You are on page 1of 3

C0-M PRECOMMISSIONING OF MECHANICAL EQUIPMENT

HYDROSTATIC TEST OF PRESURE VESSEL TEST REPORT

PRE-COMMISSIONING INSPECTION C0M-14


PROJECT TITLE: NPMC IMPROVEMENT PROJECTS
PROJECT NAME:
PROJECT No.:
CLIENT: NPMC
CONTRACTOR: VISAVAKIT PATANA CORP., LTD (VIPCO)
CONTRACT/PO NO.:
AREA/LOCATION:
EQUIPMENT NAME:
EQUIPMENT No.:
PID No.:
TEST PACKAGE No:

Inspected Inspected
Inspection check list N/A by by
Contractor Engineer

1. Confirm off site or factory pressure tests have been completed and   
certification is available. If yes confirm details on vessel/tank plate are stamped
to reflect the completion of the pressure test. If the pressure test is complete and
acceptable there is no requirement to further pressure test on site.

GA Drawing: Testing Spec: Test Date:

2. Testing Data: Test Pressure   


Test normal working Test pressure of tank: Test
pressure: medium
:

Inhibitor: Test Duration: Hold


Time:

Approx Volume required: Weight of tank & Test Medium: Frequen


cy of
data
logging:

3. All commissioning consumables and special tools are available   


4. All test instruments operational, calibrated and are available.   
5. Isolate all instruments, tank nozzles and off - takes   
6. All Safety signs/tape in place   
7. Fill tank/vessel with test medium to the specified level.   
8. Gross Leak Test: In accordance with the relevant specification, fill the   
tank/vessel and perform gross leak test and confirm rate is within project
acceptable limits. This test should also check for leaks on flanged connections
etc.

. 2
C0M-14 Rev. 0 Page 1 of 3
C0-M PRECOMMISSIONING OF MECHANICAL EQUIPMENT

HYDROSTATIC TEST OF PRESURE VESSEL TEST REPORT

PRE-COMMISSIONING INSPECTION C0M-14


PROJECT TITLE: NPMC IMPROVEMENT PROJECTS
PROJECT NAME:
PROJECT No.:
CLIENT: NPMC
CONTRACTOR: VISAVAKIT PATANA CORP., LTD (VIPCO)
CONTRACT/PO NO.:
AREA/LOCATION:
EQUIPMENT NAME:
EQUIPMENT No.:
PID No.:
TEST PACKAGE No:

Inspected Inspected
Inspection check list N/A by by
Contractor Engineer
9. Pressure Test:   
Using the relevant project specification, pressurise the tank/vessel and record
the relevant data.

10. RECORD:   
Start time: Start date: Start
temp;
End time: End date: End
temp:

11. DATE TIME LEVEL AMBIENT TEST HOLD   


TEMP CO PRESSURE PRESSURE

12 On Completion ensure:
 Tank/ Vessel is drained and dried   
 All instruments, equipment and valves re-installed   
 All re-installed instruments, equipment and valve connections have
  
gaskets and seals fitted and all flange bolts tight.
13. Safety Signs/ tape removed   
14. Punch List completed   
NOTE:

. 2
C0M-14 Rev. 0 Page 2 of 3
C0-M PRECOMMISSIONING OF MECHANICAL EQUIPMENT

HYDROSTATIC TEST OF PRESURE VESSEL TEST REPORT

PRE-COMMISSIONING INSPECTION C0M-14


PROJECT TITLE: NPMC IMPROVEMENT PROJECTS
PROJECT NAME:
PROJECT No.:
CLIENT: NPMC
CONTRACTOR: VISAVAKIT PATANA CORP., LTD (VIPCO)
CONTRACT/PO NO.:
AREA/LOCATION:
EQUIPMENT NAME:
EQUIPMENT No.:
PID No.:
TEST PACKAGE No:

Inspected Inspected
Inspection check list N/A by by
Contractor Engineer
This test assumes no factory pressure test has been performed. If a factory or off-
site pressure test has been performed, the test certificate must be attached to this
test report and conformation stamp verified.
REMARKS: ...................................................................................................................................................................
.........................................................................................................................................................................................

CONTRACTOR: ......................................................... DATE: .........................................................


MHT-NPMC QA/QC ......................................................... DATE: .........................................................
MHT-NPMC ......................................................... DATE: .........................................................
SUPERINTENDENT

. 2
C0M-14 Rev. 0 Page 3 of 3

You might also like