PT BUMI SUKSESINDO
JANUARI 2022
PT BUMI SUKSESINDO
Jln. Pancer – Sumberagung – Pesanggaran – Banyuwangi , 68488 PO BOX 227 Phone: +62-333 710368 Fax +62-333 710100
Banyuwangi, 24 Desember 2021
ANALYSIS REPORT
Client:
Prepared by:
Rev. 0 Page: 2
ACKNOWLEDGEMENT
ANALYSIS REPORT
Prepared for:
Rev. 0 Page: 3
Sample Marked: The sample was obtain from wall of solar tank 04-FT-01, PT.
BumiSuksesindo
Objective of Test:
Detecting the presence of hydrocarbon on the wall after cleaning that reduce
potassium permanganate less than 30 minutes.
Step of work:
1. Prepare wall wash test sample from solar tank
3 sample is prepared to perform wall wash test based on rotation degree
from manhole inside tank
Sample
Location
number
Sample 1 0°
Sample 2 90°
Sample 3 180°
Rev. 0 Page: 4
Observation result:
The observation is carried out for 45 minutes
Sample information (form left to right):
1. Standard solution (water and KMnO4)
2. Testing solution 1 (sample 1 and KMnO4)
3. Testing solution 2 (sample 2 and KMnO4)
4. Testing solution 3 (sample 3 and KMnO4)
Standar 0 Minutes
solution
Initial condition After 15 minutes running test
Conclusion:
From the above result, the color of sample was changed from purple to yellow pale
after 45 minutes. Mean that pass wall wash test PTT > 30 minutes and free hydro
carbon.
Banyuwangi, 20 January 2022
ANALYSIS REPORT
Client:
Prepared by:
Rev. 0 Page: 2
ACKNOWLEDGEMENT
ANALYSIS REPORT
Prepared for:
Rev. 0 Page: 3
Sample Marked: The sample was obtain from wall of MIA solar tank FT-02,
PT. Bumi Suksesindo
Refference
API Manual of Petroleum Measurement Standard – Ch. 17.8
Objective of Test:
Detecting the presence of hydrocarbon on the wall after cleaning that reduce
potassium permanganate less than 30 minutes.
Step of work:
1. Prepare wall wash test sample from solar tank
3 sample is prepared to perform wall wash test based on rotation degree
from manhole inside tank
Sample
Location
number
Sample 1 0°
Sample 2 90°
Sample 3 180°
Rev. 0 Page: 4
11. Record the time when the purple color fades to yellow pale (orange)
Appraisal Characteristics
Permanganate Time Test (PTT) Result
15 Minutes High Hidrocarbon Remain
30 Minutes Moderate Hidrocarbon Remain
45 Minutes Low Hidrocarbon Remain
Observation result:
The observation is carried out for 45 minutes
Sample information (from left to right):
1. Standard solution (water and KMnO4)
2. Testing solution 1 (sample 1 and KMnO4)
3. Testing solution 2 (sample 2 and KMnO4)
4. Testing solution 3 (sample 3 and KMnO4)
Standar 0 Minutes
Solution
Initial condition After 15 minutes running test
Conclusion:
From the above result, the color of sample was changed from purple to yellow pale
after 45 minutes. Mean that pass wall wash test PTT > 30 minutes and free hydro
carbon.
PT BUMI SUKSESINDO
Jln. Pancer – Sumberagung – Pesanggaran – Banyuwangi , 68488 PO BOX 227 Phone: +62-333 710368 Fax +62-333 710100
BLASTING PAINTING MIA FT-01 & FT-02 PROJECT BUMI
SUKSESINDO
SEISO BSI
REV. DATE DESCRIPTION
Prepared by Approved by Review & Approved
0 17-Jan-22 Issued for Review RB RF
Document Number
Document type Report
SEI/BP/REP/001
Project Name Document Status
For Approval
BLASTING PAINTING MIA FT-01 & FT-02 PROJECT BUMI
Rev. Date Lang. No. of Pages
SUKSESINDO
0 17-Jan-22 EN 10
Scanned by TapScanner
Scanned by TapScanner
Scanned by TapScanner
Scanned by TapScanner
Scanned by TapScanner
Scanned by TapScanner
Scanned by TapScanner
Scanned by TapScanner
Scanned by TapScanner
PT BUMI SUKSESINDO
Jln. Pancer – Sumberagung – Pesanggaran – Banyuwangi , 68488 PO BOX 227 Phone: +62-333 710368 Fax +62-333 710100
FUEL TANK CLEANING & INSPECTION PROJECT BUMI
SUKSESINDO
SEISO BSI
REV. DATE DESCRIPTION
Prepared by Approved by Review & Approved
0 26-Des-21 Issued for Review RB NH
Document Number
Document type Report
SEI/NDT/REP/002
Project Name Document Status
For Approval
FUEL TANK CLEANING & INSPECTION PROJECT BUMI
Rev. Date Lang. No. of Pages
SUKSESINDO
0 26-Des-21 EN 3
PT BUMI SUKSESINDO
Jln. Pancer – Sumberagung – Pesanggaran – Banyuwangi , 68488 PO BOX 227 Phone: +62-333 710368 Fax +62-333 710100
FUEL TANK CLEANING & INSPECTION PROJECT BUMI
SUKSESINDO
SEISO BSI
REV. DATE DESCRIPTION
Prepared by Approved by Review & Approved
0 26-Des-21 Issued for Review RB NH
Document Number
Document type Report
SEI/NDT/REP/003
Project Name Document Status
For Approval
FUEL TANK CLEANING & INSPECTION PROJECT BUMI
Rev. Date Lang. No. of Pages
SUKSESINDO
0 26-Des-21 EN 3
PT BUMI SUKSESINDO
Jln. Pancer – Sumberagung – Pesanggaran – Banyuwangi , 68488 PO BOX 227 Phone: +62-333 710368 Fax +62-333 710100
FUEL TANK CLEANING & INSPECTION PROJECT BUMI
SUKSESINDO
SEISO BSI
REV. DATE DESCRIPTION
Prepared by Approved by Review & Approved
0 26-Des-21 Issued for Review RB RF
Document Number
Document type Report
SEI/NDT/REP/006
Project Name Document Status
For Approval
FUEL TANK CLEANING & INSPECTION PROJECT BUMI
Rev. Date Lang. No. of Pages
SUKSESINDO
0 26-Des-21 EN 3
FUEL TANK CLEANING & INSPECTION PROJECT BUMI
SUKSESINDO
SEISO BSI
REV. DATE DESCRIPTION
Prepared by Approved by Review & Approved
0 21-Jan-22 Issued for Review RB RF
Document Number
Document type Report
SEI/NDT/REP/009
Project Name Document Status
For Approval
FUEL TANK CLEANING & INSPECTION PROJECT BUMI
Rev. Date Lang. No. of Pages
SUKSESINDO
0 21-Jan-22 EN 4
PT BUMI SUKSESINDO
Jln. Pancer – Sumberagung – Pesanggaran – Banyuwangi , 68488 PO BOX 227 Phone: +62-333 710368 Fax +62-333 710100
FUEL TANK CLEANING & INSPECTION PROJECT BUMI
SUKSESINDO
SEISO BSI
REV. DATE DESCRIPTION
Prepared by Approved by Review & Approved
0 21-Jan-22 Issued for Review RB RF
Document Number
Document type Report
SEI/NDT/REP/010
Project Name Document Status
For Approval
FUEL TANK CLEANING & INSPECTION PROJECT BUMI
Rev. Date Lang. No. of Pages
SUKSESINDO
0 21-Jan-22 EN 5
PT BUMI SUKSESINDO
Jln. Pancer – Sumberagung – Pesanggaran – Banyuwangi , 68488 PO BOX 227 Phone: +62-333 710368 Fax +62-333 710100
FUEL TANK CLEANING & INSPECTION PROJECT BUMI
SUKSESINDO
SEISO BSI
REV. DATE DESCRIPTION
Prepared by Approved by Review & Approved
0 21-Jan-22 Issued for Review RB RF
Document Number
Document type Report
SEI/NDT/REP/011
Project Name Document Status
For Approval
FUEL TANK CLEANING & INSPECTION PROJECT BUMI
Rev. Date Lang. No. of Pages
SUKSESINDO
0 21-Jan-22 EN 4