Section SWIFT
Reservoir Souring Control Action Item Reviewed by KPT/LBH/MAS/IIM
Date Aug17-21
Approved by ARY
Revision Rev.4
Subsection No. Area Action Items Deliverables Assigned To:Support From Estimated StartEstimated Finish % Completion
• H2S wells list with well test data (Prod/WC/Total Gas/Prod Choke/ GL Rate/H2S Conc./FTHP) 1) Background:
Aug17-21 Aug20-21
• Reservoir souring limit with a treatable amounts of H2S • Root Cause (Continuous Non-compliance)
Produced Water
Subsurface
Aug23-21 Aug27-21
• Existing H2S removal facilities • Impact: Production Deferment
1 SAM KUEH
Aug30-21 Sep03-21
• Loss in Production: XX BOPD; Potential LIP • Production restoration (Protect the reservoir)
• #2.Pragmatic Surveillance; #3. WIM; 4#. PIM; 5#. Effective of FM Sep06-21 Sep10-21
Aug23-21 Aug27-21
• Well Completion Diagram • Improvement strategy in place
3 LBH COB TEAM
Aug30-21 Sep03-21
• CDFT & Annulus Pressure Report • Potential Chemical Treatment for H2S in the Producing well (Protect well tub
Surface