BEKEM INFRAPROJECTS PVT LTD

BRAMHANI BRIDGE
BADAKAMARA Date-26.11.2022
SOCKETING LENGTH CONCRETE QUANTITY
TOTAL
TOTAL BORE TOTAL BORE SOCKETING SOCKETING TOTAL TOTAL
CUT-OFF PILE ROCK TOTAL SOCKET REVISED REVISED SOCKET TOTAL INCREASE CONCRETE
SL NO LOCATION TIP LEVEL LENGTH OF PILE LENGTH OF PILE in LENGTH LENGTH DECREASE IN CONCRETE REMARKS
LEVEL TOP LEVEL LENGTH IN M TIP LEVEL LENGTH IN M IN (M)FOR EACH QUANTITY
in M M (REV) INCREASE DECREASE (M)FOR EACH QUANTITY
PILE CAP 102NOS
DIFFERENCE DIFFERENCE PILE CAP 102NOS PILES
PILES (REV)
1 A1 54.850 41.480 32.480 9.000 22.370 32.480 9.000 22.370 0.000 238.241 238.241 A1 & A2 Each
2 A2 54.850 42.931 33.931 9.000 20.919 33.931 9.000 20.919 0.000 222.787 222.787 06nos piles
3 P1 49.600 40.245 32.245 8.000 17.355 27.200 13.045 22.400 5.045 25.225 154.026 198.800
4 P2 49.600 39.642 31.642 8.000 17.958 31.600 8.042 18.000 0.042 0.210 159.377 159.750
5 P3 49.600 37.166 29.166 8.000 20.434 29.200 7.966 20.400 -0.034 -0.17 181.352 181.050
6 P4 49.600 39.334 31.334 8.000 18.266 31.300 8.034 18.300 0.034 0.170 162.111 162.413
7 P5 49.600 38.774 30.774 8.000 18.826 28.100 10.674 21.500 2.674 13.370 167.081 190.813
8 P6 49.600 38.784 30.784 8.000 18.816 27.700 11.084 21.900 3.084 15.420 166.992 194.363
9 P7 49.600 37.606 29.606 8.000 19.994 24.600 13.006 25.000 5.006 25.030 177.447 221.875
10 P8 49.600 39.189 31.189 8.000 18.411 31.000 8.189 18.600 0.189 0.945 163.398 165.075
Each pile cap
11 P9 49.600 36.841 28.841 8.000 20.759 27.200 9.641 22.400 1.641 8.205 184.236 198.800
have 05 nos
12 P10 49.600 37.346 29.346 8.000 20.254 28.500 8.846 21.100 0.846 4.230 179.754 187.263
pile
13 P11 49.600 38.474 30.474 8.000 19.126 30.500 7.974 19.100 -0.026 -0.13 169.743 169.513
14 P12 49.600 37.96 29.96 8.000 19.640 30.000 7.960 19.600 -0.040 -0.2 174.305 173.950
15 P13 49.600 38.202 30.202 8.000 19.398 28.600 9.602 21.000 1.602 8.010 172.157 186.375
16 P14 49.600 36.026 28.026 8.000 21.574 26.400 9.626 23.200 1.626 8.130 191.469 205.900
17 P15 49.600 36.401 28.401 8.000 21.199 25.600 10.801 24.000 2.801 14.005 188.141 213.000
18 P16 49.600 35.571 27.571 8.000 22.029 23.800 11.771 25.800 3.771 18.855 195.507 228.975
19 P17 49.600 38.065 30.065 8.000 19.535 29.000 9.065 20.600 1.065 5.325 173.373 182.825
20 P18 49.600 40.191 32.191 8.000 17.409 30.500 9.691 19.100 1.691 8.455 154.505 169.513
Total Pile length increase 155.585 3576.002 3851.278
Total Pile length decrease 0.500
Concrete quanity increased
Total Pile length increased 155.085m 275.2M3