C0-M PRECOMMISSIONING OF MECHANICAL EQUIPMENT

SUMP PUMP TEST REPORT


PRE-COMMISSIONING INSPECTION C0M-37

PROJECT TITLE: MHT – NPMC IMPROVEMENT PROJECTS


PROJECT NAME: OEP – OXIDE EXPANSION PROJECT
PROJECT No.: 1090
CLIENT: NPMC
CONTRACTOR:
CONTRACT/PO NO.:
AREA/LOCATION:
EQUIPMENT NAME:
EQUIPMENT No.:
PID No.:
TEST PACKAGE No:

Inspected Inspected
Inspection check list N/A by by
Contractor Engineer

1 All Manufacturer’s requirements complied with   


2 Pump Base Frame bolts in place/ Grouting complete   
3 Installation checked against Drawings   
4 All debris and waste material removed from sump and surrounding areas   
5 Motor/Pump Shaft locking clamps removed   
6 Bearings where grease nipples fitted (Motor/Shaft/Barrel) have 2 full pumps with   
grease gun
7 Grease Packed Bearing Initial fill checked   
8 Discharge Pipe installed correctly, right gaskets in place and all bolts tight   
9 Ensure no load is transmitted to pump from discharge piping   
10 V Belt Pulleys Alignment complete (attach check sheet C0M50)   
11 Manually rotate pump as per directional arrow with V Belts removed. If no free   
movement adjustment of impeller will be required
12 Isolation Valve on discharge line installed correctly, right gaskets in place and   
all bolts tight
13 High/Low level floats installed   
14 All Safety Guards Installed and checked for pinch points   
15 All safety signage installed   
16 Punch list Completed   

REMARKS: ...................................................................................................................................................................
.........................................................................................................................................................................................
MHT-NPMC MHT-NPMC
CONTRACTOR
QA/QC SUPERINTENDENT

Signature:

Name:

Date:

. 2
C0M-37 Rev. 0 Page 1 of 2