1. Take the current meter reading for gas, electricity and water.
Formula:
“Flow rate = Volume/Time (L/Min)”
Hot water: 11 L/Min
Cold water: 16 L/Min
4. Inspect the type of lighting used and determine the KW/H (1000
Watt = 1 KWH) used in that department based on typical or given
workplace practices during operation.
Waste collection:
Glass Bottles
her (Broken
Paper (%)
Cans (%)
ilk Cartons
Card (%)
(%)
rganic (%)
Location
Bin Size
Date/
Time
Glass)
(%)
(%)
14/ 9p
08 m Recycle 1 15 L 1 1 85 13 0 0 0 0
14/ 9p
08 m Waste 1 30 L 3 1 0 0 96 0 0 0
14/ 9p
08 m Waste 2 50 L 0 0 0 0 100 0 0 0
Air condition :
Garden/Outdoor:
Glass bottle
Things Practices
Grass Cut them once in a month
Plastic bag Re use for carry thing for
10. List the purchasing strategies which are currently in place
including environmentally sustainable approaches; carbon foot
print considerations (for example use local supplies from
growers etc.)
Hazards:
Using the equipment correctly
Using cleaning material carefully
Using wrong position to work
Using chemicals correctly
Using chemicals carefully
Resources: Benefits:
Save money
Save energy
Save environments
Best practices:
Air condition setting @ 22 - 25 / Using in time table
Turn off gas when not using
Close taps to avoid dripping of water, etc.
Turn off the light when not using
Open the windows or doors instead air condition
Technologies:
Using energy efficient equipment (Such as: bulbs, lights, dishwasher,
air condition, etc.)
Introducing computer based system
Using POS instead copies paper
2. Set your targets in a table or spreadsheet based on your findings
of the analysis.
For this part of the assessment project you are required to write and
environmental resource efficiency improvement plan which details the
following:
Plan Reason
Change air condition setting To save energy and money
temperature
Using energy saving lights To save energy and money
Taping off water when not using To save energy and money
Resource Target
Water Saving $0.8 and 20 L of water/Day
Organising regular staff training : Staff may feel discomfort when any
new changes are introduced. They might be unsure about the new
processes and might think that it will be hard for them to follow the
new rules and regulations.
8 light bulbs rated at 1.00 KWH in Service area with 8 energy saving
bulbs rated at 0.012 KWH which would represent an energy saving of
0.988 Kw per hour x $0.28 = $0.2766 per hour
Or at 6 hours per day : $0.2766 x 6 = 1.66 / Day / Bulb
For a 6 day operation this then equates to a potential saving of $
360 minus the proportion of the cost of the energy saving bulb @ $
7.50 /5000 hours ($1.50 per 1000 hours use) versus an ordinary bulb
@ $ 0.75 /1000 hours lifespan.
4 light tubes rated at 1.00 KWH in Service area with 8 energy saving
bulbs rated at 0.012 KWH which would represent an energy saving of
0.988 Kw per hour x $0.28 = $0.2766 per hour
Or at 6hours per day : $0.2766 x 6 = 1.66 / Day / Tube
For a 6 day operation this then equates to a potential saving of $
360 minus the proportion of the cost of the energy saving bulb @ $
7.50 /5000 hours ($1.50 per 1000 hours use) versus an ordinary bulb
@ $ 0.75 /1000 hours lifespan.
8. The provisions for communication to periodically discuss and
network with colleagues to make adjustments and identify
progress;
Communication:
All businesses have different approaches of communicating results
depending on their culture, size and spread. The type of communication
must suit the audience and the occasion. Different ways can be used to
communicate results. They are:
Regular meetings
Email updates and summary information
Staff room noticeboards
Executive meetings
Newsletters Project management tool reports
External channels
Equipment/Products Tools/method
Air Conditioner Temperature log
Recycle bin Checklist
Refrigerator Temperature log
Freezer Temperature log
Microwave Watt Log
Evaluate strategies:
Compare usage with targets : The main goal is to ensure that the
business is committed to environmental improvement processes. The
evaluation process must be fare.
Report : It will show the highest waste areas within the business and
will help to priorities the initiatives which will benefit the company.