SUPPLY OF MATERIALS AND LABOR CHARGES FOR THE VERIFICATION OF DEVICES WITH TESTING AND COMMISSIONING
Project Name:
OF FIRE PROTECTION SYSTEM OF DEPARTMENT OF CIVIL DEFENSE BUILDING
Client: DPWH-7
Project Location: Brig. Gen. Benito N. Ebuen Airbase, Sangi Road, Brgy. Pajo, Lapu-Lapu City

PROJECT COST ESTIMATE

Part
DESCRIPTION UNIT Qty Unit Price Total Amount Remarks
No
FIRE PROTECTION SYSTEM CHECKING AND VERIFICATION AS PER TENDER DRAWING AND FIRE PROTECTION RISER DIAGRAM WITH PIPE, SPRINKLER
HEAD, FIRE HOSE CABINET LEAK TEST CHARGES

VERIFICATION OF SPRINKLER HEADS AND PIPELINE WITH TESTING


Part 1 Lot 1 830,700.00 830,700.00
AND COMMISSIONING FROM GROUND TO 3RD FLOOR

LABOR CHARGES FOR THE VERIFICATION, TESTING AND AND


Part 2 COMMISSIONING OF ELECTRIC DRIVEN MAIN FIRE AND JOCKEY PUMP Lot 1 184,000.00 184,000.00
TO INCLUDE PROTECTION AND CONTROL SYSTEM

Part 3 GENERAL REQUIREMENTS FOR THE EXECUTION OF THE PROJECT Lot 1 33,500.00 33,500.00
1,048,200.00
1,048,200.00

Note:
Estimated project leadtime is 3-4wks
All prices are VAT inclusive and subject to change without prior notice.
Price validity Valid for 1-month from the date of quotation and need to be conformed in writing.
Thereafter subject for confirmation.

PAYMENT TERMS
Check payment payable to DCNC SALES and SERVICES CORP.

Prepared & submitted by; Received and agreed upon by;

ENGR. NELSON P. COLO ____________________


Chief Operations Officer Signature over Printed Name
DCNC SALES and SERVICES CORP. Date: _______________
Date: _______________

SALES MAINTENANCE SERVICES AUTOMATION AUDIO/VIDEO INSTRUMENT/CONTROL SAFETY SECURITY CIVIL MEP WORKS 1/2
DCNC SALES AND SERVICES CORP.

SN Item Description Unit Qty Unit Price Sub-Total Comments


FIRE PROTECTION SYSTEM CHECKING AND VERIFICATION AS PER TENDER DRAWING AND FIRE PROTECTION RISER DIAGRAM WITH PIPE, SPRINKLER HEAD, FIRE HOSE CABINET LEAK
TEST CHARGES
Part 1 VERIFICATION OF SPRINKLER HEADS AND PIPELINE WITH TESTING AND COMMISSIONING FROM GROUND TO 3RD FLOOR
Supply of consummable items, pipe leak test, set to work and commission the fire protection system including
but not limited all fire fighting pipeline and sprinkler heads at the ground floor area consisting grooved fittings
expansion joints, galvanized hangers and supports and paintings (groove fittings), as per drawings.
1.1 Reference Drawing No. : M-05, Sheet no. 87/101 Lot 1.00 191,100.00 191,100.00
No. of prinkler heads @ ground floor : 98
Pipe leak test shall be of compressed air as the area is already occupied

Supply of consummable items, pipe leak test, set to work and commission the fire protection system including
but not limited all fire fighting pipeline and sprinkler heads at the second floor area consisting grooved fittings
expansion joints, galvanized hangers and supports and paintings (groove fittings), as per drawings.
1.2 Reference Drawing No. : M-06, Sheet no. 88/101 Lot 1.00 212,550.00 212,550.00
No. of prinkler heads @ ground floor : 109
Pipe leak test shall be of compressed air as the area is already occupied

Supply of consummable items, pipe leak test, set to work and commission the fire protection system including
but not limited all fire fighting pipeline and sprinkler heads at the third floor area consisting grooved fittings
expansion joints, galvanized hangers and supports and paintings (groove fittings), as per drawings.
Reference Drawing No. : M-07, Sheet no. 89/101
1.3 Lot 1.00 235,950.00 235,950.00
No. of prinkler heads @ ground floor : 121
Pipe leak test shall be of compressed air as the area is already occupied

Supply of consummable items, pipe leak test, set to work and commission the fire protection system including
but not limited all fire fighting pipeline and fire hose cabinet at the ground, second & third floor area consisting
grooved fittings expansion joints, galvanized hangers and supports and paintings (groove fittings), as per
drawings.
1.4 Lot 1.00 35,100.00 35,100.00
Reference Drawing No. : M-05, Sheet no. 87/101, M-06, Sheet no. 88/101 & M-07, Sheet no. 89/101
Total no. of Fure Hose Cabinet : 6
Pipe leak test shall be of compressed air as the area is already occupied

1.5 Rental of compressor and accessories for leak test activity Lot 1.00 123,500.00 123,500.00
Supply of hardware and mechanical devices and accessories for fire protection like fittings, bolts, nuts and
1.6 Lot 1.00 32,500.00 32,500.00
temporary blind flanges and pressure gauges

VERIFICATION OF SPRINKLER HEADS AND PIPELINE WITH TESTING AND COMMISSIONING FROM GROUND TO 3RD FLOOR - SUB-TOTAL 830,700.00

LABOR CHARGES FOR THE VERIFICATION, TESTING AND AND COMMISSIONING OF ELECTRIC DRIVEN MAIN FIRE AND JOCKEY PUMP TO INCLUDE PROTECTION AND CONTROL
Part 2
SYSTEM
Supply of consumables, functional test, set to work, and commissioning of Electric fire PUMP 1 of 40-HP to
provide cut in pressure of 70PSIG, operating at 220/3/60 Hz. Works include verification of installed devices
2.1 and accessories if it is still working as per requirements to conforme functional and specification requirements, Lot 1.00 42,000.00 42,000.00
Reference Drawing No. : M-03, Sheet no. 85/101 (Pump house)

Supply of consumables, functional test, set to work, and commissioning of Jockey Pump of 5-HP to provide cut
in / cut out pressure of 100 / 110 PSIG, operating at 220/3/60 Hz. Works include verification of installed
2.2 devices and accessories if it is still working as per requirements to conforme functional and specification Lot 1.00 42,000.00 42,000.00
requirements,
Reference Drawing No. : M-03, Sheet no. 85/101 (Pump house)
Supply of materials and labor charges of motor/pump dry run protection by installing level control system in
2.3 order not to run and stop the motor from running if the water level is not sufficient and include this function to Lot 1.00 49,000.00 49,000.00
the entire system.

2.4 Programming of PLC to conforme requirement of functional system Lot 1.00 36,000.00 36,000.00
2.5 Supply of hardware and electrical devices and accessories for Fire pump House Lot 1.00 15,000.00 15,000.00
LABOR CHARGES FOR THE VERIFICATION, TESTING AND AND COMMISSIONING OF ELECTRIC DRIVEN MAIN FIRE AND JOCKEY PUMP TO
184,000.00
INCLUDE PROTECTION AND CONTROL SYSTEM - SUB-TOTAL
Part 3 GENERAL REQUIREMENTS FOR THE EXECUTION OF THE PROJECT
3.1 Mobilization, demobilization of tools, equipment and manpower Lot 1 15,000.00 15,000.00
3.2 Health & Safety,PPE,Tools and Equipments Lot 1 8,500.00 8,500.00
3.3 Charges for the use of tools and test equipments Lot 1 10,000.00 10,000.00
GENERAL REQUIREMENTS FOR THE EXECUTION OF THE PROJECT - SUB-TOTAL 33,500.00
GRAND TOTAL 1,048,200.00

FEBRUARY 2023 FIRE PROTECTION WORKS 2 of 2