Professional Documents
Culture Documents
INSULATOR
Ear Protection
Respiratory Protection
www.saudirockwool.com
Address:
Postal Code:
Synonyms: Mineral wool, Rockwool, Manmade Vitreous Fiber , Manmade Vitreous mineral Fiber.
Mineral wool has been classified by EU as locally irritating (irritate the skin),
This product is not asbestos product free from freeformaldehyde and Environment friendly with CFC
and HCFC free , ,and chemically inert, with Zero ODP Ozone Depletion Potential &Zero GWP Global
Warming Potential .
Skin Contact : Flush with clean water, If discomfort persists, seek medical attention.
Eye Contact: Flush with clean water, If discomfort persists, seek medical attention.
Advice to Doctor: Any symptoms and signs of ill-health are likely to be due to other causes. Can be
slightly itchy on prolonged contact with skin. Does not produce any acute
or chronic health effects. Treatment should be directed toward cleansing the skin and symptomatic
treatment as necessary.
Suitable extinguishing media: As needed for surrounding fire conditions. Any extinguishing media may
be used as required. Water fog may be used to cool intact containers and nearby storage areas.
Hazards from combustion products: Saudi Rockwool Insulation is non-flammable, but the plastic
wrapping, resin binder, and some facings may decompose, or burn in a fire or when heated above
300ºC.
Fire Fighting Procedures: As needed for surrounding fire conditions, If required evacuate area and
contact emergency services, remain upwind and notify those downwind of fire hazard, and wear
protective equipment including Self-Contained Breathing Apparatus (SCBA).
Clean Up Procedure: Personnel directly involved in clean-up of loose material should wear personal
protective equipment, clean area so as to avoid dispersion
Handling: These products are safe in use. Once installed, the product does not release dust or fibers.
Handling, installing or removing the product may result in some dust and airborne fiber. Minimize eye or
skin contact and inhalation during handling, installation and removal, Observe good personal hygiene,
including washing hands before eating. Remove personal protective equipment before entering eating
areas
Storage: Store in sealed container in cool, dry area, removed from foodstuffs. Ensure packages area
adequately labeled, protected from physical damage, and sealed when not in use. Avoid packaging being
stored under UV light (direct sunlight) for long periods.
Incompatibilities: None.
will be required. However, if installing in dusty or poorly-ventilated areas, or during the first heat up
cycle in high-temperature industrial applications, local exhaust ventilation should be considered. Work
practices should aim to minimize the release of, and exposure to, fibers and/or dust. Hand tools
generate the least amount of dust and fibers. If power tools are used directly on the product
appropriate dust collection systems are recommended.
Personal Hygiene: Washing of exposed skin with soap and water at the end of a shift or as required is
recommended as a comfort measure.
Skin Protection: Direct skin contact can be minimized by wearing long-sleeved shirts and long trousers, a
cap or hat, and standard duty gloves .Work clothes should be washed regularly and separately from
other clothes. Comfort sleeve gloves are recommended for improved comfort when handling and
installing Rockwool Insulation
Eye Protection: When handling these products, particularly overhead or in enclosed or poorly ventilated
areas such as ceiling spaces or risers, eye contact with dust or fiber can be avoided by wearing ventilated
non-fogging dust resistant goggles.
Chemical Stability: Stable. The cured resin is stable and will remain intact for the life of the
product under normal atmospheric conditions
Incompatible Materials: None . No reported incompatibilities. Acids, alkalis or organic solvents
may cause degradation of resin binder.
In October 2001, IARC completed a re-evaluation of respirable mineral wool fibers and classified them in
Group 3 (not classifiable as to their carcinogenicity to humans).
Persistence and Degradability: Rockwool Insulation is bio-soluble and in most ecosystems it would be
expected to solubilise over a period of weeks to months. Binder-coated insulation wool is hydrophobic,
and no adverse environmental effects would be expected if accidentally released in water or soil.
Ozone Depleting Potential: No Ozone Depleting Substances are involved in either the manufacture
or composition of this product & therefore has an ozone depletion potential of zero.
This product is not toxic to animal and plants or fish , Place in plastic bags or containers and close or
seal for disposal in accordance with local authority guidelines. Label as NON-HAZARDOUS insulation
wool or as general building waste (non-hazardous), as appropriate to assist local authorities waste
disposal sites, and local authorities will usually advise any local handling arrangements at their disposal
sites.
SECTION 14 — TRANSPORT INFORMATION
Transport Rockwool Insulation products are not classified as Dangerous Goods and have
Requirements: no special transport requirements.
HAZCHEM code: None allocated
Poisons Schedule: Not scheduled. No specific regulatory requirements are applicable regarding
occupational health and safety, consumer protection or environmental
protection measures.
www.saudirockwool.com
DOCUMENT NO.
METHOD STATEMENT CN-100-7001-MST
(Thermal Insulation and Cladding Works on
Piping and Equipment) PAGE 1 of 21 REV.B
SECL DOCUMENT NO.
APOC PDH/UTOS PROJECT
SC6677-CB0P-MTD-1007001
B 04-SEP-2022 Issue for Approval J.Y LEE (G.SI) J.H KIM S.J LEE
A 18-AUG-2022 Issue for Approval J.Y LEE (G.SI) J.H KIM S.J LEE
No part of this document or the information it contains may be reproduced or transmitted in any form or by any means electronic or mechanical, including
photocopying, recording, or by any information storage and retrieval system, without permission in writing from APOC and Samsung Engineering
DOCUMENT NO.
METHOD STATEMENT OF CN-100-7001-MST
THERMAL INSULATION AND PAGE 2 of 21 REV. B
CLADING WORKS ON PIPING
SECL DOCUMENT NO.
AND EQUIPMENT
SC6677-CB0P-MTD-1007001
SUBCON DOCUMENT NO.
APOC PDH/UTOS PROJECT
BFIM-SESA-INS-MS-01
A - First Issue
Add: "The materials shall be stored manufactured under recommended Temperature"
B 6.4
//Replacement of material after exposure to high temperature is the last step
All such gaps shall be refitted and not refilled - as per APOC specification - AES-S-
7.3.3. d
006- 25.1.5
7.3.3.m Mitered - Metered
7.8 Include: Vapor barrier mastic shall be applied in a minimum of two coats
7.13 Metal Joint Sealing - As the section describes the process & not the material to be used
9 the Topic is "Tools" any description to be laid out lower in the paragraph
No part of this document or the information it contains may be reproduced or transmitted in any form or by any means electronic or mechanical, including
photocopying, recording, or by any information storage and retrieval system, without permission in writing from APOC and Samsung Engineering
DOCUMENT NO.
METHOD STATEMENT OF CN-100-7001-MST
THERMAL INSULATION AND PAGE 3 of 21 REV. B
CLADING WORKS ON PIPING
SECL DOCUMENT NO.
AND EQUIPMENT
SC6677-CB0P-MTD-1007001
SUBCON DOCUMENT NO.
APOC PDH/UTOS PROJECT
BFIM-SESA-INS-MS-01
TABLE OF CONTENTS
PAGES
1.0 Purpose 4
2.0 Scope 4
3.0 References 4
4.0 Materials 4
5.0 Responsibility 5
9.0 Tools 18
12.0 Attachments 21
No part of this document or the information it contains may be reproduced or transmitted in any form or by any means electronic or mechanical, including
photocopying, recording, or by any information storage and retrieval system, without permission in writing from APOC and Samsung Engineering
DOCUMENT NO.
METHOD STATEMENT OF CN-100-7001-MST
THERMAL INSULATION AND PAGE 4 of 21 REV. B
CLADING WORKS ON PIPING
SECL DOCUMENT NO.
AND EQUIPMENT
SC6677-CB0P-MTD-1007001
SUBCON DOCUMENT NO.
APOC PDH/UTOS PROJECT
BFIM-SESA-INS-MS-01
1.0 PURPOSE
To describe the insulation materials, sequence, and method of application in Hot, Cold and
Acoustic insulation for piping and equipment.
2.0 SCOPE
This procedure covers the requirement of installation for all Hot, Cold and Acoustic
insulation being carried out by BINZAGR FACTORY FOR INSULATION MATERIALS
LTD.
3.0 REFERENCES
4.0 MATERIALS:
No part of this document or the information it contains may be reproduced or transmitted in any form or by any means electronic or mechanical, including
photocopying, recording, or by any information storage and retrieval system, without permission in writing from APOC and Samsung Engineering
DOCUMENT NO.
METHOD STATEMENT OF CN-100-7001-MST
THERMAL INSULATION AND PAGE 5 of 21 REV. B
CLADING WORKS ON PIPING
SECL DOCUMENT NO.
AND EQUIPMENT
SC6677-CB0P-MTD-1007001
SUBCON DOCUMENT NO.
APOC PDH/UTOS PROJECT
BFIM-SESA-INS-MS-01
5.0 RESPONSIBILITY:
5.1 Project Manager / Construction Manager are responsible for the
implementation of this procedure. He shall ensure that all engineers, supervisors,
foremen and craftsmen associated with this job will comply with this procedure
and shall ensure availability of required tools and equipment for the job described
in this procedure.
5.3 Safety Engineer / Supervisor / inspector will ensure safety regulations and
rules as required by the project.
5.4 Insulation Supervisor is responsible to provide his site team with appropriate
resources to ensure that works based on the approved procedures, Project
requirements and specification including safety compliance. Confirm the
availability of the materials, tools and required personnel who will carry out the
work.
6.1 Ensure that all material receiving has been approved and inspected prior to application.
6.2 Insulation material shall be transported and stored vertically with care and as per
manufacturer recommendation.
No part of this document or the information it contains may be reproduced or transmitted in any form or by any means electronic or mechanical, including
photocopying, recording, or by any information storage and retrieval system, without permission in writing from APOC and Samsung Engineering
DOCUMENT NO.
METHOD STATEMENT OF CN-100-7001-MST
THERMAL INSULATION AND PAGE 6 of 21 REV. B
CLADING WORKS ON PIPING
SECL DOCUMENT NO.
AND EQUIPMENT
SC6677-CB0P-MTD-1007001
SUBCON DOCUMENT NO.
APOC PDH/UTOS PROJECT
BFIM-SESA-INS-MS-01
6.3 From delivery up to site storage area, materials shall be at all times be protected from all
elements such as:
a. Flammable materials shall be stored safely away from probale ignition sources.
b. All materials shall be stored in a well ventilated area to avoid contamination from
humid air.
c. All materials shall be stored in a manner that prevents contamination by water,
process chemicals and even physical damage.
d. Materials stored shall be on pallets, covered with tarpaulin and have adequate
drainage.
B 6.4 Mastics, adhesives and sealers shall be stored properly and materials exposed to
temperatures beyond the manufacturers recommended temperature range during storage
must be removed and replaced. All should stored at cold container. The materials shall
be stored manufactured under recommended Temperature
6.5 Materials that exceed their shell life must be removed and replaced with new items.
a. Personnel protection safety equipment for safe handling of insulation and hazardous
b. Fire protection equipment
c. Hazardous materials disposal area (damage insulation, containers).
6.7 Material handling and storage instructions from manufacturers are available at site.
6.9 Materials package in cans or tubes shall be in original sealed containers. All insulation
and accessory materials shall be stored in area protected from the weather before and
during the application.
7.1 GENERAL
a. The piping shall have been tested and inspected as required by relevant specification
prior to installation of insulation.
c. All surfaces to be insulated shall be clean and dry. All loose scale and foreign matter
shall be removed from surfaces before applying insulation. Insulation shall not be
applied over wet surface.
d. All insulation materials shall be protected from rain and moisture and keep it dry.
No part of this document or the information it contains may be reproduced or transmitted in any form or by any means electronic or mechanical, including
photocopying, recording, or by any information storage and retrieval system, without permission in writing from APOC and Samsung Engineering
DOCUMENT NO.
METHOD STATEMENT OF CN-100-7001-MST
THERMAL INSULATION AND PAGE 7 of 21 REV. B
CLADING WORKS ON PIPING
SECL DOCUMENT NO.
AND EQUIPMENT
SC6677-CB0P-MTD-1007001
SUBCON DOCUMENT NO.
APOC PDH/UTOS PROJECT
BFIM-SESA-INS-MS-01
e. Insulation sections shall be trimmed as required to achieve close fit to avoid major
voids and gaps.
f. All joints of multi-layer insulation shall be staggered as possible.
g. SS Wire and Bands used to secure the insulation shall be installed straight and in
proper tension without crushing the insulation. Filament tape shall be used for
securing pipe insulation.
i. All external surfaces of insulation shall be weather jacketed to keep insulation dry
and provide mechanical protection to the system.
j. A minimum clearance of 50mm (2") shall be maintained between the outer surface
of insulation and any adjacent piping, equipment or structural member under all
temperature conditions of operation.
7.2.2 INSTALLATION
a. Insulation thickness having greater than 80mm shall be applied with
multilayer application.
c. When multiple layers are required, the staggered joint method shall be
used. The second layer shall be applied so that both the circumferential and
longitudinal joints are staggered. On multiple layer construction, each layer
shall be wired or banded separately.
No part of this document or the information it contains may be reproduced or transmitted in any form or by any means electronic or mechanical, including
photocopying, recording, or by any information storage and retrieval system, without permission in writing from APOC and Samsung Engineering
DOCUMENT NO.
METHOD STATEMENT OF CN-100-7001-MST
THERMAL INSULATION AND PAGE 8 of 21 REV. B
CLADING WORKS ON PIPING
SECL DOCUMENT NO.
AND EQUIPMENT
SC6677-CB0P-MTD-1007001
SUBCON DOCUMENT NO.
APOC PDH/UTOS PROJECT
BFIM-SESA-INS-MS-01
f. The ends of the upper and lower layers shall not be apart less than 100mm.
g. All joints shall be tight fitting. Any void or gap larger than 1/8" (3 mm)
shall be filled. Fill material shall be same as the insulation material used.
h. Insulation shall be installed in such a way that the gap between insulated
surface and insulation is less than 1/8" (3 mm) unless oversized insulation
is required to the accommodate heat tracer.
7.3.1 MATERIALS:
a. Polyisocyanurate with Density shall be minimum of 40 kg/m3 as per
ASTM C ASTM C591, type 2.
7.3.3 INSTALLATION
a. Insulation pieces shall be sized to ensure the space between the insulated
surface and the inner layer or joint gaps between insulation is approximately
less than 1/8”(3mm).
b. The joint sealer shall be applied to the face side and all edge surface single
layer of insulation and the outer layer only for multiple layer insulation. The
joint sealer shall be applied in a thickness sufficient to fill the joints.
c. Joints between the insulation pieces shall be “tight” over their entire length. To
reduce voids or gaps the installer shall pre-fit each insulation piece and trim as
required.
B d. When voids or gaps greater than 1/16” (3 mm) exist they shall not be filled. All
such gaps shall be refitted and not refilled
f. When a single layer insulation system is specified the staggered joint method
shall be utilized. Joints shall be staggered approximately 1/3” of the insulation
length.
No part of this document or the information it contains may be reproduced or transmitted in any form or by any means electronic or mechanical, including
photocopying, recording, or by any information storage and retrieval system, without permission in writing from APOC and Samsung Engineering
DOCUMENT NO.
METHOD STATEMENT OF CN-100-7001-MST
THERMAL INSULATION AND PAGE 9 of 21 REV. B
CLADING WORKS ON PIPING
SECL DOCUMENT NO.
AND EQUIPMENT
SC6677-CB0P-MTD-1007001
SUBCON DOCUMENT NO.
APOC PDH/UTOS PROJECT
BFIM-SESA-INS-MS-01
g. When a multiply layer insulation system is specified the staggered joint method
shall be utilized. The circumferential and longitudinal joints of the outer layer
shall be staggered vs the joints of the inner layer. Joints shall be staggered
approximately 1/3 of the insulation length.
h. If the insulated item is heat traced the insulation shall be “oversized” to the
nearest standard size which still accommodates the tracing.
l. All insulation pieces shall be securely held in place, a minimum of two bands is
required per full length insulation section.
B m. When metered sections or small insulation pieces are required each piece shall
be secured with a band. Bands shall be spaced evenly whenever possible and no
closer than 1”/25mm from the ends of an insulation piece.
B n. Metal parts such as equipment skirts and legs, pipe supports, saddles and
bracket, Insulated connections in piping and other miscellaneous attachments
which protrude through the insulation shall be insulated for approximately four
(4) times the insulation thickness from the outer surface of equipment or piping
or minimum of 305mm from the surface.
Insulation up to ≤ 12"
ROCK WOOL Insulation 12” to 42” OD Over 42” Insulation OD
OD
single/inner
16 gauge SS tie wire 13x0.5mm (1/2")SS band 19x0.5mm (3/4")SS band
layer
outer layer 16 gauge SS tie wire 13x0.5mm (1/2")SS band 19x0.5mm (3/4")SS band
No part of this document or the information it contains may be reproduced or transmitted in any form or by any means electronic or mechanical, including
photocopying, recording, or by any information storage and retrieval system, without permission in writing from APOC and Samsung Engineering
DOCUMENT NO.
METHOD STATEMENT OF CN-100-7001-MST
THERMAL INSULATION AND PAGE 10 of 21 REV. B
CLADING WORKS ON PIPING
SECL DOCUMENT NO.
AND EQUIPMENT
SC6677-CB0P-MTD-1007001
SUBCON DOCUMENT NO.
APOC PDH/UTOS PROJECT
BFIM-SESA-INS-MS-01
Insulation up to ≤ 12"
PIR Insulation 12” to 42” OD Over 42” Insulation OD
OD
single/inner Filament 13x0.5mm(1/2”)SS band
19x0.5mm (3/4")SS band
layer Tape / Filament Tape
13x0.5mm(1/2”) ss
outer layer 13x0.5mm(1/2”)SS band 19x0.5mm (3/4")SS band
band
spacing 300mm ( 12") 300mm (12") 300mm (12")
d. All voids found at joints on both directions shall fill with the same material as
the insulation.
a. Flat block curve segments or small slab of PIR shall be applied for the
equipment or tank. Insulation section shall be fabricated in accordance to the
manufacturer and tightly butted to eliminate voids, gaps or open joints. The
insulation shall be refitted to achieve the tight fit. Insulation shall fit the
curvature of the surface to be insulated.
b. Each Insulation segment should be fitted to the surface or item to be insulated
and adjacent segments so that the joints form a tight barrier.
c. Joints of insulation shall be staggered as far as possible.
d. Temporary bands shall be utilized when pre-fitting the insulation pieces and
ensure the insulation pieces are tightly butted together prior to installing the
permanent bands.
a. Insulating cover at body of equipment and tank shall be secured and fastened
in place using SS bands for a close fit to surface.
b. Heads of horizontal and head of vertical equipment a floating ring made of
6mm diameter rod (SS rod for SS equipment and CS rod for CS equipment)
shall be placed at the center where bands shall be hooked to hold the
insulation in place.
No part of this document or the information it contains may be reproduced or transmitted in any form or by any means electronic or mechanical, including
photocopying, recording, or by any information storage and retrieval system, without permission in writing from APOC and Samsung Engineering
DOCUMENT NO.
METHOD STATEMENT OF CN-100-7001-MST
THERMAL INSULATION AND PAGE 12 of 21 REV. B
CLADING WORKS ON PIPING
SECL DOCUMENT NO.
AND EQUIPMENT
SC6677-CB0P-MTD-1007001
SUBCON DOCUMENT NO.
APOC PDH/UTOS PROJECT
BFIM-SESA-INS-MS-01
c. Man ways, nozzle, vessel clips or other attachment may interfere with the
band spacing. As an option a ring may be fabricated by inter weaving strands
of stainless-steel wire. 2 strand rings shall be used to support 6 or less bands
and 3 or more strand is required when multiply bands are necessary.
No part of this document or the information it contains may be reproduced or transmitted in any form or by any means electronic or mechanical, including
photocopying, recording, or by any information storage and retrieval system, without permission in writing from APOC and Samsung Engineering
DOCUMENT NO.
METHOD STATEMENT OF CN-100-7001-MST
THERMAL INSULATION AND PAGE 13 of 21 REV. B
CLADING WORKS ON PIPING
SECL DOCUMENT NO.
AND EQUIPMENT
SC6677-CB0P-MTD-1007001
SUBCON DOCUMENT NO.
APOC PDH/UTOS PROJECT
BFIM-SESA-INS-MS-01
a. The expansion joint shall be used for rigid insulation on the piping and equipment.
b. Each expansion/contraction joint shall be filled up with fiber glass wool insulation
material for compression and or extension.
c. In the case of vertical piping and equipment with support ring / stiffener ring a
expansion and contraction joint shall be provided under each ring.
WEATHER JACKETING
7.8.1 Metal Jacketing Thickness
No part of this document or the information it contains may be reproduced or transmitted in any form or by any means electronic or mechanical, including
photocopying, recording, or by any information storage and retrieval system, without permission in writing from APOC and Samsung Engineering
DOCUMENT NO.
METHOD STATEMENT OF CN-100-7001-MST
THERMAL INSULATION AND PAGE 14 of 21 REV. B
CLADING WORKS ON PIPING
SECL DOCUMENT NO.
AND EQUIPMENT
SC6677-CB0P-MTD-1007001
SUBCON DOCUMENT NO.
APOC PDH/UTOS PROJECT
BFIM-SESA-INS-MS-01
a. Jackets shall be secured with screws and/or bands. (Screw shall not be
used in cold insulation
b. All bands, seals, screw clips, rivet and springs shall be type 304/302
stainless steel
d. On cold pipe / vessel and tracing line shall be secured with bands on
maximum of 300 mm on center and rivet as required.
f. If Insulation diameter > 42” Ø), 19.0 x 0.5mm ss band type 304
Securement shall be used space at 300 mm OC.
i. Top head of the cold vessels and tanks shall be secured with ss type 304
rivets and where the head remains the rivet to avoid water entrance.
j. On vertical pipe, tanks, vessel, and equipment S clip shall be placed on the
perimeter of each sheet with minimum two clips and J-clips shall be used
for the bands.
No part of this document or the information it contains may be reproduced or transmitted in any form or by any means electronic or mechanical, including
photocopying, recording, or by any information storage and retrieval system, without permission in writing from APOC and Samsung Engineering
DOCUMENT NO.
METHOD STATEMENT OF CN-100-7001-MST
THERMAL INSULATION AND PAGE 15 of 21 REV. B
CLADING WORKS ON PIPING
SECL DOCUMENT NO.
AND EQUIPMENT
SC6677-CB0P-MTD-1007001
SUBCON DOCUMENT NO.
APOC PDH/UTOS PROJECT
BFIM-SESA-INS-MS-01
a. Elbows cover for 3” Ø and below, 90º & 45 º elbows shall be pre-fabricated in
a maximum of two precision formed sections. Pipe elbows 4” diameter and
over shall be mitered type.
b. Insulation shall be cut into sections sufficiently to form a close fit with the
bend.
a. All flanges on the equipment body shall be covered with rock wool or else
otherwise specified by the client and flat aluminum sheet/SS Sheet as metal
jacketing.
b. Valve covers shall be flange-shaped casing line with line with the insulation.
d. The clearance between the flanges and insulation covers shall be long
enough to facilitate the removal of bolts in all direction prior to any repair.
e. Bolt clearance may vary from bolt length plus 1” inch on both sides from the
face of the flange.
a. Cut joints in weather jacket shall be caulked with sealant to prevent entry of
water.
b. Seal longitudinal joints of vertical pipe, and circumferential joints of
horizontal pipe.
No part of this document or the information it contains may be reproduced or transmitted in any form or by any means electronic or mechanical, including
photocopying, recording, or by any information storage and retrieval system, without permission in writing from APOC and Samsung Engineering
DOCUMENT NO.
METHOD STATEMENT OF CN-100-7001-MST
THERMAL INSULATION AND PAGE 16 of 21 REV. B
CLADING WORKS ON PIPING
SECL DOCUMENT NO.
AND EQUIPMENT
SC6677-CB0P-MTD-1007001
SUBCON DOCUMENT NO.
APOC PDH/UTOS PROJECT
BFIM-SESA-INS-MS-01
c. Metal joint sealant shall be applied on all cut joints of removable covers to
prevent entry of water.
No part of this document or the information it contains may be reproduced or transmitted in any form or by any means electronic or mechanical, including
photocopying, recording, or by any information storage and retrieval system, without permission in writing from APOC and Samsung Engineering
DOCUMENT NO.
METHOD STATEMENT OF CN-100-7001-MST
THERMAL INSULATION AND PAGE 17 of 21 REV. B
CLADING WORKS ON PIPING
SECL DOCUMENT NO.
AND EQUIPMENT
SC6677-CB0P-MTD-1007001
SUBCON DOCUMENT NO.
APOC PDH/UTOS PROJECT
BFIM-SESA-INS-MS-01
8.3 Materials
a. Absorptive Layer
i. Sound absorbing material shall be fibrous glass 96-128 kg/m3 (6-8
lb/ft3)
b. Sound barrier material shall be lead sheet with a minimum mass of 5kg/m2
i. Vinyl Sheet
No part of this document or the information it contains may be reproduced or transmitted in any form or by any means electronic or mechanical, including
photocopying, recording, or by any information storage and retrieval system, without permission in writing from APOC and Samsung Engineering
DOCUMENT NO.
METHOD STATEMENT OF CN-100-7001-MST
THERMAL INSULATION AND PAGE 18 of 21 REV. B
CLADING WORKS ON PIPING
SECL DOCUMENT NO.
AND EQUIPMENT
SC6677-CB0P-MTD-1007001
SUBCON DOCUMENT NO.
APOC PDH/UTOS PROJECT
BFIM-SESA-INS-MS-01
B 9.0 TOOLS
a. These are the following to be used while performing the insulation and metal
jacketing activity.
b. Ensure that all the tools are inspected prior to use.
c. Any damage tools shall not be used.
9.1 Tools to be use for mineral wool, PIR and Cellular Glass insulation
a. Wool Cutter
b. Wire Cutter
c. Hand Saw
d. Scrapper
e. Masonry Trowel
f. Measuring tape
g. Band Tighter
No part of this document or the information it contains may be reproduced or transmitted in any form or by any means electronic or mechanical, including
photocopying, recording, or by any information storage and retrieval system, without permission in writing from APOC and Samsung Engineering
DOCUMENT NO.
METHOD STATEMENT OF CN-100-7001-MST
THERMAL INSULATION AND PAGE 19 of 21 REV. B
CLADING WORKS ON PIPING
SECL DOCUMENT NO.
AND EQUIPMENT
SC6677-CB0P-MTD-1007001
SUBCON DOCUMENT NO.
APOC PDH/UTOS PROJECT
BFIM-SESA-INS-MS-01
Note: Personnel carrying out the application of insulation shall be wearing Kevlar or similar suitable
hand gloves, including other required PPE’s. If any cutter shall be used for Mineral wool, PIR, and
CG.
Note: Any protrusion sharp edges will be bent and rendered safe to avoid injury and personnel
carrying out the application of cladding shall be wearing Kevlar or similar suitable hand gloves,
including other required PPE’s.
i. The delegated responsibilities of the several sections of the works and all
procedure, method statements and inspection test plan (ITP).
ii. The method statement shall be described, the execution plan, materials, trade
and quality procedure.
iii. In the ITP, all the test procedures shall be described such as the number of
samples, hold/witness points, test frequencies, acceptance/rejection criteria
etc. of all the application insulation system.
iv. Inspection shall be carried out prior, during and after completion of any stage
of the work, beginning with the material checks and ending with final
performance checks.
v. The quality plan shall be clearly indicated and in which stages material test
reports shall be available and how it is documented.
No part of this document or the information it contains may be reproduced or transmitted in any form or by any means electronic or mechanical, including
photocopying, recording, or by any information storage and retrieval system, without permission in writing from APOC and Samsung Engineering
DOCUMENT NO.
METHOD STATEMENT OF CN-100-7001-MST
THERMAL INSULATION AND PAGE 20 of 21 REV. B
CLADING WORKS ON PIPING
SECL DOCUMENT NO.
AND EQUIPMENT
SC6677-CB0P-MTD-1007001
SUBCON DOCUMENT NO.
APOC PDH/UTOS PROJECT
BFIM-SESA-INS-MS-01
a. Inspection of materials
i. All materials shall be complying with the minimum requirements and approved
by the client.
ii. All materials shall be inspected at the workshop and upon arrival on site.
iii. Prior to commencement of the work, data sheet, safety data sheet and method
statement of the various materials shall be submitted together with test
certificate.
i. Prior to release for insulation, ensure that the following that had been check as
required.
ii. The relevant documents are signed from all required parties.
iii. Verify Surface to be insulated is dry, clean and free from dust, dirt etc.
iv. QC Inspector shall coordinate with the other inspector to conduct inspection as
required.
v. Stages of Inspection and verification, characteristics to be checked, acceptance
criteria and inspection / verification authority for hot/cold insulation shall be as
per Inspection and Test Plan for Thermal Insulation.
i. Make sufficient check to verify that the materials being applied are the same as
the specified or approved materials.
ii. Verify the insulated items, insulation code, thickness and weathering.
iii. Verify that the insulation surface is uniform without gaps and voids.
iv. Inspect tightness of joints and fasteners
v. Inspect the location of bands.
vi. Verify that the insulation segments are properly staggered.
i. Verify that the insulation is completely dry and free from gaps.
ii. Inspect for proper overlap of metal flashing
iii. Verify the application of sealant at the circumferential overlap of metal jacketing
on horizontal pipe.
iv. Verify the location of bands, screw, s-clips and j-clips are specified.
v. Ensure that the moisture protection and weatherproofing at cut outs, protrusions
and locations where possible entry of moisture are properly applied.
11.1 Approved Work Permit shall be obtained prior to start any Insulation Works.
No part of this document or the information it contains may be reproduced or transmitted in any form or by any means electronic or mechanical, including
photocopying, recording, or by any information storage and retrieval system, without permission in writing from APOC and Samsung Engineering
DOCUMENT NO.
METHOD STATEMENT OF CN-100-7001-MST
THERMAL INSULATION AND PAGE 21 of 21 REV. B
CLADING WORKS ON PIPING
SECL DOCUMENT NO.
AND EQUIPMENT
SC6677-CB0P-MTD-1007001
SUBCON DOCUMENT NO.
APOC PDH/UTOS PROJECT
BFIM-SESA-INS-MS-01
11.2 The insulation supervisor with the assistance of the safety department will
carry-out a safety risk assessment identifying the actual hazard and possible
precaution to be taken to eliminate or lessen the risk prior to start of any
activities.
11.4 Workers shall always wear their Personnel Protective Equipment (PPE’s)
required for the work.
11.5 Certified Permit Receiver, in case of any confined space work a hole watcher
trained by CONTRACTOR Training Department and Work in-charge should
be at worksite during the execution of the work.
11.6 Tools to be secured with a restrainer string at open areas during working time
to prevent possibility of injury due to falling objects.
11.9 The scrap of the cellular Glass/PIR/Mineral Wool materials will be keep in a
trash bag and sending to BFIM temporary facility area and place it in waste
container to be collected by waste disposal company as per Environmental
Company.
12.0 ATTACHEMENTS
12.1 Attachment 1 – Job Safety Analysis
No part of this document or the information it contains may be reproduced or transmitted in any form or by any means electronic or mechanical, including
photocopying, recording, or by any information storage and retrieval system, without permission in writing from APOC and Samsung Engineering
1.2.1. Involved personnel must attend Safety Induction and
necessary trainings
1.2.2. TBT meeting to be conducted by concerned supervisor and EHSS Supervisor
discuss the hazards which can expect while performing the Site supervisor/ EHSS
1.2. Untrained personnel
work, its reduction method and Preventive action to be known Officer
to each employee. PTW Receiver
1.2.3. Only trained and authorized personnel are allowed to perform
the work.
4.5.1. Check Dead man’s switch of power tools and ensure that it
is functioning properly; electrical tools shall stop running
when finger is released from the trigger.
4.5.2. All power tools to be used are connected to electrical panel
Site supervisor/ EHSS
4.5. Electrical shock board that area provided with RCCB/ELCB.
Officer
4.5.3. Panels and electrical tools/equipment must be checked as
per the checklist
4.5.4. Ensure that proper hand gloves are provided and worn.
E.g., Rubber coated gloves and/or leather gloves
4.6.1. Provide barricade and signage in the working area Site supervisor/ EHSS
4.6. Unauthorized personnel entry
4.6.2. Constant supervision shall be ensured and in place. Officer
8.1.1. Remove all the debris from work area on a daily basis
8.1.2. Stack the materials properly, provide access in between
8.1. Slip trip and fall. stacked materials. Site supervisor/Foreman
8.1.3. Ensure good housekeeping conducted before, during and
8 Post cleaning of work area prior to leaving the area
8.1.4. Ensure materials are lowered to the ground prior to leaving
the work area. Supervisor/ EHSS
8.2 Fall from heights, falling object
8.1.5. Adhere to proper and safe manual handling/lifting Personnel
technique.
8.1.6. Use correct tools and equipment when lowering materials
such as manila rope 18 mm min., duffle bag, canvas bag
with SWL and pulley.
8.1.7. Manual lifting area to be barricaded and provided with
appropriate signs
8.1.8. Ensure all personnel involved in elevated areas are
provided and wearing full body harness and maintaining
100% tie-off.
Personal Protective Equipment (PPE):- Safety Helmet, Safety Shoes, Safety Glass, Visible Safety Vest, gloves and Face Mask.
NOTE: Ensure all safety requirements in this JSA are met and provided. If there are emergency hazards identified as per site condition, stop and re-assess work activity and provide mitigating
measures. Conduct 360° assessment of the work area prior to start of activity. Share and discuss JSA with work crew.
Date:
APOC PDH/UTOS PROJECT
Illumination Plan September 20, 2022
1.0 Title
Illumination Plan
2.0 Purpose
3.0 Requirements
Each facility-Lighting shall be designed for safe and efficient operation and
maintenance of the site (project).
Feeder shall originate in a distribution center. The conductors shall be run as multi
conductor cord or cable assemblies or where not subject to physical damage, they
may be run as open conductors or insulators no less than 3.3 m (10.8 ft ) apart.
Branch circuits shall originate in a power outlet or panel board. Conductors shall be
run as Multi conductor cord or cable assemblies or open conductors, or shall be
run in raceways.
All conductors shall be protected by over current devices at their capacity. Runs of
open Conductors shall be located where the conductors will not be subject to
physical damage
Date:
APOC PDH/UTOS PROJECT
Illumination Plan September 20, 2022
And the conductors shall be fastened at intervals not exceeding 3.3 m (10.8 ft). No
branch Circuit conductors shall be laid on the floor. Each branch circuit that supplies
receptacles or fixed equipment shall contain a separate equipment grounding
conductor if the branch Circuit is run as open conductors.
PARTICULARS SPECIFICATIONS