P055bzor 0051 Q 236 - G
P055bzor 0051 Q 236 - G
This document has not been published and is the sole property of KIPIC and is lent to the borrower for its confidential use only and in consideration of the loan of
this document, the borrower promises and agrees to return it upon request and agrees that it shall not be reproduced, copied, lent or otherwise disposed of
directly or indirectly, nor used for any purpose other than that for which it was furnished
KIPIC
Date Revision Description Made Checked Approved
Rev
[1,2,3
[dd-mmm-yy] ISSUED FOR APPROVAL
….]
Revision
Project Number Supplier Document Number
number
[XXXXXXXXXXXXXXXXXXXXXX] [XX]
Revision
P055BZOR FDH JV Document Number
number
(L9ZR-X-XXXX-XX-XXX-XXXXX] [1,2,3….]
Revision
PO Number KIPIC Document number
number
[L9ZR-X-XXXX-XX-XXX]
Page 1 of 4
KIPIC ZOR Project
Supplier LOGO Inspection and Test Plan
Steel Structure Erection (Vendor)
P055BZOR-0051-Q-236
Rev.: G, 30-Nov-19
PROJECT CONTRACT NO.: [L9ZR-X-XXXX-XX-XXX] INSPECTION AND TEST PLAN DOC. No.: [XXXXXXXXXXXXXXXXXXXXXX]
DESCRIPTION: [CONTRACT DESCRIPTION] STEEL STRUCTURE ERECTION (VENDOR) REV.: [XX] DATE: [dd-mmm-yy]
1.0 GENERAL
Verify and Ensure latest revisions of IFC
1.1 drawings, Specification etc. are being IFC Drawing Drawing Register H R R
utilized.
Verify testing equipment, Operating manuals
and Calibration Certificate(s),
Manufacturer procedure
1.2 Calibration certifications are currently Operating Manuals, H R R
P055BZOR-0051-Q-015
available P055BZOR-0051-Q-864
Conduct a pre-construction quality control
1.3 Attachment E Sec. 5.4 Minutes of Meeting I H W
meeting
3.0 ERECTION
3.1.4 Bolt Tightening Inspection (Snug-Tightened DEP 34.28.00.31-Gen, PIP STS05130, P055BZOR-0051-Q-455 I W S
Page 2 of 4
KIPIC ZOR Project
Supplier LOGO Inspection and Test Plan
Steel Structure Erection (Vendor)
P055BZOR-0051-Q-236
Rev.: G, 30-Nov-19
PROJECT CONTRACT NO.: [L9ZR-X-XXXX-XX-XXX] INSPECTION AND TEST PLAN DOC. No.: [XXXXXXXXXXXXXXXXXXXXXX]
DESCRIPTION: [CONTRACT DESCRIPTION] STEEL STRUCTURE ERECTION (VENDOR) REV.: [XX] DATE: [dd-mmm-yy]
Page 3 of 4
KIPIC ZOR Project
Supplier LOGO Inspection and Test Plan
Steel Structure Erection (Vendor)
P055BZOR-0051-Q-236
Rev.: G, 30-Nov-19
PROJECT CONTRACT NO.: [L9ZR-X-XXXX-XX-XXX] INSPECTION AND TEST PLAN DOC. No.: [XXXXXXXXXXXXXXXXXXXXXX]
DESCRIPTION: [CONTRACT DESCRIPTION] STEEL STRUCTURE ERECTION (VENDOR) REV.: [XX] DATE: [dd-mmm-yy]
Hold Point: Indicates an inspection or test which is considered vital to the quality, integrity and safe functioning of the material or services and which can only be achieved at this point. It is an Inspection/Test
Activity on the ITP that requires the presence of the Contractor Representative. The Production/Erection process cannot proceed beyond this point until it has been cleared by the Contractor Representative
Witness Point: Indicates an Inspection/Test Activity on the ITP that requires a request for the presence of the Contractor Representative
Review Point: Review of a document to verify accuracy, completeness, and legibility
Inspect Point: Physical inspection or check of an activity
Surveillance: An activity subject to surveillance monitoring. This typically involves monitoring an activity on a random basis - but the frequency may increase if necessary
List of QVD’s:
Page 4 of 4