You are on page 1of 48

DELTA TAB

Company Profile 2022


Air and Hydronic Testing, Adjusting and Balancing
services

DELTA
TAB
DELTA
TAB

DELTA
TAB

DELTA TAB
‫ﺷﺮﻛﺔ دﻟﺘﺎ ﻟﻠﻀﺒﻂ و اﻟﻤﻮازﻧﺔ‬

DELTA is a promising company in the field of testing, adjusting and balancing for the
central air conditioning systems (HVAC Systems)
Our professional team employs a systematic approach to ensure the highest standards
of design and construction, whilst implementing value engineering and excellent
management to provide the best customer satisfaction through a professional
innovative approach
OUR MOTTO IS ACCURACY AND COMMITMENT

03
VISION
DELTA has the commitment through technology and education to become the leading
Testing & Balancing and Commissioning firms in the industry and will continue to grow
and adapt to the industry's ever changing needs and demands. We focuses on
Attracting, developing and retaining high caliber staff, Utilizing most up-to-date
measuring techniques and Instrumentation and Sustaining and expanding our profile
and markets

04
DELTA
TAB

MISSION
DELTA aspire to serve public and private sectors to the absolute pinnacle of our ability
and enrich the industry. This cannot be done without state of the art technology used by
extensively trained individuals and a proactive approach to enhance our operations
quality and standards
Our key measure of success is Client satisfaction

What’s Our
BUSINESS SERVICE

DELTA offers a wide range of TAB services. These include:

Reviewing project shop drawings

HVAC Equipment Performance for (AHUs, FCUs,


Fans, Pumps, Chillers, Cooling towers, etc….)

Air and Water flow measurement for both


equipments and terminals

Balance of Air side and Water side of the


equipment

Indoor air temperature and relative humidity


measuring

HVAC systems problem analysis and


recommendations

Perform full technical TAB Report

05
Used for: measuring air volume flowing through

Used for: measuring water flow rates for both


heating and cooling water systems

INSTRUMENTATION

We have modern combination of air measurment and water measurement instruments


that are calibrated annually to keep their measurements always accurate without
significant error being noted on the device

Used for: measuring air velocity, calculates flow

06
DELTA
TAB

AIR CAPTURE HOOD


Used for: measuring air volume flowing through
registers, diffusers and grilles

HYDRONIC MANOMETER
Used for: measuring water flow rates for both
heating and cooling water systems

ROTATING VANE ANEMOMETER


Used for: measuring air velocity, calculates flow
rate, performs averaging, and can determine
minimum and maximum readings

07
TACHOMETER
Used for: Measuring rpm for rotational equipment Used for: Measuring sound pressure level in dB and

PITOT TUBE
Used for: Measuring static pressure with duct Used for: Measuring vibration for HVAC Equipment
traverse

FLUKE CLAMP METER


Used for: Measuring amperage and voltage Used for: Measuring water flow rates and pressure

08
DELTA
TAB

SOUND LEVEL METER


Used for: Measuring sound pressure level in dB and
NC

VIBRATION ANALYZER
Used for: Measuring vibration for HVAC Equipment

COMDRONIC FLOW METER


Used for: Measuring water flow rates and pressure

09
ORGANIZATIONAL STRUCTURE

ACOUNTANT
Khaled Eisa

TECHNICIAN
Karam Foad

ENGINEER
Mahmoud Saad TECHNICIAN
Mohammed Ashraf

MANAGER
Abdelrahman Fahmy

TECHNICIAN
ENGINEER Emara Mohammed

Mohammed Naser

TECHNICIAN
Mostafa Abdo

DELTA LAWYER
Ahmed Farag

TAB
A b d - E l r a h m a n
F a h m y
T E S T I N G , A DJ U S T I N G A N D B A L A N C I N G E N G I N E E R

ABOUT ME EXPERIENCES
GENERAL MANAGER DELTA TAB COMPANY
▶ Date of Birth: Dec 1984 2021 - PRESENT here is a sample of projects that carried out:
• Masjid 2000 - Elkayan Elaskry
▶ Place of Birth: Cairo • Ophthalmology Hospital
• Soap Factory - Industrial District
▶ Nationality: Egyptian • EDEN Healthcare Hospital - 6th of October

▶ Marital Status: Married


OPERATIONS MANAGER EBC-INTERNATIONAL COMPANY
2016 - 2020 here is a sample of projects that carried out:
▶ Military Status: Completed
• Alexandria Airport
• Point 90 Mall
• Almostasmereen GIS Substation
• QNB Bank-10th of Ramadan
• El-katamya Airport
• Cancer Center Hospital
• Suez University Theater
• Aramex new office
CONTACT • Maxim Mall
• Hanger 7000

Address: OPERATIONS MANAGER THE ENGINEERING TAB SERVICES COMPANY (QATAR)


9 Ebrahim Kotb, El _ Meholate,
2015 - 2015 here is a sample of projects that carried out:
El_Matbaa – El_ Harame street,
• Administration Building – AL Rayyan
Giza, Egypt • AL Layali Restaurant
• Lagoona mall
Mobile: • The Pearl area
010 29999552 • The Gate Mall
• Cocacola Factory

Email:
• Equipment & Planet

delta.tab@yahoo.com
• MIC Building

Projects Manager EGY-TAB COMPANY


here is a sample of projects that carried out:
2009 - 2014
• Hurghada International Airport
SKILLS • Edita New Premises Factory
• Extension Of Wadi El Neel General Hospital
• Mall Of Arab Multiplex Cinemas
PROJECT MANAGEMENT • Chipsy Factory 6th October City
• Repositioning Of 27 Military Factory
AUTOCAD • Alazhar Univeristy Hospital
• Imax 3d Theater 6th Octoper City
REVIT • Le Meridien Pyramids Hotel

MICROSOFT OFFICE
• American University in Cairo

DRIVING LICENSE

EDUCATION

HELWAN UNIVERSITY FACULTY OF ENGINEERING


2004 - 2009 Bachelor of Mechanics Power Engineering
M a h m o u d
S a a d
T E S T I N G , A DJ U S T I N G A N D B A L A N C I N G E N G I N E E R

ABOUT ME EXPERIENCES

▶ Date of Birth: Jan 1987


OPERATIONS MANAGER DELTA TAB COMPANY

▶ Place of Birth: Cairo 2021 - PRESENT here is a sample of projects that carried out:
• Masjid 2000 - Elkayan Elaskry
▶ Nationality: Egyptian • Ophthalmology Hospital
• Soap Factory - Industrial District
▶ Marital Status: Single • EDEN Healthcare Hospital - 6th of October

▶ Military Status: Completed

TAB ENGINEER EGY-TAB COMPANY

2011 - 2019 here is a sample of projects that carried out:


• Extension of Wadi El Nile Hospital
• Al Azhar University Hospital
• Hilton Marsa Alam Resort
• Old Palace Resort - Sahl Hasheesh
CONTACT • Relocating 27 Military Factory - Abu Zaabl
• P&G Factory Extension - 6 October
• Marsa Matrouh International Airport
Address: • Cairo East Air Base
Building 220, 7th District, 3rd Settlement, • National Research Center
New Cairo, Egypt • Koom Oshim Air Base - Fayoom

SITE ENGINEER ALMOHNDS CONTRACTING COMPANY


Mobile:
010 62743201 2009 - 2011 I was working as a mechanical site engineer in HVAC
011 15101198 and plumbing works
PROJECT: Extension of Wadi Elneel Hospital
Email:
delta.tab@yahoo.com
EDUCATION

AIN SHAMS UNIVERSITY FACULTY OF ENGINEERING


SKILLS
2004 - 2009 Bachelor of Mechanics Power Engineering

PROJECT MANAGEMENT

AUTOCAD

REVIT MEP

MICROSOFT OFFICE

DRIVING LICENSE
Tel: 010 62743201
E-Mail: delta.ta@yahoo.com
AIR HANDLING UNITS (AHU)

A. AHU and Air Distribution System Checks:


1. AHU & Air Distribution System Installation should be completed as per project
documents.
2. All balancing devices (V.D) are properly placed and fully opened.
3. Air filters should be Clean and properly placed.
4. Control system installations completed and operate properly.
5. AHU Start-up completed and operates properly before TAB work.
6. Served area construction should be completed(doors, Window, etc...).
7. All related Supply and or Exhaust air systems should be operating .(if applicable)
8. Deficiencies should be reported for rectification.
9. Proceed TAB work after System deficiencies rectification.

B. AHU performance test procedures:


1. Verify all AHU-Air Distribution System Checks.
2. Measure Fan Speed & Motor Speed, Voltage and Ampere (Motor not overloaded).
3. Adjust O.A, R.A & S.A dampers for the proper position as required per design values.
4. Measure Fan Total and external static pressure.
5. locate the proper point for duct traverse section after a straight length of duct for total fan
air flow.
6. Fan total air flow should be ±10% of design, if fan total air flow less or more than the
acceptable limits, adjust the fan speed to achieve the required design air flow.
7. Deficiencies should be reported for rectification.
8. Proceed TAB work after System deficiencies rectification.

C. AHU Air Distribution System Balance:


1. Verify fan adjustment to the required total system air flow.
2. Perform testing, adjusting and balancing(TAB) for air distribution system terminals as
per NEBB TAB Procedures to values within ±10% of design.
3. After completion of balancing air terminals, record the final readings as per required data
for TAB test forms for both air terminals and AHU.
4. Deficiencies should be reported for rectification.
5. Proceed TAB work after System deficiencies rectification.

D. Completion of TAB Report:


1. Recorded final readings and data obtained from Project documents, name plate and filed
installation should be as per required data for TAB test forms for both air terminals and
AHU.
2. Report should include all remained System deficiencies.(if applicable).

Tel: 010 62743201


E-Mail: delta.tab@yahoo.com
FAN COIL UNIT (FCU)

A. FCU and Air Distribution System Checks:


1. FCU & Air Distribution System Installation should be completed as per project
documents.
2. All balancing devices (V.D) are properly placed and fully opened.
3. Air filters should be Clean and properly placed.
4. Control system installations completed and operate properly (FCU operating at rated
speed).
5. FCU Start-up completed and operates properly before TAB work.
6. Served area construction should be completed(doors, Window, etc...).
7. All related Supply and or Exhaust air systems should be operating .(if applicable)
8. Deficiencies should be reported for rectification.
9. Proceed TAB work after System deficiencies rectification.

B. FCU Air Distribution System Balance:


1. Verify fan adjustment to the required total system air flow.
2. Perform testing, adjusting and balancing(TAB) for air distribution system terminals as
per NEBB TAB Procedures to values within ±10% of design.
3. After completion of balancing air terminals, record the final readings as per required data
for TAB test forms for both air terminals and FCU.
4. FCU total air flow should be ±10% of design.
5. Deficiencies should be reported for rectification.
6. Proceed TAB work after System deficiencies rectification.

C. Completion of TAB Report :


1. Recorded final readings and data obtained from Project documents, name plate and filed
installation should be as per required data for TAB test forms for both air terminals and
FCU.
2. Report should include all remained System deficiencies.(if applicable)

Tel: 010 62743201


E-Mail: delta.tab@yahoo.com
FANS

A. FAN and Air Distribution System Checks:


1. FAN & Air Distribution System Installation should be completed as per project
documents.
2. All balancing devices (V.D) are properly placed and fully opened.
3. Air filters should be Clean and properly placed.(If applicable)
4. Control system installations completed and operate properly.
5. FAN Start up completed and operates properly before TAB work.
6. Served area construction should be completed(doors, Window, etc...).
7. All related Supply and or Exhaust air systems should be operating .(if applicable)
8. Deficiencies should be reported for rectification.
9. Proceed TAB work after System deficiencies rectification.

B. FAN performance test procedures:


1. Verify all FAN-Air Distribution System Checks.
2. Measure Fan Speed & Motor Speed, Voltage and Ampere(Motor not overloaded).
3. Adjust FAN Main damper for the proper position as required per design values.
4. Measure Fan Total and external static pressure.
5. locate the proper point for duct traverse section after a straight length of duct for total fan
air flow .
6. Fan total air flow should be ±10% of design, if fan total air flow less or more than the
acceptable limits, adjust the fan speed to achieve the required design air flow.
7. Deficiencies should be reported for rectification.
8. Proceed TAB work after System deficiencies rectification.

C. FAN Air Distribution System Balance:


1. Verify fan adjustment to the required total system air flow.
2. Perform testing, adjusting and balancing(TAB) for air distribution system terminals as
per NEBB TAB Procedures to values within ±10% of design.
3. After completion of balancing air terminals, record the final readings as per required data
for TAB test forms for both air terminals and FAN.
4. Deficiencies should be reported for rectification.
5. Proceed TAB work after System deficiencies rectification.

D. Completion of TAB Report:


1. Recorded final readings and data obtained from Project documents, name plate and filed
installation should be as per required data for TAB test forms for both air terminals and
FAN.
2. Report should include all remained System deficiencies.(if applicable).

Tel: 010 62743201


E-Mail: delta.tab@yahoo.com
Tel: 010 62743201
E-Mail: delta.tab@yahoo.com
PUMPS AND WATER CIRCUITS

A. Pump and Water Circuit Checks:


1. Pump Water Circuit Installation should be completed as per project documents.
2. All balancing devices (B.V) are properly placed and fully opened.
3. Water Strainers should be Clean and properly placed.
4. Control system installations completed and operate properly.
5. All automatic control valves at the maximum load condition.
6. Pump Start up completed and operates properly before TAB work.( water circuit
components as well)
7. Verify water circuit flushing, chemical treatment and pressurization.(Verify make up
water if applicable)
8. Deficiencies should be reported for rectification.
9. Proceed TAB work after System deficiencies rectification.

B. Pump performance test procedures:


1. Verify all Pump and Water Circuit Checks.
2. Measure Pump Speed & Motor voltage and Ampere(Motor not overloaded).
3. Adjust the B.V for each Pump for the proper position within ±10% of design.
4. Measure and record Pump total head and water flow for each pump.
5. Measure and record Pump B.V differential pressure, water flow & valve position.
6. Deficiencies should be reported for rectification.
7. Proceed TAB work after System deficiencies rectification.

C. Water Circuit Balance:


1. Verify Pump adjustment to the required total water circuit flow.(apply maximum load
condition)
2. Perform testing, adjusting and balancing(TAB) for water circuit terminals as per NEBB
TAB Procedures to values within ±10% of design.
3. After completion of balancing water circuit, record the final readings as per required data
for TAB test forms for both water terminals and Pump.
4. Deficiencies should be reported for rectification.
5. Proceed TAB work after System deficiencies rectification.

D. Completion of TAB Report:


1. Recorded final readings and data obtained from Project documents, name plate and filed
installation should be as per required data for TAB forms for water circuit terminals B.V
and pump.
2. Report should include all remained System deficiencies.(if applicable)

Tel: 010 62743201


E-Mail: delta.tab@yahoo.com
CHILLERS

A. Chiller and Water Circuit Checks:


1. Chiller & Water Circuit Installation should be completed as per project documents.
2. All balancing devices (B.V) are properly placed and fully opened.
3. Water Strainers should be Clean and properly placed.
4. Control system installations completed and operate properly.
5. All automatic control valves at the maximum load condition.
6. Chiller Start up completed and operates properly before TAB work.( water circuit
components as well)
7. Verify water circuit flushing, chemical treatment and pressurization.(Verify make up
water if applicable)
8. Deficiencies should be reported for rectification.
9. Proceed TAB work after System deficiencies rectification.

B. Chiller performance test procedures:


1. Verify all chiller and Water Circuit Checks.
2. Adjust the B.V for each chiller for the proper position within ±10% of design.
3. Measure and record cooling chiller differential pressure and water flow for both
evaporator and Condenser.
4. Measure and record chiller B.V differential pressure, water flow & valve position.
5. Deficiencies should be reported for rectification.
6. Proceed TAB work after System deficiencies rectification.

C. Completion of TAB Report :


1. Recorded final readings and data obtained from Project documents, name plate and filed
installation should be as per required data for TAB forms for chiller B.V, evaporator and
condenser.
2. Report should include all remained System deficiencies.(if applicable)

Tel: 010 62743201


E-Mail: delta.tab@yahoo.com
COOLING TOWER

A. Cooling Tower and Water Circuit Checks:


1. Cooling Tower & Water Circuit Installation should be completed as per project
documents.
2. All balancing devices (B.V) are properly placed and fully opened.
3. Water Strainers should be Clean and properly placed.
4. Control system installations completed and operate properly.
5. All automatic control valves at the maximum load condition.
6. Chiller Start up completed and operates properly before TAB work.( water circuit
components as well)
7. Verify water circuit flushing, chemical treatment and Verify make up water.
8. Deficiencies should be reported for rectification.
9. Proceed TAB work after System deficiencies rectification.

B. Cooling Tower performance test procedures:


1. Verify all cooling tower and Water Circuit Checks.
2. Adjust the B.V for each cooling tower for the proper position within ±10% of design.
3. Measure and record cooling tower differential pressure and water flow.
4. Measure and record cooling tower B.V differential pressure, water flow & valve position.
5. Deficiencies should be reported for rectification.
6. Proceed TAB work after System deficiencies rectification.

C. Completion of TAB Report :


1. Recorded final readings and data obtained from Project documents, name plate and filed
installation should be as per required data for TAB forms for cooling tower and its B.V.
2. Report should include all remained System deficiencies.(if applicable)

Tel: 010 62743201


E-Mail: delta.tab@yahoo.com
Tel: 010 62743201
E-Mail: delta.tab@yahoo.com
‫شركة دلتا تاب‬
‫ألعمال الضبط والموازنة‬
Project: Date:
System: System tag:

AIR HANDLING UNIT TEST SHEET

UNIT DATA
Model No
Serial No
Manufacturer
Unit Location
Area Served

FLOW RATE
TEST DATA DESIGN ACTUAL PERCENTAGE
Total Supply Air (Traverse)
Total Supply Air (Outlets)
Total Retun Air (Traverse)
Total Return Air (Outlets)
Outside Air
Total Static Pressure

SUPPLY FAN RETURN FAN


Manufacturer Manufacturer
Model Model
Max RPM Max RPM
Total SP Total SP
MOTOR DATA MOTOR DATA
Motor HP Motor HP
Manufacturer Manufacturer
Motor Pulley Motor Pulley
Fan Pulley Fan Pulley
Belts Belts
TEST DATA DESIGN ACTUAL TEST DATA DESIGN ACTUAL
Phase / Hertz Phase / Hertz
Volt Volt
Ampere Ampere
Motor RPM Motor RPM
Fan RPM Fan RPM

REMARKS:

Prepared By:
‫شركة دلتا تاب‬
‫ألعمال الضبط والموازنة‬
Project: Date:
System: System tag:

FRESH AIR FAN TEST SHEET

UNIT DATA
Model No
Serial No
Manufacturer
Unit Location
Area Served

FLOW RATE
TEST DATA DESIGN ACTUAL PERCENTAGE
Total Supply Air (Traverse)
Total Supply Air (Outlets)
Total Static Pressure

SUPPLY FAN
Manufacturer
Model
Max RPM
Total SP
MOTOR DATA
Motor HP
Manufacturer
Motor Pulley
Fan Pulley
Belts
TEST DATA DESIGN ACTUAL
Phase / Hertz
Volt
Ampere
Motor RPM
Fan RPM

REMARKS:

Prepared By:
‫شركة دلتا تاب‬
‫ألعمال الضبط والموازنة‬
Project: Date:
System: System tag:

EXHAUST AIR FAN TEST SHEET

UNIT DATA
Model No
Serial No
Manufacturer
Unit Location
Area Served

FLOW RATE
TEST DATA DESIGN ACTUAL PERCENTAGE
Total Exhaust Air (Traverse)
Total Exhaust Air (Outlets)
Total Static Pressure

Exhaust FAN
Manufacturer
Model
Max RPM
Total SP
MOTOR DATA
Motor HP
Manufacturer
Motor Pulley
Fan Pulley
Belts
TEST DATA DESIGN ACTUAL
Phase / Hertz
Volt
Ampere
Motor RPM
Fan RPM

REMARKS:

Prepared By:
‫شركة دلتا تاب‬
‫ألعمال الضبط والموازنة‬
Project: Date:
System: System tag:

DUCT TRAVERSE (RECTANGULAR) TEST SHEET

Duct (in x in)


Area (ft2)

Velocity Profile
Position 1 2 3 4 5 6 7 8 9 10
1
2
3
4
5
6
7
8
9
10
Sum

FLOW RATE
TEST DATA DESIGN ACTUAL
Air Velocity
Air Flow

REMARKS:

Prepared By:
‫شركة دلتا تاب‬
‫ألعمال الضبط والموازنة‬
Project: Date:
System: System tag:

DUCT TRAVERSE (ROUND) TEST SHEET

Duct Diameter (in)


Area (ft2)

Velocity Profile
Position 1 2 3 4 5 6 7 8 9

FLOW RATE
TEST DATA DESIGN ACTUAL
Air Velocity
Air Flow

REMARKS:

Prepared By:
‫شركة دلتا تاب‬
‫ألعمال الضبط والموازنة‬
Project: Date:
System: System tag:

FAN COIL TEST SHEET

Unit Area CFM Ampere Volt


Manuf. Model
Tag Served Design Actual Design Actual Design Actual

10

11

12

13

14

15

REMARKS:

Prepared By:
‫شركة دلتا تاب‬
‫ألعمال الضبط والموازنة‬
Project: Date:
System: System tag:

OUTLETS TEST SHEET

Terminal Area Terminal Terminal Design Actual CFM


Number Served Type Size CFM CFM Percent.%
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15

REMARKS:

Prepared By:
‫شركة دلتا تاب‬
‫ألعمال الضبط والموازنة‬
Project: Date:
System: System tag:

CHILLER TEST SHEET

UNIT DATA
Model No
Serial No
Manufacturer

EVAPORATOR
TEST DATA DESIGN ACTUAL PERCENTAGE
Flow Rate (GPM)
Pressure Drop (ft)
Entering Water Temp (˚F)
Leaving Water Temp (˚F)
Water ΔT

CONDENSER
TEST DATA DESIGN ACTUAL PERCENTAGE
Flow Rate (GPM)
Pressure Drop (ft)
Entering Water Temp (˚F)
Leaving Water Temp (˚F)
Water ΔT

REMARKS:

Prepared By:
‫شركة دلتا تاب‬
‫ألعمال الضبط والموازنة‬
Project: Date:
System: System tag:

PUMP TEST SHEET

UNIT DATA
Model No
Serial No
Manufacturer
Location
Impeller Size (mm)

HEAD & FLOW RATE


TEST DATA DESIGN ACTUAL PERCENTAGE
Water Flow Rate (GPM)
Pump Head (KPa)
Pump Discharge Pressure (KPa)
Pump Suction Pressure (KPa)
No Flow Differential Pressure
No Flow Discharge Pressure (Kpa)
No Flow Suction Pressure (Kpa)

MOTOR DATA
Motor HP
Manufacturer
Motor Pulley
Fan Pulley
Belts
TEST DATA DESIGN ACTUAL
Phase / Hertz
Volt
Ampere
Motor RPM
Fan RPM

REMARKS:

Prepared By:
‫شركة دلتا تاب‬
‫ألعمال الضبط والموازنة‬
Project: Date:
System: System tag:

BALANCING VALVE TEST SHEET

Valve Data Design Balancing Data


Equipment Valve
Item Valve Tag Size flow
Served Location Manufac. Model H.W.P Kvs GPM %
DN(mm) (GPM)
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15

REMARKS:

Prepared By:
Tel: 010 62743201
E-Mail: delta.tab@yahoo.com
Masjid 2000 (Elkayan elaskry)
Location: New Capital
Main Contractor: Elaseel company
Consultant: Sabbour consultancy group
The project consist of 3 buildings
(Masjid, Library and occasions Hall)
Description:
Full testing, adjusting and balancing
works done for the HVAC system

Tel: 010 62743201


E-Mail: delta.tab@yahoo.com
Ophthalmology Hospital
Location: GIZA
Main Contractor: Elaamer Company
Full testing, adjusting and balancing
Description: works done for Operation Rooms,
laboratories and Clinics

Tel: 010 62743201


E-Mail: delta.tab@yahoo.com
EDEN Healthcare Hospital
Location: 6th of October city
Main Contractor: Tiba Contracting Company
Full testing, adjusting and balancing
Description: works done for Operation Rooms,
Recovery Room and Intensive Care Units

Tel: 010 62743201


E-Mail: delta.tab@yahoo.com
Open Air Mall – Mall (C)
Location: Madinaty
Main Contractor: Square Contracting Company
Consultant: Engineering Consultants Group (ECG)
Full testing, adjusting and balancing
Description:
works done for the HVAC system

Tel: 010 62743201


E-Mail: delta.tab@yahoo.com
Soap Factory
Location: Industrial District, Suez Road
Main Contractor: Tiba Contracting Company
Testing, adjusting and balancing works
Description: done for the ventilation system of the
factory

Tel: 010 62743201


E-Mail: delta.tab@yahoo.com
Al-Ahrar Oncology Center
Location: Zagazig, Sharqia
Main Contractor: Al- Amin Contracting Company
Testing, adjusting and balancing works
Description:
done for all clinics of the center

Tel: 010 62743201


E-Mail: delta.tab@yahoo.com
Qeft Hospital
Location: Qeft, Qena
Main Contractor: Al- Naggar Contracting Company
Testing, adjusting and balancing works
Description:
done for all Operation Rooms

Tel: 010 62743201


E-Mail: delta.tab@yahoo.com
MAHMOUD SAAD MAHMOUD
HAS MET ALL REQUIREMENTS FOR NEBB CERTIFIED TECHNICIAN
STATUS IN THE FOLLOWING DISCIPLINE

Testing, Adjusting and Balancing of Environmental Systems


This Certificate, as well as individual affiliation with a NEBB Certified Firm and associated NEBB Certification Stamp
are REQUIRED to provide a NEBB Certified Report. Participation in the NEBB Quality Assurance Program
requires the Certificant be affiliated with a NEBB Certified Firm

CT-22382 _______________________________________
_______________________________________
NEBB President
NEBB Certification Number

December 31, 2022


_______________________________________
Expiration Date _______________________________________
NEBB President-Elect
LETTER OF ENDORSEMENT

Date: May 2021

To Whom It May Concern,

This letter is in appreciation to Delta TAB Company. Who carried out The Testing, Adjusting &
Balancing works for EDEN Medical Center Project.

During the testing & Balancing of this project, Delta TAB showed a professional attitude and
took ownership of the job.They worked very well to ensure all systems are working to ultimate
conditions.Delta TAB showed a good systems trouble shooting and finaly presented a comore-
hansive Testing and Balancing reports with all needed details in a simple format.

In future , I’d select to work with Delta TAB again for the positive attitude and high experience
they showed during working in our Project.

Sincerely,
Eng. AMR FATHY
Technical Office Manager