You are on page 1of 2

THREE (3) DAYS WORK SCHEDULE

PS1 DATE: 09/13/13

YESTERDAY'S WORKS TODAY'S WORKS TOMORROW'S WORKS DAY AFTER TOMORROW'S WORKS
Item Thursday, September 12, 2013 Friday, September 13, 2013 Saturday, September 14, 2013 Sunday, September 15, 2013
LOCATION ACTIVITY TIME LOCATION ACTIVITY TIME LOCATION ACTIVITY TIME LOCATION ACTIVITY TIME

Fire Fightiang Preparation for fire fighting system Fire Fightiang Preparation for fire fighting system Fire Fightiang
1) 07h to 18h 07h to 18h Fire Fighting system Installation 07h to 18h
System Are installation System Are installation System Are

2)

3)

4)

5)

DIRECT MANPOWER LIST EQUIPMENTS LIST


ITEM FUNCTION QTY ITEM DESIGNATION QTY
1) Engineers 1 1) Crane 50T 0
2) Supervisor 1 2) Forklift 7T 0
3) Forman 0 3) Generator 100 KVA 0
4) Welders 1 4) Welding Machine 3
5) Pipe Fitters 2 5) Compressor 0
6) Erectors 2 6) Painting machine 0
7) Painters 0
8) Sand blasters 0

9) Crane Driver 0
10 ) Store keeper 0
11 ) Electricians 1

12 ) Mechanical Technicians 0
THREE (3) DAYS WORK SCHEDULE

NFCS Site DATE: 04/28/10

YESTERDAY'S WORKS TODAY'S WORKS TOMORROW'S WORKS DAY AFTER TOMORROW'S WORKS
Item Tuesday, April 27, 2010 Wednesday, April 28, 2010 Thursday, April 29, 2010 Friday, April 30, 2010
LOCATION ACTIVITY TIME LOCATION ACTIVITY TIME LOCATION ACTIVITY TIME LOCATION ACTIVITY TIME

Outlet of Outlet of Alignment, Adjustment & Tack welding of BW Outlet of UT Inspection of BW B11/B12, B12/B13, Outlet of Alignment, Adjustment & Tack welding of
1) Welding of BW B9/B10. 07h to 18h 07h to 18h 10h:00 07h to 18h
Regulating Tank Regulating Tank B3/B3-1/B4 Regulating Tank B13/B14, B14/B15 Regulating Tank BW B15/B15-1/B16

Surface Preparation, Inspection & Internal


Outlet of Outlet of Outlet of
2) Welding of BW B8/B9. 07h to 18h Painting of BW B11/B12, B12/B13, 07h to 18h Welding of BW B3/B3-1. 07h to 18h
Regulating Tank Regulating Tank Regulating Tank
B13/B14, B14/B15

Outlet of Inspection before welding of BW B3/B3-1, Outlet of UT Inspection of BW B4/B5, B5/B6, B6/B7,
3) 08h:00 10h:00
Regulating Tank B3-1/B4. Regulating Tank B7/B8

Outlet of
4) Welding of BW B3-1/B4. 07h to 18h
Regulating Tank

5)

DIRECT MANPOWER LIST EQUIPMENTS LIST


ITEM FUNCTION QTY ITEM DESIGNATION QTY
1) Engineers 1 1) Crane 50T 1
2) QC Agent 1 2) Forklift 7T 0
3) Forman 1 3) Generator 100 KVA 1
4) Welders 2 4) Welding Machine 7
5) Pipe Fitters 1 5) Compressor 0
6) Erectors 4 6) Painting machine 0
7) Painters 1
8) Sand blasters 1

9) Crane Driver 1
10 ) Store keeper 1
11 ) Electricians 0

12 ) Mechanical Technicians 1