Settlement costs totaled $ 2.5 million and was inaugurated by Sir Cecil Clementi , the Straits
Governor on 12th February 1934. The opening ceremony was also attended by Andrew
Caldecott (British Colonial Secretary) , Major General Lewin (Commanding Officer) , Dr RD
Fitzgerald (Director of Medical Treatment and Health) , N.W. Millington (Resident
Counselor) and distinguished guests including 700 people of Malacca .

Melaka Hospital provides expertise in multidisciplinary treatment of patients. It also


provides day care treatment. The services provided not only for the people of Melaka but also
for customers from northern, southern Johor and Negeri Sembilan. Before the establishment
of Sustainability Program, Hospital Melaka has its own committee which is known as
Komuniti Amalan Hijau. This committee play an important roles in the hospital in reducing
the electrical energy consumption and educate the staff about energy management.

Currently, there are 8 Energy Account Center (EAC) that has been established for
Hospital Melaka. The information for each EAC are as follow:

EAC Location Person in Charge


MSB 1 (Admin Block,
EAC 1 TBA
Kompleks Ilmu)
MSB 2 (Jaring Room, CT
EAC 2 TBA
Scan, Blok A, B, C, D, E)
EMSB 1 (Pump House, Pump House: En Nazri
EAC 3
VVIP Ward) (Medivest)
SB Chiller #1
EAC 4 SB Chiller #2 En. Hakimi (Medivest)
SB Chiller #3
MSB 2A & MSB 2B
(Dewan Bedah, ICU, CCU,
EAC 5 SCN, XRAY, Day Care, TBA
Klinik Pakar, Dental,
Kitchen, Farmasi)
6|Page
HOSPITAL MELAKA
DOCUMENT MONTHLY ENERGY MANAGEMENT REPORT VERSION 2.0
TYPE NUMBER
REPORT 28/2/17 Page 7 of 53
PERIOD

SB AHU (Air Handling Unit


EAC 6 Room) for Specialist Clinic, En. Ferdaus (Medivest)
Dental, SCN, Pathology and
Labour Room.
EAC 7 SSB PT1&2 (Jabatan TBA
Patologi)
EAC 8 TBA
SB CSSD (CSSD)

Table 2.0 Energy Account Center and Covered Area

7|Page
HOSPITAL MELAKA
DOCUMENT MONTHLY ENERGY MANAGEMENT REPORT VERSION 2.0
TYPE NUMBER
REPORT 28/2/17 Page 8 of 53
PERIOD

Table below shows the hospital building details.


Gross floor area (m²) 125,913.21
Hospital
Building Gross floor area that is air conditioned (m²) 22,268.18
Details Parking area that is enclosed ( m²) 23,803.00
Staff 3475
Designed Bed capacity (please specify unit) 1091
Actual BOR (%)

Table 2.1: Building details for Hospital Melaka.

Figure 1.0: Hospital Plant Layout & EAC Area

8|Page
HOSPITAL MELAKA
DOCUMENT MONTHLY ENERGY MANAGEMENT REPORT VERSION 2.0
TYPE NUMBER
REPORT 28/2/17 Page 9 of 53
PERIOD

4.0 ENERGY POLICY

Figure 2.0: Energy policy for Hospital Melaka.

9|Page
HOSPITAL MELAKA
DOCUMENT MONTHLY ENERGY MANAGEMENT REPORT VERSION 2.0
TYPE NUMBER
REPORT 28/2/17 Page 10 of 53
PERIOD

5.0 ENERGY MANAGEMENT COMMITTEE

The organization structure for the Energy Management committee is constructed as in

Fig. 3.0 below.

Figure 3.0: Organization chart for Energy Management committee

10 | P a g e
HOSPITAL MELAKA
DOCUMENT MONTHLY ENERGY MANAGEMENT REPORT VERSION 2.0
TYPE NUMBER
REPORT 28/2/17 Page 11 of 53
PERIOD

6.0 ENERGY MANAGEMENT MATRIX

Table 3.0: Energy Management Matrix table

Target
Actual

11 | P a g e
HOSPITAL MELAKA
DOCUMENT MONTHLY ENERGY MANAGEMENT REPORT VERSION 2.0
TYPE NUMBER
REPORT 28/2/17 Page 12 of 53
PERIOD

Referring to Table 3.0 Energy Management Matrix, based on the assessment done

during preliminary audit, it is found that Hospital Besar Melaka is on level two for four

categories. The energy policy has been signed by the Hospital Director. Besides, the Energy

Manager in post reporting to ad-hoc committee but the line management and authority are

unclear. In term of energy information system, the monitoring and targeting reports is based

on supply meter data installed and TNB bills.

Hospital Melaka scores about two in motivation and investment. Therefore, this

hospital need improvement on every aspect of EnMS by especially getting a commitment

from the top management and formulate the strategy to develop a committee to execute the

energy program and monitor the result. In marketing aspect, the level had increase from level

one to level two. An awareness campaign had been done on 25th April 2016. This campaign

is to train the hospital staff about energy management. A person in charge need to be

appointed for each EAC.

The table of Energy Management Matrix score will be revised base on agreement

during Sustainability Program meeting.

12 | P a g e
HOSPITAL MELAKA
DOCUMENT MONTHLY ENERGY MANAGEMENT REPORT VERSION 2.0
TYPE NUMBER
REPORT 28/2/17 Page 13 of 53
PERIOD

Policy Score Explanation

Energy Policy 3 Energy policy has been


signed by Hospital Director
Energy Team Energy Manager located on
site, but hospital line
2
management is unclear.
Person in charge for each
EAC still not be appointed.
Motivation Distribution of campaign
material such as flyers and
poster in progress. Also an
2
explanation about
Sustainability Program to
user is done during the
brochure distribution.
Information System All electricity bills are
collected by Medivest and
2
compiled each month to be
reported in the Energy
Monthly report.
Marketing 2 Awareness training has been
held on 25 April 2016.
Investment 1 Only Data Manager & DPM
installation been done.

Table 3.1: Energy Management Matrix table

13 | P a g e
HOSPITAL MELAKA
DOCUMENT MONTHLY ENERGY MANAGEMENT REPORT VERSION 2.0
TYPE NUMBER
REPORT 28/2/17 Page 14 of 53
PERIOD

7.0 PART A – ENERGY HIGHLIGHT

7.1 BUILDING ENERGY INDEX AND ENERGY EFFICIENCY INDEX


(EEI)

The Gross Floor Area (GFA) is being used as a factor for the calculation of Building

Energy Index and Energy Efficiency Index (EEI). The graph below shows the trending for the

the BEI and Energy Efficiency Index over the period of one year. The formula that has been

used to calculate the BEI and EEI as below formula respectively:

Total Energy Consumption(kWh)


BEI= 2
Gross Floor Area(GFA )(m )/ yr

Figure 4.0: BEI value from 2014 until 2016

14 | P a g e
HOSPITAL MELAKA
DOCUMENT MONTHLY ENERGY MANAGEMENT REPORT VERSION 2.0
TYPE NUMBER
REPORT 28/2/17 Page 15 of 53
PERIOD

Building Energy Index (Monthly)


156.00
155.00 BEI Montly baseline : 155.01
154.00
153.00
kWh/sqm
kWh/m2

152.00
151.00
150.00
149.00
148.00
Jan-16 Feb-16Mar-16 Apr-16May-16 Jun-16 Jul-16 Aug-16Sep-16 Oct-16 Nov-16 Dec-16 Jan-17
Months

BEI Current BEI Baseline (July2014 - Jun2015)

Figure 4.1: Graph trend for BEI Monthly from January 2016 to February 2017

Monthly Energy Consumption(kWh )


EEI = 2
Gross Floor Area (GFA )(m )

ENERGY EFFICIENCY INDEX


14.00
13.40
13.30 13.13
12.81 12.95
12.69
12.60
12.62 12.50 12.47 12.55 12.55
12.30 12.27
11.90
EEI

11.64
11.20 EEI Baseline: 12.56kWh/sqm

10.50

MONTHS

EEI (kWh/sqm)

Figure 4.2: Graph trend for EEI January 2016 to January 2017

15 | P a g e
HOSPITAL MELAKA
DOCUMENT MONTHLY ENERGY MANAGEMENT REPORT VERSION 2.0
TYPE NUMBER
REPORT 28/2/17 Page 16 of 53
PERIOD

As showed in figure 4.0 the value of building energy index(BEI) for 2014, 2015 and

2016 is 148 kWh/sqm/yr, 151 kWh/sqm/yr and 151 kWh/sqm/yr respectively, from those

value it can be concluded that the trend is increasing from year 2014 to 2015. Comparing BEI

for 2015 and 2016 the value of BEI is constant. It can tell us that starting from 2016 the

energy consumption for hospital Melaka is being controlled by the building owner even

though there are increase value of Cooling Degree Days which reflect that Air Conditioning

System is demanding much more energy from the previous year.

From the graph in Fig. 4.1, the overall monthly Building Energy Index (BEI) for

Hospital Melaka show a fluctuation trend from January 2016 until January 2017. The baseline

for the monthly BEI are taken from July 2014 until June 2015. The baseline value is 155.01

kWh/m². On January 2017, the BEI show some decrement from December 2016, 151.33

kWh/m² to 151.07 kWh/m². From January 2016 to January 2017, all the BEI are lower than

the baseline value. Month July 2016 still holds the lowest BEI value which is 150.95 kWh/m²

and month March 2016 is the highest BEI value recorded which 151.93kWh/m².

From the graph in Fig. 4.2, the overall Energy Efficiency Index (EEI) shows a

fluctuation trend from January 2016 until January 2017 for Hospital Melaka. The baseline for

the EEI are taken from January 2015 to December 2015. The baseline value is 12.56 kWh/m².

On January 2017, the EEI maintain same with December 2016, 12.55 kWh/m 2 which is still

lower than the baseline. From January 2016 to January 2017, there are 7 months where the

value is lower than the baseline which is on February 2016, June 2016, July 2016, September

2016, November 2016, December 2016 and January 2017. Month February 2016 still holds

the lowest EEI value which is 11.64 kWh/m 2 but then soar up to 13.4 kWh/m 2 on the

following month. Lowest value of EEI is on February 2016 is due to lowest billing days in the
16 | P a g e
HOSPITAL MELAKA
DOCUMENT MONTHLY ENERGY MANAGEMENT REPORT VERSION 2.0
TYPE NUMBER
REPORT 28/2/17 Page 17 of 53
PERIOD

electricity bill which is 29 days. On March 2016, the EEI value is the highest value ever

recorded which 13.40 kWh/m2 this is due the highest value of Cooling Degree Days that

ever recorded which is 353°C the further explanation is in section 7.4.

17 | P a g e
HOSPITAL MELAKA
DOCUMENT MONTHLY ENERGY MANAGEMENT REPORT VERSION 2.0
TYPE NUMBER
REPORT 28/2/17 Page 18 of 53
PERIOD

7.2 ENERGY CONSUMPTION BY EACH EAC

EAC 1
9000 6,752
7,826
8000 6,768 6,653
7,031 7,041
7000
6000
5000
kWh/Day

4000
3000
2000
1000
0
16 16 r-16 r-16 16 16 l-16 16 16 t-16 16 16 17
a n- e b- a p a y- un- J u ug- e p- c ov- e c- a n-
J F M A M J A S O N D J

Month

Figure 5.1 Energy Consumption for Administration Block, Cafeteria, & Komplek Ilmu

From figure show the energy consumption per day from January 2016 until January 2017.

The trend show some fluctuated on the energy consumption. The consumption trend we can

see it decreasing from month of October 2016 to January 2017. The decrement can be assume

due to the total of outpatient trend that show decreasing from 35,218 for October 2016 to

23,327 for January 2017. It indirectly reduces the energy consumption on this area. There are

some data losses and meter offline on April 2016 to October 2016 due to the damage of

dongle and it intermittent in Wi-Fi signal.

18 | P a g e
HOSPITAL MELAKA
DOCUMENT MONTHLY ENERGY MANAGEMENT REPORT VERSION 2.0
TYPE NUMBER
REPORT 28/2/17 Page 19 of 53
PERIOD

EAC 2
6,360
6,656 6,356 6,251
7000 6,356
6,048
6000
5000
4000
kWh/day

3000
2000
1000
0
16 16 r-16 r-16 -1
6 16 l-16 16 16 t-16 16 16 17
n- b- a p ay n- u g- p- c ov- e c- n-
Ja Fe M A M J u J Au S e O N D J a

Months

Figure 5.2 Energy Consumption for (EAC2)Block A, B, C, D, E, & CT Scan

For figure above, the energy consumption for EAC 2 are show decreasing trend from month

of December 2016 to January 2017. The decrement is by 3,265.25 kWh or 1.66 %. This

decrement can be assumed due to the BOR that show some decrement from 82.27% on

December 2016 to 79.47% in the January 2017. Indirectly it contributes to the decrease of

energy consumption. There are some data losses and meter offline on April 2016 to October

2016 due to the damage of dongle and it intermittent in Wi-Fi signal.

19 | P a g e
HOSPITAL MELAKA
DOCUMENT MONTHLY ENERGY MANAGEMENT REPORT VERSION 2.0
TYPE NUMBER
REPORT 28/2/17 Page 20 of 53
PERIOD

EAC 3
700 626 594
600 570 559
506 504
500
400
kWh/Day

300
200
100
0
16 16 16 16 16 16 16 16 16 16 16 16 17
a n- eb- ar- pr- ay- un- Jul- ug- ep- ct- ov- ec- an-
J F M A M J A S O N D J

Month

Figure 5.3 Energy Consumption for EAC 3

Energy consumption for EAC 3 which cover area of Pump House and VVIP ward from

months December 2016 and January 2017. There are some data losses and meter offline on

April 2016 to October 2016 due to the damage of dongle and it intermittent in Wi-Fi signal.

EAC 4
12000 11,098
10000 8,449 8,945
8000
kWh/Day

6000
4000
2000
0
Nov-16 Dec-16 Jan-17
Month

Figure 5.4 Energy Consumption for EAC 4(Chillers at Main Plant Room)

Above figure the energy consumption for EAC 4. As we can see, the trend is fluctuated.

There are some increasing on the energy consumption for months of December 2016 until

January 2017. The increasing of the chillers consumption due to the increment of

20 | P a g e
HOSPITAL MELAKA
DOCUMENT MONTHLY ENERGY MANAGEMENT REPORT VERSION 2.0
TYPE NUMBER
REPORT 28/2/17 Page 21 of 53
PERIOD

consumption at Air Handling Unit (AHU). As we can see the services of cooling tower that

was started in Dec 2016 contribute to lower energy consumption following by the next month.

EAC 5
14400 14,252
14200
14000
13800
kWh/Day

13600 13,467
13400 13,335
13200
13000
12800
Nov-16 Dec-16 Jan-17
Month

Figure 5.5 Energy Consumption for EAC 5

Above figure shows energy consumption for EAC 5, which cover main wards and critical unit

in Wad Aras that are OT, ICU, CCU, MRI, DC, Hospimart, MSB2A-AHU,KTC,SCN, LAB,

Blood Bank, Labour Room, Dental, Farmasi, Unit Hasil, PABX, Specialist Clinic, A&E and

also X-Ray department or in other word covers New Block except for Wad Aras and Forensic

Department. The trend of energy consumption are decreasing from November 2016 to

January 2017. This is because of the total operation at Operation Theatres that had been done

show some reduction from 3108 cases in November 2016 to 2859 cases in December. It

reduce to1354 cases in January 2017. From the figure above number of OT cases give

significance impact to the energy consumption at EAC 5.

21 | P a g e
HOSPITAL MELAKA
DOCUMENT MONTHLY ENERGY MANAGEMENT REPORT VERSION 2.0
TYPE NUMBER
REPORT 28/2/17 Page 22 of 53
PERIOD

EAC 6
1700
1650
1600 1,571
kWh/day

1550 1,537
1,516
1500
1450
1400
Nov-16 Dec-16 Jan-17
Month

Figure 5.6 Energy Consumption for EAC 6

EAC 6 as figure above is the energy consumption for Air Handling Unit that covers

AHU room in Hospital Melaka. We can see that the trend is increasing about from December

2016 to January 2017. Although the surrounding temperature (CDD) on January 2017 is

decrease from 290ºC to 280ºC but number in patient are increase compare to December 2016.

The number in patient in December are 6,169 while in January are 26,877. With the increase

of number in patient, it indirectly also increase the usage of air conditioning system to operate

in order to get the comfort level and setting temperature. Increment in January 2017 compared

to December 2016 is by 3.6%. Proposal of installation of timer at the Specialist Clinics can

lower the energy consumption by month reduce the kWh by monthly.

22 | P a g e
HOSPITAL MELAKA
DOCUMENT MONTHLY ENERGY MANAGEMENT REPORT VERSION 2.0
TYPE NUMBER
REPORT 28/2/17 Page 23 of 53
PERIOD

EAC 7
900
800 748 767
700 631
600
kWh/day

500
400
300
200
100
0
Nov-16 Dec-16 Jan-17
Month

Figure 5.7 Energy Consumption for EAC 7

Figure 7.2.7 covers energy consumption for Pathology department in Hospital Melaka as we

can see the trend is increasing from month of December 2016 to January 2017. The increasing

is due to the total of lab test are increase compare to December. The total lab test for the

December are 92,684 while total lab test for January are 253,348.

EAC 8
160 148
138
140
120 115
100
kWh/day

80
60
40
20
0
Nov-16 Dec-16 Jan-17
Month

Figure 5.8 Energy Consumption for EAC 8

23 | P a g e
HOSPITAL MELAKA
DOCUMENT MONTHLY ENERGY MANAGEMENT REPORT VERSION 2.0
TYPE NUMBER
REPORT 28/2/17 Page 24 of 53
PERIOD

EAC 8 covering the area of CSSD (Central Sterile Service Department) as in the

above figure there is decrement from December 2016 to January 2017. This reflect with the

number of operation on January 2017 that show some decrement compare to the number of

operation on December 2016. So, the equipment that need undergo sterile is less compare to

previous month.

24 | P a g e
HOSPITAL MELAKA
DOCUMENT MONTHLY ENERGY MANAGEMENT REPORT VERSION 2.0
TYPE NUMBER
REPORT 28/2/17 Page 25 of 53
PERIOD

7.3 ENERGY PURCHASING HISTORY

Table 4.0 below shows the power purchasing history for the year 2015 while table 4.1 shows the power purchasing from January 2016

until December 2016. The graph bar in Fig. 6.1 and Fig. 6.2 was plotted to analyze the electrical energy consumption and the total purchase cost

in 2015 until December 2016.

Table 4.0: Power purchasing history for year 2015.


25 | P a g e
Meter 0310 0056
  Year: 2016
No. : 7699 00
Total Total Purchase (Peak/Off Peak) PF
Capacity RE Charge Total Cost (incl
Month Purchase Off-Peak Total Purchase Penalty ICPT (RM)
Peak (kWh) MD (kW) (RM) GST) (RM)
(Flat Rate) (kWh) (kWh) (RM)
January - 1,028,651 584,199 1,612,850 2,966 0.00 24,515.32 10,241.36 662,745.00
February - 938,985 526,554 1,465,539 3,000 0.00 22,276.19 9,535.64 617,659.16
March - 1,089,269 597,693 1,686,962 3,096 0.00 25,641.82 10,737.54 694,918.99
April - 1,016,588 571,842 1,588,430 3,098 0.00 24,144.14 10,221.87 661,828.13
May - 1,065,298 588,227 1,653,525 3,110 0.00 25,133.58 10,573.72 684,441.20
June - 992,098 556,883 1,548,981 2,964 0.00 23,544.51 9,928.54 642,737.36
July - 999,587 574,007 1,573,594 2,967 0.00 23,918.63 10,035.82 649,554.91
August - 1,051,522 578,847 1,630,369 3,037 0.00 24,781.61 10,406.98 673,600.59
September - 1,008,271 562,201 1,570,472 3,040 0.00 23,871.17 10,096.90 617,281.67
October - 1,026,725 571,189 1,597,914 3,106 0.00 24,288.29 10,284.51 665,887.38
November - 993,270 552,069 1,545,339 2,999 0.00 23,489.15 9,943.39 643,794.51
December - 1,010,708 569,688 1,580,396 3,042 0.00 24,022.02 10,139.40 656,411.55
Total       19,054,371.00     289,626.43   7,870,860.44
Electricity
  C2              
Tariff Code
Average       1,587,864.25         655,905.04

Table 4.1: Power purchasing history from January 2016 until December 2016.
HOSPITAL MELAKA
DOCUMENT MONTHLY ENERGY MANAGEMENT REPORT VERSION 2.0
TYPE NUMBER
REPORT 28/2/17 Page 27 of 53
PERIOD

Meter No. : 0310 0056 7699 00 Year: 2017


Total Purchase (Peak/Off Peak)
Total Purchase Capacity MD PF Penalty RE Charge Total Cost (incl GST)
Month Total Purchase ICPT (RM) GST 6% (RM)
(Flat Rate) Peak (kWh) Off-Peak (kWh) (kW) (RM) (RM) (RM)
(kWh)
January - 1,011,058 569,452 1,580,510 3,044 0.00 24,023.75 10,142.05 0.00 619,996.12
February - 929,201 515,892 1,445,093 3,028 0.00 21,965.41 9,460.50 0.00 578,776.06
March -
April -
May -
June -
July -
August -
September -
October -
November -
December -
Total 3,025,603.00 45,989.16 0.00 1,198,772.18
Electricity
C2
Tariff Code
Average 1,512,801.50 99,897.68
Table 4.2: Power purchasing history for February 2017.

27 | P a g e
HOSPITAL MELAKA
DOCUMENT MONTHLY ENERGY MANAGEMENT REPORT VERSION 2.0
TYPE NUMBER
REPORT 28/2/17 Page 28 of 53
PERIOD

Figure 6.1: Bar graph for electrical energy consumption for 2015

28 | P a g e
HOSPITAL MELAKA
DOCUMENT MONTHLY ENERGY MANAGEMENT REPORT VERSION 2.0
TYPE NUMBER
REPORT 28/2/17 Page 29 of 53
PERIOD

Figure 6.2: Bar graph for electrical energy consumption from January 2016 to January 2017

29 | P a g e
HOSPITAL MELAKA
DOCUMENT MONTHLY ENERGY MANAGEMENT REPORT VERSION 2.0
TYPE NUMBER
REPORT 28/2/17 Page 30 of 53
PERIOD

Monthly Energy Comparison 2015 ,2016 & 2017


1,800,000

1,600,000

1,400,000

1,200,000

1,000,000
kWh

800,000

600,000

400,000

200,000

0
January February March April May June July August September October November December

Months

2015 2016 2017

Figure 6.3: Bar graph of Monthly Energy Comparison from 2015 until February 2017

30 | P a g e
HOSPITAL MELAKA
DOCUMENT MONTHLY ENERGY MANAGEMENT REPORT VERSION 2.0
TYPE NUMBER
REPORT 28/2/17 Page 31 of 53
PERIOD

750,000.00
Monthly Energy Cost for 2015, 2016 and 2017
700,000.00

650,000.00

600,000.00

550,000.00
RM

500,000.00

450,000.00

400,000.00

350,000.00

300,000.00
January February March April May June July August September October November December

Months

Figure 6.4: Bar graph of total purchase cost in 2015 until February 2017

31 | P a g e
HOSPITAL MELAKA
DOCUMENT MONTHLY ENERGY MANAGEMENT REPORT VERSION 2.0
TYPE NUMBER
REPORT 28/2/17 Page 32 of 53
PERIOD

Figure 6.5: Bar graph of Maximum Demand in 2015 until February 2017

From the figure above it can be seen that energy demand trend is increasing by comparing the reading from 2015 to January 2017.

32 | P a g e
From Fig. 6.1 and 6.2, shows the usage of energy consumption for Off peak and On

peak for 2015 and 2016 include Januari 2017, the time for On Peak is from 8:00am until

10:00pm and from 10:00pm until 8:00am for Off peak. The highest recorded of energy

consumption during Off peak in 2015 is on May 2015 which is 611,605kWh, and for 2016 is

on March 2016 which is 697,653 kWh.

As for January 2017, there is slightly increment on energy consumption compared to

December 2016 which is from 1,580,396 kWh to 1,580,510 kWh, it is 114kWh or 0.007%. In

term of cost, the increment is RM 166.01. Besides that, some variable factors such as

surrounding temperature or ambient temperature, number of laboratory test and number of in-

patient day also contribute to the increment of electricity usage.

From Fig.6.5, the highest Maximum Demand (MD) was recorded in May 2016 which

is 3,110 kW. While for January 2017, the Maximum Demand (MD) recorded was 3,044 kW.

There is increment in maximum demand (MD) from December 2016 to January 2017 which is

from 3,042 kW to 3,044 kW increment by 0.07%. By comparing January 2016 and January

2017 the value of Maximum Demand slightly increase by 78 kW or 0.03%,.

33 | P a g e
7.4 INDEPENDENT ENERGY VARIABLE AND STATIC FACTORS

Table 7.1 and 7.2 below shows the Independent Energy Variable for year 2015 and year 2016.

Table 7.1: Independent Energy Variables for year 2015

34 | P a g e
Energy Variables Table No.
Plant: Year 2016
Name of Variables
Month OT Maternity In Patient Out Patient Laboratory CDD Working Day Public Holiday School Holiday In Patient In Patient
No. of Operation No. of Delivery BOR % No. of Patient No. of Test °C Day Day Day No. of Patient Patient Days
January 3,568 956 83.74 36,088 96206 324 31 1 3 6,912 28,321
February 2,916 846 79.84 34,131 92007 288 29 2 0 6,289 25,260
March 3,054 871 83.39 38,753 123415 353 31 0 9 6,943 28,202
April 3,199 931 82.05 35,962 102625 350 30 1 0 6,284 26,855
May 3,069 873 82.05 37,031 96456 337 31 3 4 6,440 27,751
June 3,058 991 81.09 36,349 94246 309 30 2 12 6,253 26,540
July 3,075 1,008 80.72 33,949 94276 312 31 2 0 6,695 27,302
August 3,561 1,000 86.34 40,262 102504 329 31 1 0 6,998 29,202
September 3,292 973 85.56 36,356 90491 309 30 2 9 6,415 28,005
October 2800 966 82.55 35218 85092 319 31 3 0 6,362 27,919
November 3108 967 83.34 36559 87449 279 30 0 5 6,195 27,277
December 2859 912 82.27 35945 92684 290 31 2 31 6,169 27,825

Table 7.2: Independent Energy Variables for year 2016

35 | P a g e
HOSPITAL MELAKA
DOCUMENT VERSION
MONTHLY ENERGY MANAGEMENT REPORT 2.0
TYPE NUMBER
REPORT
31/01/17 Page 36 of 53
PERIOD

Energy Variables Table No.


Plant: Year 2017
Name of Variables
Month OT Maternity In Patient Out Patient Laboratory CDD Working Day Public Holiday School Holiday In Patient In Patient
No. of Operation No. of Delivery BOR % No. of Patient No. of Test °C Day Day Day No. of Patient Patient Days
January 1,354 869 79.47 23,327 253,348 280 31 2 3 26,877 867.00
February 1,656 838 82.83 21,751 260,178 256 28 0 0 25,302 903.64
March
April
May
June
July
August
September
October
November
December

Table 7.3: Independent Energy Variables for year 2017

36 | P a g e
Table 7.1, 7.2 and 7.3 shows the value for each independent energy variables for 2015,
2016 and January 2017. The data was obtained from several departments to be analyse and
justifying the relationship it with the monthly electrical energy consumption in this hospital.
On January 2017, the number of operation in operating theater decrease from 2,859 to 1,354
of cases, it is a decrement by 52.64%. The number of maternity was also decrease from 912 to
869 or in other words decrease by 4.71%. The BOR percentage also decrease from 83.34% to
79.47% in other words it is a decreases by 3.87% . The Cooling Degree Days (CDD)
definition is a daily cumulative sum value of different for average ambient temperature
and base temperature or the number of degrees that a day's average temperature is
above 65o Fahrenheit@18DegC and people start to use air conditioning to cool their
buildings. Cooling Degree days comparing from December 2016 and January 2017 it is
290degC and 280degC respectively it is a decrement by 3.45%.

7.4.1 LIST OF STATIC FACTORS

37 | P a g e
HOSPITAL MELAKA
DOCUMENT VERSION
MONTHLY ENERGY MANAGEMENT REPORT 2.0
TYPE NUMBER
REPORT
PERIOD
31/01/17 Page 38 of 53

Table 7.4: List of electrical appliances registered from August 2015 to June 2016

38 | P a g e
Table 7.5: List of electrical appliances registered from August 2015 – June 2016

Table 7.6: List of electrical appliances registered from August 2015 – June 2016

39 | P a g e
Table 7.7: List of electrical appliances registered from July 2016 – September 2016

Table 7.8: List of electrical appliances registered from July 2016 – September 2016

40 | P a g e
Table 7.4 until table 7.8 respectively shows the list of asset that had been registered /
installed from July 2015 till June 2016. While Table 5.7 and Table 5.8 shows the list of asset
that were registered / installed from July 2016 till September 2016. These list of electrical
applianes that were installed after the period of baseline are known as Static Data or Static
Factor. The total power consumption for the asset that had been registered / installed from
August 2015 till June 2016 are 37,468 kWh per month. While the additional power
consumption for the asset that had been registered / installed from July 2016 to September
2016 are 13,230 kWh per month. These values (Static Factor) must to be considered during
calculating the energy saving every month.

Energy Savings (kWh) =Adjusted Baseline + Static Data – Actual Energy Consumption

41 | P a g e
7.5 BASELINE AND ADJUSTED BASELINE

The period of the baseline was selected from July 2014 until June 2015 (12 months) to cater for all possible variations of energy variables

during the baseline period. The baseline and adjusted baseline as per below.

Adjusted consumption = Actual Consumption + static factor

working Gross Floor Actual Static Adjusted


Month BEI Baseline
days Area Consumption Factor Consumption
Jul-2014 31 125913.21 1,564,986.00 63,755 1,628,740.60 155.01
Aug-2014 31 125913.21 1,595,160.00 63,755 1,658,914.60 155.01
Sep-2014 30 125913.21 1,567,125.00 61,698 1,628,823.00 155.01
Oct-2014 31 125913.21 1,506,452.00 63,755 1,570,206.60 155.01
Nov-2014 30 125913.21 1,560,490.00 61,698 1,622,188.00 155.01
Dec-2014 31 125913.21 1,512,502.00 63,755 1,576,256.60 155.01
Jan-2015 31 125913.21 1,544,381.00 63,755 1,608,135.60 155.01
Feb-2015 28 125913.21 1,398,632.00 57,585 1,456,216.80 155.01
Mar-2015 31 125913.21 1,626,910.00 63,755 1,690,664.60 155.01
Apr-2015 30 125913.21 1,599,981.00 61,698 1,661,679.00 155.01
May-2015 31 125913.21 1,682,092.00 63,755 1,745,846.60 155.01
Jun-2015 30 125913.21 1,608,277.00 61,698 1,669,975.00 155.01

Table 8.0 Adjusted Consumption during baseline period


BEI Baseline−BEI Current
BEI saving = X 100 %
BEI Baseline

42 | P a g e
HOSPITAL MELAKA
DOCUMENT VERSION
MONTHLY ENERGY MANAGEMENT REPORT 2.0
TYPE NUMBER
REPORT
PERIOD
31/01/17 Page 43 of 53

working Gross Floor Actual Static Adjusted Target 10% Saving


Month BEI Baseline BEI Current
days Area Consumption Factor Consumption Saving (%)

1,637,596.0
Jul-2015 31 125913.21 1,637,596.00   155.01 149.62 139.51 3.47%
0
1,619,602.0
Aug-2015 31 125913.21 1,619,602.00   155.01 149.82 139.51 3.35%
0
1,582,662.0
Sep-2015 30 125913.21 1,582,662.00   155.01 149.94 139.51 3.27%
0
1,573,529.0
Oct-2015 31 125913.21 1,573,529.00   155.01 150.47 139.51 2.93%
0
1,522,919.0
Nov-2015 30 125913.21 1,522,919.00   155.01 150.18 139.51 3.12%
0
1,578,161.0
Dec-2015 31 125913.21 1,578,161.00   155.01 150.70 139.51 2.78%
0
1,612,850.0
Jan-2016 31 125913.21 1,612,850.00   155.01 151.24 139.51 2.43%
0
1,465,539.0
Feb-2016 29 125913.21 1,465,539.00   155.01 151.77 139.51 2.09%
0
1,686,962.0
Mar-2016 31 125913.21 1,686,962.00   155.01 152.25 139.51 1.78%
0
1,588,430.0
Apr-2016 30 125913.21 1,588,430.00   155.01 152.16 139.51 1.84%
0
1,653,525.0
May-2016 31 125913.21 1,653,525.00   155.01 151.93 139.51 1.99%
0
1,548,981.0
Jun-2016 30 125913.21 1,548,981.00   155.01 151.46 139.51 2.29%
0
1,573,594.0
Jul-2016 31 125913.21 1,573,594.00   155.01 150.95 139.51 2.62%
0
1,630,369.0
Aug-2016 31 125913.21 1,630,369.00   155.01 151.04 139.51 2.56%
0
1,570,472.0
Sep-2016 30 125913.21 1,570,472.00   155.01 150.94 139.51 2.62%
0
1,597,914.0
Oct-2016 31 125913.21 1,597,914.00   155.01 151.13 139.51 2.50%
0

43 | P a g e
HOSPITAL MELAKA
DOCUMENT VERSION
MONTHLY ENERGY MANAGEMENT REPORT 2.0
TYPE NUMBER
REPORT
PERIOD
31/01/17 Page 44 of 53

1,545,339.0
Nov-2016 30 125913.21 1,545,339.00   155.01 151.31 139.51 2.39%
0
1,580,396.0
Dec-2016 31 125913.21 1,580,396.00   155.01 151.33 139.51 2.37%
0
1,580,510.0
Jan-2017 31 125913.21 1,580,510.00   155.01 151.07 139.51 2.54%
0

Table 8.1: Adjusted consumption and BEI saving calculation

44 | P a g e
Building Energy Index (BEI)
180.00

135.00

90.00

45.00

0.00
Dec-2013 Feb-2014 May-2014 Aug-2014 Oct-2014 Jan-2015 Apr-2015 Jun-2015 Sep-2015 Nov-2015 Feb-2016 May-2016 Jul-2016 Oct-2016 Jan-2017

BEI Baseline BEI Current

Figure 7.0: Baseline graph for Building Energy Index

45 | P a g e
HOSPITAL MELAKA
DOCUMENT VERSION
MONTHLY ENERGY MANAGEMENT REPORT 2.0
TYPE NUMBER
REPORT
PERIOD
31/01/17 Page 46 of 53

Table 6.0 show the energy consumption and adjusted baseline during the baseline
period which is from July 2014 to June 2015. While the table 6.1 show the adjusted baseline
and BEI saving that has been achieved every month.

Refer to the table 6.1, comparing with the BEI baseline, the BEI for January 2017
decrease from 155.01 kWh/m² to 151.07 kWh/m². From that decrement, the saving is
calculated and get 2.54% saving for January 2017.

The monthly energy saving can be obtain from equation below.

BEI Baseline−BEI Current


Saving = X 100 %
BEI Baseline

46 | P a g e
HOSPITAL MELAKA
DOCUMENT ENERGY SAVING PROPOSAL – INSTALLATION OF VERSION 1.0
TYPE TIMER FOR AHU NUMBER
REPORT 2017 Page 47 of 55
PERIOD

8.0 PART B – ENERGY CONSERVATION MEASURES


8.1 PROPOSED ENERGY CONSERVATION MEASURES

8.1.1 Installation of Solar Hot Water at Block A New Building Hospital Melaka

8.1.1.1 Intoduction of Solar Hot Water and Working Principles of Centralized Solar Hot
Water System
Unlike conventional electric boiler that consumes a huge of amount of electricity to heat up
the water, the Centralized Solar Hot Water System capitalized on the free solar energy using
the high efficiency and high temperature evacuated tube solar collectors to produce the
heating effect.The construction of the evacuated tube solar collectors consists of a 2.5mm
thick borosilicate glass tube vacuum condition beneath the glass tube, aluminum absorber fin
coated with selective sputtering aluminum nitrate, and the copper heat pipe with the
protruding condenser as shown in Figure 8 below.

47 | P a g e
HOSPITAL MELAKA
DOCUMENT ENERGY SAVING PROPOSAL – INSTALLATION OF VERSION 1.0
TYPE TIMER FOR AHU NUMBER
REPORT 2017 Page 48 of 55
PERIOD

With vacuum condition, these solar collectors guarantee high efficiencies with minimum or
almost no heat loss. Vacuum serve as the best insulation that eliminates the heat transfer via
conduction and convection. Heat transfer can only happen via radiation coming from the solar
energy to the selective coating of the absorber, which best in absorbing the radiation energy.
Figure 8: Construction of Heat Pipe Evacuated Tube Solar Collectors
The construction of these solar collectors also guarantees a fast heat transfer rate whenever
there is solar radiation. Inside the heat pipe, it is charged with a little bit of water and
condition is also evacuated until the water can boil at 20°C. When there is solar radiation
shining upon the absorber fin, it has enough energy to boil the water. When water turns to
vapor, it rises up to the condenser tip. As we continuous to have sun radiation, the condition at
the condenser tip becomes superheated, where the temperature can go very high. When we
have cold water at about 26°C passing by the condenser tip, a high rate of heat transfer occurs
as the difference in temperature is very big. Should the evacuated tube solar collectors is
placed under the sun without any water passing by to remove the heat, the temperature at the
condenser tip may go up to 247°C. Figure 2 illustrates on how the heat transfer happens from
these evacuated tube solar collectors.
These type of solar collectors also guarantees easy installation with their plug in / plug out
construction.
There are no water flowing into the evacuated tubes, thus minimizes the possibility of water
leakage problem. The condenser tip is only fit in the heat transfer pocket in the manifold
header.

ENERGY SAVING PROPOSAL – INSTALLATION OF TIMER FOR AHU Page 48


HOSPITAL MELAKA
DOCUMENT ENERGY SAVING PROPOSAL – INSTALLATION OF VERSION 1.0
TYPE TIMER FOR AHU NUMBER
REPORT 2017 Page 49 of 55
PERIOD

8.1.1.2 Investment Cost Analysis

No. Ite ms Esixting System of Hot Proposed Solar Hot


Descriptions
wate r water
Total hot water consumption
1 Capacity 16,000 16,000
(li ters)
Nominal running kW 28.99 1.45
Runni ng Hour 24 24
Electricity Consumption
Average power consumption
695.81 34.79
2 (kWh/day)
Category Tariff-C2
Electricity Tariff Peak (RM/kWh) 0.365
3 Off Peak (RM/kWh) 0.224
Consumption (kWh)(1 year) 253,972 12,699
Cost (RM)(1 year) Peak 54,071.49 2,703.54
Electricity Cost
Cost (RM)(1 year) Off Peak 38,627.79 1,931.36
4 Total Cost (RM) 1 Year 92,699.29 4,634.90
Savi ng (kWh) Nil 241,273
Energy cost saving per year Savi ng (RM)(1 year) Nil 88,064.39
5 Savi ng (%) Nil 95.00%
Investment cost Analysis
Return of Investment (ROI) - Without Government Incentive
140,000.00 1,106,300.00
*Based on replacement of *Based on whole Solar
current Hot Water System
exi sting Heat Pump only. Project.
Ini tial Investment Cost (RM)
** Excluding Calori fier Tank, ** Including Calorifier
Hot Water Tank, Hot Water
Pi ping, Thermal Control Pipi ng, Thermal Control
Sys tem System

Investment Cost (Compare in 10 years) (RM) 280,000.00 1,106,300.00

Additional Investment Cost on Solar Hot Water - 826,300.00

7
Return of Investment (Years)((Solar -Electric)/savings) - 9.38

Savings in 10 Years (RM) - 880,643.90

Savings in 20 Years (RM) - 1,761,287.79

Carbon Footprint Reduction CO2 Reduction per year (kg) (based on kWh
savings per year –1 MWh = 600kg CO2 emission) Nil 144,764

Trees Planted (assumed each tree absorbs 22 kg CO2 each year over its
lifespan of 40 years)
Nil 6,580

ENERGY SAVING PROPOSAL – INSTALLATION OF TIMER FOR AHU Page 49


HOSPITAL MELAKA
DOCUMENT ENERGY SAVING PROPOSAL – INSTALLATION OF VERSION 1.0
TYPE TIMER FOR AHU NUMBER
REPORT 2017 Page 50 of 55
PERIOD

8.2 LIST OF ENERGY CONSERVATION MEASURES (ECMs) ACTIVITIES


/ PROJECTS

Actual
Target Status (Proposed/In
Name of Implementation ECM cost Target Savin Actual
Saving Progress/Completed/
ECM Plan (RM) ROI g ROI
(RM) Delay)
(RM)
Digital
Power Meter Install at SS1 108,521.18 N/A N/A N/A N/A Completed
(DPM)
Digital Install at SS3
Completed
Power Meter and Chiller N/A N/A N/A N/A N/A
(November 2016)
(DPM) (1,2,3)
1st Meeting
Sustainability Proposed
for
Program N/A N/A N/A N/A N/A
Sustainabilit (Early April 2017)
progress 2017
y Program
Energy Awareness Proposed (March
N/A N/A N/A N/A N/A
walkthrough briefing 2017)
2nd Meeting
Sustainability In-progress
for
Program N/A N/A N/A N/A N/A (expected early
Sustainabilit
progress 2017 August 2017)
y Program
Digital Install at
Power Meter Multilevel TBA N/A N/A N/A N/A Proposed
(DPM) parking
Install at AHU
Klinik
Timer for pakar,AHU Unit 36,147.60 0.72 (9
14,310 N/A N/A Proposed
AHU Rekod and AHU per year months)
Seminar Rumah
Mayat
Proposed
Installation
installation at
of Solar Hot 1.106M 88,063 9.38 N/A N/A Proposed
Block A of New
Water
Block

Table 10.1: Status of ECMs activities/ projects

ENERGY SAVING PROPOSAL – INSTALLATION OF TIMER FOR AHU Page 50


HOSPITAL MELAKA
DOCUMENT ENERGY SAVING PROPOSAL – INSTALLATION OF VERSION 1.0
TYPE TIMER FOR AHU NUMBER
REPORT 2017 Page 51 of 55
PERIOD

8.3 List of Training Activities

No. of
Training Programme Trainer Date Venue Remark
Participants
DPM survey & Data Mohd 13/9/2015 Hospital 4 Done
Gathering Hassaidi Melaka

CEM Training Report Mohd 12/10/2015 Renaissanc 60 Done


Hassaidi e Hotel

DPM Troubleshoot RDM Asia


Saiful Sujak 22/02/2016 6 Done
Training Sdn Bhd

Hotel Sri 23(Hospital’s


EMTC Training UTM & 29 Feb – 4 Malaysia, Engineer and
Done
Greentech March 2016 Ayer Energy
Keroh Mnager)

REEM- 25th April Hospital


Awareness Program Muhd Azan 2016 45 Done
Melaka,
b. Fazil

Table 10.2: List of training activities conducted

ENERGY SAVING PROPOSAL – INSTALLATION OF TIMER FOR AHU Page 51


HOSPITAL MELAKA
DOCUMENT ENERGY SAVING PROPOSAL – INSTALLATION OF VERSION 1.0
TYPE TIMER FOR AHU NUMBER
REPORT 2017 Page 52 of 55
PERIOD

9.0 PART C – ECMs FINANCIAL AND PURCHASING


STATUS

Purchasing Status
Payment Status
No. Name of ECM Order
Request No. PO Amount (Pending/Done)
No.
DPM installation MKA/SP/15010 - RM Paid
1. 108,521.18
(3 units)
DPM installation TBA - RM Paid
2. 100,915.43
(9 units)
CEM Report (December) MKA/SP/EM/ - RM 6360.00 Paid
3.
17001

Table 11.0: ECMs Financial and Purchasing Status

ENERGY SAVING PROPOSAL – INSTALLATION OF TIMER FOR AHU Page 52


HOSPITAL MELAKA
DOCUMENT ENERGY SAVING PROPOSAL – INSTALLATION OF VERSION 1.0
TYPE TIMER FOR AHU NUMBER
REPORT 2017 Page 53 of 55
PERIOD

10.0 PART D – IMPROVEMENT ACTIONS

Improvement Item PIC Status Remarks


Hospital director to sign the CEM/ESE & Complet
Energy policy had been sign.
energy policy. Hospital Director e
Has been setup and the hospital
To setup Energy Management CEM/ESE & Complet
representative has been
Committee (EMC). JOHN e
appointed.
EAC has been setup.
To setup Energy Accounting CEM/ESE &
On-going Representative for each EAC
Center (EAC). JOHN
will be appointed.
3rd phase installation still in
To install sub-meter. REEM/ CEM On-going
progress.
To conduct preliminary audit to
study the energy profile & Complet Report has been submitted to
REEM/ CEM
Energy Management System e Hospital’s engineer.
level.

Table 12.0: List and status of improvement items

Some improvement activities already made on 2016. It start with repair and service all
chillers. Repair and service focused on shell and tube cleaning, overhaul the chiller and
replacement the worn parts. Repairing the cooling tower is the second phase. A new motor
and bearing had been replace the old motor and bearing at cooling tower number 1 and 3.
Besides that, the infill also replace with the new infill. All these repair and servicing to ensure
that the HVAC system is in optimize condition where the CDW input temperature and CHW
output temperature can be achieve with low consumption. Besides that, system AHU, FCU &
Package unit in wards and departments also been repairs and services. The scope of works is
to do the chemical cleaning, major overhaul, and replacing the worn parts. With this activities,
perhaps that the centralize air conditioning system can work as per design and it will directly
reduce the usage of split unit air conditioner. The preliminary audit already done and the
report already submitted to Hospital. The purpose of this audit is to study the energy profile &
Energy Management System level for Hospital Melaka.

53 | P a g e
HOSPITAL MELAKA
DOCUMENT ENERGY SAVING PROPOSAL – INSTALLATION OF VERSION 1.0
TYPE TIMER FOR AHU NUMBER
REPORT 2017 Page 54 of 55
PERIOD

10.0 CONCLUSION

From the Building Energy Index (BEI) graph from figure 4.0 the trend from year of

2014 and 2015 is increasing, comparing the BEI for 2015 and 2016 the trend is not much

different. As showed above BEI trend, the energy consumption on the building is under

control although there is generally increases in Cooling Degree Days and additional of

electrical equipment as in table 5.7 until 5.8 in 2016. EEI for January 2017 maintain same

with December 2016 which is 12.55 kWh/m². The highest EEI was recorded on March 2016

which is 13.40 kWh/m2. From Figure 6.3, the lowest energy consumption was in February

2015 that is 1,398,632 kWh and the highest energy consumption was on March 2016 which is

1,686,962 kWh. Refer Figure 6.3, on January 2017 the energy consumption slightly increase

compare to December 2016 which is 1,580,396 kWh to 1,580,510 kWh. The increment in

energy consumption is about 0.007% or equivalent to 114 kWh. Refer to Figure 6.4, the total

purchase cost for month of January 2017 had increase about 0.027% or equivalent to RM

166.01.

Refer to the table 6.1, comparing with the BEI baseline, the BEI for January 2017

decrease from 155.01 kWh/m² to 151.07 kWh/m². From that decrement, the saving is

calculated and get 2.54% saving for January 2017.

Besides the surrounding temperature (CDD) that contribute to the increasing energy

consumption, have others factor that contribute to increasing the energy consumption is from

54 | P a g e
HOSPITAL MELAKA
DOCUMENT ENERGY SAVING PROPOSAL – INSTALLATION OF VERSION 1.0
TYPE TIMER FOR AHU NUMBER
REPORT 2017 Page 55 of 55
PERIOD

usage of air conditioning system. Although the CDD on January 2017 is decrease from 290ºC

to 280ºC but number in patient are increase compare to December 2016. Indirectly, this also

increase the usage of air conditioning system.

We can see that the electrical energy consumption trend fluctuates every month but

after the adjusted baseline was calculated, the actual energy consumption is lower than

adjusted baseline. The comprehensive awareness on energy efficiency and what does staffs of

the hospital can contribute need to be done in order to increase the awareness among the user

so that can reduce the energy consumption and avoid energy wastage .

ENERGY SAVING PROPOSAL – INSTALLATION OF TIMER FOR AHU Page 55


HOSPITAL MELAKA
DOCUMENT ENERGY SAVING PROPOSAL – INSTALLATION OF VERSION 1.0
TYPE TIMER FOR AHU NUMBER
REPORT 2017 Page 56 of 55
PERIOD

ATTACHMENT
Attachment 1 – Monthly TNB Bill

56 | P a g e

You might also like