Lecture 9
- The formwork slip upwards by hydraulic jacks at a rate between 15 cm - 30 cm per hour.
- This rate is determined according to the cement used in the concrete.
- Fast curing cement differs from other types and also the curing method used, so it is
necessary to know the initial curing time of the concrete or the degree of solidification
that allows the concrete to maintain its formation with high accuracy, otherwise the
concrete will fall when slipping up.
Use of the vertical slip formwork:
Advantages :
Disadvantages :
Slides 19-21 .. projects by vertical slip form system.