PURCHASE ORDER
Vendor Code :- VA83 Order No. :- 3900014662/146
VIKRANT FORGE PRIVATE LIMITED Order Date :- 22.08.2022
2B, SHYAMKUNJ Release Date :- 28.11.2022
12C, LORD SINHA ROAD
KOLKATA Contact Person :- B RAVINDRA KUMAR
West Bengal E-Mail :- b.ravindra@partners.tatasteel.com
Pin Code: 700071 Phone No :- 9199439209
India Fax No :-
E-Mail :- vikrantforge@smithy.in Collective No :- SEG.ROLLER
Phone No :- 9874029654 Validity Start Date :- 30.08.2022
Fax No. :- Validity End Date :- 25.08.2023
Quotation :- 22-23/176 /28.07.2022
Please deliver/execute the following goods/services according to the terms ,conditions and
instructions as specified herewith.Please acknowledge this order.
Item Details
Item text :
Complete manufacturing and supply as per the finished drg. no.-
2271-27-127/0
Item Charges
Gross Price 21,700.000 INR
694,400.000 INR
IN: Integrated GST 18.000 %
124,992.000 INR
--------------
819,392.000 INR
---------------------------------------------------------------------------------------
Item No. :- 00030 Total Qty :- 32.000NOS
Gross Price :- 23,700.00 INR Per1 NOS
Requisitioner:- 153650(Atul KumarKarn),Email:ATULK.KARN@TATASTEEL.COM
Material No :- T00000000227127152 All CGST-SGST/IGST @ 18% Creditable
WBS No :-TGCRS/0000550-38-05
Critical Spare :-
Order Continuation Sheet
Page: 2 of 31
Order No. 3900014662/146
Item Details
Item text :
Complete manufacturing and supply as per the finished drg. no.-
2271-27-152/0
Item Charges
Gross Price 23,700.000 INR 758,400.000 INR
IN: Integrated GST 18.000 % 136,512.000 INR
--------------
894,912.000 INR
---------------------------------------------------------------------------------------
Item No. :- 00040 Total Qty :- 18.000NOS
Gross Price :- 24,700.00 INR Per1 NOS
Requisitioner:- 153565_A(ROHITMAHATO),Email:rohit.mahato@partners.tatasteel.com
Material No :- T00000000227127128 All CGST-SGST/IGST @ 18% Creditable
WBS No :-TGCRS/0000550-37-01
Critical Spare :-
Material Desc :- ROLLER DIA 130x695
Material Group :- 802
Material Group Desc :- Machined Part TGS
Item Details
Item text :
"Complete manufacturing and supply of ROLLER DIA 130x695 as per
finished drawing no.- 2271-27-128/0
Delivery text :
Item Charges
Gross Price 24,700.000 INR 444,600.000 INR
IN: Integrated GST 18.000 % 80,028.000 INR
--------------
524,628.000 INR
---------------------------------------------------------------------------------------
Item No. :- 00050 Total Qty :- 32.000NOS
Gross Price :- 27,700.00 INR Per1 NOS
Requisitioner:- 153650(Atul KumarKarn),Email:ATULK.KARN@TATASTEEL.COM
Material No :- T00000000227127153 All CGST-SGST/IGST @ 18% Creditable
WBS No :-TGCRS/0000550-38-06
Critical Spare :-
Material Desc :- ROLLER DIA 140x695
Material Group :- 802
Material Group Desc :- Machined Part TGS
Prod./insp. memo :- X20Cr13+QT 800
Ind. Std Desc :- -
Drawing Document :- 2271-27-153 Doc Vers No:- 0
Item Details
Item text :
Complete manufacturing and supply as per the finished drg. no.-
2271-27-153/0
Item Charges
Gross Price 27,700.000 INR 886,400.000 INR
IN: Integrated GST 18.000 % 159,552.000 INR
--------------
1,045,952.000 INR
---------------------------------------------------------------------------------------
Item No. :- 00070 Total Qty :- 36.000NOS
Gross Price :- 25,700.00 INR Per1 NOS
Requisitioner:- 153650(Atul KumarKarn),Email:ATULK.KARN@TATASTEEL.COM
Material No :- T00000000227127162 All CGST-SGST/IGST @ 18% Creditable
WBS No :-TGCRS/0000550-38-07
Critical Spare :-
Material Desc :- ROLLER DIA 150x575
Material Group :- 802
Order Continuation Sheet
Page: 4 of 31
Order No. 3900014662/146
Item Details
Item text :
Complete manufacturing and supply as per the finished drg. no.-
2271-27-162/0
Item Charges
Gross Price 25,700.000 INR 925,200.000 INR
IN: Integrated GST 18.000 % 166,536.000 INR
--------------
1,091,736.000 INR
---------------------------------------------------------------------------------------
Item No. :- 00080 Total Qty :- 24.000NOS
Gross Price :- 31,600.00 INR Per1 NOS
Requisitioner:- 153565_A(ROHITMAHATO),Email:rohit.mahato@partners.tatasteel.com
Material No :- T00000000227127163 All CGST-SGST/IGST @ 18% Creditable
WBS No :-TGCRS/0000550-37-05
Critical Spare :-
Material Desc :- ROLLER DIA 150x695
Material Group :- 802
Material Group Desc :- Machined Part TGS
Item Details
Item text :
"Complete manufacturing and supply of ROLLER DIA 150x695 as per finished
drawing no. 2271-27-163/0
Delivery text :
Bill To & Ship To
Tata Steel Limited
11, Station Road,
Burma mines,
Jamshedpur
831007
GST No-: 20AAACT2803M2ZO
Delivery Address : ,
Telephone No :
Fax No :
Unloading Point : Project stores
Item Charges
Gross Price 31,600.000 INR 758,400.000 INR
IN: Integrated GST 18.000 % 136,512.000 INR
--------------
894,912.000 INR
---------------------------------------------------------------------------------------
Header Details
Header text:
"=====================================================================
GENERAL CONDITION OF CONTRACT:
=======================================================================
ORDER ACCEPTANCE NOTE:
-------------------------------------
PLEASE CONFIRM ACCEPTANCE AND RECEIPT OF PURCHASE ORDER WITHIN A WEEK'S
TIME TO THE BUYER E-mail: Ravindra.kumar2@tatasteel.com
=======================================================================
COMMMUNICATION PROTOCOL:-
-----------------------------------------------------------------------
All post order communication should be addressed to (mandatory):
a. expeditingkpo@tatasteel.com
-----------------------------------------------------------------------
All inspection related issues should be marked to (mandatory):
a. kpoinspectionoffice@tatasteel.com
======================================================================="
Header note:
"TERMS AND CONDITIONS FOR SUPPLY ORDERS AT TGS
=============================================
1. SCOPE OF SUPPLY
Unless otherwise expressly limited in the Technical Specifications as
per Annexure-A, the Supplier #s obligation cover design &
engineering, Manufacture, Supply of Equipment / Materials / Items /
Bulks etc., modification, if any, testing, pre-commissioning; start-up
& commissioning and guarantee the performance guarantee parameters
of the Equipment / Materials / Items / Bulks etc. as per applicable BIS
or other specified standards, in accordance with the plans,
specifications, drawings, codes and any other documents.
2. PRICE BASIS
The Purchaser hereby agrees to pay to the Supplier the Contract Price in
consideration of the performance by the Supplier of its res
ponsibilities, liabilities and obligations under the Agreement. The Contract Price shall be the
aggregate of: [amount of foreign
currency in words], [amount in figures]. The Purchaser will pay only
Goods & Services Tax (GST) and applicable cess thereto over
Contract Price and all other taxes, duties, cess, levies etc. shall in
Supplier#s #s account.
The Supplier shall support Purchaser on a best effort and timely basis
to sort out the discrepancies communicated by GSTIN, if any.
3. TIME OF COMPLETION
Entire supply shall be completed in all respects within ### months from
the date of award of this Order/ Drawing approval, as applicable.
9. GUARANTEE
The equipment and materials supplied by the Supplier shall be guaranteed
Order Continuation Sheet
Page: 8 of 31
Order No. 3900014662/146
If due to any reason whatsoever the tests were not witnessed by the
Purchaser/his authorized representative, the Inspection Certificate and
the DCC may be issued by the Purchaser within Seven (7) days after the
receipt of the inspection and test reports from the Supplier, provided
such inspection and test reports are in compliance with agreed
Inspection and Test Procedure.
No Equipment/ items shall be shipped or otherwise dispatched before the
DCC has been issued by the Purchaser/his authorized representative.
To follow up and expedite manufacturing activities, the Purchaser and/or
his authorized representative shall have exclusive right to visit all
manufacturing premises of the Supplier or his Sub-Suppliers to ascertain
progress of manufacturing and accessories as per the details reported by
the Supplier in his status reports/periodic detailed reports on
manufacturing. Supplier's status report will indicate the progress of
manufacturing vis-à-vis requirements as per the agreed manufacturing
programme. Delays, if any, in manufacturing will be identified in the
status report by the Supplier together with suggested remedial measures
and action plan for meeting the schedule. The Supplier shall provide all
necessary assistance to the Purchaser and/or his authorized
representative to visit manufacturer's premises and conduct reviewing of
status of manufacture and collect information thereof.
Under circumstances where Purchaser discovers No response from supplier/
sub-supplier, Purchaser shall intimate the supplier by a written notice
to respond within fifteen (15) days, after which Purchaser has a sole
right to purchase the items from elsewhere at the risk and cost of the
supplier.
11. MARKINGS
Marking in English block letters shall be clearly stenciled on the
packages with good quality non-fading paint in characters sufficiently
large as the size of the package will permit.
One and the same set of marking should appear on all four sides of the
packages. No marking need be made on top and bottom. The following
markings shall appear prominently on all the four sides of the packages
with 75 mm high letters.
TATA STEEL GROWTH SHOP,
#########.. (Description of Equipment/item)
Jamshedpur
Jharkhand, India
Purchase Order No. ................, dated ####..
Package No. ................
Brief Description: Equipment/Accessories/Commissioning Items /Initial
Fills (to mark as applicable)
Order Continuation Sheet
Page: 9 of 31
Order No. 3900014662/146
17.2 The items of supply those are completed and ready for final
inspection within twenty-one (21) days after the supplier#s receipt of
notice of termination shall be accepted by the Purchaser at the Contract
terms and price. For the remaining items of works the Purchaser may
select.
i. To have any portion completed and delivered at the contract terms and
prices and/or.
ii. To cancel the remainder and pay to the supplier an agreed amount for
partially completed works.
18. INDEMINITY
18.1 The supplier assumes responsibility and shall hold harmless the
Purchaser from all liabilities, claims, demands, costs, charges,
expenses, taxes and assessments, including penalties, direct damages,
proceedings, reasonable attorney's fees and litigation expenses, arising
Order Continuation Sheet
Page: 11 of 31
Order No. 3900014662/146
iv. Any claim with regard to designs, methods, process including but not
limited to claims arising out of infringement of Intellectual Property
legislations and amendments there to, patent, trademark, property
information, know-how, copyright, unpatented inventions or any
unauthorised use of work.
The Supplier shall defend at his own expenses any suit proceedings for
any claim asserted against the Purchaser. The Purchaser shall give
reasonable assistance required in defending the suit and Purchaser
reserves the right to defend/settle the claim if Supplier fails to
defend diligently any such suits or proceedings without relieving the
Supplier of his obligation.
20. REMEDIES
The Purchaser shall be entitled to recover all costs, charges, damages
Order Continuation Sheet
Page: 12 of 31
Order No. 3900014662/146
or expenses, which the Purchaser may have paid, for which under the
Contract/order the Supplier is liable. All costs or expenses for which
the Supplier may become liable to the Purchaser shall be recovered by
the Purchaser from the invoices of the Supplier. Such recovery can
further be made by the Purchaser from any sum then due or which at any
time thereafter may become due to the Supplier under this or any other
Contract/order with the Purchaser. Should this sum be not sufficient to
cover the full amount recoverable, the Supplier shall pay to the
Purchaser, on demand, the remaining balance due.
21.2 The Purchaser will promptly notify the Supplier in writing of any
such claim, suit, action or proceeding coming to its attention or
knowledge, giving authority and all available information and assistance
for the Supplier's defence of the same. If at any time the installation
of the Plant or any part thereof which has been manufactured or procured
based on the said Design and Drawing, knowhow, technical knowledge, or
the use thereof in India for the purpose for which it is furnished, or
the sale of products produced by the said Plant , is prevented or
enjoined because of patent infringement or claimed infringement related
to the Design and Drawing, knowhow, technical knowledge supplied by the
Supplier, the Supplier shall promptly at his own expense, either procure
for the Purchaser the right to use and continue to use such Plant or
replace the same at his own expense with equally efficient
non-infringing Plant satisfactory under all requirements of the Contract
within the reasonable period to be agreed between the parties, so that
the operation of the Purchaser's Plant will not be unduly delayed or
interrupted to mitigate the loss of Purchaser as far as possible. If
shipment of the plant, or any part thereof is prevented by attachment,
injunction or otherwise at, or in the course of transit from the
Supplier's factory or other point of origin to the site, as a result of
any claim of Patent infringement, the Supplier shall, at his own cost
and expense, promptly furnish and post the necessary bond or take such
other steps as may be necessary to enable shipment to be made without
delay. The Purchaser will have the right to retain counsel of its own
choice to collaborate in the defense of any such claim, suit, action or
proceeding.
22. COPYRIGHT
The copyright in all drawings, documents and other materials containing
data and information furnished by the Supplier to the Purchaser herein,
shall remain vested in the Supplier; however, the Purchaser shall have
Order Continuation Sheet
Page: 13 of 31
Order No. 3900014662/146
the right to use all such drawings, documents and other material, data
and information for execution of the contract and operation &
maintenance of the Project being subject of the Contract.
24. JURISDICTION
The parties hereby agree that jurisdiction over any dispute arising
under this Contract shall be vested only in the Courts of India and the
parties submit to the exclusive jurisdiction of the said courts at
Jamshedpur in the state of Jharkhand.
25. ARBITRATION
Any dispute arising out of or in connection with this Purchase Order or
its performance, including the validity, interpretation, application,
breach or cancellation thereof shall be settled and finally decided as
per the Indian Arbitration and Conciliation Act 1996 and amendments
therein. The arbitration shall be conducted by a Sole Arbitrator, with
Jamshedpur as the seat and language of arbitration being English.
arrived at within a period of one (1) month from the expiry of the three
(3) months referred to above, the Contract shall be deemed to have
expired at the end of the said three (3) months referred to above. The
above-mentioned expiry of the Contract will imply that both the parties
have the obligation to reach an Agreement regarding the winding up and
financial settlement of the Contract.
29. SEVERANCE
If any provision of this Agreement is prohibited by law or judged by a
court to be unlawful, void or unenforceable, the provision shall, to the
extent required, be severed from this Agreement and rendered ineffective
as far as possible without modifying the remaining provisions of this
Agreement, and shall not in any way affect any other circumstances of or
the validity or enforcement of this Agreement.
Shipping instructions:
"ANNEXURE-D, PACKING AND HANDLING
================================
The Seller confirms that the Items shall be packed in accordance with
the norms followed internationally so as to protect the contents from
damage during transit from point of manufacture until its arrival at
Tata Steel, Growth Shop (TGS) or any location as specified by the
Purchaser, under conditions which may involve multiple handling, ocean
shipment, storage under tropical conditions as well as subsequent
movement by road transport in India, exposure to heat, moisture, rain
etc. and possibility of pilferage. Packing shall be of quality suitable
for sea transport and for storage in tropical conditions. However,
special precautions out-lined in clauses below shall be followed by the
Order Continuation Sheet
Page: 15 of 31
Order No. 3900014662/146
Seller.
SPECIAL PRECAUTIONS
-------------------
a) The Seller shall properly clean the Plant and Equipment and apply one
coat of rust inhibitor and a shop coat of paint as per Purchaser#s
requirement for Painting.
Seller shall ensure that the all shipments are properly marked with CG,
so as to ensure safety of the consignments during transit and handling.
2. HANDLING
The Seller shall, wherever required furnish his expert advice and
handling instructions to the Purchaser, free of cost in regard to the
safe handling while transportation, storage, installation and erection
of Supplied items.
However, if the damages are due to the fault of the Purchaser (for not
complying with the handling instructions as communicated by the Seller),
then the same shall be modified/replaced by the Seller on chargeable
basis to the Purchaser.
"
Terms of payment:
100% payment within 30 days from the date of GRN
:
E&P/NO/2022/03815 Date 29.07.2022
It is mandatory for all vendors to comply with SA8000 norms as per the
checklist submitted by you to us. Non-compliance of the same detected at
any point of time will lead to cancellation of the order or any other
action or both as deemed fit by Tata Steel.
Vehicles having age more than 15 years would not be allowed inside the
plant. Hence all suppliers/contractors & transporters are requested to
take note of this & ensure that this is strictly followed as security
will not allow over age vehicles effective from these dates.
Vehicles / cars shall be provided with back and side view mirrors and
Order Continuation Sheet
Page: 18 of 31
Order No. 3900014662/146
seat belts in the front as well as at the back seats. All passengers
shall tie the seat belts while travelling in the vehicles / cars.
Vehicles / cars shall possess tool kits, jack, Stepney, first aid box
and an umbrella.
4. Drivers shall possess all valid documents while driving the vehicles
/ cars such as driving licence, owner book, tax token, insurance, road
permit, pollution certificate etc.
Definitions
'Purchaser' means Tata Steel Limited, who awards the supply order to
Supplier and shall include its directors, employees, successors,
engineers, agents or any of them.
1) Order Date
The Order Release Date mentioned in the Order is the Order Date.
2) Pricing type
2.1 The prices indicated are FOR Door Delivery, Tata Steel Growth Shop
,Gamharia-832108 (unless otherwise specified in the order), properly
packed, by road transport. For locations other than Tata Steel Growth
Shop, the destination will be as specified in the order.
2.2 The prices indicated shall remain fixed, firm and binding (unless
otherwise specifically indicated elsewhere in the order) till completion
of delivery of all equipment/goods.
2.3 The Supplier shall be solely responsible and liable for his wrong
assumptions/omissions/consideration, if any, and shall inclusive of
all-applicable taxes and duties in the order price. In addition to
above, taxes and duties, if any, which are prevailing on the date of
issuance of order, as the case may be, but not considered by the
Supplier in the order price, shall be borne and paid for by the
Supplier.
Order Continuation Sheet
Page: 19 of 31
Order No. 3900014662/146
3. Freight charges:
The risk/title and ownership of goods shall remain with the Supplier
till the Equipment/items and materials are received by the Purchaser at
destination as per the order, in satisfactory condition.
Education cess payable against each item is indicated against the item
in the item charges in the order. Excise Duty and education cess &
Secondary higher education cess are payable by the Purchaser at actual
to the Supplier against documentary evidence to be submitted by the
Supplier subject to a maximum amount indicated separately in the Order
elsewhere (wherever applicable).
If the party has not submitted the proper excise invoice then payment
will be made after deducting the service tax and cess amount.
Cess amount plus the applicable taxes on the aforesaid excise element,
in case such amount has already been paid to the Supplier.
6. Sales tax.
Order Continuation Sheet
Page: 21 of 31
Order No. 3900014662/146
6.1 The supplier shall follow all the statutory provision of the
Jharkhand VAT Act, 2005 so that the Purchaser can avail the benefit of
Input Tax Credit (ITC) where ever applicable. The supplier shall also
issue form JVAT 404 against supply made by them on yearly basis.
In case of interstate purchase under CST Act. 'C" form shall be issued
under CST Act/Rules only when concessional rate of tax under CST has
been availed by the company.
6.1.1 bills@tatasteel.com
6.1.2 tgscform@gmail.com
On quaterly basis for obtaining 'C' form.
7. Terms of Delivery:
8. Road permit:
The supplier shall approach for issue of road permit, along with details
required to issue the road permit, at least 21 days prior to dispatch
date. For road permit please generate your request in e -procurement
site of Tata Steel. The details of training module for generation of
road permit request is available at e-Procurement site of Tata Steel.For
any further clarification please send your mail to the buyer concerned.
For road permit/waybill kindly raise the request to following email id-
1) tgsroadpermit@tatasteel.com
2) Contact number - 0657-6511381
The Supplier shall be responsible and liable for any loss of Road
Permits issued to him. In the event of loss of Road Permits, the
Supplier shall immediately lodge a F.I.R. in the nearest police station
and publish the information in local newspaper( One in English and other
in local language). The Supplier shall submit to the Purchaser one copy
each of the F.I.R. filed and the newspaper publication. Unless this is
done with respect to lost Road Permits, no fresh Road Permit shall be
issued to the Supplier.
SUPPLIER shall compensate the PURCHASER for any LOSS, COST, DAMAGE
,PENALTY suffered by the purchaser on account of loss of road permit/and
non-submission of required documents the demand levied by the Commercial
Tax Department on the PURCHASER .Supplier authorises the Purchaser to
recover the said amount of loss (any amount demanded by the Commercial
Tax Department including penalty etc), damage from the pending bills of
the Supplier. The Supplier undertakes to pay the Purchaser the same
amount as indicated above by a cheque/demand draft in case no amount can
be recovered from the pending bills of the Supplier.
9. Terms of Payment:
" Material description shall be clear and legible as per the order.
C) which under normal and proper use and maintenance proves defective
in workmanship or materials or deficient in performance, subject to
12. Delivery In the event of any variance between the delivery dates
indicated against the Item and the date calculated based on completion
period given in the Text of the Order, the date calculated based on the
completion period given in Text shall be binding for all contractual
purposes.
which Purchaser reserves the right to cancel the order and procure
materials from alternate suppliers and recover loss, if any, from the
supplier from any outstanding sums that may be due from Tata Steel to
the supplier against any of the orders/agreements entered into with the
supplier.
Tata Steel reserves the right to impose suitable penalty wrt late
delivery if any.
16. Markings:
One and the same set of marking should appear on all four sides of the
packages. No marking need be made on top and bottom. The following
markings shall appear prominently on all the four sides of the packages.
Each consignment must relate to one purchase order only and for each
package a separate set of challans must be submitted.
Packing of materials against more than one order in a case should be
done in a manner that the material against each order should be
separately packed, marked and listed on separate challans for easy
identification.
Jharkhand, India
Height ....................
Order Continuation Sheet
Page: 25 of 31
Order No. 3900014662/146
17. Shelf Life Items : In case of shelf life items, the remaining life
of the material at the time of delivery must be at least 80% of the
total life. In emergency, the item may be accepted after taking due
approval, if it is likely to be consumed within the expiry of the shelf
life.
Order.
In any of the cases described above, the Purchaser shall inform the
Supplier of its decision to cancel the Contract/Order or to terminate
the Supplier's services, in whole or part under it, specifying in such
notice the reason or the basis for this decision. The Supplier shall
within fifteen (15) days from the above notice of default, correct such
default or satisfy the Purchaser regarding the action taken by him for
the corrective action, failing which the Purchaser at his option will
cancel the Contract/Order. The Supplier shall immediately stop all work
in connection with the Contract/Order, except as directed by the
Purchaser. In such case, the Purchaser shall be at liberty to contract
with other parties or to perform with his own personnel those supplies/
services undertaken by the Supplier in the Contract/Order. In such case,
the Supplier shall be liable for any costs incurred by the Purchaser for
obtaining and/or erecting the balance of the plant from another party in
excess of the ordered price. In case of termination of part of the
Contract/Order, the Supplier will continue performance of the
Contract/Order to the extent not terminated by the Purchaser.
20. Arbitration:
The Award made by the Arbitral Tribunal shall become final and binding
upon the parties and shall be enforced in accordance with applicable
provisions of the Arbitration and Conciliation Act, 1996.
22. Inspection and Rejection: The Purchaser shall reserve the right to
reject/part accept the goods under following conditions;
e) Short/excess supply
23.1 Vehicle having age more than 15 years is not allowed inside the
Purchaser's premises.
23.4 Material Safety Data Sheet shall accompany each item (as specified
in the material specification) at the time of delivery.
herein and PURCHASER's RFQ. In case any conflict between the terms and
conditions given this Order and those in the RFQ, Technical
Specification or other tender documents, the terms and conditions given
herein shall prevail.
Ethics Counsellor :
A. Documents :
1) Invoice 1 + 1 Copies
2) Inspection Clearance Certificates2 ( Two )
3) Material Receipted Challan (wherever applicable) 2 (two)
4) Packing List duly Signed by Vendor 2 (two)
5) Original Buyers copy of Excise Duty Invoice 1+3 copies
6) Original Freight Document ( for reimbursement ) and Freight Bill 1 +
copies
7) Material Test Certificates / Inspection Report/MSDS 2 (two)
8) Bank Guarantee / Corporate Guarantee (wherever applicable) 1+3
copies
Name
PLEASE NOTE THAT THE COMMERCIAL INVOICE (IF ANY) / ORIGINAL FOR BUYER
(FOR EXCISABLE GOODS) / FREIGHT BILLS (IF ANY) ARE TO BE SUBBMITTED TO
INVOICE VERIFICATION (IV) SECTION OF TGS ACCOUNTS AND DUPLICATE FOR
TRANSPOTER, ROAD PERMITS AND OTHER DOCUMENTS ARE TO BE SUBMITTED,
ALONGWITH THE MATERIAL TO THE TGS STORES/KPO STORES ON THE CASE MAY BE.
Order Continuation Sheet
Page: 30 of 31
Order No. 3900014662/146
RMP &TSJ:
S. Murali
Sr. Manager, Cash Flow, E&P F&A
Tata Steel Limited
T-37, 1st Floor, Project Centre,
Jamshedpur- 831001
India
s.murali@tatasteel.com
TGS:
Amit Kumar Thakur,
Manager F&A,
B) Progress Bill :
Bills/Invoices must be prepared as per the Order requirements adhering to the GST norms
and with necessary documentation as per order and the check list given in Annexure-1
B.1 Submission of digitally signed Invoice in E-Proc System
B.2 Compile and scan GST Invoice with all supporting documents as mentioned above in one /
single PDF file and then digitally sign the document. Upload the digitally singed invoice along
with supporting documents in E-Proc Site. Details guidelines may be referred on E-Proc Site on
bill submission
C) Retention Claim:
C.1 Prepare claim letter in official letter head with bill wise detailsas per terms of payment
in the order. Scan the claim letter with detailsand retention certificate in one / single PDF
file. Digitally sign the PDF file and upload in E-Proc System.
If the retention is released against BG, vendor is required to submit the Original BG before
submission of Retention claim with locational F&A team for processing and confirmation
BG Submission: Same as A1
D) GST no for TATA STEEL
For TSL#s location:
In Odisha 21AAACT2803M1ZN
In Jharkhand 20AAACT2803M2ZO
Authorised Signatory
B RAVINDRA KUMAR