Professional Documents
Culture Documents
On
In
Civil Engineering
By
Dharmendra
DEPARTMENT OF CIVIL
ENGINEERING
Date :
30thAugust,2022
i
ACKNOWLEDGMENTS
ii
ABSTRACT
The high growth number of vehicles will increase the movement and the
use of transport infrastructure. Road widening is one of the action that can be
used as the solution. However, this solution also increase the traffic
performance.
This is because people will switch to use the new road widened because
they believe this road can accommodate the existing traffic volume. For finding
out the effects of road widening towards the increasing of traffic performance
and road capacity, it is necessary to conduct a research and an analysis.
The road network of any city is its lifeline and the evaluation of their
performance is very necessary for future traffic planning, design, operation and
maintenance, etc. Traffic flow in most cities of India is a mixed traffic
characteristics and also the traffic congestion is the common problem in most
major cities in India. In Bengaluru city, most of the roads are congested and
operate in Level of Service E or F. The objective of the present study is to
improve the performance operation of the urban road network by proposing the
proper alternatives to enhance the traffic capacity.
iii
CONTENTS
1. INTRODUCTION
2. GEOMETRIC DESIGN
4. LAB TESTS
iv
5. CONSTRUCTION EQUIPMENTS
6. METHODOLOGY
7. CONCLUSION ----------------------------------------------------------- 38
8. REFERENCES ----------------------------------------------------------- 38
v
LIST OF TABLES
vi
LIST OF FIGURES
vii
1. INTRODUCTION
This project envisages widening of roads in Jagtial district of Telangana. Under this
project single lane roads are modified as double lane roads. The project includes the
improvement roads connecting Metpalli to Rangarao pet.
Length of Road : 10 km
1
2. GEOMETRIC DESIGN
Ruling design speed should be the guiding criterion for the purpose of geometric design.
Minimum design speed may, however, be adopted where site condition and cost does not
permit a design based on “Ruling Design Speed”
2
Table 3: Carriage width
2.4 Camber
The camber on straight of road should be as recommended in below table.
Table 4: Camber
At super-elevated road section, the shoulder should normally have the slope of same
magnitude and direction as the pavement slope subject to the minimum cross-fall allowable
for shoulder. The camber for earth shoulder should be at least 0.5 % more than that for the
pavement subject to the minimum of 4 %. However, 1 % more slope than the camber for
pavement is desirable.
3
2.5.2 Super elevation
(0.75 V)2
e=
gR
Where
4
3. COMPONENTS OF FLEXIBLE PAVEMENT
=80mm
1.67 m
=250mm
1.82 m
=200mm
1.92 m
5
Subgrade – Compacted Soil
3.1.1 Introduction
Granular material for use in sub-base course shall be a naturally occurring gravel,
blended as necessary with fine or coarse material and screened to produce the specified
gradation. Crushing of natural granular material shall not normally be required, unless for
meeting the grading requirements, producing a higher quality sub-base with improved
mechanical stability or when shown on the Drawings.
Gravel shall consist of hard, durable and sound rock fragments, free from dirt, organic
matter, shale and other deleterious substances.
The material shall have a 10 % fines value of 50 KN or more (for absorption value of
the coarse aggregate shall be determined as per IS: 2386(part-3); if this value is greater than
2%, the soundness test shall be carried out on the material delivered to site as per :383. For
Grading 2 and 3 materials the CBR shall be determined at the density and moisture content
likely to be developed in equilibrium conditions which be taken as being the density relating
to a uniform air voids content of 5 %.
6
Table 6: Grading of Granular Material
Aggregates used are of the smaller sizes, varies between the 4.75 mm to 20 mm sizes
and the binders(stone dust or quarry dust having PI(Plasticity Index) not less than 6%) are
premixed in a batching plant or in a mixing machine. Then they are brought to the site for
overlaying and compaction.
The PI (plasticity Index) of the binding material is kept low because it should be a
sound and non-plastic material. If the plasticity index is more then there are the chances of
the swelling and more water retention properties. So this value should be kept in mind.
3.2.2 Scope
Wet mix macadam shall consist of laying and compacting clean, crushed, graded
aggregate and granular material, pre mixed with water, to a dense mass on a prepared sub
grade/sub base/base or existing pavement as the case may be in accordance with the
requirements of these specifications. The material shall be laid in one or more layers as
necessary to lines, grades and cross sections shown on the approved drawings or as direction
by the engineer.
Coarse aggregate shall be crushed stone. If the crushed gravel/shingle is used, not less
than 90% by weight of gravel/shingle peace retained on 4.75mm sieve shall have at least two
fractured faces.
7
If the water absorption value of the coarse aggregate is not less than 2%, the
soundness test shall be carried out on the material delivered to site.
To determine this combined proportion, the flaky stone from a representative sample
should first be separated out. Flakiness index is weight of flaky stone metal divide by weight
of stone sample only the elongated particles be separated out from the remaining (non-flaky)
stone metal. Elongation index is weight of elongated particles divided by total non-flaky
particles. The value of flakiness index and elongation index so found are added up.
8
3.2.4 Preparation
Soil stabilizing machinery as Wet Mix Macadam Plants is the Synonym for High
quality Top notch performance, Lower operating costs, Superb Service back up... translating
into productivity and return in turn High profits for the customer. Conforming to international
standards the WMM range of Wet Mix Plants also conforms fully to the latest MORTH
(Ministry of Road Transport & Highway) specification.
The Standard configuration of the plants comprise of the following units: Cold
Aggregates Bin Feeders – Over Size Removal Vibrating Screen - Slinger Conveyor – Pugmill
Mixing Unit – Load Out Conveyor with anti Segregation gob hopper – Water Storage Tank –
Fully Automatic Control Panel, Weather Proof Control Cabin.
Series
9
i. Four Bin Feeder
10
3.3 Prime Coat
3.3.1 Scope:
This work shall consist of application of a single coat of low viscosity liquid
bituminous material to a porous granular surface preparatory to the superimposition of
bituminous treatment or mix .The work shall be carried out on a previously prepared
granular/stabilized surface.
3.3.2 Materials:
The primer shall be cationic bitumen emulsion SS1 grade conforming to IS:8887 or
medium curing cutback bitumen conforming to IS:217 or as specified in the contract.
Quantity of SS1 grade bitumen emulsion for various types of granular surface shall be
given in table.
WMM 0.7-1.0
Stabilized soil bases/crusher run macadam 0.9-1.2
3.4.2 Materials:
Bitumen:
The bitumen shall be viscosity grade paving bitumen complying with the Indian
standard specification IS:73, modified bitumen complying with specified in contract.
Coarse aggregate:
The coarse aggregates shall consist of crushed stone, crushed gravel or other hard
material retained on 2.36mm sieve. They shall be clean, strong, durable, of fairly cubical
11
shape, free from disintegrated pieces, organic or other deleterious substances.
If crushed gravel is used not less than 90 % by weight of the gravel pieces retained on
4.75 mm sieve shall have at least two fractured faces.
Fine aggregates:
Fine aggregates shall be the fraction passing 2.36 mm sieve and retained on 75 micron
sieve, consisting of crusher run screening, gravel, sand or a mixture of both. These shall be
clean, hard, durable, uncoated, dry and free from dust, soft or flaky pieces and organic or
other deleterious matter. Natural sand shall not be allowed in binder courses. However,
natural sand up to 50 % of the fine aggregate may be allowed in base courses.
Filler:
Filler shall consist of finely divided mineral matter such as rock dust, cement as
approved by the engineer. The filler shall be graded within the following limits:
12
IS Sieve designation % passing the sieve by weight
600 micron 100
300 micron 95-100
75 micron 85-100
37.50 100
26.50 90 – 100
19 71 – 95
13.2 56 – 80
4.75 38 – 54
2.36 28 – 42
0.3 7 – 21
0.075 2–8
3.4.3 Preparation
i. Plant Performance:
• The capacity is based on mean density of 1.6 ton/m3 and hot mix temperature of
160oC at mixer outlet.
• When density is less or hot mix temperature requirement is high or moisture content is
high, the production capacity drops proportionately.
13
• The plant capacity shall be 90 t/h when mean moisture content in aggregate is 6%,
and 120 t/h when mean moisture content is 3%.
• Aggregate shall not contain oversized material, which may block the feeding path.
• Filler shall contain less than 1% moisture and shall be free form agglomeration.
14
ii. Cold Aggregates Bin Feeder
iii. Burner
15
iv. Four Deck Vibrating Screen
Completely enclosed Four Deck vibrating screen (1200mm wide x 3600mm long),
sieves and stores four different aggregate sizes. The Inclined circulating, vibrating type
screen is provided with duplex spring absorbers, and is powered by a 7.5 kW four-pole
motor.
Supplied along with One set of Sieves with the following sieve sizes:
3 x 4 mm, 7 mm , 16 mm , 24 mm, 30 mm, 40 mm.
Four compartment hot aggregates bin with 12 m3 storage capacity, over flow and over
size rejection chute, bin level indicators, pneumatic controlled cut off gates and a sampling
device on each compartment.
Automatic accumulating, weighing type Aggregate weigh hopper, with four point
suspension hopper and load cell transducer.
Automatic individual weighing type Asphalt and Filler weigh hopper with four points
suspension hopper and load cell transducer.
All weighing hoppers are fitted with proper shock isolation device.
5.5 kW, 450 Lpm, Jacketed, gear type Asphalt transfer pump for feeding asphalt from
the storage tank to the asphalt weigh hopper complete with skid and wiring.
7.5 kW, 800 Lpm, hot oil jacketed asphalt gear type Spray pump for spraying asphalt
into the pug mill mixer via spray bars. Complete unit with controls and wiring.
16
ix. Pug Mill type Mixer Unit
Twin shaft, 1400 kg mixing capacity, jacketed pug mill with welded steel shell, lined
with replaceable wear resistant spiral liners. Provided with a wide opening slide gate for
quick discharge of hot mix.
The work shall consist of the application of a single coat of low viscosity liquid
bituminous material to existing bituminous preparatory to the superimposition of a
bituminous mix, when specified in the contract or as instructed by the Engineer.
3.5.2 Materials
The binder used for tack coat shall be either Cationic bitumen emulsion or suitable
low viscosity paving bitumen of VG 10 grade.
This work shall consist of construction of Bituminous concrete, for use in wearing and
profile corrective courses. This work shall consist of construction in a single layer of
bituminous concrete on a previously prepared bituminous bound surface. A single layer shall
be 30 mm/ 40 mm/ 50mm thick.
3.6.2 Materials:
1. Bitumen,
2. Coarse aggregates,
3. Fine aggregates,
4. Filler and
5. Aggregates Gradation.
17
3.6.3 Aggregate Grading with Binder Content
When tested in accordance with IS:2386 (Part – I) , the combined grading of the
coarse and fine aggregates and filler shall fall within the limits shown in below Table 12.
13.20 90 – 100
9.5 70 – 88
4.75 53 – 71
2.36 42 – 58
1.18 34 – 48
0.6 26 – 38
0.3 18 – 28
0.15 12 – 20
0.075 4 – 10
18
4. LAB TESTS:
The CBR test is used for the evaluation of subgrade strength of roads and pavements.
The CBR value obtained by this test is used with the empirical curves to determine the
thickness of pavement and its component layers. This is the most widely used method for the
design of flexible pavement.
Tests are carried out on natural or compacted soils in water soaked or un-soaked
conditions and the results so obtained are compared with the curves of standard test to have
an idea of the soil strength of the subgrade soil.
19
Generally, the CBR value at 2.50mm penetration will be greater than that at 5.00mm
penetration and in such case take the value at 2.50mm as the CBR value.
Determination of field density of cohesion less soil is not possible by core cutter
method, because it is not possible to obtain a core sample. In such situation, the sand
replacement method is employed to determine the unit weight. In sand replacement method, a
small cylindrical pit is excavated and the weight of the soil excavated from the pit is
measured. Sand whose density is known is filled into the pit. By measuring the weight of
sand required to fill the pit and knowing its density the volume of pit is calculated. Knowing
the weight of soil excavated from the pit and the volume of pit, the density of soil is
calculated. Therefore, in this experiment there are two stages, namely
20
1. Calibration of sand density
2. Measurement of soil density
21
Table 15: Measurement of soil density
1. Weight of the wet soil from the hole (Ww) in gms 2310 2400 2280
Determination of the relationship between the moisture content and density of soils
compacted in a mould of a given size with a 2.5 kg rammer dropped from a height of 30 cm.
the results obtained from this test will be helpful in increasing the bearing capacity of
foundations, Decreasing the undesirable settlement of structures, Control undesirable volume
changes, Reduction in hydraulic conductivity, Increasing the stability of slopes and so on.
Soil compaction is the process in which a stress applied to a soil causes densification
as air is displaced from the pores between the soil grains. It is an instantaneous process and
always takes place in partially saturated soil (three phase system). The Proctor compaction
test is a laboratory method of experimentally determining the optimal moisture content at
which a given soil type will become most dense and achieve its maximum dry density.
22
Figure 12: Compaction of Soil
23
Plot a curve between water content and as ordinate.
Sieve analysis helps to determine the particle size distribution of the coarse and fine
aggregates. This is done by sieving the aggregates as per IS: 2386 (Part I) – 1963. In this we
use different sieves as standardized by the IS code and then pass aggregates through them and
thus collect different sized particles left over different sieves.
24
The apparatus used are –
i) Sieves used are 45 mm, 37.5 mm, 26.5 mm, 19 mm, 13.2 mm, 9.5 mm, 4.75 mm, 2.36
mm, 1.18 mm, 0.6 mm, 0.3 mm, 0.15 mm, 0.075 mm and are arranged according to the sizes
with largest aperture sieve at the top and smallest aperture sieve at the bottom.
ii) Balance or scale with an accuracy to measure 0.1 % of the weight of the test sample.
25
4.5 Penetration Value Of Bitumen:
Penetration value is a measure of hardness or consistency of bituminous material. It
is the vertical distance traversed or penetrated by the point of a standard needle in to the
bituminous material under specific conditions of load, time and temperature. This distance is
measured in one tenths of a millimeter. This test is used for evaluating consistency of
bitumen. It is not regarded as suitable for use in connection with the testing of road tar
because of the high surface tension exhibited by these materials.
2. The test is widely used all over the world for classifying bituminous materials into
different grades.
3. Depending upon the climatic conditions and type of construction, bitumen of different
penetration grade are used. Commonly used grades are 30/40, 60/70 and 80/100.
4. In warmer regions, lower penetration grades are preferred and in colder regions bitumen
with higher penetration values are used.
5. The test is not intended to estimate consistency of softer materials like cut back which are
usually graded by viscosity test.
26
Table 18: Values of Penetration test
Sample Penetration
Readings Mean
1 79
76 76.33
74
2 79
75 76
74
3 80
75 76
73
Softening point denotes the temperature at which the bitumen attains a particular degree of
softening under the specifications of test. The test is conducted by using Ring and Ball
apparatus. A brass ring containing test sample of bitumen is suspended in liquid like water or
glycerine at a given temperature. A steel ball is placed upon the bitumen sample and the
liquid medium is heated at a rate of 5 C per minute. Temperature is noted when the softened
bitumen touches the metal plate which is at a specified distance below. Generally, higher
softening point indicates lower temperature susceptibility and is preferred in hot climates.
Bitumens are viscoelastic materials without sharply defined melting points; they
gradually become softer and less viscous as the temperature rises. For this reason, softening
points must be determined by an arbitrary and closely defined method if results are to be
reproducible.
27
Figure 16: Softening point
28
5. CONSTRUCTION EQUIPMENTS
5.1 Excavators
• For earth work, the commonly used excavators are hydraulic excavators, which work
with great efficiency.
• They consist of a boom, stick (dipper arm), bucket and cab on a rotating platform
known as the house that sits a top an undercarriage with tracks or wheels.
• It can remove the big sized boulders. It is used in various types such as digging in
gravel banks, clay pits, digging cuts in road works and filling the shoulders.
29
• A motor grader is a huge productive earth-moving apparatus equipped with a
long blade which is used to level a surface of roads and construction sites.
• Graders can produce inclined surfaces to give cant (camber) to roads. At the
end it has a plow which stays close to the ground. A blade is situated under
the cab to spread and push gravel.
5.3 Dozers
5.4 Compacters
1. Earth Compactor
30
• It is used to compact the soil and gravel in the construction of roads.
2. Asphalt Compactor
• After laying asphalt with paver and compacting it with asphalt compactors are
used for final smoothening purpose.
31
• Asphalt pavers are used for distribution, shaping and compaction of asphalt layer.
• Normally the asphalt pavers are self propelled but sometimes they are towed by the
dump trucks delivering the asphalt.
• This Emulsion sprayer is used for the spraying the Prime coat on the WMM and Tack
coat on the DBM.
32
6. METHODOLOGY
6.1 Subgrade
Actually that is a single lane road. The task is to make it into widen the road. One side is
excavated till a depth of 95 cm. The other side was not excavated and the vehicles are
allowed from that side. The plan is that, after completion of one side of construction they will
start constructing road on other side and allows the vehicles on to constructed part.
Widen part of 1.92m width from the edge of existing road on one side cut a depth of
95cm and fill the soil like morum or clay and compact it by using soil compactors up to a
depth of 50cm.
The granular sub base is laid on the compacted Subgrade soil to a depth of 200 mm in two
layers as upper sub base and lower sub base, the thickness of each layer is 100 mm.
40 mm Aggregates – 17%
20 mm Aggregates – 18%
12 mm Aggregates – 32%
Dust – 33%
33
Mixture of these aggregates and dust laid on sub grade with the help of grader. After
that compaction is done by using vibratory roller till to get the dry density 2.16 gr/cc and
OMC is 7%.
The Wet Mix Macadam (WMM) is laid on the Granular sub-base with the thickness
of 250 mm.
Mixed proportions:
40 mm Aggregates -18%
20 mm Aggregates -20%
12 mm Aggregates -30%
Dust – 32%
Wet Mix Macadam is prepared in mixing plant and immediately after mixing, it is
spread uniformly and evenly upon the prepared GSB. Then it is compacted properly to obtain
maximum dry density of 2.17 g/cc and OMC is 7%.
34
Figure 27: Wet mix macadam
Prime coat is sprayed with the help of emulsion sprayer on the wet mix macadam
with the range of 0.7 kg/sq.m
35
6.5 Dense Bituminous Macadam(DBM)
The mix proportions of DBM
20 mm aggregates – 21 %
12 mm aggregates – 15 %
6 mm aggregates – 25 %
Dust – 39 %
Bitumen – 4.5 %
The DBM is prepared with these proportions and it is laid with the help of sensor
paver. The levelling is done while laying for maintaining camber. It is laid for a thickness of
50 mm. Compaction is done by Roller.
36
6.7 Bituminous Concrete (BC)
The mix proportions of BC
12 mm aggregates – 53 %
6 mm aggregates – 25 %
Dust – 22 %
Bitumen – 4.5 %
Bituminous concrete is laid on the Dense bituminous macadam with the help of
sensor paver with a thickness of 53mm and it was compacted by asphalt compactor up to a
thickness of 30mm.
37
7. CONCLUSION
As the population is increasing day by day we need to improve our roads for better
efficiency in transportation. And the roads are to be constructed by keeping in mind the future
aspects. This road is been constructing to full fill the requirements of road users. All
environmental effects, vehicular characteristics, human characteristics are taken into account.
All the lab tests and field tests are conducted as per IRC guidelines. MORT&H specifications
are used for laying out pavement.
8. REFERENCES
• Ministry of Road Transportation and Highways, “Specifications for Road and Bridge
Works”.
38