ASHRAE Guideline 0-2013

(Supersedes ASHRAE Guideline 0-2005)

The Commissioning
Process

See Appendix Q for approval dates by the ASHRAE Standards Committee and the ASHRAE Board of Directors.

This guideline is under continuous maintenance by a Standing Guideline Project Committee (SGPC) for which the Standards Com-
mittee has established a documented program for regular publication of addenda or revisions, including procedures for timely, doc-
umented, consensus action on requests for change to any part of the guideline. The change submittal form, instructions, and
deadlines may be obtained in electronic form from the ASHRAE website (www.ashrae.org) or in paper form from the Manager of
Standards. The latest edition of an ASHRAE Standard or Guideline may be purchased from the ASHRAE website (www.ashrae.org)
or from ASHRAE Customer Service, 1791 Tullie Circle, NE, Atlanta, GA 30329-2305. E-mail: orders@ashrae.org. Fax: 678-539-
2129. Telephone: 404-636-8400 (worldwide), or toll free 1-800-527-4723 (for orders in US and Canada). For reprint permission,
go to www.ashrae.org/permissions.

© 2013 ASHRAE ISSN 1049-894X


© ASHRAE (www.ashrae.org). For personal use only. Additional reproduction, distribution,
or transmission in either print or digital form is not permitted without ASHRAE's prior written permission.

ASHRAE Standing Guideline Project Committee 0


Cognizant TC: TC 9.1, Large Building Air-Conditioning Systems
SPLS Liaison: Janice C. Peterson
Timothy F. Corbett, Chair Walter D. Horn
Thomas R. Meyer, Vice-Chair Gerald J. Kettler
Michael Amstadt, Secretary Kevin K. Knueven
Thomas E. Cappellin Guopeng Liu
Charles E. Dorgan Larry S. Ross
Justin Foster Garner

ASHRAE STANDARDS COMMITTEE 2013–2014


William F. Walter, Chair David R. Conover Malcolm D. Knight
Richard L. Hall, Vice-Chair John F. Dunlap Rick A. Larson
Karim Amrane James W. Earley, Jr. Mark P. Modera
Joseph R. Anderson Steven J. Emmerich Cyrus H. Nasseri
James Dale Aswegan Julie M. Ferguson Janice C. Peterson
Charles S. Barnaby Krishnan Gowri Heather L. Platt
Steven F. Bruning Cecily M. Grzywacz Douglas T. Reindl
John A. Clark Rita M. Harrold Julia A. Keen, BOD ExO
Waller S. Clements Adam W. Hinge Thomas E. Werkema, Jr., CO
Debra H. Kennoy

Stephanie C. Reiniche, Manager of Standards

SPECIAL NOTE
This Guideline was developed under the auspices of ASHRAE. ASHRAE Guidelines are developed under a review process, identifying
a guideline for the design, testing, application, or evaluation of a specific product, concept, or practice. As a guideline it is not definitive but
encompasses areas where there may be a variety of approaches, none of which must be precisely correct. ASHRAE Guidelines are written
to assist professionals in the area of concern and expertise of ASHRAE’s Technical Committees and Task Groups.
ASHRAE Guidelines are prepared by project committees appointed specifically for the purpose of writing Guidelines. The project
committee chair and vice-chair must be members of ASHRAE; while other committee members may or may not be ASHRAE members, all
must be technically qualified in the subject area of the Guideline.
Development of ASHRAE Guidelines follows procedures similar to those for ASHRAE Standards except that (a) committee balance is
desired but not required, (b) an effort is made to achieve consensus but consensus is not required, (c) Guidelines are not appealable, and
(d) Guidelines are not submitted to ANSI for approval.
The Manager of Standards of ASHRAE should be contacted for:
a. interpretation of the contents of this Guideline,
b. participation in the next review of the Guideline,
c. offering constructive criticism for improving the Guideline, or
d. permission to reprint portions of the Guideline.

DISCLAIMER
ASHRAE uses its best efforts to promulgate Standards and Guidelines for the benefit of the public in light of available information and
accepted industry practices. However, ASHRAE does not guarantee, certify, or assure the safety or performance of any products, components,
or systems tested, installed, or operated in accordance with ASHRAE’s Standards or Guidelines or that any tests conducted under its
Standards or Guidelines will be nonhazardous or free from risk.

ASHRAE INDUSTRIAL ADVERTISING POLICY ON STANDARDS


ASHRAE Standards and Guidelines are established to assist industry and the public by offering a uniform method of testing for rating
purposes, by suggesting safe practices in designing and installing equipment, by providing proper definitions of this equipment, and by providing
other information that may serve to guide the industry. The creation of ASHRAE Standards and Guidelines is determined by the need for them,
and conformance to them is completely voluntary.
In referring to this Standard or Guideline and in marking of equipment and in advertising, no claim shall be made, either stated or implied,
that the product has been approved by ASHRAE.
© ASHRAE (www.ashrae.org). For personal use only. Additional reproduction, distribution,
or transmission in either print or digital form is not permitted without ASHRAE's prior written permission.

CONTENTS
ASHRAE Guideline 0-2013,
The Commissioning Process
SECTION PAGE
Foreword .....................................................................................................................................................................2
1 Purpose.............................................................................................................................................................2
2 Scope ................................................................................................................................................................2
3 Utilization...........................................................................................................................................................3
4 Definitions .........................................................................................................................................................3
5 Predesign Phase...............................................................................................................................................4
6 Design Phase....................................................................................................................................................8
7 Construction Phase.........................................................................................................................................12
8 Occupancy/Occupation Phase........................................................................................................................16
Informative Annex A: Guide for Developing Supplementary Technical Guidelines for the
Commissioning Process ....................................................................................................................19
Informative Annex B: Commissioning Process Flow Chart ...................................................................................22
Informative Annex C: Cost and Benefits of the Commissioning Process..............................................................24
Informative Annex D: Commissioning Process Documentation Matrix .................................................................25
Informative Annex E: Commissioning Process Request for Qualifications ...........................................................28
Informative Annex F: Roles and Responsibilities ..................................................................................................31
Informative Annex G: Commissioning Plan...........................................................................................................33
Informative Annex H: Acceptance Plan.................................................................................................................34
Informative Annex I: Owner’s Project Requirements Workshop Guidance ...........................................................36
Informative Annex J: Owner’s Project Requirements............................................................................................38
Informative Annex K: Basis of Design (BoD).........................................................................................................42
Informative Annex L: Specifications ......................................................................................................................43
Informative Annex M: Construction Checklists......................................................................................................49
Informative Annex N: Quality-Based Sampling Examples ....................................................................................54
Informative Annex O: Systems Manual .................................................................................................................57
Informative Annex P: Training Manual and Training Needs..................................................................................59
Informative Annex Q: Addenda Description Information .......................................................................................65

NOTE

Approved addenda, errata, or interpretations for this guideline can be downloaded free of charge from the ASHRAE
Web site at www.ashrae.org/technology.

© 2013 ASHRAE
1791 Tullie Circle NE · Atlanta, GA 30329 · www.ashrae.org · All rights reserved.
ASHRAE is a registered trademark of the American Society of Heating, Refrigerating and Air-Conditioning Engineers, Inc.
ANSI is a registered trademark of the American National Standards Institute.
© ASHRAE (www.ashrae.org). For personal use only. Additional reproduction, distribution,
or transmission in either print or digital form is not permitted without ASHRAE's prior written permission.

(This foreword is not part of this standard. It is merely Clear, concise, complete, and correct documenting of the
informative and does not contain requirements necessary OPR allows for emphasis on commissioning as an integral
for conformance to the standard. It has not been pro- process for achieving the facilities owner's expectations. The
cessed according to the ANSI requirements for a standard goal of a Guideline 0 Commissioning Plan is a fully func-
and may contain material that has not been subject to tional, fine-tuned facility, including all facility elements and
public review or a consensus process. Unresolved objec- assemblies, complete documentation, and a trained operating
tors on informative material are not offered the right to and maintenance staff at the significant completion milestone.
appeal at ASHRAE or ANSI.) It provides a methodology for implementing the commission-
ing process to building elements and assemblies for new con-
FOREWORD struction, and major renovations to existing facilities at a
level compatible with Owner input.
The latest version of Guideline 0 continues in demonstrat- A Guideline 0 Commissioning Plan places emphasis on
ing best practice principles for applying the whole-building documentation that transfers the OPR to the design criteria
commissioning quality process in facility elements. Guideline and construction documents, and on continuity of information
0 outlines the process for achieving, validating, and document- from one party to the next, providing value and the opportu-
ing the performance of facility elements in meeting the defined nity to improve the work process. The Guideline 0 Commis-
objectives and criteria of the Owner. This quality process sioning Plan also provides for the facility operating and
extends through all phases of new or major renovation proj- maintenance personnel training using actual performance
ects, from predesign to owner occupancy and operation, with documentation demonstrating the design, installation, and
tasks during each phase to ensure verification of design, con- intent of the building elements and assemblies in meeting the
struction, and operator training meeting the Owner's Project OPR. Owners can use this process in validating their stated
Requirements (OPR). Guideline 0 describes the overall com- objectives and criteria from the significant completion mile-
missioning process in providing a uniform, integrated, and stone onward. Application of this facility performance docu-
consistent approach for commissioning facilities. mentation provides the Owner with the opportunity to
This edition of Guideline 0 recognizes and addresses continue the benefits of whole-building commissioning in
changes in project delivery systems resulting from the evolu- improving facility performance during the post occupancy
tion of whole-building commissioning into the life cycle and phase and beyond.
sustainable facilities measurement and verification pro- Annexes to this guideline have been included to assist in
cesses. Guideline 0 is a guide to methods in performing, further understanding the commissioning process. Based on
measuring, validating, and documenting information in the specific project experiences, annexes suggest ways to improve
design and building processes used in constructing new current practices. Annexes illustrate varying applications of
facilities and renovating existing facilities. These commis- commissioning processes for all projects, and can be viewed
sioning processes are applicable to all building elements as examples for how to develop documents and to define
used in the construction process. owner's needs, design criteria, basis of design, design con-
Guideline 0 applies to all project delivery phases in iden- cepts, verification and functional performance testing
tifying and applying the whole-building commissioning pro- requirements, documentation, and operator training.
cesses, activities, and requirements for all building elements The commissioning process, beginning at project incep-
and assemblies. This guideline provides the format that serves tion, is a valuable tool to the Owner in controlling the project
as the pattern for the Commissioning Plan for specific facility through each milestone. Structuring the phases of a typical
elements or assemblies. This common content organization project around the OPR gives the Owner the advantage of
focuses on specific information in achieving a closely coordi- continuously monitoring the progress and the cost of the proj-
nated set of documents used together in any combination ect on a real time basis. This includes predesign, design
accommodating specific OPRs. Varying OPRs and applicable development, construction documents, construction, and
levels of commissioning follow a uniform method. Guideline 0 postconstruction phases.
organization also provides for technical commissioning This update of Guideline 0 describes the total building
guidelines that avoid repeating general commissioning pro- commissioning process and the responsibilities of the Commis-
cesses, activities, and requirements, making them more con- sioning Authority and the Owner. Selecting and developing a
cise in focusing on their technical subjects. Commissioning Plan following Guideline 0 assures the Owner
Guideline 0 acknowledges the integration and interdepen- of whole-building commissioning meeting the OPR, and a sus-
dency of facility elements; i.e., a performance deficiency of tainable facility at the time of final acceptance of the work.
one element can result in less than optimal performance by
other elements. To achieve satisfactory performance of the 1. PURPOSE
facility and all of its elements, the entire facility should experi- 1.1 The purpose of this guideline is to describe the Commis-
ence commissioning beginning at the inception of the project. sioning Process capable of verifying that a facility and its sys-
This update of Guideline 0 emphasizes the important role tems meet the Owner’s Project Requirements (OPR).
of the Owner in determining the level and focus of the Com-
missioning Plan. This begins with more emphasis on defining 2. SCOPE
and clearly documenting the OPR in a Commissioning Plan 2.1 The procedures, methods, and documentation require-
detailing the Owner’s objectives in the work. ments in this guideline describe each phase of the project

2 ASHRAE Guideline 0-2013


© ASHRAE (www.ashrae.org). For personal use only. Additional reproduction, distribution,
or transmission in either print or digital form is not permitted without ASHRAE's prior written permission.

delivery and the associated Commissioning Processes from cable regulatory requirements, standards, and guidelines. The
predesign through occupancy and operation, without regard document includes both narrative descriptions and lists of
to specific elements, assemblies, or systems, and provide the individual items that support the design process.
following:
checklists: Verification checklists that are developed and used
a. Overview of Commissioning Process Activities during all phases of the commissioning process to verify that
the Owner’s Project Requirements are being achieved. This
b. Description of each phase’s processes
includes checklists for general verification, plus testing, train-
c. Requirements for acceptance of each phase
ing, and other specific requirements.
d. Requirements for documentation of each phase
e. Requirements for training of operation and maintenance commissioning (Cx): See Commissioning Process.
personnel Commissioning Authority (CxA): An entity identified by the
Owner who leads, plans, schedules, and coordinates the com-
2.2 These Commissioning Process guideline procedures
missioning team to implement the Commissioning Process.
include the Total-Building Commissioning Process (TBCxP)
as defined by National Institute of Building Sciences (NIBS) Commissioning Plan (Cx Plan): A document that outlines
in its Commissioning Process Guideline 0. the organization, schedule, allocation of resources, and docu-
mentation requirements of the Commissioning Process.
3. UTILIZATION
Commissioning Process (Cx Process): A quality-focused pro-
3.1 The application of this guideline depends on the Owner’s cess for enhancing the delivery of a project. The process
Project Requirements and how the project is designed, built, and focuses on verifying and documenting that the facility and all
operated. The process described in this guideline is written for a of its systems and assemblies are planned, designed, installed,
generic project and must be adapted to each project. tested, operated, and maintained to meet the Owner's Project
3.2 This guideline describes the Commissioning Process, and Requirements.
is supplemented by companion technical guidelines. A tech- Commissioning Process Activities (Cx Process Activities):
nical guideline describes the specific details to properly Components of the Commissioning Process.
implement the Commissioning Process relative to a specific
facility system or assembly. Annex A in this guideline pro- Commissioning Process Progress Report (Cx Process Prog-
vides the required format for developing technical guidelines ress Report): A document that details activities completed as
for the Commissioning Process. part of the Commissioning Process and significant findings
from those activities, which is continuously updated during
4. DEFINITIONS the course of a project. Usually incorporated into the Com-
missioning Plan as an ongoing appendix.
acceptance: A formal action, taken by a person with appro-
priate authority (which may or may not be contractually Commissioning Process Report (Cx Process Report): A docu-
defined) to declare that some aspect of the project meets ment that records the activities and results of the Commission-
defined requirements, thus permitting subsequent activities to ing Process. Usually developed from the final Commissioning
proceed. Plan with all of its attached annexes.
Basis of Design (BoD): A document that records the con- Commissioning Team (Cx Team): The individuals who
cepts, calculations, decisions, and product selections used to through coordinated actions are responsible for implement-
meet the Owner’s Project Requirements and to satisfy appli- ing the Commissioning Process.

FIGURE 1 Relationship between commissioning guidelines.

ASHRAE Guideline 0-2013 3


© ASHRAE (www.ashrae.org). For personal use only. Additional reproduction, distribution,
or transmission in either print or digital form is not permitted without ASHRAE's prior written permission.

construction checklist: A form used by the contractor to ver- similar product, assembly, or system; or a random sampling
ify that appropriate components are on-site, ready for installa- that has scientific statistical basis.1, 2, 3
tion, correctly installed, and functional. Also see checklists. recommissioning: An application of the Commissioning Pro-
construction documents: These include a wide range of doc- cess requirements to a project that has been delivered using
uments that vary from project to project and with the Owner’s the Commissioning Process. This may be a scheduled recom-
needs and with regulations, laws, and countries. Construction missioning developed as part of an Ongoing Commissioning
documents usually include the project manual (specifica- Process, or it may be triggered by use change, operations
tions), plans (drawings), and general terms and conditions of problems, or other needs.
the contract. retrocommissioning: The Commissioning Process applied to
contract documents: These include a wide range of docu- an existing facility that was not previously commissioned.
ments that vary from project to project and with the Owner’s This guideline does not specifically address retrocommission-
needs and with regulations, laws, and countries. Contract doc- ing. However, the same basic process should be followed
uments frequently include price agreements, construction from Predesign through Occupancy and Operations to opti-
management process, subcontractor agreements or require- mize the benefits of implementing the Commissioning Pro-
ments, requirements and procedures for submittals, changes, cess philosophy and practice.
and other construction requirements, timeline for completion, systems manual: A system-focused composite document that
and the construction documents. includes the operation manual, maintenance manual, and
coordination drawings: Drawings showing the work of all additional information of use to the Owner during the Occu-
trades to illustrate that equipment can be installed in the space pancy/Operations Phase.
allocated without compromising equipment function or test procedure: A written protocol that defines methods, per-
access for maintenance and replacement. These drawings sonnel, and expectations for tests conducted on components,
graphically illustrate and dimension manufacturers’ recom- equipment, assemblies, systems, and interfaces among sys-
mended maintenance clearances. tems.
issues and resolution log: A formal and ongoing record of training plan: A document that details the expectations,
problems or concerns—and their resolution—that have been schedule, budget, and deliverables of Commissioning Process
raised by members of the Commissioning Team during the Activities related to training of project operating and mainte-
course of the Commissioning Process. nance personnel, users, and occupants.
nominal group technique: A formal, structured brainstorm- verification: The process by which specific documents, com-
ing process used to obtain the maximum possible ranked ponents, equipment, assemblies, systems, and interfaces
input from a variety of viewpoints in a short period of time. among systems are confirmed to comply with the criteria
The typical approach is a workshop session where a question described in the Owner’s Project Requirements.
is presented; the attendees record their responses individually
on a piece of paper; the individual responses are recorded on a 5. PREDESIGN PHASE
flip chart without discussion in a round robin fashion, all of 5.1 Introduction
the responses are discussed; and then the participants rank 5.1.1 Predesign is a preparatory phase of the project delivery
their top five responses. process in which the OPR is developed and defined. Informa-
Ongoing Commissioning Process (OCx): A continuation of tion about the project is gathered, including program require-
the Commissioning Process well into the Occupancy/Opera- ments, community context, codes and regulations, site and
tions Phase to verify that a project continues to meet current climate, facility context and function, facility technology, sus-
and evolving Owner’s Project Requirements. Ongoing Com- tainability, cost, schedule, and the client’s (including owner,
missioning Process Activities occur throughout the life of the occupants, operators, and maintenance personnel) needs and
facility; some of these will be nearly continuous in implemen- capabilities.
tation, and others will be either scheduled or unscheduled (as 5.1.2 This phase is critical to the Cx Process because the
needed). documented OPR forms the foundation for the design, con-
Owner’s Project Requirements (OPR): A document that struction, and occupancy and operation of the facility and are
details the functional requirements of a project and the expec- the basis for the Cx Plan and schedule. Starting the Cx Pro-
tations of how it will be used and operated. These include cess during the Predesign Phase facilitates project communi-
project goals, measurable performance criteria, cost consider- cation by monitoring the OPR from Predesign through
ations, benchmarks, success criteria, and supporting informa- Design, Construction, and Occupancy and Operations and by
tion. (The term Project Intent is used by some owners for their verifying decisions in these phases with the written docu-
Commissioning Process Owner’s Project Requirements.) ments called the Owner's Project Requirements and the BoD.
5.1.3 Predesign-Phase Cx Process objectives include the
quality-based sampling: A process for evaluating a subset following:
(sample) of the total population. The sample is based on a
known or estimated probability distribution of expected val- a. Developing the OPR
ues; an assumed statistical distribution based on data from a b. Identifying a scope and budget for the Cx Process

4 ASHRAE Guideline 0-2013


© ASHRAE (www.ashrae.org). For personal use only. Additional reproduction, distribution,
or transmission in either print or digital form is not permitted without ASHRAE's prior written permission.

c. Developing the initial Cx Plan include testing soils, surveying, or other requirements during
d. Acceptance of Predesign-Phase Cx Process Activities Predesign.
e. Review and use of lessons-learned information from pre- 5.2.1.6 Responsibilities of the Cx Team during the Prede-
vious projects sign Phase include the following:
5.2 Predesign-Phase Cx Process Activities a. Assist Owner in preparing requests for project services
5.2.1 Predesign-Phase Cx Process Responsibilities that outline the roles and responsibilities developed in the
Cx Plan.
5.2.1.1 During the Predesign Phase, a Cx Team is formed
b. Facilitate development and documentation of the OPR.
to oversee, implement, and accomplish the Cx Process Activ-
c. Develop scope and format for project systems manual and
ities detailed in this guideline. Responsibility for leadership
select/designate entity responsible for developing this
of the Cx Team should be defined and assigned at the begin-
manual. Add this entity to the Cx Team where appropri-
ning of the Predesign Phase. The term used for the person
ate.
with overall responsibility for the Cx Process is “Cx Author-
d. Develop scope and budget for project-specific Cx Process
ity (CxA).” The Cx Team members must be available for
Activities.
meetings, have the qualifications to contribute to the develop-
e. Verify that Cx Process Activities are clearly stated in all
ment of the Owner's Project Requirements, and have the
project scopes of work.
authority to make decisions binding on the firms/constituen-
f. Integrate the Cx Process Activities into the project sched-
cies they represent. Lines of authority and lines of communi-
ule.
cation in determining Cx Team members’ responsibilities
g. Build and maintain cohesiveness and cooperation among
shall be documented. The Cx Team composition must be
the project team.
based on the scope of the Cx Process services established for
h. Coordinate Owner’s representative’s participation as
the project.
defined in Section 5.2.1.2.
5.2.1.2 The Owner must assign (or contract for) appropri- i. Conduct and document Cx Team meetings.
ate representatives to participate on the Cx Team, both from j. Identify who will accomplish the Cx Process Activities.
within and external to their organization. Cx Team responsi- k. Review Predesign-Phase documents for compliance with
bilities should be consistent with the agreements between par- the OPR.
ties involved in the project, and such agreements must clearly l. Write the initial Cx Plan.
address Cx Process responsibilities. m. Develop the initial format to be used for Issues and Reso-
5.2.1.3 Essential team members during the Predesign lution Logs throughout, and for each phase of, the Cx Pro-
Phase include Owner’s representatives, the CxA, predesign cess.
and programming professionals, design professionals, and (if n. Track and document issues and deviations relating to the
known) the construction/program/project managers. The CxA OPR and document resolutions in the Issues and Resolu-
can assist the Owner in identifying and selecting these initial tion Log.
Cx Team members. Owner's representatives will include the o. Write and review Cx Process Progress Reports.
project manager, occupants or users, facility manager, and
operation and maintenance personnel. Including operation 5.2.2 Develop OPR
and maintenance personnel on the Cx Team will help ensure 5.2.2.1 The OPR forms the basis from which all design,
that important operation and maintenance issues are included construction, acceptance, and operational decisions are made.
in the Owner's Project Requirements. The Owner will gener- An effective Cx Process depends on a clear, concise, and
ally need to reconcile conflicting project requirements and comprehensive OPR document. It includes information to
provide feedback on decisions to the Cx Team. The design help the project team to properly plan, design, construct,
team members and CxA can assist the Owner in reconciling operate, and maintain systems and assemblies.
conflicting technical requirements. 5.2.2.2 The CxA facilitates the development of the OPR.
5.2.1.4 The Cx Team will evolve as a project progresses. Input will be gathered from all team members.
During successive phases, the active membership of the Cx 5.2.2.3 Each item of the OPR shall have defined perfor-
Team may shift to meet the unique requirements of each mance and acceptance criteria. Those that can be bench-
phase. Contractors and vendors, for example, may join the Cx marked should have the benchmark defined in specific terms
Team after they are under contract or after the start of con- and the means of measurement defined.
struction. 5.2.2.4 The OPR should include the following:
5.2.1.5 Predesign-Phase Cx Process Activities described a. Project schedule and budget.
in this section to be performed by the design team must be b. Cx Process scope and budget.
included in the scope of services described in the “Owner- c. Project documentation requirements, including format for
Design Professional Service Agreement.” These Cx Process submittals, training materials, reports, and the systems
Activities may be more than are normally required in their manual. Consideration should be given to use of elec-
scope of services. The scope of services in the “Owner- tronic format documents and records where appropriate.
Design Professional Service Agreement” should also include d. Owner directives.
the requirement to cooperate with the CxA during Predesign, e. Restrictions and limitations.
Design, and Construction phases of the project. This may f. User requirements.

ASHRAE Guideline 0-2013 5


© ASHRAE (www.ashrae.org). For personal use only. Additional reproduction, distribution,
or transmission in either print or digital form is not permitted without ASHRAE's prior written permission.

g. Occupancy requirements and schedules. reports and workshop outcomes, and other activities in the
h. Training requirements for Owner’s personnel. Predesign Phase.
i. Warranty requirements. 5.2.3 Identify the scope and budget for the Cx Process.
j. Benchmarking requirements. 5.2.3.1 The scope of the Cx Process will vary from one
k. Operation and maintenance criteria for the facility that project to another. The Cx Team develops the scope for the
reflect the Owner’s expectations and capabilities and the Cx Process. The experiences of the programming team, users,
realities of the facility type. designers, CxA, and the Owner with similar and previous
l. Equipment and system maintainability expectations, facilities and projects can aid in establishing a scope for the
including limitations of operating and maintenance per- Cx Process. Additional insight regarding the scope of the Cx
sonnel. Process can be obtained from code officials, regulations, pub-
m. Quality requirements for materials and construction. lished information on similar facilities, and information in the
n. Allowable tolerance in facility system operations. technical Cx Process guidelines.
o. Energy efficiency goals. 5.2.3.2 A well-defined scope permits the establishment of
p. Environmental and sustainability goals. an appropriate budget allocation for the Cx Process. The Cx
q. Community requirements. Process budget should be realistic, distributed by phase, activ-
r. Adaptability for future facility changes and expansion. ity, and entity (Owner, CxA, design professional, and contrac-
s. Systems integration requirements, especially across disci- tors), and not subject to reduction without an express change
plines. in the Cx Plan. Lack of a properly defined and maintained Cx
t. Health, hygiene, and indoor environment requirements. Process budget will adversely affect the Cx Process and the
u. Acoustical requirements. success of the facility in meeting the OPR.
v. Vibration requirements. 5.2.3.3 Typically the Owner will focus the Cx Process
w. Seismic requirements. efforts on selected systems or assemblies based on the budget,
x. Accessibility requirements. systems or assemblies where the Owner has experienced pre-
y. Security requirements. vious problems, on complex systems and assemblies, or on
z. Aesthetics requirements. the criticality of the system or assembly in providing for the
aa. Constructability requirements. OPR. The Cx Process can focus on the following:
ab. Communication requirements. a. Substructure: includes basement and foundations
ac. Applicable codes and standards. b. Shell: includes superstructure, roof, walls, fenestration,
(See Table J-1 in Annex J for an example matrix that can and exterior doors
assist in the development of the OPR.) c. Interiors: includes interior construction, wall, floor, and
5.2.2.5 Obtaining the information and criteria for the ceiling finishes, partitions, interior doors, stairways, hard-
OPR document requires input from all key facility users and ware, and fitting specialties
operators. The method used to obtain the information should d. Services: includes controls, HVAC&R systems, electrical
allow the different user groups and operators to interact. systems, fire and life safety systems and assemblies, secu-
Nominal group technique workshops, interviews, and surveys rity systems, communication systems, plumbing systems,
can be used to obtain this input, with decreasing levels of conveying systems, and specialty or technology systems
interaction attained, respectively, for each type. See Annex I e. Equipment and furnishings
for additional guidance. f. Sitework
5.2.2.6 The OPR becomes part of the systems manual g. Landscaping
documentation.
5.2.4 Develop the Cx Plan
5.2.2.7 The OPR is a document that evolves through each
project phase. As decisions are made during the Design, Con- 5.2.4.1 The Cx Plan identifies processes and procedures
struction, and Occupancy/Operations Phases, this document necessary for a successful Cx Process. The Cx Plan addresses
will be updated to reflect the current project requirements of the OPR and reflects the defined scope and budget for the Cx
the Owner. It is the primary tool for benchmarking success Process.
and quality at all phases of the project delivery and through- 5.2.4.2 The Cx Plan includes a schedule of Cx Process
out the life of the facility. Activities, individual responsibilities, documentation require-
5.2.2.8 Make reference to the Owner's Project Require- ments, communication and reporting protocols, and evalua-
ments in the bidding documents as “information available to tion procedures. Evaluation procedures include the review
bidders.” It must be noted in the contract documents that the and verification to the OPR of the design documents, contract
OPR is issued for information only and that this document documents, construction and test procedures.
shall not define, nor shall it be used to interpret, the require- 5.2.4.3 The Cx Plan is continually updated during the life
ments of the contract. of a project to reflect changes in planning, design, construc-
5.2.2.9 Use quality-based sampling for verification of tion, and occupancy and operations. During the Predesign
each activity or task to determine how well it meets or relates Phase, the Cx Plan focuses on the scope of the Cx Process
to the OPR in the Predesign Phase. This includes program- during the Design Phase. The Construction-Phase and Occu-
ming documents, defined scope-of-design services, special pancy/Operations Phases are included, but details are usually

6 ASHRAE Guideline 0-2013