Professional Documents
Culture Documents
KHAIRUNNISA
PROJECT
Prepared by SHAMIRA BT
ENGINEER
21 JUN 2022
KHAIRUL
Checked by
1.2 Objective
This method statement describes the overall sequence of public works that will be carried out on site.
It also states the materials to be used, equipment, manpower, management, safety and control and
methods and procedures to ensure the work is carried out safely and in accordance with the
requirements of the contract.
This method statement and define the method of Horizontal Directional Drilling (HDD) for laying of
one circuit of 11Kv XLPE Power Cables for Tenaga Nasional Berhad.
1.4.1 Site Survey, Planning and Design the Bore
1.4.2 Drilling Fluid
1.4.3 Drilling Operation
1.4.3.1 Site Preparation
1.4.3.2 Setting Up and Calibration
1.4.3.3 Pilot Drill
1.4.3.4 Pull Back Installation (Stringing of Pipes)
1.4.3.5 Site Cleaning
1.5 Material
1.6 Machineries/Equipment
The major machineries that will be used for this HDD work are as follows:
1.6.1 HDD Machine
1.6.2 Reamer Swivel
1.6.3 Drill Rod
1.6.4 Pipe Jointer
1.6.5 Tracing Equipment/Tools
1.6.6 DiGi Track
MACHINERIES/EQUIPMENT/TOOLS
HDD Machine Reamer Swivel
The supervisor shall be responsible for the operating of the machine in accordance with the method
statement. He shall be responsible for the safety of the site workers.
Staff information Sheet
Please read the entire sheet before beginning, if you have any questions, please contact your Site
Manager.
a) Prior to any site excavation, a survey of the site shall be carried out to determine the
presence (if any) of buried third party cables or services.
b) Warning signs and colour bunting shall be erected at location of overhead power cables.
c) Warning signs (DANGER KEEP AWAY) shall be erected at all sites of excavation.
d) Workers will be equipped with Personnel Protective Equipment (PPE) i.e. safety helmet,
safety boot etc.
e) Pre-start-up safety meeting will be held and recorded by main contractor prior to any work
on site.
f) Regular safety toolbox meetings will be held and recorded.
a) Safety Helmet
b) Gloves
c) Safety boots
d) Safety glasses (where appropriate)
e) Safety masks (due to current pandemic state)
a) Dispose of waste and spoil to the designated area or skip provided for waste.
ERT (TNB)
1. Jurutera Pembinaan Kanan TNB (………………………..)
2. Jurutera Pembinaan TNB (………………………..)
3. Juruteknik TNB (………………………..)
Kontraktor Kabel : Kontraktor HDD : Pelan Pengurusan Trafik
ABC SDN. BHD. SMF ENGINEERING SDN. BHD. XYZ SDN. BHD.
…………………… ABD MALEK BIN AZIT (017-371 ……………………
0058)
- Emergency Response Coordinator (ERC) adalah pegawai yang dilantik sebagai orang
utama untuk membuat keputusan apabila berlaku insiden di tapak kerja
- Pegawai ERC utama dalam projek ini adalah jurutera Pembinaan Kanan TNB dan
pegawai ERC pengganti adalah Jurutera Pembinaan TNB
Nombor-nombor Kecemasan
Jabatan No Telefon
Bomba 05-5474444
Polis 05-2451222
Hospital 05-2085000
EMERGENCY RESPONESE PLAN PROCEDURE
STAFF & WORKER’S NAME’S LIST TEAM 1
BI NAME ID CARD No. NIOSH No. CIDB No. KKT No.
L
MOHAMAD
1 FAJRULASHRAF BIN 910702-05-5413 TNB028620N M81100320100008 HDD 004/2020
MOHD AINI
AMIRUL TAQIYUDDIN
2 AL AMIN BIN 941029-10-6445 TNB063968N 1941029SL1900705987 N/A
ZULKARNAIN
MUHAMMAD ROZLAN
3 BIN HARAP
860624-06-5057 TNB001047N W41210320070007 N/A
NORSUZANDI BIN
6 MAMAT
740906-03-6151 TNB062532N 1740906PH1900575386 HDD 0012/2021
General Precautions
2.0 PPE
All site workers will wear Safety boots, and protective clothing at all times, other items of PPE such
as eye protection and gloves are available to be worn as and when necessary.
3.0 Preparation & Induction
All members of staff required to work on any contract will be given copies of risk assessments and
method statements, any queries or concerns will be raised with the contract manager who will ensure
it is dealt with. Staff will be inducted onto each site by the site or project manager and will follow all
site rules and safety procedures.
7) Two mixing tanks are used for bentonite mixing. One of it acts as a
standby tank while the other one is being discharged.
9) When the drilling fluid at 1st mixing tank is nearly empty, the
discharge valve of the 1st tank will be closed. At the same time, the
discharge valve for the 2nd mixing tank will be opened. By this
practice, continuous consumption of the bentonite can be achieved.
10) Before re-mixing of bentonite into the empty tank, the tank needs
to be cleaned by flushing with water.
1) Site Preparation
a. Drill path will be marked on the ground according to the design
path.
b. A small pit [1.5m length x 1.0m width x 1.0m depth] shall be
dug at the entry and exit point to cater for the cut material and
bentonite fluid. Also, these pits serve to verify that the vicinity
is hazard free from utilities.
c. Adjust the jacks of the rig machine until the receiver shows
that the rig is set at the designed entry degree. The entry
degrees are shown in the designed HDD profiles.
3) Pilot Drill
a. The 1st length of the drill rod guided by the drill head will be
rotated and jacked into the ground without any bending.
Bending will be start during the 2nd rod drilling.
b. When the end of the 1st rod reach the jaw of the machine, one
rod is considered drilled into the ground and the 2nd rod is then
jointed at its end. Bending is start at 2nd rod drilling.
d. If the drill head strays off course, the locator technician shall
inform the drilling operator via two ways radio. The operator
will make the required adjustment until the drill head gets back
to its original course.
e. Drilling will be continued until the drill head exit at the exit pit.
f. Once the Drill Head reached the exit pit, the drill head will be
removed, and a fluid jet reamer is attached and the back
reaming operation is reversed from exit pit towards entry pit.
k. The required final size of the tunnel is at least 1.5 times the
product pipe diameter. This is reducing the friction exerts on
the product pipes during pull back activity
b. The reamer used during pipe installation is to ensure that the hole is
properly enlarged and conditioned in order to reduce the friction
and pulling pressure.
c. A 6” diameter puller eye will be used and jointed at the end of the
6” product pipe (the end which first enters the ground).
d. With proper D-shackles, the puller eye is connected to the tones
swivel. Reamer is installed at the front of swivel.
f. Once the reamer and puller eyes reach to the entry pit, the reamer
and swivel will be dismantled. Puller eyes will be cut out and the
pipes are properly sealed off.
5) Site Cleaning
a. Upon completion of all installation works, the drilling equipment
will be properly packed and ready for demobilization.
b. Site area will then be cleaned from any other dumped and unused
material.
Care of equipment
1) All equipment or tools must be thoroughly cleaned in either water or the relevant solvent at
the end of each shift
2) All items should be stored properly inside proposed storage area. (if any)