2015 International Conference on Computer Science and Applications

The Application of PDCA Cycle Management in Project Management

Ning Ling
Meng-meng Ren
Department of Industrial Engineering
Department of Industrial Engineering
Nanjing Tech University
Nanjing Tech University
Nanjing 210009, China
Nanjing 210009, China
e-mail: 758062063@qq.com
e-mail: rmp0511@sina.com

Xia Wei Shu-hai Fan


Department of Industrial Engineering, Department of Industrial Engineering,
Nanjing Tech University Nanjing Tech University
Nanjing 210009, China Nanjing 210009, China
e-mail: eva.weixia@outlook.com e-mail: fan@njut.edu.cn

Abstract—Two important stages of project management are beforehand control and dynamic control. Management plan
decision-making stage and implementation stage. In the is in line with the reality, whether the goal plan has a
decision-making stage of the project, the main task of dynamic feature, how to ensure the effect so that the
management is to target planning and target demonstration. management reached or infinite close to optimal value, all
In the implementation stage of the project, the core task of the the problems need to be solved. The PDCA cycle through
project management is the target control. Due to long-term the layers of circulation, make the management plan at or
and complexity in the implementation of the project, the goal near an infinite value. So, the PDCA cycle management in
of project management control to the dynamic control, the engineering of all kinds of management is indispensable,
dynamic control principle is the core principle of project research of the application of PDCA cycle in engineering
target control. PDCA cycle management, as a dynamic control management is also very necessary.
principle and application of a typical representative of the The purpose of this study is to systematically introducing
method, has been widely used in engineering project
PDCA cycle, and the PDCA cycle in project schedule
management at home and abroad, its effectiveness also for the
management, quality management and engineering cost
industry greatly respected. This article detailed discusses the
PDCA cycle management in engineering project construction management in operation mode.
schedule management, quality management, cost management II. PDCA CYCLE IN PROJECT SCHEDULE MANAGEMENT
application specific ways, to the PDCA circulation in the
popularization and application of the guidance to help. A. Project Schedule
Keywords-PDCA cycle; engineering; management quality; The main steps of the project preparation schedule:
progress; cost Collect compilation basis:
a) Determine the unit project schedule control
I. INTRODUCTION b) Objective to determine the construction sequence
PDCA cycle is known as the Deming circle, and it is and construction project
proposed by Shewhat, the father of statistical quality control. c) Calculation of quantities
PDCA cycle is evolved by the PDS. Operation of d) Paraphrase the construction quota
management activities cannot leave the management cycle e) Calculate the amount of labor or machinery
of rotation. To improve and solve the quality problem and f) Determine the duration of the construction
catch up with the advanced level of each work all need to project
apply the scientific application of PDCA cycle. The PDCA g) Determine the overlapping relationship
circulation method is applied to the engineering project h) Preparation of the initial program schedule.
management, it will play an active role in improving the When the schedule is satisfied, preparing the schedule of
level of project management and promoting the scientific formal preparation and explanation, Risk analysis unit
and standardization of the project management [1]. project construction schedule and to develop control
First of all, control engineering project management measures, then submitted for review.
based on project goals. The core principles of the target The main method of preparing the project schedule:
control is the dynamic control principle. Practice proves that Gantt Chart Method Gantt diagram method is an
the PDCA cycle is effective dynamic control principle. intuitive method of schedule. With map, appearances
Secondly, in the process of engineering project management, combined formed the starting time of the project activities,
the management goal is to advocate active control, end time and duration [2].

978-1-4799-9961-3/15 $31.00 © 2015 IEEE 267


268
DOI 10.1109/CSA.2015.84

Authorized licensed use limited to: b-on: UNIVERSIDADE DO MINHO. Downloaded on January 08,2022 at 17:42:36 UTC from IEEE Xplore. Restrictions apply.
Network Diagram Method By calculating the C. Actual Schedule Check The Processing Of The Results
parameters of the network time, it can clearly be seen that To deal with the results of the actual schedule check,
the earliest and latest start time working hours of the work general progress check result by project leaders or
and the corresponding end time, total float and free float; collaboration with relevant management personnel written
You can define the critical path work composed by a key; progress control report on time, can also according to the
You can see which work must be completed on schedule, time interval, meadow, week (month) report writing. After
which allows maneuvering time work; You can optimize checking the schedule shall prepare a progress report on the
and compare the planned programs (See FIG. 1). following [4]:
B. Inspection of project progress a˅A comprehensive description of the progress of
implementation.
Construction Project Schedule Inspection Process:
a) Survey: Use Daily progress reports, Report job b˅The actual and planned progress of comparative
status, Site field inspection and other methods to on the information.
whole construction process of tracking and monitoring, c˅Analysis of implementation issues and reasons
collecting information. schedule.
d˅Impact on the progress of implementation, such as
quality, safety and cost.
e˅Measures and projections for the future schedule.
f˅Need to adjust schedule when necessary.
Progress report can be compiled separately according to
the above content, can also be a merger with quality, cost,
safety, and other reports to write, put forward the
comprehensive progress report.
D. The Basic Method To Solve The Problem Of Schedule
Delays
Delays in the progress that has been generated generally
have the following basic methods:
a˅Take active measures to work, in order to make up
for the delay of has been done. Has a complete project
should be finish as soon as possible, for not completing a
FIG. 1 with a network diagram of schedule project or a half late should timely adjust plan modification
b) Clear up: The survey data into finishing the progress, and modify the network plan.
construction schedule and comparable data will reflect the b˅Do not take special measures, based on the current
actual construction schedule. state of progress, still arrange late work in accordance with
c) Comparative analysis: Use S-curve method, Banana the original plan. However, under normal circumstances,
Curve and other check the contrast methods to compare the the impact of the delay will be more and more, sometimes
actual progress and planned progress, combine graphics only the start of a week or two delay, the final outcome will
and contrast analysis, find out the problems existing in the lead to a year delay.
progress, finally, suit the remedy to the case and be solved.
III. THE APPLICATION OF PDCA CYCLE IN THE PROJECT
Inspection of the project schedule
QUALITY MANAGEMENT
Gantt Chart Checks Comparative Law: The
advantages is simple, intuitive and easy to grasp the image, A. The Quality Of The Project Plan
But it is based Gantt Chart Program, the logical relationship
The main content
between each work is not obvious, Critical work and critical
path cannot be visually manifested, While some progress a˅Basis of compilation: Refers to the quality manual
varies, it is difficult to predict the impact on the entire and quality system procedures provided by the method,
duration of follow-up and cannot determine the adjustment quality objectives, guidelines, etc.
program [3]. b˅Project profile: Quality planning is a series of
S-curve Comparison Method: S-curve in the figure the documents rather than separate documents
abscissa represents the time schedule, the ordinate represents c˅Construction quality target: To pursue the purpose of
the accumulated amount to complete the task, eventually quality, the goal must be clear to all departments and all the
forming a cumulative time to complete the task as planned members of the project ,in order to facilitate inspection;
amount of graphics. Usually, Progress Control staff before d˅Organization and the practical application of the
implementation of the scheme drawn first S-shaped curve, process steps in organization.
with the implementation of the project, in accordance with e˅The quality control and management of the system
the actual situation and plans to complete the task S-curve description, and to determine the key processes and special
check drawn on the same sheet of drawings can be drawn processes and operations
from the actual progress of S-shaped curve. Engineering Quality Planning Process

269
268

Authorized licensed use limited to: b-on: UNIVERSIDADE DO MINHO. Downloaded on January 08,2022 at 17:42:36 UTC from IEEE Xplore. Restrictions apply.
a˅To formulate and decompose the quality management Quality Control In The Process Of Completion and
objectives; Acceptance
b˅start up; ķ Check the performance of the contract, promote the
c˅general equilibrium; construction project put into production and delivery in time,
d˅Under development plan: The quality plan shall be report investment benefit in time;
directly or by reference to the appropriate form of a ĸ Summarizes the lessons and experiences of the
document or other documents Explains how to implement construction for future construction. Quality control in the
the required construction activity, when a request is not process of completion and acceptance mainly contains
consistent with the quality management system of the preparation of the finishing touches and completion dataǃ
enterprise to adjust and approve the deal. preliminary acceptance of the completion acceptanceǃthe
B. The Implementation Of The Project Quality Plan completion acceptance and review of the project quality etc..
Quality management should the division of quality D. Main Work In The Process Of The Project Quality
control process, and should be in accordance with the Completion Inspection And Acceptance
provisions of the saving control record; When quality Generally, the completion inspection and acceptance of
problem or accident, should be timely analysis the quality or work can be divided into two steps: firstly, self-inspection
the cause of the accident, then distinguish and rectify; by the construction unit; secondly, formal acceptance.
Technical personnel should regularly organize a qualified Mutual acceptances include construction units, building
prosecutors and the quality of internal quality auditors to units and monitoring units. After the acceptance inspection,
verify the implementation of the quality plan effect; The the project can be handed over to the engineering
emergence of non-compliance and quality issues, technical construction unit officially.
personnel should take timely measures to solve, if the
ķSelf-inspection of the completion. The standard of
problem recurs or solve, those responsible should be held
accountable in accordance with the provisions of, and self-inspection should be the same as the standard of formal
punishment according to verify the results of the evaluation. acceptance. The main basis includes whether the project
completion is in line with the construction drawings and
C. The Engineering Quality Control meet the use of design requirements; whether the quality of
The quality control of construction preparation stage the project is in compliance with the standards and
from the contractor's point of view, the quality control of requirements prescribed by the national and local
construction preparation work mainly includes the following government; whether the project reach the requirements of
content: the contract and standards, etc.
a˅The qualification of subcontractors. ĸ The recheck. On the basis of the self-inspection,
b˅Check this unit of the quality management system completely repairs the problems found out during the
and the establishment of project quality management system. self-inspection, through the recheck, solves the remain
c˅Construction project management planning problems, prepares for the formal acceptance.
(construction organization design) review. Ĺ Formal acceptance.
d˅Construction layout, equipment configuration and E. Review Of The Project Quality
control.
Return is contractor project normal function and in the
e˅Design Details and drawings mixed control.
work plan, procedures and the working content of the quality
f˅Construction site management environment, check system. Through the review to understand the user opinion
the technical environment. of project quality after project completion delivery; to
g˅Construction management, review of qualified promote the contractor to improve engineering quality
workers and the quality of education and training. management, to provide customers with high quality
h˅Review of construction Readiness Review and start services. The quality problems that be met in the review
conditions [5]. should be solved according to the promise of quality
The Quality Control In The Process Of Construction guarantee in time.
• Technical clarification Generally, the construction unit of leadership should
• Measurement control conduct the review through organizing technologist in the
• Material control production, technology, quality, water and electricity (may
• Machinery and equipment control include contract and budget) of aspect. When meet the
• Measurement control Measuring work under quality problem that hard to solve, the construction unit
construction contain feeding measurement and should invite relevant experts. The review must be serious,
monitoring measurement when the construction and should be recorded. Shouldn’t take the review as a form
conducting ǃ and test ǃ inspection ǃ analysis of or go through the motions.
measurement of the project, product, and process etc.
• Process control
• Special and key process control
• Engineering change control [6].

270
269

Authorized licensed use limited to: b-on: UNIVERSIDADE DO MINHO. Downloaded on January 08,2022 at 17:42:36 UTC from IEEE Xplore. Restrictions apply.
IV. PDCA CYCLE IN ENGINEERING COST MANAGEMENT
A. Project Cost Plan

Prepare the formal cost


Collect and organize information

A P

C D Determine the target

Preparation of cost plan draft Decomposition and implementation of


Preparation of cost plan draft target cost responsibility plan

Fig.2 Cost planning program under PDCA circle


Project Cost Prediction: Cost prediction is based on
cost information and the specific situation of the cost planning The inspection standard
construction project, using a special method, cost level and
its possible development trend of the future make scientific
estimate, it is to the estimate of the cost before construction. The construction process
Through cost forecast, under the premise of meet the
requirements of the owner and the enterprise, choose low
cost and good benefit best practices, strengthen cost control, The cost of forming
to overcome the blindness and improve predictability [7]. Take measures
Now we have two kinds of commonly used cost prediction
method: qualitative method and quantitative prediction Compared with the cost plan
method. Qualitative prediction method mainly includes The analysis reason
expert meeting method, Delphi method, the subjective
probability method and survey method, etc. Quantitative Yes or No
prediction method (statistical forecast method) generally
divided into time series forecasting method and regression
forecast method. The cost target
The preparation of project cost plan: The cost plan of the
establishment of project cost plan is very important, it is not Fig3. The cost control process
only a few pieces of the schedule, more important is the cost
scheme is selected. Technically feasible and economically C. The construction project cost control measures
reasonable and achieve the optimal plan has always been the a˅ set up the accounting system for project cost center;
goal of cost planning. In general, large and medium-sized b˅ of the actual cost data;
projects generally. Use hierarchical way, small projects c˅"three is" tracking analysis: in order to timely, accur
centralized general establishment. Either way, the program ately and effectively, "three is" trace analysis should be divi
also follows PDCA cycle, the preparation on cost planning ded according to the division, disciplines content and cost fa
for the PDCA cycle in the following (as shown in figure 2). ctors "three is" analysis project, first drawn up separately ac
cording to the cost factors, and then summary partial compr
B. The Basic Method Of Engineering Cost Check
ehensive cost. Contract cost budget, construction budget, the
Engineering cost control is to accounting and monitoring relationship between the actual budget cost can be expresse
of project capital spending, cost control is a part of cost d in figure 4.
management. Cost control work is carried out on the basis of
cost control plan, it is according to the actual cost of each
work need and plan cost comparison, evaluate the cost, and
to forecast the unfinished project, cost control within the
scope of budget work [8].
Project Cost Control Process
The general cost control program is shown in figure 3.

271
270

Authorized licensed use limited to: b-on: UNIVERSIDADE DO MINHO. Downloaded on January 08,2022 at 17:42:36 UTC from IEEE Xplore. Restrictions apply.
The contract budget cost unnecessary costs and losses and protect their rights and
interests in the law. The third is the project personnel should
Construction cost budget
pay close attention to the execution of the contract during
the performance of the contract to find the breach of contract
Costin

claims; what’s more, the project personnel must pay


attention to their behaviors to prevent the other team.
The actual cost
V. CONCLUSION
This article mainly discusses the PDCA cycle
management in the construction of the project quality
Time management, schedule management, cost management and
so on the concrete application of ways in order to spread and
Fig 4. contract and the relationship between the construction budget cost and actual cost application of PDCA cycle to guide a certain help.
Through research, we get the following opinions: PDCA
Organizational Measures: cycle in quality management of the project, schedule
a) Clear the institutional setup and personnel in charge management and cost management has a very important
of construction project management, coordinate all aspects role. In the enterprise project management process, we need
of the responsibility, right and benefit relationship. to integrate into PDCA circulation method of management
b) Clear cost controller and its mission, the use of experience and the essence of the planning, implementation,
scientific, reasonable and economic construction plan and inspection, review and improvement process into every
aspect of project management to go, and each cycle need to
arrangement, making someone responsible for cost control,
be resolved Some problems, so that the next cycle can
to avoid cost, cost, causing problems such as unclear
achieve higher levels. Through this iterative process, so as to
responsibility. gradually enhance project quality, reduce project costs, and
Technical Measures: We should give full play to the reasonable arrangements for schedule effectively
technical personnel's subjective initiative, the main technical implemented. By PDCA circulation, management gradually
solutions to make the necessary technical and economic approaches the optimum value.
argumentation, to seek a more economic and reliable
solution, in order to achieve shorten the construction period, ACKNOWLEDGMENT
improving quality, reducing project cost.
This work was supported by National Natural Science
Economic Measures: Economic measures are mainly
from the economic aspects of humans, materials, machines Foundation of China (Grant No.71171110) and National
and other costs of control. Especially for the material Natural Science Foundation of China (Grant No.71371097).
control, we should do the following three points: REFERENCES
Firstly, we should do well on the amount of material
[1] Zhang zy, sen-lin li. Training project management in the work of the
control. Insist on determining the material consumption continuing education [M]. 2006. (8)
according to the quota, and the limits of the system. [2] Ordnance Guo Xingxiang Wei Yanpeng. Fourth party logistics
Secondly, the project personnel can improve the quality management and monitoring system design [J]. Science and
construction technology and promote the use of new technology innovation herald. 2010.6
technology to reduce material consumption, and analyze the [3] Du Xingliang. Analyze the PDCA circulation method in the
function of the project and the performance analysis of application of the engineering project management. [J]. Zhengzhou:
material, all of those analyses strive to replace expensive Henan finance and tax college journal, 2010, 2 (2).
materials, strengthen the management of turnover materials. [4] Fendler j.h. polymerized surfactant vesicles: that the dark clouds, Lv
The purchasing department should investigate the market Zhanjun. Engineering project schedule management methods in the li
Yang in the four seasons engineering application [J]. Journal of
quotation in the purchase in advance, and make preferential project management technology. 2008, (3).
purchase in the premise of ensuring the quality. [5] Li xing, wang junxia. Theory of hydropower construction project
Contract Measures: First of all, to strengthen the cost management [J]. Modern economic information, 2011, (7): 20 to
contract management and claims management, project 22.
personnel should ensure that the project must be carried out [6] Li Zhenjuan Fan Yu. Extraction of PDCA circulation method in the
within the project contract strictly, collect and save the application of the library information service quality control [J].
construction of the contract related information. Secondly, Journal of intelligence development of science and technology and
economy, 2009, (9): 35 ~ 36.
the study may cause the risk of cost changes in the
[7] Wang Lixia. Project construction organization and management [M].
identification and analysis, and then take the necessary Zhengzhou: Zhengzhou university press, 2007
measures to reduce the possibility of risk, and to make these
[8] G peak. The project management by objectives theory application in
measures reflect the specific terms of the contract, in order HDS company ha hot project research [J]. [master thesis]. Xian
to ensure that the construction process to minimize university of science and technology. 2007.3(23)

272
271