DESIGN, SUPPLY, INSTALLATION AND COMMISSIONING OF FIRE ALARM SYSTEM

JOB SAFETY ANALYSIS

Document. No. Unit Project Number Date: Page No. Rev No

SCSP-OP_PRJ-PRC_JSA OP 26/05/17 Page 1 of 5 D01

JOB/ACTIVITY: INSTALLATION, TESTING AND COMMISIONING OF FIRE ALARM SYSTEM DATE: 2605/17
TASK: INSTALLATION, TESTING AND COMMISIONING OF FIRE ALARM SYSTEM JHA REVIEW TEAM COMPOSITION: EMMANUEL AKEMU- HSE LEAD,SCSP; CLEMENT OLAWU
PROJECT COORDINATOR,SCSP; GOLD-SITE SUPEVISOR/PROJECT ENGR, SCSP.
Task steps Hazard/hazard Threat Top event/ Consequences Who or what Inh. Barrier/control Recovery Action
Source Hazard aspect (HSE effect/ may be Risk (Legal ref. And (contingency Responsible
impact) Harmed procedure training plan) ref and Party
procedure
1. Site 1- Manual 1.1-Carelessnss/ -INJURY -PERSONNEL P2A C-1.1.1-Adhere to work R1-FISRT AID CONTROLS
mobilization – material horse play -Cut / Bruises procedures and R2-MEDEVAC Gold-Site superv
materials & handling JHA’s/adequate
personnel 1.2-Poor material supervision/ work Emmanuel Ak
Handling. carefully/ No horse play HSE Officer

1.3-sharp edges/ C-1.1.2-Proper handling R1 To R2


PPE violation. of materials. Emmanuel Akem
Site
C-1.1.3- Use Coverall,
Safety shoe, knit hand
gloves, Hard hat.
2-Sharp Object 2.1-Incompetent -Cut / Bruises -MINOR INJURY -PERSONNEL P1C C-1.2.1-Competent R1-FISRT AID CONTROLS
personnel person R2-MEDEVAC Gold-Site superv

2.2-Carelesness C-1.2.2-Carefuness Emmanuel Ak


HSE Officer
2.3-PPE Violation C-1.2.3-Use Coverall,
Safety shoe, Leather R1 To R2
hand gloves, nose Emmanuel Akem
mask, eye goggle and Site
Hard hat
3-Road 3.1 – Incompetent -Accident -MAJOR/ -PERSONNEL P2A C-1.3.1-Use of R1-FISRT AID CONTROLS
transportation driver (damage to asset, - ASSET competent and fit R2-MEDEVAC Gold-Site superv
DESIGN, SUPPLY, INSTALLATION AND COMMISSIONING OF FIRE ALARM SYSTEM

JOB SAFETY ANALYSIS

Document. No. Unit Project Number Date: Page No. Rev No

SCSP-OP_PRJ-PRC_JSA OP 26/05/17 Page 2 of 5 D01

JOB/ACTIVITY: INSTALLATION, TESTING AND COMMISIONING OF FIRE ALARM SYSTEM DATE: 2605/17
TASK: INSTALLATION, TESTING AND COMMISIONING OF FIRE ALARM SYSTEM JHA REVIEW TEAM COMPOSITION: EMMANUEL AKEMU- HSE LEAD,SCSP; CLEMENT OLAWU
PROJECT COORDINATOR,SCSP; GOLD-SITE SUPEVISOR/PROJECT ENGR, SCSP.
injury, loss of MINOR INJURY driver
3.2 – Poor visibility lives. Emmanuel Ak
and bad road ASSET DAMAGE C-1.3.2-Use of vehicle HSE Officer
condition in good condition
R1 To R2
3.3 – Faulty and ill C-1.3.3-Strict Emmanuel Akem
managed vehicle. adherence to driving Site
rules and regulation

4-Tripping 4.1-Poor -Trip/fall of -INJURY -PERSONNEL P1A C-1.4.1-Conduct proper R1-FISRT AID CONTROLS
Objects housekeeping personnel housekeeping R2-MEDEVAC Gold-Site superv

4.2-Carelessness C-1.4.2-Carefulness Emmanuel Ak


HSE Officer
4.3-PPE Violation C-1.4.3- Use Coverall,
Safety shoe, Leather R1 To R2
hand gloves and Hard Emmanuel Akem
hat Site

2. Concrete 1-Weight of 1.1-Poor Lifting -Back Sprain -ILL HEALTH -PERSONNEL P2A C-2.1.1-Apply proper R1-FIRST AID CONTROLS
Mixing Materials Technique lifting technique Gold-Site superv
-Fall of personnel R2-MEDIVAC
2- Contact with 1.2-Horseplay/ Use C-2.1.2-Adhere to safe Emmanuel Ak
Skin of mobile phone. work practice. HSE Officer

1.3-Incompetent C-2.1.3-Competent and R1 To R2


3- Contact with personnel/Poor fit to work Emmanuel Akem
eyes material Handling. personnel/Proper Site
handling of materials
1.4-PPE Violation
DESIGN, SUPPLY, INSTALLATION AND COMMISSIONING OF FIRE ALARM SYSTEM

JOB SAFETY ANALYSIS

Document. No. Unit Project Number Date: Page No. Rev No

SCSP-OP_PRJ-PRC_JSA OP 26/05/17 Page 3 of 5 D01

JOB/ACTIVITY: INSTALLATION, TESTING AND COMMISIONING OF FIRE ALARM SYSTEM DATE: 2605/17
TASK: INSTALLATION, TESTING AND COMMISIONING OF FIRE ALARM SYSTEM JHA REVIEW TEAM COMPOSITION: EMMANUEL AKEMU- HSE LEAD,SCSP; CLEMENT OLAWU
PROJECT COORDINATOR,SCSP; GOLD-SITE SUPEVISOR/PROJECT ENGR, SCSP.
C-2.1.4-Use Coverall,
Safety shoe, knit hand
gloves, Hard hat
2-Adverse 2.1 Rain. -Drench -ILL HEALTH -PERSONNEL P1C C-2.2.1- Do not work R1-FISRT AID CONTROLS
Weather personnel under rain. Gold-Site superv
Condition. 2.2 Intense Heat R2-MEDEVAC
from sun. -Fatigue/ C-2.2.2-Rest and take Emmanuel Ak
Dehydration water at intervals HSE Officer
2.3 Slippery
surfaces -Fall of personnel C-2.2.3-Use rain boot, R1 To R2
coverall, hard hat and Emmanuel Akem
hand gloves. Site

3. Sharp Edges 3.1-PPE Violation -Cut/bruises -INJURY -PERSONNEL P2C C-2.3.1-Use Coverall, R1-FIRST AID CONTROLS
Safety shoe, Leather R2-MEDIVAC Gold-Site superv
3.2Horse play/Use hand gloves & Hard hat
of cell phone Emmanuel Ak
C-2.3.2-Avoid horse HSE Officer
play/mobile phone
R1 To R2
Emmanuel Akem
Site Chinda Pre
Site
5-Working with 5.1- Defective -Hearing losses Minor & Major -PERSONNEL P1C C-2.5.1-use ear muffs R1-FISRT AID CONTROLS
power tools ( equipment injury R2-MEDEVAC Gold-Site superv
Drill, grinding, -Eye injury C-2.5.2- No horse play/
pipe cutting 5.2-Electricity use of mobile phone Emmanuel Ak
machine ) -Crushing HSE Officer
5.3-Iimproper C-2.5.3- Use Coverall,
use of -Back injury Safety shoe, knit hand R1 To R2
equipment gloves, Hard hat, Emmanuel Akem
DESIGN, SUPPLY, INSTALLATION AND COMMISSIONING OF FIRE ALARM SYSTEM

JOB SAFETY ANALYSIS

Document. No. Unit Project Number Date: Page No. Rev No

SCSP-OP_PRJ-PRC_JSA OP 26/05/17 Page 4 of 5 D01

JOB/ACTIVITY: INSTALLATION, TESTING AND COMMISIONING OF FIRE ALARM SYSTEM DATE: 2605/17
TASK: INSTALLATION, TESTING AND COMMISIONING OF FIRE ALARM SYSTEM JHA REVIEW TEAM COMPOSITION: EMMANUEL AKEMU- HSE LEAD,SCSP; CLEMENT OLAWU
PROJECT COORDINATOR,SCSP; GOLD-SITE SUPEVISOR/PROJECT ENGR, SCSP.
-Burns googles Site
5.4-Poor
maintenance -Electrocution

5.5-Untrained
workers

5.6Flying object

3- Installation- 1-Working with 3.1- Defective -Hearing losses Minor & Major -PERSONNEL P1C C-3.1.1-use ear muffs R1-FIRST AID CONTROLS
Drilling, electricity equipment injury R2-MEDIVAC Gold-Site superv
-Eye injury C-3.1.2- No horse play/
2- Working with 3.2-Electricity use of mobile phone Emmanuel Ak
power tools -Crushing HSE Officer
3.3-Iimproper C-3.1.3- Use Coverall,
use of -Back injury Safety shoe, knit hand R1 To R2
equipment gloves, Hard hat, Emmanuel Akem
-Burns googles Site
3.4-Poor
maintenance -Electrocution C-3.1.4- Lock out tag
out ( LOTO) procedure
3.5-Untrained to be followed during
workers testing &
commissioning.
3.6Flying object
C-3.1.5- Only those
persons who have been
adequately trained and
certified in the work of
electricity to allow for
the same.
DESIGN, SUPPLY, INSTALLATION AND COMMISSIONING OF FIRE ALARM SYSTEM

JOB SAFETY ANALYSIS

Document. No. Unit Project Number Date: Page No. Rev No

SCSP-OP_PRJ-PRC_JSA OP 26/05/17 Page 5 of 5 D01

JOB/ACTIVITY: INSTALLATION, TESTING AND COMMISIONING OF FIRE ALARM SYSTEM DATE: 2605/17
TASK: INSTALLATION, TESTING AND COMMISIONING OF FIRE ALARM SYSTEM JHA REVIEW TEAM COMPOSITION: EMMANUEL AKEMU- HSE LEAD,SCSP; CLEMENT OLAWU
PROJECT COORDINATOR,SCSP; GOLD-SITE SUPEVISOR/PROJECT ENGR, SCSP.

4- Others 1-Choking & 1.1-Unauthorized, -Minor & Major -PERSONNEL P1C C-4.1.1-Proper R1-FIRST AID CONTROLS
Suffocation untrained workers -Skin injury injury materials handling R2-MEDIVAC Gold-Site superv

1.2-Spillage -Ingestion C-4.1.2- Use Coverall, Emmanuel Ak


Safety shoe, Leather HSE Officer
1.3-Poor -Eye injury hand gloves and Hard
ventilation hat R1 To R2
-Environment Emmanuel Akem
1.4-Fire affect Site

-Property damage
1.5-Health hazards
( External / -Occupational
Internal ) health
2-Adverse 2.1 Rain. -Drench -ILL HEALTH -PERSONNEL P1B C-4.2.1- Do not work R1-FISRT AID CONTROLS
Weather personnel under rain. R2-MEDEVAC Gold-Site superv
Condition.
2.2 Intense Heat -Fatigue/ C-4.2.2-Rest and take Emmanuel Ak
from sun. Dehydration water at intervals HSE Officer

2.3 Slippery -Fall of personnel C-4.2.3-Use rain boot, R1 To R2


surfaces coverall, hard hat and Emmanuel Akem
hand gloves. Site