Professional Documents
Culture Documents
PRELIMINARIES:
The Inspecting Officer will follow the following procedure on reaching the works of
the supplier:
1. Obtain detailed offer letter with details of rating and quantity to be inspected.
2 .Identify & verify the rating and quantity of transformers offered for
inspection.
3.Obtain the sequence of testing and the list of equipment required for conducting
the tests, including special tests as directed by the order placing authority. Carry
out the inspection according to the plan.
7.Affix his Identification mark on the tank of the transformers offered for
inspection / testing.
8.Check and verify the make, rating and quantity, etc. of accessories of the
transformer as per approved general arrangement drawing and shipping /
packing list.
9.Obtain & verify the manufacturer’s test certificates for the bought out
items if provided in P.O. / specification / nomination letter.
8.May obtain and examine original type test reports if desired by the Purchaser /
Order Placing Authority.
STAGE INSPECTION:
No. TESTS
1 Voltage Ratio / Turns Ratio Test.
No. TESTS
1 Verification of Assembly & dimensions of
transformers.
2 Verification of accessories and fittings on
transformers, including their make & rating.
SPECIAL ATTENTION:
Do not witness any test in which the equipment / instruments used are not of the specified
accuracy class or better.
1. Do not permit high voltage tests when the power supply is from a captive
diesel generating set during power failures.
2. Do not permit test for measurement of Acoustic Noise level test if the
ambient noise is beyond permissible limits.
3. Ensure that 3 phase 4 wire watt meter is used for loss measurement. During
no load test, maintain rated frequency & rated voltage. Current range and
rating of watt meter / ampere meter should be adequate to read accurately
on low range also. In case the frequency is less than the rated, the
measured loss has to be corrected to the rated frequency.
4. Ensure that while carrying out the measurement, the proper current / voltage
/ power ranges are selected corresponding to the values as will be observed.
The percentage error of the measuring equipment shall also be within the
specified and required accuracy, i.e., class 0.5 or better. This should be
ensured by checking the calibration report of the measuring equipment.
5. Ensure that the connections to the measuring instruments are correctly made
and tightened fully.
6. Ensure that the measuring equipments are connected to the required ratios /
tappings.
7. Ensure that oil / ambient temperatures are noted for
measurements affected by temperature.
9. Ensure that transformer oil samples are drawn after all electrical
tests have been conducted but before the measurement of the oil
required for the first filling.
10. Ensure that there is no excessive air draft or air circulation around
the transformer during temperature rise test.
12. Check that the accessories fit perfectly on the corresponding part
of the transformer.
13. Check that the instruments and equipment are provided on the
transformer as per approved drawing and purchase order.
CONCLUDING: