METHOD OF STATEMENT HORIZONTAL DIRECTIONAL DRILLING (HDD)

By: Pelita Dinamik Engineering Sdn. Bhd.

Table of Contents

1. Introduction ……………………………………………………………………………… 2

2. Scope of Work ……………………………………………………………………………… 2

3. Reference Drawing ……………………………………………………………………………… 3-6

4. Roles & Responsibilities ……………………………………………………………………………… 7-8


a) Project Manager
b) Safety Supervisor
c) Field Supervisor
d) Worker

5. Resources ……………………………………………………………………………… 8-9

a) Machineries
b) Tools & Equipment
c) Manpower

6. Job Safety Analysis ……………………………………………………………………………… 9-12

1
METHOD OF STATEMENT FOR HORIZONTAL DIRECTIONAL DRILLING (HDD) WORKS
By: Pelita Dinamik Engineering Sdn. Bhd.

i. Introduction

Pelita Dinamik Engineering Sdn. Bhd. is a contractor specializing in:


 Horizontal Directional Drilling (HDD)
 Underground Cable Laying (11kV to 33kV)

We provide reliable underground installations of pipes and conduits for a wide variety of  services,
utilities, & cables.

We maintain plenty of quality equipment, in operation with proper maintenance and support,
including compact equipment for in-city work and heavy-duty pipelines and multiple duct / pipe
installations. 

HDD Installation involves four main steps:


1. Pre-site planning
2. Drilling and pilot hole
3. Expanding the pilot hole by reaming; and
4. Pull back of pre-fabricated pipe

Properly performed, this method of Trenchless Technology has zero settlement to the ground
surface, since there is no excavation displacement is used instead of excavation.

ii. Scope of Work

This method statement covers the method utilized to construct an underground pipeline utilizing
Horizontal Directional Drilling. We are proposing to use HDD (Horizontal Directional Drilling)
equipment. This method statement will apply for the followings:

Project Name :
Project No. :
PO No. :
Client :
Scope : Horizontal Directional Drilling Works (4 ways 225 mm) HDPE PN10 pipe.

2
METHOD OF STATEMENT HORIZONTAL DIRECTIONAL DRILLING (HDD)
By: Pelita Dinamik Engineering Sdn. Bhd.

iii. Reference Drawings

3
METHOD OF STATEMENT FOR HORIZONTAL DIRECTIONAL DRILLING (HDD) WORKS
By: Pelita Dinamik Engineering Sdn. Bhd.

4
METHOD OF STATEMENT FOR HORIZONTAL DIRECTIONAL DRILLING (HDD) WORKS
By: Pelita Dinamik Engineering Sdn. Bhd.

5
METHOD OF STATEMENT HORIZONTAL DIRECTIONAL DRILLING (HDD)
By: Pelita Dinamik Engineering Sdn. Bhd.

HDD PILOT PROFILE

6
METHOD OF STATEMENT HORIZONTAL DIRECTIONAL DRILLING (HDD)
By: Pelita Dinamik Engineering Sdn. Bhd.

iv. Roles & Responsibilities


Every employee is required to play his part in promoting accident prevention
commensurate with his area of responsibility. Therefore, all employees must familiarize
themselves with site safety regulation and comply with them at all times.

1. Project Manager

The Prime responsibility for site safety rests with him.

 He must be fully conversant with all safety requirements in the contract.


 Ensure that all supervisors are aware of and comply with the safety regulations and
accident prevention requirements.
 Institute a system of inspection and correction for potential hazards.
 Hold weekly supervisor’s meeting at which safety problems will be discussed.
 Discuss accident prevention recommendation with the site safety supervisor and initiate
action.
 Ensure an adequate supply of the correct type of personal protective equipment is
available.
 Check continuity of safety training.
 By example, promote and encourage safety awareness in employees at all levels.

2. Safety Supervisor

The Site Safety Supervisor is responsible to the Project Manager for the day-to-day
implementation of the safety program.

 He must be familiar with all the safety requirements in the contract along with the safety
local regulations and applicable safety codes and practices.
 Carryout regular site safety audits and reports, correct unsafe work practices and
potential hazards.
 Investigate and report all accidents including “near miss” incidents and recommend
preventive measures.
 Maintain a record of all injuries and damages on site and submit reports as required.
 Assist with safety training.
 Attend weekly supervisor’s meeting and discuss accident prevention techniques and
safety performance.
 Ensure maintenance of good hygiene standards and availability of first aid treatment.
 Advise field supervision on safe working methods.
 Enforce the observance of the work permit procedures.
 Promote an understanding among the work force that accident prevention is an
indispensable part of any efficient construction activity.

7
METHOD OF STATEMENT FOR HORIZONTAL DIRECTIONAL DRILLING (HDD) WORKS
By: Pelita Dinamik Engineering Sdn. Bhd.

3. Field Supervisor

The effectiveness of the company’s accident prevention effort will largely depend on the
attitude and approach of the field supervisor.

 He must understand and comply with requirements of client’s safety manual and work
permit procedures.
 Organize the work area so that men can perform their duties without maximum risk to themselves
or equipment’s.
 Maintain a good housekeeping.
 Inspect equipment and tools before use and ensure correct storage facilities are available and
properly utilized.
 Enforce the use of applicable personnel protective equipment.
 Correct unsafe conditions immediately as they arise.
 Conduct induction training on weekly safety meetings with work crews.
 Attend weekly supervisor’s meeting.
 Cooperate with site safety supervisor to create and maintain safe workings conditions in all
operations being performed.
 Set a personal example.

4. Workers

The workmen, also has responsibilities for accident prevention, for not even the best
supervisor can watch over each man every minute of the working day.

  Use correct tools and personal protective equipment provided.


  Obey safety rules and do not damage or removed safety devices.

v. Resources

Materials

1. HDPE Red Pipe PN10 150mm


2. HDPE Red Pipe PN10 200mm

Tools & Equipment

Type Quantity
HDD Machine 2
Crane Truck 2
Excavator 4
Electromagnetic Locator 1
Transmitter 2
Pipe Jointer Set 2
Generator Set 3
Water Pump 2
Mag 6 Big Sonde 1
Mag 6 Small Sonde 1
Cable Winch 2

8
METHOD OF STATEMENT FOR HORIZONTAL DIRECTIONAL DRILLING (HDD) WORKS
By: Pelita Dinamik Engineering Sdn. Bhd.

Safety Equipment -

Manpower

Role Quantity
Supervisor 1
Machine Operator 1
Tracker Operator / Locator  1
Pipe Jointer / Welder 1
Bentonite Mixer  1
Helper 1

vi. Job Safety Analysis

WORK DESCRIPTION POTENTIAL HAZARDS PREVENTION MEASURES


1. Mobilization Unsecured load, Items falling Ensure everything is secure,
from vehicles. inspection by driver before leaving.

Vehicle moving/shifting while Check height & weight restrictions.


being loaded. Check brakes chock wheels

Forgetting safety supplies Ensure proper road signs, cones,


while loading vests, fire extinguisher, First Aid Kits
and other materials are loaded.

Undersized equipment for Ensure equipment is sized to safely


weight to be lifted. lift the required loads.

2. Traffic Control Work area not properly Ensure there is adequate advance
identified with Traffic Control signage, flaggers, cones, flashers &
Devices. strobes as required.

Trucks & workers getting hit by Pull off roadway as far as safely
other vehicles in traffic control possible. Use Caution Entering &
zone. Exiting vehicles.

Excessive Noise from High Wear Hearing Protection If Working


Traffic Volume Adjacent to Noisy Traffic, Especially
For
Extended Periods of Time.

9
METHOD OF STATEMENT FOR HORIZONTAL DIRECTIONAL DRILLING (HDD) WORKS
By: Pelita Dinamik Engineering Sdn. Bhd.

3.Exavation/Trenching Obstructions to trenching path Thoroughly inspect equipment before


such as tree stumps, use. Make sure all safety devices
abandoned concrete, metal and guards are intact & operable.
etc.

Damaging buried utilities Ensure locates are in place and


current. Check terrain for excavation
that may have been missed. Check
for private buried lines that would not
be identified through the locate.

Excavating Around Energized Use Extreme Caution Around


Cables Existing Utilities, Always Use a
Lookout! While Hand Digging Around
Energized Cables Use Caution,
Wear FR Clothing, "Hot Boots" And
Appropriate Rubber Goods for The
Voltage Involved. Always Have a
Partner Standing by.
Toxic Material In Ground Be Aware of Unusual Odors and
Ground Color While Excavating 

4. HDD Works Damaging Existing Utilities Use safe and appropriate potholing
techniques to the planned drill path's
depth to expose any hidden
underground utilities.

Mud Spillage Stop work for a moment, clean mud


spillage using water pump & make
sure no mud spillage then continue
work.
Dirty Site Environment Always make sure the site is clean
and throw all the rubbish in a work
area.
5. Unloading Excavating Equipment Sliding Off Trailer, Check Wheels, Set Brake and Park
Equipment
Trailer Moving While on a Firm & Level Surface While
Unloading Unloading. 
6. Operating Excavating Equipment Tipping Over, Check The Angle Limits of the
Equipment
Overloading Equipment & Operate Well Below
Them. Know The Limits of the

10
METHOD OF STATEMENT FOR HORIZONTAL DIRECTIONAL DRILLING (HDD) WORKS
By: Pelita Dinamik Engineering Sdn. Bhd.

Machinery and Operate Well Within


Them. Call For A Backhoe Or Other
Equipment If In Doubt 
Struck by Or Caught in Watch for Swinging Buckets, Stay
Equipment Clear of Trenching Blades, Make
Sure the Operator Is Aware of Your
Presence If On the Ground
7. Pulling Cable Pulling Sock Coming Loose Always Use Banding To Secure
from Cable  Pulling Socks To Cable 

Cable exposed to watery area Make sure the digging area is dry
and if the area is watery, use a water
pump to dry the area.
8. Cable Installation In Trench Trench Wall Collapse While Installing Cable in Trench
Trench
While Standing At Edge  Lines, Enter The Trench. Do Not
Install From The Edge
9. Cable Installation Installing Cable In Energized Use Extreme Caution. Always Have
("Hot") Pedestals, Switchgear, Another Qualified Person at The
Transformers  Location. Tape The Ends Before
Installation And Secure The Cable,
Don't Leave A Dangerous Situation 
Mixing Phases  Phase All Cable Before Installation

Leaving Tools or Material at Review the Work Area to Ensure


Work Site Everything Is Accounted
10. Testing & Grounding Grounding Accidental Contact Test & Ground All Equipment Before
with Energized Parts  Performing Any Tasks. Spike All
Conductors Before Cutting Using a
Shotgun, FR Clothing, Safety
Glasses & Face Shield 
11. Jointing Wrong Phasing Always make sure the cables are
marking correctly before jointing.
Defect on Joints Always make sure joints are in a
good condition before start jointing. If
there is a defect on joints, cut off the
joints & re joint the cables.
12. Termination Works Accidental Contact with Rubber up Energized Equipment If
Energized Parts  Terminating or Working in Close
Proximity to Other Energized Parts.
Rubber Gloves Must Be Worn While
Terminating Secondary, Overhead

11
METHOD OF STATEMENT FOR HORIZONTAL DIRECTIONAL DRILLING (HDD) WORKS
By: Pelita Dinamik Engineering Sdn. Bhd.

and URD
Mixing Phases- Flash or Phase All Cable Before Terminating 
Outage 
Sharp Edges or Corners  Wear Leather Gloves While
Terminating 
Damage to Conductors Being Ensure Proper Tools Are Used to
Terminated Avoid Damaging the Conductors 
13. Final Testing Grounds Still on When Testing Ensure Grounds Are All Removed
Before Testing
Forgetting to Test A Cable Double Check to Ensure All Cables
Before Energizing  Have Been Tested Before Placing
into Service
Testing Equipment Not Verify Testing Equipment Is in
Working Properly  Working Order at Each Switch Point,
Equipment Must Be Clean, Within
Test Dates and Functional
Mixing Phases  Check Phasing (Hot Phase/Bottle)
Before Energizing
Stray Voltages and Neutral Be Aware of The Possibility of Such
Imbalances Conditions and Test