ENGINEERS PVT. LTD.
410‐411 Notus IT Park,
Plot D, Sarabhai Campus,
Near Genda Circle,
Vadodara ‐ 3900023
CLIENT : GNFC BHARUCH
CONTRACTOR : SUVIDHA ENGINEERS
________________________________________________________________________________________________
Date: 13‐12‐2022
FEASIBILITY REPORT
To,
Chief Executive Engineer
Mr. K K Bhatt
Dear Sir,
Kindly find our feasibility report for below mentioned subject matter as under.
Subject: ‐ Execution feasibility for replacement of RCC supports of existing switchyard equipment’s with
new structural supports.
Existing RCC support structure to be dismantled and new lattice structure to be installed along with there
respective civil work, kindly refer below feasible options.
OPTION: 1
New foundation to be casted adjoining existing foundation with around 600mm to 750mm distance from
existing column center, refer following sketch.
Coloured is the new foundation and column; grey is existing foundation and columns.
With this option, more or less identical foundation and structure work can be done.
Herein following shall be the steps for execution:
Shutting down electrical supply and uninstall the electrical equipment’s.
Excavate for foundation work.
1|Page
PCC work.
Surface preparation for joining of new and old foundations.
Rebaring in existing foundation.
Concreting of new foundation and pedestals.
Installation of structure.
Installation of equipment’s.
Con’s:
No power supply can be done until entire execution is completed in any phase.
Equipment location will change and re‐alignment on new axis with respect to new foundation shifting
FEASIBILITY REPORT
direction will take place.
Removed equipment will remain aside till foundation work, structure work and re‐installation will
require separate care.
Air clearance with adjacent bya/equipment may temporarily compromised, though in acceptable
range.
More time consuming.
More earthwork involved.
OPTION: 2
New foundation to be casted in between existing foundation, refer following sketch.
Coloured is the new foundation and column; grey is existing foundation and columns.
Herein following shall be the steps for execution:
Excavate for foundation work.
PCC work.
Concreting of new foundation and pedestals.
Installation of structure upto equipment bottom.
Shutting down power supply.
Installation of equipment’s.
With this option, foundation and structure work will be designed separately considering standard
SWYD practices and requirements.
Pro’s:
Power supply curtailed for minimum duration. Bay side or segment wise work is possible.
Less time consuming.
Less earthwork involved.
Equipment will be located on same location with same alignment axis. No issues with respect to air
clearance with other bay/equipment.
2|Page
Equipment shall be taken off from location for short period. No major issues with respect to
preservation etc.
Open space within switchyard will marginally increase and hence the visibility across switchyard also
increases.
FEASIBILITY REPORT
Option:1 Single equipment single structure
Option:2 3 equipment’s single structure