You are on page 1of 54

Research Design and Standards Organization

(RDSO)

LUCKNOW

SUMMER INDUSTRIAL TRAINING


Department: BRIDGE AND STRUCTURE
Under the guidance of :-

Mr. Srijan Tripathi


From: 16th June 2014 To 21st August 2014
SUBMITTED BY:

Syed. Mohd. Mashood

(0115CE111058)

NRI INSTITUTE OF INFORMATION SCIENCE & TECHNOLOGY


BHOPAL (M.P.)

DEPARTMENT OF CIVIL ENGINEERING

1
NRI INSTITUTE OF INFORMATION SCIENCE & TECHNOLOGY
BHOPAL (M.P.)

(AFFILIATED TO R.G.P.V , BHOPAL)

SESSION 2014-15

DECLARATION
I hereby declare that the work presented in this project titled “Bridge
Construction For New Broad Gauge Line” submitted towards
completion of Summer Industrial Training Report in Seventh Semester
of B.Tech (CIVIL ENGINEERING) at the NRI Institute of Science and
Technology, Bhopal affiliated to RGPV, Bhopal is authenticate work and
had not been submitted to any University or Institute for any award

NAME: SYED. MOHD. MASHOOD

EMROLL.NO. (0115CE111058)

2
NRI INSTITUTE OF INFORMATION SCIENCE & TECHNOLOGY
BHOPAL (M.P.)

(AFFILIATED TO R.G.P.V , BHOPAL)

SESSION 2014-15

CERTIFICATE

This is to certify that the project report entitled. “Bridge Construction For New
Broad Gauge Line” submitted by Syed Mohd Mashood in partial fulfillments for the
requirements of the Degree of Bachelor of Engineering in Civil Engineering From
R.G.P.V,BHOPAL

Mr. Srijan Tripathy Mr. J.P.Nanda Dr. S.C.Kapoor

Project Guide Head Of Department Director

Bridge&Structure(RDSO) Civil Engineering NIIST,Bhopal

Dr.Monika Vishwakarma

Principal

(NIIST,Bhopal)

3
NRI INSTITUTE OF INFORMATION SCIENCE & TECHNOLOGY
BHOPAL (M.P.)

(AFFILIATED TO R.G.P.V , BHOPAL)

SESSION 2014-15

APPROVAL CERTIFICATE

The Project Report Entitiled “Bridge Construction For New Broad Gauge
Line”being submitted by SYED MOHD MASHOOD Has been examined by us
and Hereby approved for the award of Degree of Bachelor of Engineering in Civil
Engineering for which it has been submitted. It is understood that by approval the
undersigned do not necessarily endorse or approve any statement made, opinion
expressed or conclusion drawn therein, but approve the dissertation only for the
purpose for which it has been submitted

___________________ ___________________

___________________ ___________________

(Internal Examiner) (External Examiner)

4
NRI INSTITUTE OF INFORMATION SCIENCE & TECHNOLOGY
BHOPAL (M.P.)

(AFFILIATED TO R.G.P.V , BHOPAL)

SESSION 2014-15

ACKNOWLEDGEMENT

I placed on record and warmly acknowledge the continuous encouragement,


invaluable supervision, Mr. Srijan Tripathy Department of Bridge And Structure,
RDSO ,Lucknow for permitting me to make use of the facilities available in the
department to carry out the project successfully

I am greatfull to Mr.J.P. Nanda , HOD of Civil Engineering


Department,for helping and motivating in bringing this report to a success full
completion..And I would also Like to thanks our teacher Mr .Iqbal Hafeez who has
always supported me till the completion of this report.

Last but not the least I express our sincere thanks to all of our friends who
have patiently extended all sorts of help for accomplishing this under taking.

Finally I extend our gratefulness to one and all who are directly or
indirectly involved in the success full completion of the project work.

5
ABSTRACT

BRIDGE CONSTRUCTION FOR NEW BROAD GUAGE LINE

From the moment human started exploring he started to travel across the world
after the world- war II due to the industrial revolution these became even intense
to travel for overseas human used only ships but to travel in his own country he
made only slow means of transport like bullock cart which not even safe. Then
human started thinking about to decrease his travel time and increase his own
safety then they invented railway service which much safe, time conserving due
to the low in expenditure to travesl by trains many middle class and lower middle
class people depended on it a lot and it even cheap to transfer the good for long
distance at low price with lead to growth of importance of railway services.
Construction of new railway is really a tough task which involve in consideration
of several parameters and several unexpected conditions. When the track is
properly aligned it is a very good means of source of revenue to government and
also good means transportation for public. At both the execution of construction
work and even the maintenance it provide huge opportunity of employment.

6
CODE AND REGULATIONS

Admixtures: - IS-9103
1. For reduction of water cement ratio:- IS-456
2. Water cement ratio:- IS-10262 ,IS-10264
3. Bridge bed block:- IS-1786-285
All the above specifications should be 2010 modifications and latest.
4. Maximum water cement ratio:- 0.40
5. Minimum cementicious material:-400kg/mt
6. Reinforcement high yield strength deformed bars: IRS-1786-1985
7. Abutments mix:-M25
8. Piers:-M30

7
CONTENTS
S.No TOPIC Page PAGE

1. CHAPTER-1 INTRODUCTION
1.1 Introduction to bridges 1
2. CHAPTER-2 TOPOGRAPHICAL SURVEY
2.1 Topographical survey 2
2.2 Alternative Alignment 2
2.3 Obligatory points 3
3. CHAPTER-3 DISCHARGE THROUGH DRAINAGE AREA
3.1 Discharge through drainage 4
4. CHAPTER-4 TYPES OF BRIDGES
4.1 Arch bridges 6
4.2 Reinforced slab bridges 6
4.3 Beam and slab bridges 7
4.4 Integral bridges 7
5. CHAPTER-5 TYPES OF FOUNDATIONS
5.1 Open foundation 9
5.2 Box foundation 10
5.3 Well foundation 10
5.3.1 Cutting edge 10
5.3.2 Curb 10
5.3.3 Steining 10
5.3.4 Bottom plug 11
5.3.5 Sand filling 11
5.3.6 Intermediate plug 11
5.3.7 Top plug 12
5.3.8 Reinforcement 12
5.3.9 Well cap 12
5.4 Sinking of wells 13
6. CHAPTER-6 PIER CONSTRUCTION
6.1 Pier construction 15
7. CHAPTER-7 PRE-STRESSED CONCRETE SLAB
7.1 Bonded post tensioned concrete 20

8
8. CHAPTER-8 POST-TENSIONED SLAB
8.1 post-tensioned concrete 22
9. CHAPTER-9 LAUNCHING OF PRE-STRESSED SLAB
9.1 Pre-tensioned slab 23
10. CHAPTER-10 INFLUENCING OF BUILDING MATERIALS
10.1 Building materials 24
10.1.1 Natural stone 24
10.1.2 Artificial stone, bricks, clinker 25
10.1.3 Reinforced and pre-stressed concrete 25
10.1.4 Steel and aluminum 27
10.1.5 Timber 29
10.2 Bridge construction technology 29
11. CHAPTER-11 TYPES OF BRIDGE CONSTRUCTION MACHINERIES
11.1 Construction machineries 31
11.1.1 Bridge cranes 31
11.1.2 Gantry cranes 32
11.1.2.1 Gantry cranes size and marking 32
11.1.2.2 Types of Gantry cranes 32
11.1.2.3 Renting gantry cranes 32
11.1.3 Floating cranes 33
11.1.3.1 Floating crane working 33
1.3.2 Floating crane uses 34
12. CHAPTER-12 TOTAL STATION
12.1 Coordinate measurement 35
12.2 Angular measurement 35
12.3 Distance measurement 35
12.4 Data processing 35
12.5 Applications 36
12.6 Mining 36
12.7 Stone block 36
13. CHAPTER-13 SLEEPERS
13.1 Wooden sleepers 37
13.2 Concrete sleepers 38
13.3 Steel sleepers 39

9
14. LIST OF FIGURES
Figure 6.1 Parts of a pier
Figure 6.2 Machine for drilling a pier
Figure 6.3 Tay Bridge
Figure 6.4 Erection of a pier
Figure 7.1 Pre-stressed slab
Figure 7.2 Pre-stressed post tensioned anchor
Figure 11.1 Bridge crane
Figure 11.2 Gantry crane
Figure 11.3 Renting gantry crane
Figure 11.4 Floating crane
Figure 13.1 Wooden sleeper
Figure 13.2 Concrete sleeper
Figure 13.3 Steel sleeper

10
CHAPTER-1
INTRODUCTION

1.1 Introduction to Railway bridges:

Our mini project is totally concreted on railway bridge construction. In general rail
way track is aligned in most economical way but sometimes railway line come
across several obligatory points like holy places, schools, areas with high land
value and even tributaries of river or streams in such cases bridges and designed
and constructed. It is done by following methods. At first and foremost step
followed align the railway line is topographical survey. In this part a topographical
map is used to check the possibilities of alignment of track and from that the best
possible path is finalized. Then the field test is carried out to get a clear idea
about the site condition. Which consist of total station survey for central line
alignment, leveling works which also results in finding the RL at different point
and even useful to transfer them to required location to avoid obstruction in
visibility, then followed by soil exploration works which involves in lab work.
Once these work is done the next procedure of work continues i.e. land
acquisition as a part of these the railway authority make contact with local
revenue department officials for land purchase from the respective owners.
Then it is followed by earth work where excavation work for different types of
foundation, as we know different methods of foundations are followed based on
the ground condition. When the main excavation work is done the bridge
construction starts ex foundation, piers to get all the piers in exact alignment total
station is used. Once the piers are done then thebed block marking is done over
which precast girders are place. All these processes go into the sub tenders form.
When the construction of bridges is done, sleepers are placed at the site for the
next process i.e. track alignment along the center marked line.

11
CHAPTER-2

TOPOGRAPHICAL SURVEY

2.1 Topographical survey

A topographic map is a type of map characterized by large-scale detail and


quantitative representation of relief, usually using contour lines in modern
mapping, but historically using a variety of methods. Traditional definitions
require a topographic map to show both natural and man-made features. A
topographic map is typically published as a map series, made up of two or more
map sheets that combine to form the whole map. A contour line is a combination
of two line segments that connect but do not intersect; these represent elevation
on a topographic map.The Canadian Centre for Topographic Information provides
this definition “A topographic map is a detailed and accurate graphic
representation of cultural and natural features on the ground.”
Other authors define topographic maps by contrasting them with another type of
map; they are distinguished from smaller-scale "chorographic maps" that cover
large regions, "plan metric maps" that do not show elevations, and "thematic
maps" that focus on specific topics. However, in the vernacular and day to day
world, the representation of relief (contours) is popularly held to define the
genre, such that even small-scale maps showing relief are commonly (and
erroneously, in the technical sense) called "topographic". The study or discipline
of topography, while interested in relief, is actually a much broader field of study
which takes into account all natural and manmade features of terrain.

2.2 Alternative alignment

As part of topographical survey all the possible alignment of railway line is


examined.

12
2.3 Obligatory points

As a part of topographical survey we come across several obstruction like, holy


place, rivers streams, which leads to change the direction or bridge construction.

13
CHAPTER-3

DISCHARGE THROUGH DRINAGE AREA

3.1 Discharge through drainage area

The catchment of a river above a certain location is determined by the surface


area of all land which drains toward the river from above that point. The river's
discharge at that location depends on the rainfall on the catchment or drainage
area and the inflow or outflow of groundwater to or from the area, stream
modifications such as dams and irrigation diversions, as well as evaporation and
evapo-transpiration from the area's land and plant surfaces. In storm hydrology
an important consideration is the stream's discharge hydrograph, a record of how
the discharge varies over time after a precipitation event. The stream rises to a
peak flow after each precipitation event, then falls in a slow recession. Because
the peak flow also corresponds to the maximum water level reached during the
event, it is of interest in flood studies. Analysis of the relationship between
precipitation intensity and duration, and the response of the stream
discharge is mm by the concept of the unit hydrograph which represents the
response of stream discharge over time to the application of a hypothetical "unit"
amount and duration of rain, for example 1 cm over the entire catchment for a
period of one hour. This represents a certain volume of water (depending on the
area of the catchment) which must subsequently flow out of the river. Using this
method either actual historical rainfalls or hypothetical "design storms" can
be modeled mathematically to confirm characteristics of historical floods, or to
predict a stream's reaction to a predated storm.
The relationship between the discharge in the stream at a given cross-section and
the level of the stream is described by a rating curve. Average velocities and the
cross-sectional area of the stream are measured for a given stream level. The
velocity and the area give the discharge for that level. After measurements are
made for several different levels, a rating table or rating curve may be developed.
Once rated, the discharge in the stream may be determined by measuring the
level, and determining the corresponding discharge from the rating curve. If a
continuous level-recording device is located at a rated cross-section, the stream's
discharge may be continuously determined.
This is done based on the records of last 10 years if fluctuation is more it can be
made up to 20 years. Based on the analyses data for the discharge of drainage the

14
bridges are finalized based on the acting on them due to discharge of water, All
the forces acting on pier, additional that can be acted on bridges, span,
reinforcement, amount of concrete is estimated at these stage.

15
CHAPTER-4

TYPES OF BRIDGES

4.1 Arch bridges

Arch bridges derive their strength from the fact that vertical loads on the arch
generate compressive forces in the arch ring, which is constructed of materials
well able to withstand these forces.
The compressive forces in the arch ring result in inclined thrusts at the
abutments, and it is essential that arch abutments are well founded or buttressed
to resist the vertical and horizontal components of these thrusts. If the supports
spread apart the arch falls down. The Romans knew all about this.
Traditionally, arch bridges were constructed of stone, brick or mass concrete since
these materials are very strong in compression and the arch could be configured
so that tensile stresses did not develop.
Modern concrete arch bridges utilize prestressing or reinforcing to resist the
tensile stresses which can develop in slender arch rings.
The shape attracted the attention of many of the early pioneers of concrete
construction. In 1930, Freyssinet was responsible for a spectacular arched bridge
at Plougastel in France and three years later, Swiss engineer, Robert Maillart
created the famously elegant
Schwandbach bridge in which slender cross-walls tie the arch to the horizontally
curved roadway.

4.2 Reinforced slab bridges

For short spans, a solid reinforced concrete slab, generally cast in-situ rather than
precast, is the simplest design. It is also cost-effective, since the flat, level soffit
means that false work and formwork are also simple. Reinforcement, too, is
uncomplicated. With larger spans, the reinforced slab has to be thicker to carry
the extra stresses under load. This extra weight of the slab itself then becomes a
problem, which can be solved in one of two ways. The first is to use pre-stressing
techniques and the second is to reduce the deadweight of the slab by including

16
'voids', often expanded polystyrene cylinders. Up to about 25m span, such voided
slabs are more economical than pre-stressed slabs.

4.3 Beam and slab bridges

Beam and slab bridges are probably the most common form of concrete bridge in
the India today, thanks to the success of standard precast pre-stressed concrete
beams developed originally by the Pre-stressed Concrete Development Group
(Cement & Concrete Association) supplemented later by alternative designs by
others, culminating in the Y-beam introduced by the Pre-stressed Concrete
Association in the late 1980s.
They have the virtue of simplicity, economy, wide availability of the standard
sections, and speed of erection. The precast beams are placed on the supporting
piers or abutments, usually on rubber bearings which are maintenance free. An
in-situ reinforced concrete deck slab is then cast on permanent shuttering which
spans between the beams. The precast beams can be joined together at the
supports to form continuous beams which are structurally more efficient.
However, this is not normally done because the costs involved are not justified by
the increased efficiency.

Simply supported concrete beams and slab bridges are now giving way to
integral bridges which offer the advantages of less cost and lower maintenance
due to the elimination of expansion joints and bearings.

4.4 Internal bridges

One of the difficulties in designing any structure is deciding where to put the
joints. These are necessary to allow movement as the structure expands under
the heat of the summer sun and contracts during the cold of winter.
Expansion joints in bridges are notoriously prone to leakage. Water laden with
road salts can then reach the tops of the piers and the abutments, and this can
result in corrosion of all reinforcement. The expansive effects of rust can split
concrete apart.

17
In addition, expansion joints and bearings are an additional cost so more and
more bridges are being built without either. Such structures, called 'integral
bridges', can be constructed with all types of concrete deck. They are constructed
with their decks connected directly to the supporting piers and abutments and
with no provision in the form of bearings or expansion joints for thermal
movement. Thermal movement of the deck is accommodated by
flexure of the supporting piers and horizontal movements of the abutments, with
elastic compression of the surrounding soil.
Already used for lengths up to 60m, the integral bridge is becoming increasingly
popular as engineers and designers find other ways of

18
CHAPTER-5

TYPES OF FOUNDATIONS

5.1 Open foundation

An open caisson is similar to a box caisson, except that it does not have a bottom
face. It is suitable for use in soft clays (e.g. in some river-beds), but not for where
there may be large obstructions in the ground.
An open caisson that is used in soft grounds or high water tables, where open
trench excavations are impractical, can also be used to install deep
manholes,pump stations and reception/launch pits for micro tunneling, pipe
jacking and other operations.
A caisson is sunk by self-weight, concrete or water ballast placed on top, or by
hydraulic jacks. The leading edge (or cutting shoe) of the caisson is sloped out at a
sharp angle to aid sinking in a vertical manner; it is usually made of steel.
The shoe is generally wider than the caisson to reduce friction, and the
leading edge may be supplied with pressurized bentonite slurry, which swells in
water, stabilizing settlement by filling depressions and voids. An open caisson may
fill with water during sinking. The material is excavated by clamshell excavator
bucket on crane.
The formation level subsoil may still not be suitable for excavation or bearing
capacity. The water in the caisson (due to a high water table) balances the up
thrust forces of the soft soils underneath. If dewatered, the base may "pipe" or
"boil", causing the caisson to sink.
To combat this problem, piles may be driven from the surface to act as: Load-
bearing walls, in that they transmit loads to deeper soils. Anchors, in that they
resist floatation because of the friction at the interface between their surfaces
and the surrounding earth into which they have been driven.
H-beam sections (typical column sections, due to resistance to bending
in all axes) may be driven at angles "raked" to rock or other firmer soils; the H-
beams are left extended above the base. A reinforced concrete plug may be
placed under the water, a process known as Tremie concrete placement. When
the caisson is dewatered, this plug acts as a pile cap, resisting the upward forces
of the subsoil.

19
5.2 Box foundation

A box caisson is a prefabricated concrete box (it has sides and a bottom); it is set
down on prepared bases. Once in place, it is filled with concrete to become part
of the permanent works, such as the foundation for a bridge pier.
Hollow concrete structures float (see WWII concrete ships), so a box caisson
must be ballasted or anchored to prevent this phenomenon until It can be filled
with concrete (indeed, elaborate anchoring systems may be required in tidal
zones); adjustable anchoring systems, combined with a GPS survey, allows
engineers to position a box caisson with pinpoint accuracy.

5.3 Well foundation

This work consists of construction of well foundation, taking it down to the


founding level through all kinds of sub-strata, plugging the bottom, filling the
inside of the well, plugging the top and providing a well cap in accordance with
the details shown on the drawing.
Well may have a circular, rectangular, or D-shape in plan and may consist of one,
two or more compartments in plan.
Well Components & their Function In brief the function of various elements is
as follows:

5.3.1 Cutting edge


The mild steel cutting edge shall be made from structural steel
sections. The cutting edge shall weigh not less than 40 kg per meter length and be
properly anchored into the well curb, as shown in the drawing.
When there are two or more compartments in a well, the bottom end of the cutting
edge of the inner walls of such wells shall be kept at about 300 mm above that of
outer walls.

5.3.2 Curb
The well curb may be precast or cast-in-situ. Steel formwork for well curb
shall be fabricated strictly in conformity with the drawing. The outer face of the
curb shall be vertical.

20
Steel reinforcements shall be assembled as shown on the drawings. The bottom
ends of vertical bond rods of staining shall be fixed securely to the cutting edge
with check nuts or by welds.
The formwork on outer face of curb may be removed within 24 hours after
concreting. The formwork on inner face shall be removed after 72 hours. It is
made up of reinforced concrete using controlled concrete of grade M-35.

5.3.3 Steining
The dimensions, shape, concrete strength and reinforcements of the well
shall strictly conform to those shown on the drawings. The formwork shall
preferably be of M.S. sheets shaped and stiffened suitably. In case timber forms
are used, they shall be lined with plywood or M.S. sheets.
The steining of the well shall be built in one straight line from bottom to
top such that if the well is tilted, the next lift of steining will be aligned in the
direction of the tilt. After reaching the founding level, the well steining shall be
inspected to check for any damage or cracks

5.3.4 Bottom plug


Its main function is to transfer load from the steining to the soil below.
For bottom plug, the concrete mix shall be design (in dry condition) to attain the
concrete strength as mentioned on the drawing and shall contained 10 per cent
more cement than that required for the same mix placed dry.

5.3.5 Sand filling


Sand filling shall commence after a period of 3 days of laying of bottom
plug. Also, the height of the bottom plug shall be verified before starting sand
filling. Sand shall be clean and free from earth, clay clods, roots, boulders,
shingles, etc. and shall be compacted as directed. Sand filling shall be carried out
up to the level shown on the drawing or as directed by the Engineer.

5.3.6 Intermediate plug


The function of the plug is to keep the sand filling sandwiched &
undisturbed. It also act as a base for the water fill, which is filled over it up to the
bottom of the well cap.

21
5.3.7 Top plug
After filling sand up to the required level a plug of concrete shall be
provided over it as shown on the drawing, It at least serves as a shuttering for
laying well cap.

5.3.8 Reinforcement
It provides requisite strength to the structure during sinking and service.

5.3.9 Well cap


It is needed to transfer the loads and moments from the pier to the well or wells
below. A reinforced cement concrete well cap will be provided over the top of the
steining in accordance with the drawing. Formwork will be prepared conforming
to the shape of well cap.
Concreting shall be carried out in dry condition. A properly designed false steining
may be provided where possible to ensure that the well cap is laid in dry
conditions After water filling, pre-cast RCC slabs shall be placed over the RCC
beams as per the drawings, as non-recoverable bottom shuttering for well cap.
Initially built false wall shall act as outer shuttering for well cap casting. In case,
there is no false wall, then steel shuttering is to be put from outer side.
For well Steining and well cap shuttering, permissible tolerances are as follows: -
Variation in dimension : +50 mm to –10mm
Misplacement from specified Position in Plan: 15mm
Variation of levels at the top : +/- 25mm
Depth of Well Foundation :
As per I.R.C. bridge code, the depth of well foundation is to be decided on the
following considerations:
The minimum depth of foundation below H.F.L should be 1.33D, where D is
the anticipated max. Depth of scour below H.F.L depth should provide proper grip
according to some rational formula.
The maximum bearing pressure on the subsoil under the foundation resulting
from any combination of the loads and forces except wind and seismic forces
should not exceed the safe bearing capacity of the subsoil, after taking into
account the effect of scour. With wind and seismic forces in addition, the
maximum bearing pressure should not exceed the safe bearing
capacity of the subsoil by more than 25%
While calculating maximum Bearing pressure on the foundation bearing
layer resulting from the worst combination of direct forces and overturning
moments. The effect of passive resistance of the earth on the sides of the
22
foundation structure may be taken into account below the maximum Depth of
the scour only.
The effect of skin friction may be allowed on the portions below the maximum
Depth of scour. Accordingly for deciding the depth of well foundation we require
correct estimation of the following:
Maximum Scour depth.
Safe bearing capacity.
Skin friction.
Lateral earth support-below maximum scour level.
It is always desirable to fix the level of a well foundation on a sandy strata bearing
capacity. Whenever a thin stratum of clay occurring between two layers of sand is
met with in that case well must be pierced through the clayey strata. If at all
foundation has to be laid on a clayey layer it should be ensured that the clay is
stiff.

5.4 Sinking of Wells


In case of well sinking on dry grounds, an open excavation up to half a meter
above subsoil water level is carried out and the well curb is laid. In case the wells
are to be sunk in mid-stream, a suitable cofferdam is constructed around the site
of the well and islands are made.
The islands in shallow water are formed by an edging of sand bags forming an
enclosure filled with sand or clay. When the water depth is of the order of 3 to 5
m. the site is surrounded by sheet piling and the enclosure so formed is filled with
clay or sand. The centre point of well is accurately marked on the island and the
cutting edge is placed in a level plain.
The wooden sleepers are inserted below the cutting edge at regular intervals so
as to distribute the load and avoid setting of the cutting edge unevenly during
concreting. The inside shuttering of the curb is generally made of brick masonry
and plastered. The outer shuttering is made of wood or steel.
Initially the well steining should be built to a height of 2m. Only. Later steining
should not allowed to be built more than 5m. at a time. For this bridge the
subsequent lifts were of 2.5 m. each.
The well is sunk by excavating material from inside under the curb. Great care
should be taken during well sinking in the initial stages because the well is very
unstable.

23
Excavation of the soil inside the well can be done by sending down workers
inside the wells. When the depth of the water inside the well becomes more than
one meter, the excavation is then carried out by a Jham or a Dredger.
The sump position at 8 equidistant locations along dredge hole sides & at
well center are taken & recorded. The dredge water level is also recorded.
Vertical reinforcement of steining shall be bent & tied properly to facilitate the
grab movement during sinking operations.
The position of the crane shall be such that the operation shall be able to see
the signalman on the well top at all the times, & the muck is safely deposited
away from the intermediate vicinity of the well.
Grabbing process shall commence normally with the grabbing at the above
designated sounding positions.
If the well is not sinking after reasonable amount of grabbing is done, say after
two rounds of grabbing, the sump position shall be checked accordingly, in
combination with the tilt position, the grabbing pattern shall vary. The sump
should not normally exceed 1.75m average. And thereafter, air jetting or water
jetting shall be resorted to.
The sinking operation shall be done in two shifts, day & night. In normal
course, the sump and the dredge hole water levels shall be observed twice in
each shift, and the cutting edge reduced level shall be checked by level at four
positions at the end of the shift.
As the well sinks deeper, the skin friction on the sides of the well progressively
increases. To counteract the increased skin friction and the loss in weight of the
well due to buoyancy, additional loading known as kentledge is applied on the
well. The kentledge is comprised of iron rail, sand bags concrete blocks etc.
Pumping out of water from the inside of the well is effective when the well has
gone deep enough or has passed through a clayey stratum so that chances of tilts
and shifts are minimized during this process.
When the well has been sunk to about 10 m. depth, sinking thereafter
should be done by grabbing, chiseling and applying kentledge. Only when these
methods have failed dewatering may be allowed up to depressed water level of
5 m. and not more.
In case of sandy strata frictional resistance developed on the outer periphery is
reduced considerably by forcing jet of water on the outer face of the well all
round.

24
CHAPTER-6

PEIR CONSTRUCTION

6.1 Pier construction

The dimensions and detailed construction of the cast-iron piers are shown in. A
single pier consisted of six columns of cast iron tied together by struts, bars and
rods made from wrought iron. Each pier in the high girders section was built up by
bolting together seven flanged cast-iron columns, giving seven tiers. The ends of
the flanges were fastened together with eight 1.125 inch (1_) wrought iron bolts
as shown in Figures 6.1 and 6.2, below.

25
26
27
The four columns, forming a rectangle in plan view, had an outside diameter of 15
inches and a wall thickness of 1 inch. The two outside columns had a diameter of
18 inches as shown in fig.
The bracing bars were secured to lugs cast as one with the column. The
horizontal bars (referred to in this unit as struts) were made from channel section
wrought iron and were secured at each end with two wrought iron bolts. The
diagonal bars (referred to in this unit as tie bars) were made from iron flats with a
cross-section of 4.5 × 0.5 inches.
Each diagonal tie bar was held by a 1.125 inch bolt at one end and was jointed
into two sling plates at the other. The sling plates were attached by another 1.125
inch bolt going through 1.25 inch (1¼) holes in the lugs. The tie bar could then be
tensioned at the joint by two cotters (opposed wedges) hammered into a slot that
also housed a gib (metal pad), as shown. As a pier was erected, the inside of each
column was filled with Portland cement, apparently to protect it against
corrosion. The total weight of a pier complete with cement filling, bars and top
plinth was about 120 tons.

28
CHAPTER-7

PRESTRESSED CONCRETE SLAB

Pre-stressed concrete is a method for overcoming concrete's natural weakness in


tension. It can be used to produce beams, floors or bridges with a longer span
than is practical with ordinary reinforced concrete. Pre-stressing tendons
(generally of high tensile steel cable or rods) are used to provide a clamping load
which produces a compressive stress that balancesthe tensile stress that the
concrete compression member would otherwise experience due to abending
load. Traditional reinforced concrete is based on the use of steel reinforcement
bars, rebars, inside poured concrete.

Pre-tensioned concrete is cast around already tensioned tendons. This method


produces a good bond between the tendon and concrete, which both protects the

29
tendon from corrosion and allows for direct transfer of tension. The cured
concrete adheres and bonds to the bars and when the tension is released it is
transferred to the concrete as compression by static friction. However, it
requires stout anchoring points between which the tendon is to be stretched and
the tendons are usually in a straight line. Thus, most pre-tensioned concrete
elements are pre-fabricated in a factory and must be transported to the
construction site, which limits their size.
Pre-tensioned elements may be balcony elements, lintels, floor slabs, beams or
foundation piles. An innovative bridge construction method using pre-stressing is
the stressed ribbon bridge design.

7.1 Bonded post-tensioned concrete

Fig (7.2)

Fig (7.2) Pre-stressed post-tension anchor on display at Instituto Superior


Técnico's civil engineering department Bonded post-tensioned concrete is the
descriptive term for a method of applying compression after pouring concrete
and the curing process (in situ). The concrete is cast around a plastic, steel or
aluminum curved duct, to follow the area where otherwise tension would occur in
the concrete element. A set of tendons are fished through the duct and the

30
concrete is poured. Once the concrete has hardened, the tendons are tensioned
by hydraulic jacks that react (push) against the concrete member itself. When the
tendons have stretched sufficiently, according to the design specifications (see
Hooke's law), they are wedged in position and maintain tension after the jacks are
removed, transferring pressure to the concrete.
The duct is then grouted to protect the tendons from corrosion. This method is
commonly used to create monolithic slabs for house construction in locations
where expansive soils (such as adobe clay) create problems for the typical
perimeter foundation. All stresses from seasonal expansion and contraction of the
underlying soil are taken into the entire tensioned slab, which supports the
building without significant flexure. Post-tensioning is also used in the
construction
of various bridges, both after concrete is cured after support by false work and by
the assembly
of prefabricated sections, as in the segmental bridge.
Among the advantages of this system over un-bonded post-tensioning are:

* Large reduction in traditional reinforcement requirements as tendons cannot


De-stress in accidents.
* Tendons can be easily "woven" allowing a more efficient design approach.
* Higher ultimate strength due to bond generated between

31
CHAPTER-8

POST TENSIONED CONCRETE

8.1 Post tensioned concrete

Un-bonded post-tensioned concrete differs from bonded post-tensioning by


providing each individual cable permanent freedom of movement relative to the
concrete. To achieve this, each individual tendon is coated with grease and
covered by a plastic sheathing formed in an extrusion process. The transfer of
tension to the concrete is achieved by the steel cable acting against steel anchors
embedded in the perimeter of the slab. The main disadvantage over bonded post-
tensioning is the fact that a cable can de-stress itself and burst out of the slab if
damaged (such as during repair on the slab).
The advantages of this system over bonded posttensioning are:
1. The ability to individually adjust cables based on poor field conditions
2. The procedure of post-stress grouting is eliminated
3. The ability to de-stress the tendons before attempting repair work.

Picture number 6.1 (below) shows rolls of post-tensioning (PT) cables with the
holding end anchors displayed. The holding end anchors are fastened to rebar
placed above and below the cable and buried in the concrete locking that end.
Pictures numbered 6.2, 6.3 and 6.4 shows a series of black pulling end anchors
from the rear along the floor edge form. Rebar is placed above and below the
cable both in front and behind the face of the pulling end anchor.
The above and below placement of the rebar can be seen in picture number
three and the placement of the rebar in front and behind can be seen in picture
number four. The blue cable seen in picture number four is electrical conduit.
Picture number 6.5 shows the plastic sheathing stripped from the ends of the
post-tensioning cables before placement through the pulling end anchors. Picture
6.6 shows the post-tensioning cables in place for concrete pouring. The plastic
sheathing has been removed from the end of the cable and the cable has been
pushed through the black pulling end anchor attached to the inside of the
concrete floor side form. The greased cable can be seen protruding from the
concrete floor side form. Pictures 6.7 and 6.8 show the posttensioning

32
cables protruding from the poured concrete floor. After the concrete floor has
been poured and has set for about a week, the cable ends will be pulled with a
hydraulic jack.

33
CHAPTER-9

LAUNCHING OF PRE-TENSIONED SLAB

9.1 Pre-tensioned slab

The technique of incremental launching has been well developed. It is used for
constructing multi span bridges across valleys and where it is desirable to
minimize interference with traffic. Typical span lengths are 20 to 40 m (65 to 130
ft), although span lengths up to 140m (459 ft) have been used with steel girders.
The launching of a steel box girder on a horizontal curve has been successfully
completed.
One example of an incrementally launched bridge is the Wupper Valley
Bridge on Autobahn 1. This project involved expanding the existing expressway
from four to six lanes, plus adding an emergency shoulder in each direction. The
only solution was to build a second bridge parallel to the existing one. The new
bridge is a seven-span structure with span lengths ranging from 44 to 72.8 m (144
to 239 ft) for a total length of 4,18.3 m (1,372 ft). The cross section of the bridge
consists of a rectangular steel U-shaped box beam (shown in figure 21a)
with deck cantilevers beyond the webs supported by inclined struts (shown in
figure 21b). Partial-depth, precast concrete deck slabs were used to eliminate the
need for false work.
The slabs were placed on soft polymer strips to seal the joints. Shear studs
from the steel beams projected into openings in the precast slabs. These openings
were filled with high-strength concrete before placing a CIP concrete deck. The
structure was incrementally launched using hydraulic jacks that pushed on the
end of the steel box beam.
The piers were equipped with sliding bearings to facilitate the launching. The
nose at the front of the structure was equipped with a hydraulically controlled
lifting device that was used to raise the front of the structure as it reached each
pier. Before launching, the precast concrete slabs in the mid-span region were
placed. The slabs over the supports were then placed from the other slabs. If the
steel construction had been moved without the concrete slabs, the slabs would
have had to be placed on the bridge from the side—resulting in additional impact
on traffic. If all concrete slabs had been placed before launching the structure, the
existing hydraulic equipment would not have had sufficient capacity. This
structure was reported to be the first to use precast deck slabs of this size.

34
CHAPTER-10

INFLUENCE OF BUILDING MATERIALS

10.1 Building materials

The traditional building materials for bridges are stone, timber and steel, and
more recently reinforced and pre-stressed concrete. For special elements
aluminum and its alloys and some types of plastics are used. These materials have
different qualities of strength, workability, durability and resistance against
corrosion. They differ also in their structure, texture and color or in the
possibilities of surface treatment with differing texture and color. For bridges one
should use that material which results in the best bridge regarding shape,
technical quality, economics and compatibility with the environment.

10.1.1 Natural stone:-


The great old bridges of the Etruscans, the Romans, the Fraters Pontific
of the Middle Ages (since about 1100) and of later master builders were built with
stone masonry. The arches and piers have lasted for thousands of years when
hard stone was used and the foundations constructed on firm ground. With stone
one can build bridges which are both beautiful, durable and of large span (up to
150 m). Unfortunately, stone bridges have become very expensive, if considered
solely from the point of view of construction costs.
Over a long period, however, stone bridges, which are well designed and well
built, might perhaps turn out be the cheapest, because they are long-lasting and
need almost no maintenance over centuries unless attacked by extreme air
pollution. Stone is nowadays usually confined to the surfaces, the stones being
preset or fixed as facing for abutments, piers or arches.
Of course, sound weather-resisting stone must be chosen, and fundamental
rock like granite, gneiss, porphyry, diabas or crystallized limestone are especially
suitable. Caution is necessary with sandstones, as only siliceous sandstone is
durable.
In Western Germany basalt-lava from the Eifel Mountains is popular. In choosing
the stone one should respect any local experience gained from old buildings and
bridges. Stone is worked upon in different ways, depending upon the direction of
the natural strata occurring in the quarry and on the requirements in the bridge

35
Very different effects can be produced with stone by the choice of the type of
masonry, the height of the courses, the proportion of the stones (length to
height), the arrangement of the joints, the surface treatment etc., and especially
the overall scale. The choice of colors of the stone is also relevant. Granite of a
uniform grey color and sawn surface can look as dull as simple plain concrete. A
harmonious mixture of different colors and slightly embossed surfaces can look
very lively, even when the masonry areas are extensive. Surfaces can also be
enlivened by bright or dark joint-filling.
The sizes of the stone blocks and theroughness of their surfaces must be
harmonized with the size of the structure, the abutments, the piers etc. Coarse
embossing does not suit a small pier only 1 m thick and 5 m high, but large sized
ashlars masonry is suitable for large arch bridges such as the Saalebrucke Jena or
the Lahntalbrucke Limburg. Granite masonry was preferred for piers of bridges
across the River Rhine, because it resists erosion by sandy water much better
than the hardest concrete.

10.1.2 Artificial stones, clinker and bricks:-


Amongst the artificial stones, clinker and hard-burned brick are used in
bridges both as liners and for bearing vaults. They were often used in northern
Germany, the Netherlands, Belgium and Denmark, because there is no suitable
natural stone available. The warm colors of clinker or brick blend happily into the
landscape. Also in an urban environment, they are preferable to plain concrete, if
brick is the regional construction material. The sizes of these stones are
standardized, and one can only choose between different types of joint
arrangements. Small differences in color and a pleasing treatment of the joints
can embellish the surfaces. Finally, one can also use split concrete blocks for
facing. If the concrete is made with colorful aggregates, which break when being
split, then masonry-work produced with these artificial blocks can also look good -
similar to masonry of natural conglomerates, which are in fact nothing else but
natural concrete.

10.1.3 Reinforced and pre-stressed concrete


Concrete is an all-round construction material. Almost every building
contains some concrete, but its questionable application in certain buildings-for
example in its use in the style of brutalism - has brought it into discredit. Its dull
grey color has contributed to the fact that the word concrete has become a

36
synonym for ugly. In the field of bridges, concrete deserves a more favorable
judgment.
Not all concrete bridges have turned out to be beauties, but pleasing bridges can
be built with concrete if one knows the art. Concrete is poured into forms as a
stiff but workable mix, and it can be given any shape; this is an advantage and a
danger. The construction of good durable concrete requires special know-how -
which the bridge engineer is assumed to have.
Good concrete attains high compressive strength and resistance against most
natural attacks though not against de-icing saltwater, or CO2 and SO2 in polluted
air. However, its tensile strength is low, and the use of concrete alone is therefore
limited to structures which are only subject to compressive stresses. But tensile
stresses also occur in abutments and piers due to earthpressure, wind, breaking
forces and to internal temperature gradients.
To resist these tensile forces, steel bars must be embedded in the concrete,
the so called reinforcing bars, and this has led to the development of reinforced
concrete. The steel bars only really come into play after the concrete cracks under
tensile stresses. If the reinforcing bars are correctly designed and placed, then
these cracks remain as fine "hair cracks" and are harmless. A second method of
resisting tensile forces in concrete structures is by pre-stressing. The zones of
concrete girders which are under tensile stress due to loads or other actions are
first put under compression - are pre-compressed - so that the tensile forces must
first reduce these compressive stresses before actual tensile stresses come into
being. This precompression is obtained by tensioning high strength steel bars or
wire bundles, which are in ducts inside the concrete girder.
Tensioning elongates the steel bars and they are anchored in this state at
the ends of the girder, transferring this tensioning force as a compressive force
onto the girder. These girders, pre-stressed with 'active steel" (pre-stressing steel)
are in addition reinforced with "passive steel" (non-stressed steel bars) for various
reasons. Pre-stressed concrete revolutionized the design and construction of
bridges in the fifties. With pre-stressed concrete, beams could be made more
slender and span considerably greater distances than with reinforced concrete.
Pre-stressed concrete - if correctly designed - also has a high fatigue strength
under the heaviest traffic loads. Pre-stressed concrete bridges soon became much
cheaper than steel bridges, and they need almost no maintenance - again
assuming that they are well designed and constructed and not exposed to de-
icing salt. So as from the fifties pre-stressed concrete came well to the fore in the
design of bridges.

37
All types of structures can be built with reinforced and pre-stressed
concrete: columns, piers, walls, slabs, beams, arches, frames, even suspended
structures and of course shells and folded plates. In bridge building, concrete
beams and arches predominate. The shaping of concrete is usually governed by
the wish to use formwork which is simple to make. Plain surfaces, parallel edges
and constant thickness are preferred. This gives a stiff appearance to concrete
bridges, and avoiding this is one task of good aesthetic design.
The extra cost for one-way curved surfaces, for tapering piers, for varying
depth of beams or arch ribs is as a rule comparatively small. Therefore one should
not hesitate to choose such divergences from the most primitive and simple
forms in order to improve appearance.
There is one great disadvantage to concrete as it emerges from the forms: the
inexpressive, dull grey color of the cement skin. The surfaces frequently show
stains, irregular streaks from placing the concrete in varying layers, and pores or
even cavities from deficient compaction, which ire then patched more or less
successfully. These deficiencies have lead to a widespread aversion to concrete,
As well as to efforts for improvement. Some of the methods used to achieve a
good concrete finish in buildings, like profiles and patterns on the formwork, ribs
oraccentuated timber veins etc. are not generally suitable.
The best effect is obtained by bush hammering as was usual between 1934 and
1945 for the bridges of the German autobahn system. The concrete coating of the
reinforcement is increased by 10 to 15 mm, so that a thin layer together with the
cement skin can be taken off by fine or coarse bush hammering. The aggregate is
then exposed with its structure and color The protection of the embedded steel is
not damaged, because the exterior cement skin is in any case the worst part of
concrete. It is very porous, because mixing water collects at the forms of vibrating
the concrete, and it is the porosity of the cement skin which makes it so
susceptible to collecting the dirt of polluted air. With bush hammering one can
adapt the degree of roughness to the size of the surfaces. Piers of viaducts, for
example, were chiseled very roughly, taking off pieces 20 to 30 mm in depth by
oblique chisel work. The color can be favorably influenced by the choice of
colored aggregates like red porphyry or yellow limestone. Such surfaces age as
well as natural stone masonry, and they retain their texture over a long period of
time. The cement skin can also be washed off by special means
after the concrete has hardened - such "exposed aggregate" surfaces can look
pleasing, depending on the color and size of the aggregates. Bush hammering was
given up after about 1950 due to the high labour cost. At that time suitable

38
machines were not yet available, but with modernmachinery this treatment
should now be taken up again to embellish concrete surfaces.
Another possibility is coloring the concrete it has been well developed during the
last decade. By the use of mineral color pigments natural warm tones can be
attained - earthy colors with tones of ochre, reddish-brown sepia. Umber, greyish-
green, slate-grey. Dark toned piers of a viaduct often look better in the landscape
than with a light grey color. Bright colored concrete with white cement-can for
example be chosen to emphasize a fascia beam.
Fritz Leonhardt has often recommended the painting of bridges in the same way
that steel bridges are painted for corrosion protection. At the same time the
dreary grey of normal concrete is converted into a harmonious colorful
statement. For painting, soft colors should again be chosen and not bright loud
colors. Before painting, the porous cement skin must be removed, so
that the paint will not peel off later. Mineral colors, especially those with flour- or
siliceous compounds, can also give an additional protection to the concrete. The
colour film must be hygroscopic, so that it does not prevent the change of
moisture content in the concrete. If the choice of color and type of paint is
based on the most up-to-date information, then these paints can last long and
keep their color like the paintwork of many old houses and churches, particularly
in the Alps, which is often more than 200 years old and still beautiful. Color
painting of concrete bridges has already been used in several places. A most
striking example is that of the long bridges along the riverbanks in Brisbane,
Australia.

10.1.4 Steel and aluminum


Amongst bridge materials, steel has the highest and most favorable
strength qualities, and it is therefore suitable for the most daring bridges with the
longest spans. Normal building steel has compressive and tensile strengths of 370
N/mm2, about ten times the compressive strength of a medium concrete and a
hundred times its tensile strength. A special merit of steel is its ductility due to
which it deforms considerably before it breaks, because it begins to yield above a
certain stress level. This yield strength is used as the first term in standard quality
terms. For bridges high strength steel is often preferred. The higher the strength,
the smaller the proportional difference between the yield strength and the tensile
strength, and this means that high strength steels are not as ductile as those with
normal strength. Nor does fatigue strength rise in proportion to the tensile

39
strength. It is therefore necessary to have a profound knowledge of the behavior
of these special steels before using them.
For building purposes, steel is fabricated in the form of plates (6 to 80mm
thick) by means of rolling when red hot. For bearings and some other items, cast
steel is used. For members under tension only, like ropes or cables, there are
special steels, processed in different ways which allow us to build bold suspension
or cable-stayed bridges. The high strengths of steel allow small cross-sections of
beams or girders and therefore a low dead load of the structure. It was thus
possible to develop the light-weight "orthotropic plate" steel decks for roadways,
which have now become common with an asphalt wearing course, 60 to 80 mm
thick. The pioneers of this orthotropic plate construction called it by the less
mysterious and less scientific name "stiffened steel slabs". Plain steel plate,
stiffened by cells or ribs, forms the chord of both the transverse cross girders and
the longitudinal main-girders. Simultaneously it acts as a wind girder. This bridge
deck owes its successful application mainly to mechanized welding, which is now
in general use and which has greatly influenced the design of steel bridges.
So plate girder construction now prevails, in which large thin steel plates must be
stiffened against buckling. Previously, vertical stiffeners were placed by
preference on the outer faces; longitudinal stiffeners were then arranged on the
inside.
Today all stiffeners are placed on this inside so as to achieve a smooth outer
surface allowing no accumulation of dust or dirt deposits that retain humidity and
promote corrosion – the "Achilles heel" of steel structures. Modern steel girder
bridges now hardly differ from prestressed concrete bridges in their external
appearance - except perhaps in their color. This is perhaps regrettable, because
stiffeners on the outside enliven the plate-faces, give scale and make the
girder look less heavy. In addition to plate girders, trusses also take full advantage
of the material properties of steel. Very delicate looking bridges can be built by
joining slender steel sections together to form a truss. Again welding has
improved the potential for good form, because hollow sections can be fabricated
and joined without the use of big gusset plates. In this way smooth looking
trusses arise without the "unrest" which occurs by joining two or four profiles of
rolled section with lattice or plates. Steel must be protected against corrosion and
this is usually done by applying a protective paint to the bare steel surface.
Painting of normal steels is technically necessary and can be used for color design
of the bridge.

40
The choice of colors is an important feature for achieving good appearance. There
are steels which do not corrode in a normal environment (the stainless steels V2A
and V4A to DIN 17440), but are so expensive that they are used only for
components that are either particularly susceptible to the attacks of corrosion or
that are very inaccessible.
From the USA came Tentor steel, alloyed with copper, its 'first corrosion layer
being said to protect it against further corrosion. This protective rust has a warm
sepia-toned color which looks fine in open country. This type of protection,
however, does not last in polluted air and the corrosion continues. For steel
bridges, good use should be made of the technical necessity of protecting the
steel with paint to improve appearance and to achieve harmonious integration of
the structure within the landscape. Aluminum was occasionally used for bridges
and the same form was used as for steel girders. Aluminum profiles are fabricated
by the extrusion process which allows many varied hollow shapes to be formed,
so that aluminum structures can be more elegant than those of steel.
Aluminum profiles are popular for bridge parapets because they need no
protective paint.

10.1.5Timber:-
Timber has favorable qualities of strength for resisting compression,
tension and bending. Rough tree trunks or sawn timber beams have been used
since primitive times for beam bridges; raking frames and arches soon allowed
larger spans. The Swiss carpenters, the brothers Grubennann reached a 100 m
span with the timber bridge across the River Rhine near Schaffhausen. Timber
should be protected against rain and therefore covered bridges with a roof
and sidewalls with windows evolved, and many of these are rightly preserved in
the Alpine countries, testifying to the high standard of their craftsmanship.
Many now only serve pedestrians. Recently timber bridges have been given
a new impetus by glue technology which allows larger cross-sections and larger
lengths of beams to be made than grow naturally. Moreover timber can now be
better protected against weather and insect attack. So new possibilities have
arisen or the choice of structure, for its shaping and for the size.
Large timber trusses and even folded space trusses have been built using steel
gusset plates for jointing the members. Timber bridges, however, have limits of
span and carrying capacity, confining them mainly to bridges for pedestrians or
for secondary roads.

41
10.2 Bridge construction technology

Bridge construction technology has evolved over the years. In this age of
advanced science, technology and machines, bridges have undergone various
changes and different types of bridges are being constructed in major countries of
the world. Construction techniques like slurry walls, post-tensioning, soil freezing,
reinforced earth walls, suspension, folding etc. are being used. Bridge
construction is changing. New construction techniques and new materials are
emerging and accordingly the construction machinery industry has played a
pivotal role.

42
CHAPTER-11

TYPES OF BRIDGE CONSTRUCTION MACHINERIES

11.1 Construction machineries

The various machineries for constructing bridges are:


Bridge Crane
Gantry Crane
Floating Crane

11.1.1 Bridge cranes:-

Bridge crane is a heavy machinery that is designed to build or fix a bridge. It


operates on two tracks and has four way horizontal movement. Bridge cranes
cover rectangular area and can be floor supported or hung from the ceiling. The
main components of bridge cranes are bridge, trolley, hoist drum, hoist cable,
hoist block, hook bumpers, pendant and limit switches. On-off
switch is on control pendant for taking emergency steps, in the event of failure of
any of the control-panels.
Bridge cranes are either double girder or single girder. Double girder bridge crane
can be utilized at any capacity where extremely high hook lift is required because
the hook can be pulled up between the girders. For high speeds and heavy
services too, double girder bridge cranes are very useful. In bridge crane rigid box

43
girder construction and durable trolley design are well suited for heavy service
applications.

11.1.2 Gantry cranes

Gantry cranes are those cranes which are generally used for moving heavy loads.
They are a common type of portable material handling equipment used in job
station or secondary task areas. Gantry cranes are quite similar to overhead
cranes except that the bridge which carries trolley is rigidly supported on two or
more legs running.

11.1.2.1 Gantry crane sizes and marking:-


Though gantry cranes are known for its huge models but, there
happen to be smaller cranes as well that are found in small industries and
warehouses etc. The cranes are available in both, adjustable as well as fixed
height. Its making too is either of steel or aluminum, depending upon the
application of the crane. Each gantry crane is designed with two upright beams
and a cross beam. It has an A-frame shaped set of two legs with wheels beneath
to render maximum mobility and portability.

44
11.1.2.2 Types of gantry cranes:-
Gantry cranes can be of different range like single girder, double girder, double
leg, single leg, and cantilever styles for indoor or outdoor service. It is also
available in fixed height steel and adjustable steel. Gantry crane is an economical
device for lifting materials anywhere in a facility. Gantry cranes are also supplied
with four roller-bearing steel wheels for easy maneuverability.

Uses of gantry cranes:-


Gantry cranes or bridge cranes are useful machinery which find its application in
constructing bridges. Lifting heavy industrial devices, lifting containers in
seaports, and are ideal for use in air craft, automotive, and marine repair shops.

11.1.2.4 Renting Gantry Crane


For companies that cannot afford to buy a whole new gantry crane, it
would be most cost effective to get a gantry crane on rent. Getting used gantry
cranes have many advantages, the best being that one does not have to shell out
a big amount upfront to get the required equipment. A floating crane refers to a
type of sea vessel which has a crane mounted on it. In earlier days, floating crane
designs were nothing more than old ships transformed to include a huge crane
mounted over the deck. Eventually, catamaran, semi-submersible designs
changed the face of floating cranes. Read on to know more about these cranes

45
11.1.3 Floating Cranes
Floating cranes are those heavy-duty cranes which are frequently used for
building bridges, and constructing ports. Fleeting applications in ports etc. They
also have great utility in loading and unloading of heavy weights on and off ships.
The floating cranes are generally selfpropelled. They have the powerful diesel
generators to work the crane winches, which can be switched to propel the craft.

11.1.3.1 Floating Cranes Working


Floating cranes can be mounted on a swing base installed on thedeck
of pontoon and can swing in a circular motion both in a clockwise and
anticlockwise direction. Apart from pontoon mounted cranes, some floating
cranes barges with a lifting capacity exceeding 10,000 tones and are used to
transport entire bridge sections.

11.1.3.2 Floating Cranes Uses


There are various uses of a floating crane. These vessels are able to
lift and maneuver huge and heavy sub-assemblies into position. Floating cranes
also felicitate the assembly of massive projects out of numerous smaller
assemblies in most weather conditions.Apart from drilling and construction
purposes, floating cranes are used for sunken ship retrieval purposes also.

Used Floating Crane


Since these are one of the most expensive types of construction cranes, the trend
of hiring used floating cranes for a given time period is quite popular among
builders and construction workers. One can find a number of floating crane
suppliers online to set hiring or purchasing deals.

46
For building bridges launching girder is an important machinery. With
sophisticated equipment, launching girder itself is a normal structure. With
different launching capacities and heights, launching girders are used for making
different kinds of bridges. Launching girder itself is a steel structure which moves
forward on the bridge piers span by span. As launching girder can handle
cast-in place concrete, as well as prefabricated elements, it is highly adaptable for
a wide range of spans and types of superstructure

47
CHAPTER-12

TOTAL STATION
12.1 Coordinate measurement
Coordinates of an unknown point relative to a known coordinate can be
determined using the total station as long as a direct line of sight can be
established between the two points.
Angles and distances are measured from the total station to points under survey,
and the coordinates (X, Y, and Z or northing, easting and elevation) of surveyed
points relative to the total station position are calculated using trigonometry and
triangulation. To determine an absolute location a Total Station requires line of
sight observations and must be set up over a known point or with line of sight to 2
or more points with known location. For this reason, some total stations also have
a Global Navigation Satellite System Interface which does not require a direct line
of sight to determine coordinates. However, GNSS measurements may require
longer occupation periods and offer relatively poor accuracy in the vertical axis.

12.2 Angle measurement


Most modern total station instruments measure angles by means of electro-
optical scanning of extremely precise digital bar-codes etched on rotating glass
cylinders or discs within the instrument. The best quality total stations are
capable of measuring angles to 0.5 arc-second. Inexpensive "construction grade"
total stations can generally measure angles to 5 or 10 arcseconds.

12.3 Distance measurement


Measurement of distance is accomplished with modulated microwave or infrared
carrier signal, generated by a small solid-state emitter within the instrument's
optical path, and reflected by a prism reflector or the object under survey. The
modulation pattern in the returning signal is read and interpreted by the
computer in the total station. The distance is determined by emitting and
receiving multiple frequencies, and determining the integer number of
wavelengths to the target for each frequency. Most total
stations use purpose-built glass corner cube prism reflectors for the EDM signal. A
typical total station can measure distances with an accuracy of about 1.5
millimeters (0.0049 ft) + 2 parts per million over a distance of up to 1,500 meters
(4,900 ft).

48
Reflector less total stations can measure distances to any object that is reasonably
light in color,
up to a few hundred meters.

12.4 Data processing


Some models include internal electronic data storage to record distance,
horizontal angle, and vertical angle measured, while other models are equipped
to write these measurements to an external data collector, such as a hand-held
computer. When data is downloaded from a total station onto a computer,
application software can be used to compute results and generate a map of the
surveyed area. The new generation of total stations (e.g. Hilti POS 15/18) can also
show the map on the touch-screen of the instrument right after measuring the
points.

12.5 Applications:-
Total stations are mainly used by land surveyors and Civil Engineers, either to
record features as in Topographic Surveying or to set out features (such as roads,
houses or boundaries). They are also used by archaeologists to record excavations
and by police, crime scene investigators, private accident re-constructionists and
insurance companies to take measurements of senesce

12.6 Mining
Total stations are the primary survey instrument used in mining surveying.
A total station is used to record the absolute location of the tunnel walls (stopes),
ceilings (backs), and floors as the drifts of an underground mine are driven. The
recorded data are then downloaded into a CAD program, and compared to the
designed layout of the tunnel. The survey party installs control stations at regular
intervals. These are small steel plugs installed in pairs in holes drilled into walls or
the back. For wall stations, two plugs are installed in opposite walls, forming a line
perpendicular to the drift. For back stations, two plugs are installed in the back,
forming a line parallel to the drift. A set of plugs can be used to locate the total
station set up in a drift or tunnel by processing measurements to the plugs by
intersection and resection

49
12.7 Stone block
The type of sleeper used on the predecessors of the first true railway (Liverpool
and Manchester Railway) consisted of a pair of stone blocks laid into the ground,
with the chairs holding the rails fixed to those blocks. One advantage of this
method of construction was that it allowed horses to tread the middle path
without the risk of tripping. In railway use with ever heavier locomotives, it was
found that it was hard to maintain the correct gauge. The stoneblocks were in any
case unsuitable on soft ground, where timber sleepers had to be used.

50
CHAPTER-13

SLEEPERS
13.1 Wooden sleepers

A variant fastening of rails to wooden ties .


A variety of softwood and hardwoods timbers are used as ties, oak, jarrah and
karri being popular hardwoods, although increasingly difficult to obtain, especially
from sustainable sources.
Some lines use softwoods, including Douglas fir; while they have the advantage of
accepting treatment more readily, they are more susceptible to wear but are
cheaper, lighter (and therefore easier to handle) and more readily available.
Softwood is treated, historically using creosote, but nowadays with other less-
toxic preservatives to improve resistance to insect infestation and rot. New
boron-based wood preserving technology is being employed by major
US railroads in a dual treatment process in order to extend the life of wood ties in
wet areas. Some timbers (such as sal, mora, jarrah or azobé) are durable enough
that they can be used untreated.
Problems with wood ties include rot, splitting, insect infestation, plate-cutting
(known as chair shuffle in the UK), (abrasive damage to the tie caused by lateral
motion of the tie plate) and spike-pull (where the spike is gradually loosened from
the tie). For more information on wood ties the Railway Tie Association maintains
a comprehensive website devoted to wood tie research and statistics.

51
13.2 Concrete sleepers

In concrete railroad ties increased after World War II following advances in the
design, quality and production of pre-stressed concrete. Concrete ties were
cheaper and easier to obtain than
timber and better able to carry higher axle-weights and sustain higher speeds.
Their greater weight ensures improved retention of track geometry especially
when installed with continuous welded rail. Concrete sleepers have a longer
service life and require less maintenance than timber due to their greater weight
which helps them remain in the correct position longer. Concrete sleepers need
to be installed on a well-prepared sub grade with an adequate depth on
free-draining ballast to perform well. In 1877, M. Monnier, a French gardener,
suggested that concrete could be used for making ties for railway track. Monnier
designed a tie and obtained a patent for it, but it was not successful. Designs were
further developed and the railways of Austria and Italy used the first concrete ties
around the turn of the 20th century. This was closely followed by other European
railways.
Major progress was not achieved until World War II, when the timbers used for
ties were scarce due competition from other uses, such as mines. Following
research carried out on French and other European railways, the modern pre-
stressed concrete tie was developed.
Heavier rail sections and long welded rails were also being installed, requiring
higher-quality ties. These conditions spurred the development of concrete ties in
France, Germany and Britain, where the technology was perfected. On the
highest categories of line in the UK (those with the highest speeds and tonnages)

52
pre-stressed concrete sleepers are the only ones permitted by Network Rail
standards.
Most European railways also now use concrete bearers in switches and crossing
layouts due to the longer life and lower cost of concrete bearers compared to
timber, which is increasingly difficult and expensive to source in sufficient
quantities and quality.
On November 8, 2011, the US Federal Railroad Administration (FRA) put into
effect new regulations on concrete ties, with notices published by the FRA in the
April 1 and September 9, 2011 U. S. Federal Register. The FRA notices say that the
need for the new rules was shown by the derailment of an Amtrak train near
Home Valley, Washington on April 3, 2005, which according to the U.S. National
Transportation Safety Board was caused in part by excessive concrete tie
abrasion. To be counted as a good tie under FRA regulation 213.109(d)(4),
a concrete ties shall not be deteriorated or abraded under the rail to a depth of
one-half inch or more. Limits on other types of concrete tie deterioration are also
given.

13.3 Steel sleepers

Steel sleepers are formed from pressed steel and are trough-shaped in section.
The ends of the sleeper are shaped to form a "spade" which increases the lateral
resistance of the sleeper. Housings to accommodate the fastening system are
welded to the upper surface of the sleeper. Steel sleepers are now in widespread
use on secondary or lower-speed lines in the UK where they have been found to
be economical to install due their ability to be installed on the
53
existing ballast bed. Steel sleepers are lighter in weight than concrete and able to
stack in compact bundles unlike timber. Steel sleepers can be installed onto the
existing ballast, unlike concrete sleepers which require a full depth of new ballast.
Steel ties are 100% recyclable and require up to 60% less ballast than concrete
ties and up to 45% less than wood ties. Historically, steel ties (sleepers) have
suffered from poor design and increased traffic loads over their normally long
service life. These aged and often obsolete designs limited load and speed
capacity but can still be found in many locations globally and performing
adequately despite decades of service. There are great numbers of steel ties with
over 50 years of service and in some cases they can and have been rehabilitated
and continue to perform well. Steel ties were also used in specialty situations,
such as the Hejaz Railway in the Arabian Peninsula, which had an ongoing
problem with Bedouins who would steal wooden ties for campfires.
Modern steel ties handle heavy loads, have a proven record of performance in
signalized track, and handle adverse track conditions. Of high importance to
railroad companies is the fact that steel ties are more economical to install in new
construction than creosote-treated wood ties and concrete ties. Steel ties are
utilized in nearly all sectors of the worldwide railroad systems including heavy-
haul, class 1’s, regional, short lines, mining, electrified passenger lines (OHLE) and
all manner of industries.
Notably, steel ties (bearers) have proven themselves over the last few decades to
be advantageous in turnouts (switches) and provide the solution to the ever
growing problem of long timber ties for such use.

54

You might also like