DAILY ACTIVITES
Sheet : 1
Date : 4-Nov-19
To : Daniel Kim Soon TR. No :
Ref. No :
Cc: Ahmad Thameem
0800H Rocks offloaded at site .Soil loading work stopped by Coast Guard For Review
1000H wheel loader mechanic arrived at site.and started fixing the tyre
1100H whee loader fixed and started filling up the hole as advised by coast guard.
1300H 800 LC excavator excavating and digging up soil from the sea and increasing the length of Access road.
1400H Received Permanent ID for mechanic.Diesel tanker refueling from outside pump
Coast guard inspected the area and were satisfied.Diesel refueling in the equipment.Excavator 420 LC
1600H
with breaker came inside the fence at site area
Breaker loaded on trailor from doosan yard.Excavators are working on access road.Hole is totally
1700H
covered.Prepared the safety documents
Tower lights turned on 800 LC excavators are working.on both sides of access road and excavating the
1800H
area .
1830H Offloading the breaker and attached it with ecavator.Excavator leveled the access road .
1900H Closing the work activities and moving the manpoer back to the camp.
Manpower