METHOD OF STATEMENT
FOR VOLTAGE
TRANSFORMER
CONTENTS
1.0 Purpose 03
2.0 Scope 03
3.0 References 03
4.0 Manpower 03
5.0 Procedure 03
9.0 Responsibilities 06
10.0 Emergency 07
11.0 Records 07
METHOD OF STATEMENT
FOR VOLTAGE
TRANSFORMER
1.0 Purpose
This method statement will give a brief step to be carried out for testing and commissioning
of voltage transformer.
2.0 Scope
This procedure describes the method to be adopted for:
VT testing.
3.0 Reference
Approved schematic drawing
Project HSE Plan
Project Quality Plan
Tender Specification
4.0 Man power
a) Project Engineer (permit holder) -01
b) Testing Engineer (DCRP) -01
c) HSE Officer -01
d) Technician -01
5.0 Procedure
Ensure that all reference documents are available at site.
Ensure that valid permits are obtained from concerned authorities wherever
applicable.
Ensure only trained persons shall operate the power tools.
Ensure all concerned personals shall use PPE and all other items are required.
Ensure adequate lighting is provided in the working area at night time.
Ensure service area/work area openings are provided with barricade, tape and safety
nets.
Ensure that wiring is done as per the schematic and wiring drawings
6.0 Preparation for testing
All materials and relevant documentation to this testing works shall be checked by the
responsible personnel prior to the commencement of testing activities.
Before any item of equipment is accepted for testing a visual inspection will be
carried out on that equipment. Where defective equipment is found it will be reported
to consultant for further action.
The testing electrical engineer/supervisor should confirm the availability of necessary
single phase for testing activities.
METHOD OF STATEMENT
FOR VOLTAGE
TRANSFORMER
7.2 IR test:
Before proceeding to IR test ensure all the earth links are open condition in switchgear.
Apply high voltage (5kV) with IR tester to each phase in CT primary with reference to
ground and measure the resistance value.
Then measure the Insulation Resistance between Secondary to Earth, Primary to Secondary,
Secondary to Secondary with 500V.
METHOD OF STATEMENT
FOR VOLTAGE
TRANSFORMER
All equipment’s, tools & tackles shall be checked by HSEA before starting the
job.
Segregated access for equipment and workers shall be provided.
Ensure enough drinking water is available at work site.
Ensure work crew is provided with adequate transportation facilities.
Ensure all employees are clear about their job, tasks and hazards involved.
Ensure all the testing kits and tools to be used are in good working condition.
9.0 Responsibilities
Project Manager is over all responsible for Safety, Quality and Progress of
the Project.
Safety Engineer Will Monitor all works are being carried out in accordance
with the safety requirements on site.
Testing Engineer shall be responsible for the site testing activities and
implementation of all testing plans.
METHOD OF STATEMENT
FOR VOLTAGE
TRANSFORMER
10.0 Emergency
In case of Emergency,
Stop the work.
Alert the nearby workers to reach to the nearest assembly point
Do not to get panic and do not run.
Inform the site HSE officer and other key personnel from the emergency
contacts numbers displayed in the site.
Call emergency services if required.
Supervisor shall make head count and report.
11.0 Records
Quality Records
Inspection forms