Daily summary sheet Document 1101

Project name Taza Revision 04


Site Nador / Morocco Approved by RE
Vessel Stacking area /dirt-dust assessment Revision date 24.09.2020

.Project information:
Location/port: Nador / Morocco
Operation date: 24.09.2021
Operation commenced: 07:30
Operation completed: 11:00
Surveyor(s): Cpt Liviu gheorghita/ E/O Amine Dasser / C/O Monir elazouane
Work scope: MWS for dirt dust affecting the discharged cargo in the stacking area

Project description:
Cargo handled: 75 Blades-108 Towers-27 Nacelles-27 Hubs
Container seals: N/A
Discrepancies/damages
Item & Item no.: Damage: Picture
1. Stacking area one Trace of dirty footsteps /dust, small drops of
60 blades grease from the cranes wires while
discharging in stacking area.
washable

Page 1 of 9
Daily summary sheet Document 1101
Project name Taza Revision 04
Site Nador / Morocco Approved by RE
Vessel Stacking area /dirt-dust assessment Revision date 24.09.2020

Page 2 of 9
Daily summary sheet Document 1101
Project name Taza Revision 04
Site Nador / Morocco Approved by RE
Vessel Stacking area /dirt-dust assessment Revision date 24.09.2020

2. Stacking area 2, Trace of dirty footsteps /dust, small drops of


15 blades grease from the cranes wires while
discharging in stacking area.
washable

Page 3 of 9
Daily summary sheet Document 1101
Project name Taza Revision 04
Site Nador / Morocco Approved by RE
Vessel Stacking area /dirt-dust assessment Revision date 24.09.2020

3. Stacking area dirt and dust on top of the towers, few drops
3,108 towers of grease from the cranes wires while
discharging in stacking area.
washable

Page 4 of 9
Daily summary sheet Document 1101
Project name Taza Revision 04
Site Nador / Morocco Approved by RE
Vessel Stacking area /dirt-dust assessment Revision date 24.09.2020

Page 5 of 9
Daily summary sheet Document 1101
Project name Taza Revision 04
Site Nador / Morocco Approved by RE
Vessel Stacking area /dirt-dust assessment Revision date 24.09.2020

4. Stacking area 4, All covered with tarpaulin, tarpaulin was dirty


27 Nacelles and covered by black dust from coal terminal .
washable

Page 6 of 9
Daily summary sheet Document 1101
Project name Taza Revision 04
Site Nador / Morocco Approved by RE
Vessel Stacking area /dirt-dust assessment Revision date 24.09.2020

5. Stacking area 4, All covered on top with tarpaulin. Dusty dirty


27 hubs –washable

Page 7 of 9
Daily summary sheet Document 1101
Project name Taza Revision 04
Site Nador / Morocco Approved by RE
Vessel Stacking area /dirt-dust assessment Revision date 24.09.2020

Page 8 of 9
Daily summary sheet Document 1101
Project name Taza Revision 04
Site Nador / Morocco Approved by RE
Vessel Stacking area /dirt-dust assessment Revision date 24.09.2020

Page 9 of 9