CONTRACTOR:
CONSTRUCTION METHOD
GENERAL REQUIREMENTS
1. Mobilization to the project site, installation of temporary facilities, protection of property, work and structures,
3. Staking out of building, establishment of lines, grades and benchmarks and erection of batter boards and
reference marks.
EARTH WORKS
4. Prior to commencement of excavation, the location shall be checked to ascertain the type of soil to be excavated
5. Excavation for building shall be carried out by using excavator and the excavated soil to be tested for suitability
and shall be stock piled at convenient locations at site if suitable for back filling purpose and surplus soil to be
6. Back filling shall be done in layers of not more than 250mm loose thickness and each layer thoroughly watered
and rammed to ensure Minimum Dry Density of 95% as per ASTM D1557.Testing of compaction will be performed
as directed by the engineer. Earth work under substructure shall be provided with anti-termite treatment for the
set or placed are close together as is practicable in order to reduce the voids to a minimum.
8. After chinking and filling, the voids between the stones shall be completely filled with grout. Care shall be taken to
prevent earth or sand from filling the spaces between the stones before the grout is poured.
PLAIN AND REINFORCED CONCRETE WORK
REINFORCING STEEL
All reinforcement will be stored on racks inside the stores. Different types & sizes will be kept separately.
All reinforcement will be kept to protect from damage, free from dirt, loose mill scale, rust scale paint, oil,
As per the specifications & drawing, the bar bending schedules & bar lists, cutting schedules for each
individual structure will be prepared by the contractor and will obtained the approval from the engineer.
All reinforcement will be cleaned by a wire brush or any other means before placing. All reinforcement
placed should comply with the drawings. Lap length will be taken in to account according to the project
The dimensions & position of formwork will be carefully checked after erection.
Before placing concrete all dirt, wood chips, hardened concrete or mortar and all other foreign matter will
be removed from the forms. Before fixing of form work, detailed drawing will be submitted to the
CONCRETING WORKS
The method for placing of concrete will be worked out to prevent segregation of the material &
MASONRY WORKS
9. Masonry works, Block laying for exterior and interior partition walls
ROOFING SYSTEM
14. Installation of Electrical system, Conduits, Boxes, Fittings, Wires and Wiring Devices, Panel Boards, and Power load
center.
FABRICATION WORKS AND PAINTING WORKS
MECHANICAL WORKS
PROJECT CLOSE-OUT
24. After all works were reviewed by the inspector, all necessary documents, test reports, and other deliverables shall
be turned over and checked by the inspector. Once all requirements are cleared, personnel and equipment shall
be demobilized.
Submitted by:
General Manager
Name of Representative of the Bidder and Signature