PLANT
Project manager
PO#
Supplier/Vendor/Contractor- SRG
Project Manager
3rd Party
Sr. No. Project Management and Requirements
Pre-bidding
1 Site Visit
2 Measurement of corroded cement lined spools
3 Prepare BOM
4 Study and verification of Isometric drawings as per site visit
Planning/ Post-PO
1 Procuring of Piping Material as per requirement
2 Prepare and submit elaborate procedure for pipe fabrication, cement lining, installation and ITP.
3 Pre-fabrication of pipe spools
4 Fabricate new cemented spool
5 Prepare and submit Safety plan, TRA and Rescue plan.
7
Preparation
1 Welding of pipe spool as per approved WPS and PQR
2 Cement lining of Pipe spools using Sulphate resistant Type V Cement (AWWA C205)
3 Sand Blasting and applying one coat of primer.
4 Assign POC personnel from end-user side to witness inspection/ repairs/ tests done by contractor
5 Blinding, Isolation and de-energizing of the pipeline.
Execution
1 Delivery of pipe spools to Kemya job site
2 Preparation of the area for hot work
3 Erection of scaffolding for pipe spool installation
4 Cutting and removal corroded cement-lined pipe at site
5 Edge preparation of cut end by grinder
6 Fit-up of pipe spools by sleeve method and applying pipe-joining compound.
7 Rigging work
8
Closing
1 Welding of sleeve with pipe spool.
2 Touch up painting on new weld joints
3 Housekeeping and site handover.
4 De-mobilization of manpower
5 De-blinding of pipeline system
6 Prepare Mechanical completion certificate and submit for signature