The document provides a work breakdown structure (WBS) summary for foundation works of a construction project. It details 3 parts of the foundation works - footing, footing tie beam, and wall footing - with the total cost and duration for each part. The total cost of all foundation works is Php 325,152.42 to be completed over 22 days.
The document provides a work breakdown structure (WBS) summary for foundation works of a construction project. It details 3 parts of the foundation works - footing, footing tie beam, and wall footing - with the total cost and duration for each part. The total cost of all foundation works is Php 325,152.42 to be completed over 22 days.
The document provides a work breakdown structure (WBS) summary for foundation works of a construction project. It details 3 parts of the foundation works - footing, footing tie beam, and wall footing - with the total cost and duration for each part. The total cost of all foundation works is Php 325,152.42 to be completed over 22 days.