1.0 PURPOSE
This Procedure is intended to provide guidance and instructions for cleaning and
Maintenance of rotameter.
2.0 RESPONSIBILITY
1.0 All the C&I personnel involved in carrying out /supervising the above activities are
required to ensure implementation of this procedure and may consult any other
relevant documents indicated under Reference section below.
1.1 In the event of any changes required in the procedure such changes may be
requested with HOD.
Page 3 of 5
Revision No. 00 Revision Date : 06-07-2017 Issue Date : 06-07-2017 No. of Pages: 4 of 5
3. Ensure proper working platform.
4. Ensure the proper usage of insulated general tools
5. Ensure safe procedure while using Bench vise
6.0 PROCEDURE
2. Identify the correct instrument by verifying the Tag Plate on the instrument or by tracing
the process connection.
3. In case of chemical lines, ensure usage of proper PPE, chemical insulated gloves and
glasses.
4. Based on Permit type (Online/Offline) ensure the main Isolation Valve of the Instrument
is isolated, if not intimate the operation personnel (Shift-in Charge) to provide isolation
required.
7. Check for any high pressure/spray of process due to passing of isolation valve.
8. Ensure that person working with the instrument should not get in contact with process.
Page 4 of 5
Revision No. 00 Revision Date : 06-07-2017 Issue Date : 06-07-2017 No. of Pages: 5 of 5
7.0 REFERENCE:
HIRA: SGPL/MAINT/C&I/BTG-S&W-017