You are on page 1of 11

Documents / Shop Drawings Submittal Form

Reference No.: B.CREST-DOC/TS-001 Issue Date: 23 Dec 2022


Project Name: BINGHATTI CREST Client: BINGHATTI Holdings
Project Proposed: G+4P+19FLOOR+ROOF Engineering Consultant: Silverstone Eng’g Consultants
Project Location: JVC DUBAI Main Contractor: Granada Europe Const. Co.

Doc. Ref.
Description Pages Discipline Remarks
No.
TS-01 Domestic Pumps Flow and Head Calculation

SHOP DRAWING: DISCIPLINE (TICK APPROPRIATE SCOPE OF WORK)


☐ Architectural ☐ Structural ☒ MEP
DOCUMENT TYPE: DISCIPLINE (TICK APPROPRIATE SCOPE OF WORK)
☐ Method Statement / TDS ☐ Warranties ☐ Other: PLUMBING

MAIN CONTRACTOR REQUESTING BY (TICK APPROPRIATE THE CONCERN PERSON)


☒ Project Manager ☒ MEP Manager / MEP Eng ☐ Industrial Manager
Eng. Najm Shah Eng. Waqar Hussain/ Eng. Mithun
Signature: Date:23.12.2022 Signature: Date:23.12.2022 Signature: Date:

The Contractor confirms herewith this document has been executed & coordinated strictly as per the approval of drawings from
the authorities and approved specifications from the engineering consultant.

This submittal is intended to:


☒ Review/ Approval ☐ Information/Records ☐ As per request ☐ Other, Specify Below

STATUS OF QA / QC DEPARTMENT
☐ Approved ☐ Approved As Noted ☐ Re-Submit
Comment/s:

Refer the Comments as attached

☐ QA/QC Civil Engineer ☐


x QA/QC MEP Engineer ☐ QA/QC Head
Signature: Signature: Signature:

STATUS OF CONSULTANT DEPARTMENT


☐ Approved ☐ Approved As Noted ☐ Re-Submit
Comment/s:

☐ ARCH Head ☐ STR Head ☐ MEP Head ☐ ID/ED Head ☐ IA Head


Signature: Signature: Signature: Signature: Signature:

Controlled Documents SS-TEC-SDS-2022-R1 1


BINGHATTI-CREST
PUMP-HEAD CALCULATION
QA/QC COMMENTS: -

1. Contractor should comply all the comments as per projection specification – “SECTION 221429 -
SUMP PUMPS” and “SECTION 221123 for “DOMESTIC WATER PUMPS” and its controls and
Sequence of operation.
2. Basement to ground floor height approximately taken (+3.5 M to 3.5 M = 7 Meter) due to the
non-availability of Approved Schematic Drawing.
3. Pipe size, pipe length and fitting quantity considered from design drawing (it was measured
Approximately +/-) since considered the safety factor 20%. So pipe routing and length will not
affect during the MEP coordination drawing preparation. In case any major changes submit
separate drawing and approval to be obtained.
4. Safety factor to be confirmed by design Team- as per the calculation for SUMP Pump 15%
irrigation pump-20% , Booster & Transfer pump safety factor considered as 20%.
5. Contractor must submit shop drawings showing pump type, capacity, certified pump curves
showing pump performance characteristics with pump and system operating point plotted.
Include NPSH
(Net positive suction head) curve when applicable and include electrical characteristics.
6. Booster pumps calculation loading units verified with nomogram chart and as per design
drawings.
7. Booster pumps calculation the shower pressure considered 2 bar, design team to be confirmed.
8. Pump type, material of construction of pumps, electric motor specification details to be
submitted in the material submittal.
9. All Pump startup arrangements to be comply as per the approved and Dewa requirements &
regulation.
10. Supplier confirmation required for the selection of pumps as per the project designs.
11. All pump panels shall have control for auto sequencing, fused circuit for each motor, main
disconnect switch, selector switch for each pump, power on indicator light, run/trip indicators.
12. Pump Control panel U/L certificate should be provided, and Cable size and Breaker rating should
be as per DEWA requirements.
13. According to the pump selection schedule pump head and flow rates considered as follows: -
Domestic booster pump: - (Head 2.8 bar : Flow rate 5.107 L/s – 1D+1S) -4 FLOORS
Domestic Transfer pump: - (Head 9.3 bar : Flow rate 13 L/s – 1D+1S)
Irrigation pump: - (Head 2.5 bar : Flow rate 3 L/s – 1D+1S)
Sump pump: - (Head 2.5 bar : Flow rate 5 L/s – 1D+1S)
14. Provide hygienic certificate showing that the selected pump package is suitable for drinking
water.
15. All pumps shall be factory assembled & tested.
16. Subject to material Submittal approval.

PRABAKARAN NARAYANASAMY –
QAQC-MEP INSPECTOR
SCHEDULE FOR DOMESTIC BOOSTER PUMP
SL:NO FLOW RATE (l/s) HEAD (Bar) QTY Remarks PURPOSE
(1 Duty+1
1 5.107 2.8 1 set BOOSTER PUMP
Standby)
DOMESTIC COLD WATER BOOSTER PUMP - B-crest@ROOF FLOOR 19,18,17,16 FLOORS

Pump head calculation


TOTAL Pressure loss in the pipe & fittings = 3.98 m H₂0
Pressure considered at outlet(WC) = 20.00 m H₂0
Total head = 23.98 m H₂0
Safety factor 20.0 % = 4.80 m H₂0
Static head = m H₂0
Total pressure loss with safety = 28.77 m H₂0
2.82 bar
AVALIABLE HEAD DUE TO GRAVITY 0.0 bar
FINAL HEAD NEEDED FOR PUMP 2.8 bar
Selected Pump
1 set of Cold water Booster pump (1 Duty + 1 Standby) @ 5.107l/s, 2.9 bar

Pipe pressure drop calculation(Water meter room) Pipe pressure drop calculation(MAIN RISER + HEADER)-3" RISER

Pipe selected Pipe selected


Ø 50 mm SCH 80 PIPE(2") Ø 90 mm SCH 80 PIPE(3")
Flow rate = 1.78 l/sec Flow rate = 5.11 l/sec
28 US-GPM 81 US-GPM
Velocity = 3.80 ft/sec Velocity = 3.93 ft/sec
1.2 m/sec 1.2 m/sec
Pipe friction loss = 1.30 Psi/100ft Pipe friction loss = 0.82 Psi/100ft
Pipe friction loss = 3.01 ft/100ft Pipe friction loss = 1.90 ft/100ft
No. of fittings No. of fittings
Pipe length (M) Pipe length (M)
E90 TEE GV STR. PRV E90 TEE GV STR. NRV
Horizontal Suction line 10.0 4 4 1 1 0
water meter 4.0 2 9 3 0 1 ROOF 19.0 5 2 1 0 1
room Riser 14.0 1 3 1

Total 4.0 2 9 3 0 1 Total 43.0 10 9 3 1 1

Total equivalent length Total equivalent length


Total Length Total Length
Qnty. Eq. Length (ft) Items Qnty. Eq. Length (ft)
(ft) (ft)
Pipe 4.0 13.1 13.12 Pipe 43.0 141.0 141.04
Fittings Fittings
E90 2 5.5 11.00 E90 10 9.0 90.00
TEE 9 9.0 81.00 TEE 9 15.0 135.00
GV 3 0.5 1.50 GV 3 1.5 4.50
STR. 0 0.0 0.00 STR. 1 14.5 14.50
NRV 1 0.0 0.00 NRV 1 14.5 14.50
Total 106.62 ft Total 399.54 ft

Total length of pipe = 106.6 ft Total length of pipe = 399.5 ft


Pressure loss = 1.30 psi/100ft Pressure loss = 0.82 psi/100ft.
Total pressure loss in pipe & fitting = 1.39 psi Total pressure loss in pipe & fitting = 3.28 psi
= 0.97 m H₂0 = 2.30 m H₂0

Pipe pressure drop calculation(CORRIDOR to Flat 05) Pipe pressure drop calculation(FLAT8 TO WC)

Pipe selected Pipe selected


Ø 40 mm PPR PIPE(1 1/4") Ø 25 mm SCH 80 PIPE(3/4")
Flow rate = 0.43 l/sec Flow rate = 0.35 l/sec
7 US-GPM
Velocity = 1.71 ft/sec Velocity = 2.95 ft/sec
0.1 m/sec 0.9 m/sec
Pipe friction loss = 0.53 Psi/100ft Pipe friction loss = 1.05 Psi/100ft
Pipe friction loss = 1.23 ft/100ft Pipe friction loss = 2.44 ft/100ft
No. of fittings No. of fittings
Pipe length (M) Pipe length (M)
E90 TEE GV STR. NRV E90 TEE GV STR. NRV

CORRIDOR 27.0 4 1 2 0 0 Inside flat 10.0 7 3 1 0 0

Total 27.0 4 1 2 0 0 Total 10.0 7 3 1 0 0

Total equivalent length Total equivalent length


Total Length Total Length
Qnty. Eq. Length (ft) Qnty. Eq. Length (ft)
(ft) (ft)
Pipe 23.0 75.4 75.44 Pipe 10.0 32.8 32.80
Fittings Fittings
E90 4 2.5 10.00 E90 7 2.0 14.00
TEE 1 4.5 4.50 TEE 3 0.5 1.50
GV 2 0.5 1.00 GV 1 0.7 0.70
STR. 0 0.0 0.00 STR. 0 0.00
NRV 0 0.0 0.00 NRV 0 0.00
Total 90.94 ft Total 49.00 ft

Total length of pipe = 90.9 ft Total length of pipe = 49.0 ft


Pressure loss = 0.53 psi/100ft Pressure loss = 1.05 psi/100ft
Total pressure loss in pipe & fitting = 0.48 psi Total pressure loss in pipe & fitting = 0.51 psi
0.34 m H₂0 = 0.36 m H₂0
BOOSTER COLD WATER DEMAND FOR 4 FLOORS(19h, 18th,17th and 16th Floor)

T.F(U) FOR (4 TOTAL L/S


TOTAL
T.F(U) PER TOTAL L/S PER FLOORS) T.F(U) FOR FOR
SL:NO FLATS EQUIPMENTS QTY F(U) T.F(U) L/S FOR 4 T(FU) TOTAL L/S
FLOOR FLOOR ,19F,18F,17F, ROOF FLOOR General
FLOORS
16F Services

EWC-STD-C 1 2
HF-C 1 1
WB-BC-C&H 1 2
1 FLAT NO-1(1BHK) 13
SHOWER-C&H 1 3
SINK-BC-C&H 1 3
WM-C 1 2
EWC-STD-C 1 2
HF-C 1 1
WB-BC-C&H 1 2
2 FLAT NO-2(1-BHK) 13
SHOWER-C&H 1 3
SINK-BC-C&H 1 3
WM-C 1 2
EWC-STD-C 2 2
HF-C 2 1
WB-BC-C&H 2 2
3 FLAT NO-3(3BHK) 21
SHOWER-C&H 2 3
SINK-BC-C&H 1 3
WM-C 1 2
EWC-STD-C 2 2
HF-C 2 1
WB-BC-C&H 2 2
4 FLAT NO-4(2BHK) 21
SHOWER-C&H 2 3
SINK-BC-C&H 1 3
WM-C 1 2
EWC-STD-C 2 2
HF-C 2 1
WB-BC-C&H 2 2
5 FLAT NO-5(1BHK) 18 164 1.782 656 5.008 18 0.33 674 5.107
SHOWER-C&H 1 3
SINK-BC-C&H 1 3
WM-C 1 2
EWC-STD-C 2 2
HF-C 2 1
WB-BC-C&H 2 2
6 FLAT NO-6(1BHK) 18
SHOWER-C&H 1 3
SINK-BC-C&H 1 3
WM-C 1 2
EWC-STD-C 2 2
HF-C 2 1
WB-BC-C&H 2 2
7 FLAT NO-7(1BHK) 21
SHOWER-C&H 2 3
SINK-BC-C&H 1 3
WM-C 1 2
EWC-STD-C 2 2
HF-C 2 1
WB-BC-C&H 2 2
8 FLAT NO-8(1BHK) 21
SHOWER-C&H 2 3
SINK-BC-C&H 1 3
WM-C 1 2
EWC-STD-C 2 2
HF-C 2 1
WB-BC-C&H 2 2
9 FLAT NO-9(1BHK) 18
SHOWER-C&H 1 3
SINK-BC-C&H 1 3
WM-C 1 2
GENERAL SERVICE

1 Bip Tap( Roof) 10

Lavatory 5 2
18 0.33

2 Bip Tap( 19,18,17,16 ) 8

Lavatory 4 2
SCHEDULE FOR IRRIGATION PUMP
SL:NO FLOW RATE (l/s) HEAD (Bar) QTY Remarks PURPOSE
1 3 2.5 1 set (1 Duty+1 Standby) IRRIGATION
IRRIGATION TANK CAPACITY(3M(L)*3M(W)*1M(H))
IRRIGATION PUMP(P4 TO FIRST FLOOR LOW LEVEL) - B-CREST,JVC P4-Irrigation water tank size (3M(L)*3M(W)*1M(H)(0.8m(w.t)+.2(f.b)
P4-Irrigation water tank capacity 9.00 cu.m
Flow rate & Pipe Sizing P4-Irrigation water tank capacity 9,000.00 l
GREEN AREA +PAM TREES
=
Total tank capacity @ Podium-03 9.00 M³ Water consumption for each Total quanitity
SL:NO DESCRIPTION UNIT QTY Remarks
plants Lit/Daily at peak in Liters
Required flow rate = 2.73 l/s
Required flow rate = 43 Us.gpm 1 Palm trees Nos 2 150 300
2 Trees Nos 11 100 1,100
Pump head calculation 3 Shrubs Nos 12 20 240
Pressure loss in the pipe & fittings = 2.3 m H₂0 4 Ground cover Nos 0 10 0
Pressure considered at discharge valve 5.0 m H₂0
Total head = 7.3 m H₂0 TOTAL Irrigation water required in Liters 1,640
Safety factor 20.0 % = 1.5 m H₂0 Daily water operation 10 min per 3times(8am,1pm,6pm) 2.73 lps
Static head = 7.8 m H₂0
Total pressure loss with safety = 16.5 m H₂0
1.6 bar

Selected Pump 7.75 Mtrs


STATIC HEAD Podium - 3 (LVL=+12.75) TO FF(LVL=+20.05)
1 set of tIrrigation pump (1 Duty + 1 Standby) @ 3.0 l/s, 2.5 bar
7.75 Mtrs
Pipe pressure drop calculation

Pipe selected
Ø 65 mm SCH 80 PIPE(2 1/2")
Flow rate = 2.73 l/sec
Velocity = 3.27 ft/sec
1.0 m/sec
Pipe friction loss = 0.80 psi/100ft
Pipe friction loss = 1.85 ft/100ft
Pipe length No. of fittings
(M) ELBOW90 TEE GV STR. NRV
Suction (A) 2.0 0 0 1 1 1

Discharge (B)+Riser
(C )+FF LOW LEVEL 51.0 9 11 1
(D)
Total 53.0 9 11 2 1 1
Total equivalent length

Qnty. Eq. Length (ft) Total Length (ft)


Pipe 53.0 173.8 173.84
Fittings
E90 9 9.3 83.70
TEE 11 9.3 102.30
GV 2 1.7 3.40
STR. 1 29.0 29.00
NRV 1 22.0 22.00
Total 414.24 ft

Total length of pipe = 414.2 ft


Pressure loss = 0.8 psi/100ft
Total pressure loss in pipe & fitting = 3.3 psi
= 2.3 m H₂0
SCHEDULE FOR SUMP PUMP
SL:NO FLOW RATE (l/s) HEAD (Bar) QTY Remarks PURPOSE
1 5 2.5 1 set (1 Duty+1 Standby) SUMP PUMP
SUMP PIT CAPACITY
SUMP PUMP(UG TO GF LOW LEVEL) - B-CREST, JVC Under Ground Domestic water tank capacity= 38,050.00 Imp.Gal
Under Ground Fire water capacity= 50,000.00 Imp.Gal
Flow rate & Pipe Sizing Under Ground water tank volume(Domestic+Fire)= 88,050.00 Imp.Gal
TOTAL VOLUME (CU.M) 400 Cu.m
= Sump pump@UG,Assume Half of the tank will drain within 12 hrs 16.68 Cu.m/hr
Total tank capacity 4.05 M³
Sump pump@UG,Assume Half of the tank will drain within 12 hrs 277.97 l/m
Required flow rate = 4.63 l/s Sump pump@B2,Assume Half of the tank will drain within 12 hrs 4.63 l/s
Required flow rate = 73 Us.gpm As per approved structural & mep -Sumpit size(1.5m(w)*1.5m(l)*1.9m(h)+0.2(f.b)
volume of water sump pit can hold 4.27 Cu.m
Pump head calculation volume of water sump pit can hold 4,270.00 l
Pressure loss in the pipe & fittings = 1.4 m H₂0 The Sump pit can hold the drain water for 10 min approximately 15 min
Pressure considered at discharge valve 5.0 m H₂0
Total head = 6.4 m H₂0
Safety factor 15.0 % = 1.0 m H₂0
Static head = 1.2 m H₂0
Total pressure loss with safety = 8.5 m H₂0
0.8 bar SUMP PIT CAPACITY 4.05 Cu.m

Selected Pump 1.15 Mtrs


STATIC HEAD UG (LVL=-0.70) TO GF(LVL=+0.85)
1 set of Sump pump (1 Duty + 1 Standby) @ 5 l/s, 2.5 bar
1.15 Mtrs
Pipe pressure drop calculation

Pipe selected
Ø 75 mm SCH 80 PIPE(3")
Flow rate = 4.63 l/sec
Velocity = 3.56 ft/sec
1.1 m/sec
Pipe friction loss = 0.71 psi/100ft
Pipe friction loss = 1.64 ft/100ft
Pipe length No. of fittings
(M) ELBOW90 TEE GV STR. NRV
Suction (A)
Discharge (B)+Riser
(C )+B/L Break
41.0 9 1 1 0 1
pressure manhole
(D)
Total 41.0 9 1 1 0 1
Total equivalent length
Total Length
Qnty. Eq. Length (ft)
(ft)
Pipe 41.0 134.5 134.48
Fittings
E90 9 11.0 99.00
TEE 1 12.0 12.00
GV 1 1.9 1.90
STR. 0 0.0 0.00
NRV 1 27.0 27.00
Total 274.38 ft

Total length of pipe = 274.4 ft


Pressure loss = 0.7 psi/100ft
Total pressure loss in pipe & fitting = 1.9 psi
= 1.4 m H₂0
SCHEDULE FOR DOMESTIC WATER TRANSFER PUMP
SL:NO FLOW RATE (l/s) HEAD (Bar) QTY Remarks PURPOSE
1 13 9.3 1 set (1 Duty+1 Standby) TRANSFER PUMP
NOTES:
1. Pump shall be mounted on a frame with common suction & discharge header
2. Each pump shall be provided with Gate valve on both side, NRV on discharge side, Strainer on suction side and float switches.

3. Presure gauges shall be provided on common suction & discharge header and limit switches on supply header.

4. Transfer water pumps shall be constructed with SS 316L Casing, impellers and Shafts.

5. Pump control panel shall be of IP55 rated.

6. All pump panels shall have control for auto sequencing, fused circuit for each motor, main disconnect switch,

selector switch for each pump, power on indicator light, run/trip indicators.
DOMESTIC WATER TRANSFER PUMP( BASEMENT FLOOR TO ROOF) - B-CREST,JVC
Flow rate & Pipe Sizing
Total tank capacity @ Roof floor = 20,000.00 Imp.Gal
Total tank capacity @ Roof floor = 90.9 M³
Filling time considered = 2.00 Hrs.
Required flow rate = 45.46 M³ / Hr.
= 200 US gpm
= 13 l/s
Pump head calculation
Pressure loss in the pipe & fittings = 4.5 m H₂0
Pressure considered at discharge valve 10.0 m H₂0
Total head = 14.5 m H₂0
Safety factor 20.0 % = 2.9 m H₂0

Static head = 77.0 m H₂0


Total pressure loss with safety = 94.3 m H₂0
9.3 bar

Selected Pump
1 set of transfer pump (1 Duty + 1 Standby) @ 13 l/s, 9.3 bar

Pipe pressure drop calculation

Pipe selected
Ø 100 mm SCH 80 PIPE(4")
Flow rate = 13 l/sec 200.15
Velocity = 5.75 ft/sec
1.8 m/sec
Pipe friction loss = 1.20 psi/100ft
Pipe friction loss = 2.76 ft/100ft Data as per Mcquay Pipe sizer
Pipe length No. of fittings
(M) ELBOW90 TEE GV STR. NRV
Suction (A) 7.0 2 1 2 1 0
Discharge
line+Riser+Roof 86.0 9 1 2 0 1
floor(B+C+D)
Total 93.0 11 2 4 1 1
Total equivalent length
Total Length
Qnty. Eq. Length (ft)
(ft)
Pipe 93.0 305.0 305.04
Fittings
E90 11 12.5 137.50
TEE 2 21.0 42.00
GV 4 2.0 8.00
STR. 1 18.5 18.50
NRV 1 18.5 18.50
Total 529.54 ft

Total length of pipe = 529.5 ft


Pressure loss = 1.2 psi/100ft
Total pressure loss in pipe & fitting = 6.3 psi
= 4.5 m H₂0

You might also like