Penggunaan SNI IEC 62446-1:2016 pada

Panduan Komisioning PLTS Off-grid


Jakarta, 16 December 2020
A Quality Best
Standards Practice
ELREN Project
Central Regional
Gov. Gov.
Training Providers
RE off-grid
C actors D B

Coordination Platform Private Sector Monitoring System


Assoc. & Database

Anchoring knowledge on RE off-grid electrification in Indonesia


Evaluation Procurement
Installation
Operation & Service &
Planning Handover
Selection Commissioning Maintenance Repair

Gov. Inst. Private Sector Province Village Private Sector

Capacity Building & Training-of-Trainers


⚓Training Institutions
A complete set of documents to guide PV Mini
Grid Systems inspection process according to
standards, regulation and best practices

What is PV Mini Grid


Commissioning
Guideline?
Background
Ensure The System Quality

Current national
ENDEV regulation only make sure the
Different
Experiences Existing standards gives list of items systems safe,
inspector,
only cover PV On to be inspected reliable, and
on more than 300 different method
Grid Systems and not detail (no environmentally
visited sites (inconsistency)
acceptance friendly
criteria)
References

• National & International Standards


• IEC 62446 Ed.1.0 :2016, “Grid connected photovoltaic system –
Minimum requirements for system documentation, commissioning
tests and inspection” (SNI)
• IEC TS 62257-1 Ed 3.0 (2005-10), “Recommendations for renewable
energy and hybrid systems for rural electrification”
• IEC 61194 Ed. 1.0 (1992-12), “Characteristic parameters of stand-
alone photovoltaic (PV) system”
• National Regulation
• Regulation of Minister of Energy and Mineral Resources #38 Year
2018
• PUIL
• Commissioning and Inspection form of several local EPC and QC
companies
• Best Practices
PERMEN ESDM No. 38
Tahun 2018 (Mata Uji PLTS)

12/15/2020 Panduan Pemeriksaan dan Pengujian PLTS Terpusat Off-grid


Users

LIT

EPC Company

System Owner

Operator

Training Institution
Project Development Stages

12/15/2020
Contents

Document and
Introduction Inspection Testing
Labelling
• Objective • General Information • General • General
• References • System Designer • Risk Identification • Safety Prerequisite
• Project Development • System Installer • Component Inspection • Component Testing
Stages • Drawings • PV Array • PV Array
• PV System • Datasheet • Inverter • Inverter
Certification Process • Emergency System • Battery • Battery
• User Target • O&M • SCC • SCC
• Distribution Board • Distribution Board
• Lightning & • Lightning and
Grounding Protection Grounding Protection
• Monitoring and • Monitoring and
Control System Control System
• System Reliability

15/12/2020
Expected Duration
Commissioning steps

According to SNI IEC 62446 Ed.1.0 :2016


Component of Commissioning
Component of Commissioning
Document and Labelling

A. Engineering drawings
• Single line Diagram
• Layout
• Connection
B. As-built drawing
C. Warning signs
D. Components identification and
labelling
E. Standard operating procedure
F. Datasheet and user manual
Photovoltaic Array (Visual Inspection)

A. Number of modules, arrays and combiner


boxes
B. PV module specification (brand, type, power,
Uoc, Isc)
C. PV array specification (number of string on
each array, tilt and orientation)
D. PV string specification (number of module on
each string, Isc and Uoc calculation)
E. Combiner box (type, IP rating, protection
system, wiring) Cabling and wiring
specification
F. Mounting structure specification
G. Combiner box
H. Installation quality
Photovoltaic Array (Performance Verification / Testing)
Kotak penggabung
Larik fotovoltaik string fotovoltaik
(combiner box)

A. Continuity test String fotovoltaik


Proteksi
String 1

B. Polarity test Modul 1.1 Modul 1.x


Proteksi
String 2

Saklar

C. Open circuit voltage measurement (Uoc) Modul 2.1 Modul 2.x


pemutus

D. Short circuit current measurement (Isc)


Proteksi
String X

E. Cable insulation
Modul x.1 Modul x.x

F. Thermography