You are on page 1of 169

Package V

Rate Analysis
Prices of Bitumen
Applicable from December 16, 2018

Bitumen Grades

VG-10 VG-30 VG-40

BITUMEN (BULKED)

PORT REF(Mumbai) 31590 32390

KOCHI 32390

KOYALI 31590 32390 33460

MATHURA 31290 32090 33360

PANIPAT 31290 32090 33360

HALDIA 30890 31690 32760

CHENNAI 31690 32490 33760

BARAUNI 31920 32320 33390

BITUMEN (PACKED)

KOCHI 35690

KOYALI 34890 35690

MATHURA 34590 35390

PANIPAT 34590 35390

HALDIA 34190 34990

CHENNAI 34990 35790

Note:
(1) The above prices are in Rs. Per MT
(2) The above prices are exclusive of GST.

PREVIOUS PRICES

RA - 1
Prices of Emulsion
Applicable from December 16, 2018

Cities Prices

RAPID MEDIUM SLOW(SS2) SLOW(SS1)

EMULSION (BULK)

HALDIA 26200

CHENNAI 25790 27430 44730

EMULSION (PACKED)

CHENNAI 29910 31550 48830

Note:
(1) The above prices are in Rs. Per MT
(2)The above prices are exclusive of GST.

PREVIOUS PRICES

RA - 2
Prices of CRMB/MT
Applicable from December 16, 2018

Cities Prices

CRMB (BULK)

CRMB-55 CRMB-60

KOYALI 33550 33730

PANIPAT 33240 33420

HALDIA 33150 33390

MATHURA 33350 33560

CHENNAI 33670 33750

CRMB (PACKED)

HALDIA 36690 36920

CRMB 60 Base VG 30 Bulk

CHENNAI 36320

Note:
(1) The above prices are in Rs. Per MT
(2) The above prices are exclusive of GST.

PREVIOUS PRICES

RA - 3
RA - 4
RA - 5
RA - 6
RA - 7
RA - 8
CHAPTER-2
SITE CLEARANCE
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
2.1 201 Cutting of Trees, including cutting of Trunks, Branches
and Removal
Cutting of trees, including cutting of trunks, branches and
removal of stumps, roots, stacking of serviceable material
with all lifts and up to a lead of 1000 metres and earth filling
in the depression/pit.
Unit = Each
(i) Girth from 300 mm to 600 mm
a) Labour
Mate day 0.020 451.00 9.02
Mazdoors for cutting trees including cutting, refilling, day 0.600 400.00 240.00
compaction of backfilling and stacking of serviceable
materials within 1000 metres lead by manual means.

b) Machinery
Tractor-trolley hour 0.100 413.60 41.36
c) Overhead charges @ 2.615% on (a+b) 7.59
d) Contractor's profit @ 10% on (a+b+c) 29.80
Rate for each tree = a+b+c+d 327.77
say 328.00
2.1 (ii) Girth from 600 mm to 900 mm
a) Labour
Mate day 0.040 451.00 18.04
Mazdoors for cutting trees including cutting, refilling, day 0.900 400.00 360.00
compaction of backfilling, and stacking of serviceable
materials within 1000 metres lead by manual means

b) Machinery
Tractor-trolley hour 0.300 413.60 124.08
c) Overhead charges @ 2.615% on (a+b) 13.13
d) Contractor's profit @ 10% on (a+b+c) 51.53
Rate for each tree = a+b+c+d 566.78
say 567.00
2.1 (iii) Girth from 900 mm to 1800 mm
a) Labour
Mate day 0.080 451.00 36.08
Mazdoors for cutting trees including cutting, refilling, day 2.000 400.00 800.00
compaction of backfilling and stacking of serviceable
materials within 1000 metres
b) Machinery
Tractor-trolley hour 0.400 413.60 165.44
c) Overhead charges @ 2.615% on (a+b) 26.19
d) Contractor's profit @ 10% on (a+b+c) 102.77
Rate for each tree = a+b+c+d 1130.48
say 1130.00
2.1 (iv) Girth above 1800 mm
a) Labour
Mate day 0.160 451.00 72.16
Mazdoors for cutting trees including cutting, refilling, day 4.000 400.00 1600.00
compaction of backfilling and stacking of serviceable
materials within 1000 metres
b) Machinery
Tractor-trolley hour 0.600 413.60 248.16
c) Overhead charges @ 2.615% on (a+b) 50.22
d) Contractor's profit @ 10% on (a+b+c) 197.05
Rate for each tree = a+b+c+d 2167.59
say 2168.00
2.3 201 Clearing and Grubbing Road Land .

SOR 2018-19 Roads-Site Clearance

RA - 9
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Clearing and grubbing road land including uprooting rank
vegetation, grass, bushes, shrubs, saplings and trees girth
up to 300 mm, removal of stumps of trees cut earlier and
disposal of unserviceable materials and stacking of
serviceable material to be used or auctioned, up to a lead of
1000 metres including removal and disposal of top organic
soil not exceeding 150 mm in thickness.

Unit = Hectare
Taking output = 1 Hectare
2.3 (ii) By Mechanical Means
A In area of light jungle
a) Labour
Mate day 0.160 451.00 72.16
Mazdoor day 4.000 400.00 1600.00
b) Machinery
Dozer 80 HP with attachment for removal of trees & hour 10.000 2454.60 24546.00
stumps
Tractor-trolley hour 1.000 413.60 413.60
c) Overhead charges @ 2.615% on (a+b) 696.42
d) Contractor's profit @ 10% on (a+b+c) 2732.82
Rate per Hectare = a+b+c+d 30061.00
say 30061.00
2.3 (ii) B In area of thorny jungle
a) Labour
Mate day 0.240 451.00 108.24
Mazdoor day 6.000 400.00 2400.00
b) Machinery
Dozer 80 HP with attachment for removal of trees & hour 12.000 2454.60 29455.20
stumps
Tractor-trolley hour 1.500 413.60 620.40
c) Overhead charges @ 2.615% on (a+b) 852.07
d) Contractor's profit @ 10% on (a+b+c) 3343.59
Rate per Hectare = a+b+c+d 36779.50
say 36779.00
2.4 202 Dismantling of Structures
Dismantling of existing structures like culverts, bridges,
retaining walls and other structure comprising of masonry,
cement concrete, wood work, steel work, including T&P and
scaffolding wherever necessary, sorting the dismantled
material, disposal of unserviceable material and stacking the
serviceable material with all lifts and lead of 1000 metres

Unit = cum
Taking output = 1.25 cum
(i) Lime /Cement Concrete
2.4 II By Mechanical Means for items No. 202( b)& ( c)
A Cement Concrete Grade M-15 & M-20
a) Labour
Mate day 0.020 451.00 9.02
Mazdoor for loading and unloading day 0.250 400.00 100.00
Mazdoor with Pneumatic breaker day 0.250 440.00 110.00
b) Machinery
Air Compressor 250 cfm with 2 leads of pneumatic hour 0.670 556.50 372.86
breaker @ 1.5 cum per hour
Tractor-trolley hour 0.270 413.60 111.67
c) Overhead charges @ 2.615% on (a+b) 18.40
d) Contractor's profit @ 10% on (a+b+c) 72.19
Cost for 1.25 cum = a+b+c+d 794.14
Rate per cum = (a+b+c+d)/ 1.25 635.31
say 635.00
2.5 202 Dismantling of Flexible Pavements

SOR 2018-19 Roads-Site Clearance

RA - 10
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Dismantling of flexible pavements and disposal of dismantled
materials up to a lead of 1000 metres, stacking serviceable
and unserviceable materials separately

Unit = cum
Taking output = 1 cum
I By Manual Means
A Bituminous courses
a) Labour
Mate day 0.060 451.00 27.06
Mazdoor for dismantling, loading and unloading day 1.500 400.00 600.00
b) Machinery
Tractor-trolley hour 0.380 413.60 157.17
c) Overhead charges @ 2.615% on (a+b) 20.51
d) Contractor's profit @ 10% on (a+b+c) 80.47
Rate per cum = a+b+c+d 885.21
say 885.00
2.5 I B Granular courses
a) Labour
Mate day 0.040 451.00 18.04
Mazdoor for dismantling, loading and unloading. day 1.000 400.00 400.00
b) Machinery
Tractor-trolley hour 0.330 413.60 136.49
c) Overhead charges @ 2.615% on (a+b) 14.50
d) Contractor's profit @ 10% on (a+b+c) 56.90
Rate per cum = a+b+c+d 625.93
say 626.00
2.5 II By Mechanical Means
A Bituminous course
a) Labour
Mate day 0.010 451.00 4.51
Mazdoor day 0.300 400.00 120.00
b) Machinery
Tractor-trolley hour 0.380 413.60 157.17
Farm tractor with ripper @ 60 cum per hour hour 0.017 423.60 7.20
c) Overhead charges @ 2.615% on (a+b) 7.55
d) Contractor's profit @ 10% on (a+b+c) 29.64
Rate per cum = a+b+c+d 326.08
say 326.00
2.10 202 Dismantling of Kilometre Stone
Dismantling of kilometre stone including cutting of earth,
foundation and disposal of dismantled material with all lifts
and lead upto 1000 m and back filling of pit.
Unit = Each
Taking output = one KM stone
A 5th KM stone
Quantity of cement concrete = 0.392 cum
a) Labour
Mate day 0.130 451.00 58.63
Mazdoor day 0.750 400.00 300.00
b) Machinery
Tractor-trolley hour 0.150 413.60 62.04
c) Overhead charges @ 2.615% on (a+b) 11.00
d) Contractor's profit @ 10% on (a+b+c) 43.17
Rate for one 5th KM stone = a+b+c+d 474.84
say 475.00
B Ordinary KM Stone
Quantity of cement concrete = 0.269 cum
a) Labour
Mate day 0.020 451.00 9.02
Mazdoor day 0.500 400.00 200.00
b) Machinery

SOR 2018-19 Roads-Site Clearance

RA - 11
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Tractor-trolley hour 0.300 413.60 124.08
c) Overhead charges @ 2.615% on (a+b) 8.71
d) Contractor's profit @ 10% on (a+b+c) 34.18
Rate for one ordinary KM stone = a+b+c+d 375.99
say 376.00
C Hectometre Stone
Quantity of cement concrete = 0.048 cum
a) Labour
Mate day 0.004 451.00 1.80
Mazdoor day 0.100 400.00 40.00
b) Machinery
Tractor-trolley hour 0.020 413.60 8.27
c) Overhead charges @ 2.615% on (a+b) 1.31
d) Contractor's profit @ 10% on (a+b+c) 5.14
Rate for one Hectometre stone = a+b+c+d 56.52
say 57.00

SOR 2018-19 Roads-Site Clearance

RA - 12
CHAPTER - 3
EARTH WORK, EROSION CONTROL AND DRAINAGE
Ref. to
MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
3.3 301 Excavation in Soil with Dozer with lead up to 100 metres

Excavation for road way in soil by mechanical means


including cutting and pushing the earth to site of
embankment up to a distance of 100 metres (average lead
50 metres), including trimming bottom and side slopes in
accordance with requirements of lines, grades and cross
sections.
Unit = cum
Taking output = 180 cum
a) Labour
Mate day 0.080 451.00 36.08
Mazdoor day 2.000 400.00 800.00
b) Machinery
Dozer, 80 HP @ 30 cum per hour hour 6.000 2454.60 14727.60
c) Overhead charges @ 2.615% on (a+b) 406.99
d) Contractor's profit @ 10% on (a+b+c) 1597.07
add Seigniorage charges Cum 0.000 30.00 0.00
Add District Mineral Fund (DMF) 30% on Seinorage 0.300 0.00 0.00
charges
Cost for 180 cum = a+b+c+d 17567.74
Rate per cum = (a+b+c+d)/180 97.60
say 98.00
3.6 301 Excavation in Soil using Hydraulic Excavator CK 90 and
Tippers with Disposal upto 1000 metres.
A Excavation for roadwork in soil with hydraulic excavator of
0.9 cum bucket capacity including cutting and loading in
tippers, trimming bottom and side slopes, in accordance with
requirements of lines, grades and cross sections, and
transporting to the embankment location within all lifts and
lead upto 1000m
Unit = cum
Taking output = 360 cum
a) Labour
Mate day 0.080 451.00 36.08
Mazdoor day 2.000 400.00 800.00
b) Machinery
Hydraulic excavator 0.9 cum bucket capacity @ 60 cum hour 6.000 2791.60 16749.60
per hour
Tipper 5.5 cum capacity, 4 trips per hour. hour 16.000 950.30 15204.80
c) Overhead charges @ 2.615% on (a+b) 857.47
d) Contractor's profit @ 10% on (a+b+c) 3364.80
add Seigniorage charges cum 0.000 30.00 0.00
Add District Mineral Fund (DMF) 30% on Seinorage 0.300 0.00 0.00
charges
Cost for 360 cum = a+b+c+d 37012.75
Rate per cum = (a+b+c+d)/360 102.81
say 103.00
B Excavation for roadwork in soil with hydraulic excavator of
0.9 cum bucket capacity including cutting and loading in
tippers, trimming bottom and side slopes, in accordance with
requirements of lines, grades and cross sections, and
transporting to the embankment location within all lifts.
Unit = cum
Taking output = 360 cum
a) Labour
Mate day 0.080 451.00 36.08
Mazdoor day 2.000 400.00 800.00
b) Machinery

SOR 2018-19 Roads- Earthwork

RA - 13
Ref. to
MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Hydraulic excavator 0.9 cum bucket capacity @ 60 cum hour 6.000 2791.60 16749.60
per hour
Tipper 5.5 cum capacity, 4 trips per hour. hour 0.000 950.30 0.00
c) Overhead charges @ 2.615% on (a+b) 459.87
d) Contractor's profit @ 10% on (a+b+c) 1804.55
add Seigniorage charges cum 0.000 30.00 0.00
Add District Mineral Fund (DMF) 30% on Seinorage 0.300 0.00 0.00
charges
Cost for 360 cum = a+b+c+d 19850.10
Rate per cum = (a+b+c+d)/360 55.14
say 55.00
3.7 301 Excavation in Ordinary Rock using Hydraulic Excavator
CK-90 and Tippers with Disposal upto 1000 metres.

Excavation for roadway in ordinary rock with hydraulic


excavator of 0.9 cum bucket capacity including cutting and
loading in tippers, transporting to embankment site within all
lifts and lead upto 1000 m, trimming bottom and side slopes
in accordance with requirements of lines, grades and cross
sections.
Unit = cum
Taking output = 240 cum
a) Labour
Mate day 0.080 451.00 36.08
Mazdoor day 2.000 400.00 800.00
b) Machinery
Hydraulic Excavator 0.90 cum bucket capacity @ 36 hour 6.000 2791.60 16749.60
cum per hour
Tipper 5.5 cum capacity, 4 trips per hour. hour 11.000 950.30 10453.30
c) Overhead charges @ 2.615% on (a+b) 733.22
d) Contractor's profit @ 10% on (a+b+c) 2877.22
add Seigniorage charges cum 0.000 30.00 0.00
Add District Mineral Fund (DMF) 30% on Seinorage 0.300 0.00 0.00
charges
Cost for 240 cum = a+b+c+d 31649.42
Rate per cum = (a+b+c+d)/240 131.87
say 132.00
3.8 301 Excavation in Hard Rock (blasting prohibited)
(I) Excavation for roadway in hard rock (blasting prohibited)
with rock breakers including breaking rock, loading in tippers
and disposal within all lifts and lead upto 1000 metres,
trimming bottom and side slopes in accordance with
requirements of lines, grades and cross sections.
A Mechanised
Unit = cum
Taking output = 36 cum
a) Labour
Mate day 0.400 451.00 180.40
Mazdoor for trimming slopes including mannul loading day 10.000 400.00 4000.00
in truck
b) Machinery
Hydraulic excavator with rock breaker attachment @ 6 hour 6.000 2791.60 16749.60
cum per hour
Tipper 5.5 cum capacity, 1 trip per hour. hour 6.500 950.30 6176.95
Credit for excavated rock found suitable for use @ 50 cum 18.000 (194.00) (3492.00)
per cent of excavated quantity
c) Overhead charges @ 2.615% on (a+b) 617.53
d) Contractor's profit @ 10% on (a+b+c) 2423.25
add Seigniorage charges cum 0.000 30.00 0.00
Add District Mineral Fund (DMF) 30% on Seinorage 0.300 0.00 0.00
charges
Cost for 36 cum = a+b+c+d 26655.73

SOR 2018-19 Roads- Earthwork

RA - 14
Ref. to
MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Rate per cum = (a+b+c+d)/36 740.44
say 740.00
Note 1. The quality and availability of rock shall be checked before
affording credit.
2. In case some rock is issued to the contractor at site,
the item of carriage shall be restricted/reduced to that
extent.
3.Being small quantity, manual loading will be economical in
this case and has been provided accordingly.

3.8 B Manual Method


(I) Unit = cum
Taking output = 16 cum
a) Labour
Mate day 1.640 451.00 739.64
Mazdoor including loading in truck day 16.000 400.00 6400.00
Chiseller day 24.000 440.00 10560.00
Blacksmith day 1.000 482.20 482.20
b) Machinery
Tipper 5.5 cum capacity, 1 trip per hour. hour 2.900 950.30 2755.87
Credit for excavated rock found suitable for use @ 50 cum 8.000 (194.00) (1552.00)
per cent of excavated
c) Overhead charges @ 2.615% on (a+b) 506.94
d) Contractor's profit @ 10% on (a+b+c) 1989.26
add Seigniorage charges cum 0.000 30.00 0.00
Add District Mineral Fund (DMF) 30% on Seinorage 0.300 0.00 0.00
charges
Cost for 16 cum = a+b+c+d 21881.91
Rate per cum = (a+b+c+d)/16 1367.62
say 1368.00
Note 1. Credit is considered for 50 per cent of quantity of work.

2. Loading for disposal will be done manually, being small


quantity.
3. In case some rock is issued to contractor at site, the
item of carriage shall be omitted to the extent of
quantity issued to the contractor.

3.11 301 Removal of Unserviceable Soil with Disposal upto 1000


metres
Removal of unserviceable soil including excavation, loading
and disposal upto 1000 metres lead but excluding
replacement by suitable soil which shall be paid separately
as per clause 305.
Unit = cum
Taking output = 360 cum
a) Labour
Mate day 0.080 451.00 36.08
Mazdoor day 2.000 400.00 800.00
b) Machinery
Excavator0.90 cum bucket capacity @ 60 cum per hour hour 6.000 2791.60 16749.60

Tipper 5.5 cum capacity, 4 trips per hour. hour 16.360 950.30 15546.91
c) Overhead charges @ 2.615% on (a+b) 866.42
d) Contractor's profit @ 10% on (a+b+c) 3399.90
add Seigniorage charges cum 0.000 30.00 0.00
Add District Mineral Fund (DMF) 30% on Seinorage 0.300 0.00 0.00
charges
Cost for 360 cum = a+b+c+d 37398.91
Rate per cum = (a+b+c+d)/360 103.89
say 104.00

SOR 2018-19 Roads- Earthwork

RA - 15
Ref. to
MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Note This item does not include replacement of unsuitable soil by
suitable soil. Replacement, where required, is to be provided
and paid separately under clause 305.
3.15 305.4.3 Scarifying Existing Bituminous Surface to a depth of 50
mm by Mechanical Means
Scarifying the existing bituminous road surface to a depth of
50 mm and disposal of scarified material with in all lifts and
lead upto 1000 metres.
Unit = sqm
Taking output = 100 sqm
a) Labour
Mate day 0.010 451.00 4.51
Mazdoor day 0.250 400.00 100.00
b) Machinery
Tractor with ripper attachment @ 60 cum per hour hour 0.080 423.60 33.89
Front end loader 1 cum bucket capacity @ 25 cum per hour 0.200 1594.70 318.94
hour
Tipper 5.5 cum capacity, 4 trips per hour. hour 0.230 950.30 218.57
c) Overhead charges @ 2.615% on (a+b) 17.67
d) Contractor's profit @ 10% on (a+b+c) 69.36
Cost for 100 sqm = a+b+c+d 762.94
Rate per sqm = (a+b+c+d)/100 7.63
say 8.00
3.16 305 Construction of Embankment with Material obtained
from Borrowpits
Construction of embankment with approved material
obtained from borrow pits with all lifts and leads, transporting
to site, spreading, grading to required slope and compacting
to meet requirement of table 300-2.
Unit = cum
Taking output = 100 cum
a) Labour
Mate day 0.040 451.00 18.04
Mazdoor day 1.000 400.00 400.00
b) Machinery
Hydraulic Excavator1 cum bucket capacity @ 60 cum hour 1.670 2791.60 4661.97
per hour
Tipper 10 tonne capacity tonne.km 160 x L 6.56 5245.66

Add 10 per cent of cost of carriage to cover cost of 524.57


loading and unloading
Dozer 80 HP for spreading @ 200 cum per hour hour 0.500 2454.60 1227.30
Motor grader for grading @ 100 cum per hour hour 1.000 3020.40 3020.40
Water tanker6 KL capacity hour 4.000 655.20 2620.80
Vibratory roller 8 -10 tonnes @ 100 cum per hour hour 1.000 2736.20 2736.20
c) Material
Cost of water KL 24.000 77.00 1848.00
Compensation for earth taken from private land cum 100.000 0.00 0.00
d) Overhead charges @ 2.615% on (a+b+c) 583.22
e) Contractor's profit @ 10% on (a+b+c+d) 2288.62
add Seigniorage charges cum 100.000 30.00 3000.00
Add District Mineral Fund (DMF) 30% on Seinorage 0.300 3000.00 900.00
charges
Cost for 100 cum = a+b+c+d+e 29074.77
Rate per cum = (a+b+c+d+e)/100 290.75
say 291.00
Note Compensation for earth will vary from place to place and will
have to be assessed realistically as per particular ground
situation. In case earth is available from Govt. land,
compensation for earth will not be required. The position is
required to be clearly stated in the cost estimate.

SOR 2018-19 Roads- Earthwork

RA - 16
Ref. to
MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
3.17 305 Construction of Embankment with Material Deposited
from Roadway Cutting
Construction of embankment with approved materials
deposited at site from roadway cutting and excavation from
drain and foundation of other structures graded and
compacted to meet requirement of table 300-2.
Unit = cum
Taking output = 100 cum
a) Labour
Mate day 0.020 451.00 9.02
Mazdoor day 0.500 400.00 200.00
b) Machinery
Dozer 80 HP for spreading @ 200 cum per hour hour 0.500 2454.60 1227.30
Motor grader for grading @ 100 cum per hour hour 1.000 3020.40 3020.40
Water tanker6 KL capacity hour 4.000 655.20 2620.80
Vibratory roller 8-10 tonnes @ 100 cum per hour hour 1.000 2736.20 2736.20
c) Material
Cost of water KL 24.000 77.00 1848.00
d) Overhead charges @ 2.615% on (a+b+c) 304.95
e) Contractor's profit @ 10% on (a+b+c+d) 1196.67
Rate for 100 cum = a+b+c+d+e 13163.34
Rate per cum = (a+b+c+d+e)/100 131.63
say 132.00
Note In case the earth cutting is done by dozer and pushed for
filling in the embankment, the input of dozer in the cost of
embankment shall be deleted as the same is already
provided in the cost of excavation. However, if the earth is
dumped by tippers from roadway cutting, the input of dozer
for spreading is required to be provided.
3.18 305 Construction of Subgrade and Earthen Shoulders
Construction of sub-grade and earthen shoulders with
approved material obtained from borrow pits with all lifts &
leads, transporting to site, spreading, grading to required
slope and compacted to meet requirement of table No. 300-2

Unit = cum
Taking output = 100 cum
a) Labour
Mate day 0.040 451.00 18.04
Mazdoor day 1.000 400.00 400.00
b) Machinery
Hydraulic excavator1 cum bucket capacity @ 60 cum hour 1.670 2791.60 4661.97
per hour
Tipper 10 tonne capacity tonne.km 175xL 6.56 5737.44

Add 10 per cent of cost of carriage to cover cost of 573.74


loading and unloading
Dozer 80 HP for spreading @ 200 cum per hour hour 0.500 2454.60 1227.30
Motor grader for grading @ 100 cum per hour hour 1.000 3020.40 3020.40
Water tanker with 6 km lead hour 4.000 655.20 2620.80
Vibratory roller 8-10 tonnes @ 80 cum per hour hour 1.250 2736.20 3420.25
c) Material
Cost of water KL 24.000 77.00 1848.00
Compensation for earth taken from private land cum 100.000 55.00 5500.00
d) Overhead charges @ 2.615% on (a+b+c) 759.08
e) Contractor's profit @ 10% on (a+b+c+d) 2978.70
add Seigniorage charges cum 100.000 30.00 3000.00
Add District Mineral Fund (DMF) 30% on Seinorage 0.300 3000.00 900.00
charges
Cost for 100 cum = a+b+c+d+e 36665.72
Rate per cum = (a+b+c+d+e)/100 366.66
say 367.00

SOR 2018-19 Roads- Earthwork

RA - 17
Ref. to
MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
3.22 307 Turfing with Sods
Furnishing and laying of the live sods of perennial turf
forming grass on embankment slope, verges or other
locations shown on the drawing or as directed by the
engineer including preparation of ground, fetching of sods
and watering.
Unit = sqm
Taking output = 100 sqm
a) Labour
Mate day 0.120 451.00 54.12
Mazdoor for preparation of ground and fetching of sods 400.00
day 3.000 1200.00
b) Machinery
Water tanker including watering for 3 months hour 2.000 655.20 1310.40
Tractor-trolley hour 1.000 413.60 413.60
c) Material
Farm yard manure @ 0.18 cum per 100 sqm at site of
cum 0.180 150.00 27.00
work
Cost of water KL 12.000 77.00 924.00
d) Overhead charges @ 2.615% on (a+b+c) 102.75
e) Contractor's profit @ 10% on (a+b+c+d) 403.19
Cost for 100 sqm = a+b+c+d+e 4435.05
Rate per 100 sqm = (a+b+c+d+e)/100 44.35
say 44.00
3.24 309 Surface Drains in Soil
Construction of unlined surface drains of average cross
sectional area 0.63 sqm in soil to specified lines, grades,
levels and dimensions to the requirement of clause 301 and
309. Excavated material to be used in embankment within a
lead of 50 metres (average lead 25 metres)
(Area - 0.625 sqm, Base - 0.5m, Ht - 0.5m, Slopes - 1 V :
1.5H)

Unit = metre
Taking output = 10 metres
A Mechanical means
a) Labour
Mate day 0.016 451.00 7.22
Mazdoor for dressing of bed and side of drain day 0.394 400.00 157.60
b) Machinery
Hydraulic Excavator 0.3 cum bucket capacity @ 30
hour 0.520 2791.60 1451.63
metres per hour
c) Overhead charges @ 2.615% on (a+b) 42.27
d) Contractor's profit @ 10% on (a+b+c) 165.87
Cost for 10 metres = a+b+c+d 1824.59
Rate per metre = (a+b+c+d)/10 182.46
say 182.00

3.24 B Manual Means


a) Labour
Mate day 0.126 451.00 56.83
Mazdoor day 3.150 400.00 1260.00
b) Overhead charges @ 2.615% on (a) 34.43
c) Contractor's profit @ 10% on (a+b) 135.13
Cost for 10 metres = a+b+c 1486.39
Rate per metre = (a+b+c)/10 148.64
say 149.00
Note Where lining of drain is provided, quantity shall be worked
out based on approved design and drawing and priced on
rate of cement concrete of approved grade or stone/brick
masonry as the case may be.

SOR 2018-19 Roads- Earthwork

RA - 18
Ref. to
MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
3.36 Suggesti Embankment Construction with Flyash/Pond ash
ve available from coal or lignite burning Thermal Plants as
waste material.
Construction of embankment with Flyash conforming to table
1 of IRC: SP: 58 - 2001 obtained from coal or lignite burning
thermal power stations as waste material, spread and
compacted in layer of 200mm thickness each at OMC, all as
specified in IRC: SP: 58-2001 and as per approved plans.

Unit = cum
Taking output = 360 cum
a) Labour
Mate day 0.160 451.00 72.16
Mazdoor day 4.000 400.00 1600.00
b) Machinery
Hydraulic Excavator 0.9 cum bucket capacity @ 60 hour 6.000 2791.60 16749.60
cum/hour
Tipper 10Tcapacity flyash 360 x 1.2 = 432 tonnes tonne.km 432 x L 6.56 76481.66

Add 10 per cent of cost of carriagefor loading and 7648.17


unloading
Dozer 80 HP for spreading @ 200 cum/hour hour 1.800 2454.60 4418.28
Motor Grader for grading @ 100 cum/hour hour 3.600 3020.40 10873.44
Water tanker6 KL capacity hour 12.000 655.20 7862.40
Vibratory Roller 8-10 tonne @ 100 cum/hour hour 3.600 2736.20 9850.32
c) Overhead charges @ 2.615% on (a+b) 3544.79
d) Contractor's profit @ 10% on (a+b+c) 13910.08
Cost for 360 cum = a+b+c+d 153010.90
Rate per cum = (a+b+c+d)/360 425.03
say 425.00
Note 1.As flyash is available free of cost as waste material from
Thermal Plants, cost of material has not been added.

2.The earth cover on sides and intermediate layers of earth


sandwiching the flyash have not been included in this
analysis. The same are required to be provided as per
approved design and priced separately as embankment
construction.

SOR 2018-19 Roads- Earthwork

RA - 19
CHAPTER - 4
SUB-BASES, BASES ( NON- BITUMINOUS) AND SHOULDERS
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
4.1 401 Granular Sub-Base with Close Graded Material (Table:-
400-1)
4.1 B By Mix in Place Method
Construction of granular sub-base by providing close graded
material, spreading in uniform layers with motor grader on
prepared surface, mixing by mix in place method with rotavator
at OMC, and compacting with vibratory roller to achieve the
desired density, complete as per clause 401
Unit = cum
Taking output = 300 cum
a) Labour
Mate day 0.480 451.00 216.48
Mazdoor skilled day 2.000 515.00 1030.00
Mazdoor unskilled day 10.000 400.00 4000.00
b) Machinery
Motor Grader 110 HP @ 50 cum hour 6.000 3020.40 18122.40
Vibratory roller 8 -10 tonne hour 6.000 2736.20 16417.20
Tractor - Rotavator hour 12.000 423.60 5083.20
Water tanker 6 KL capacity hour 3.000 655.20 1965.60
c) Material
Close graded Granular sub-base Material as per table 400-1

For Grading-I Material


53 mm to 9.5 mm @ 50 per cent cum 192.000 944.60 181363.20
9.5 mm to 2.36 mm @ 20 per cent cum 76.000 652.54 49593.04
2.36 mm below @ 30 per cent cum 115.200 333.00 38361.60
Cost of water KL 18.000 77.00 1386.00
OR
For Grading-II Material
26.5 mm to 9.5 mm @ 35 per cent cum 134.400 1071.19 143967.94
9.5 mm to 2.36 mm @ 25 per cent cum 96.000 652.54 62643.84
2.36 mm below @ 40 per cent cum 153.600 333.00 51148.80
Cost of water KL 18.000 77.00 1386.00
OR
For Grading-III Material
9.5 mm to 4.75 mm @ 35 per cent cum 134.400 760.47 102207.17
4.75 mm to 2.36 mm @ 12.5 per cent cum 48.000 436.69 20961.12
2.36 mm below @ 52.5 per cent cum 201.600 333.00 67132.80
Cost of water KL 18.000 77.00 1386.00
4.1B (i) Rate per cum for grading-I Material
d) Overhead charges @ 2.615% on (a+b+c) 8303.64
e) Contractor's profit @ 10% on (a+b+c+d) 32584.24
add seignorage charges cum 382.200 75.00 28665.00
Add District Mineral Fund (DMF) 30% on Seinorage 0.300 28665.00 8599.50
charges
Cost for 300 cum = a+b+c+d+e 395691.09
Rate per cum = (a+b+c+d+e)/300 1318.97
Add lead charges of metal 25.00 Km 575.36
say 1894.00
4.1B (ii) Rate per cum for grading-II Material
d) Overhead charges @ 2.615% on (a+b+c) 8001.42
e) Contractor's profit @ 10% on (a+b+c+d) 31398.29
add seignorage charges cum 384.000 75.00 28800.00
Add District Mineral Fund (DMF) 30% on Seinorage 0.300 28800.00 8640.00
charges
Cost for 300 cum = a+b+c+d+e 382821.16
Rate per cum = (a+b+c+d+e)/300 1276.07
Add lead charges of metal 25.00 Km 575.36
say 1851.00
4.1B (iii) Rate per cum for grading-III Material

SOR 2018-19 Roads-Sub Base

RA - 20
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
d) Overhead charges @ 2.615% on (a+b+c) 6237.35
e) Contractor's profit @ 10% on (a+b+c+d) 24475.93
add seignorage charges cum 384.000 75.00 28800.00
Add District Mineral Fund (DMF) 30% on Seinorage 0.300 28800.00 8640.00
charges
Cost for 300 cum = a+b+c+d+e 306675.25
Rate per cum = (a+b+c+d+e)/300 1022.25
Add lead charges of metal 25.00 Km 575.36
say 1598.00
Note Any one of the grading for material may be adopted as per
design
4.6 403 Cement Treated Crushed Rock or combination as per
clause 403.2 and table 400.4in Sub base/ Base
Providing, laying and spreading Material on a prepared sub
grade, adding the designed quantity of cement to the spread
Material, mixing in place with rotavator, grading with the motor
grader and compacting with the road roller at OMC to achieve
the desired unconfined compressive strength and to form a
layer of sub-base/base.
Unit = cum
Taking output = 300 cum (600 tonnes)
Quantity of cement assumed as 4 per cent of quantity of
crushed rock by weight.
a) Labour
Mate day 0.480 451.00 216.48
Mazdoor skilled day 2.000 515.00 1030.00
Mazdoor day 10.000 400.00 4000.00
b) Machinery
Motor Grader 110 HP @ 50 cum per hour hour 6.000 3020.40 18122.40
Vibratory roller 8 - 10 tonne hour 6.000 2736.20 16417.20
Tractor with Rotavator and blade @ 25 cum per hour hour 12.000 423.60 5083.20
Water tanker 6 KL capacity hour 10.000 655.20 6552.00
c) Material
Cement at site @ 4 per cent by weight of crushed
tonne 24.000 3900.00 93600.00
aggregate (600 tonne)
Grading of material for sub-base course
37.5 mm to 9.5 mm @ 55 per cent cum 211.200 811.80 171452.16
9.5 mm to 4.75 mm @ 20 per cent cum 76.800 760.47 58404.10
4.75 mm to 75 micron @ 25 per cent cum 96.000 384.84 36944.64
Cost of water KL 60.000 77.00 4620.00
or
Grading of material for Base course
37.5 mm to 9.5 mm @ 32.5 per cent cum 124.800 811.80 101312.64
9.5 mm to 4.75 mm @ 5 per cent cum 19.200 760.47 14601.02
4.75 mm to 75 micron @ 62.5 per cent cum 240.000 384.84 92361.60
Cost of water KL 60.000 77.00 4620.00
4.6 (i) For Sub-Base course
d) Overhead charges @ 2.615% on (a+b+c) 10889.96
e) Contractor's profit @ 10% on (a+b+c+d) 42733.21
Cost for 300 cum = a+b+c+d+e 470065.35

add seignorage charges cum 384.000 75.00 28800.00


Add District Mineral Fund (DMF) 30% on Seinorage 0.300 28800.00 8640.00
charges
Add lead charges of metal 25.00 Km 575.36
Rate per cum = (a+b+c+d+e)/300 2267.04
say 2267.00
4.6 (ii) For Base course
d) Overhead charges @ 2.615% on (a+b+c) 9359.52
e) Contractor's profit @ 10% on (a+b+c+d) 36727.61
Cost for 300 cum = a+b+c+d+e 404003.67

SOR 2018-19 Roads-Sub Base

RA - 21
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
add seignorage charges cum 384.000 75.00 28800.00
Add District Mineral Fund (DMF) 30% on Seinorage 0.300 28800.00 8640.00
charges
Add lead charges of metal 25.00 Km 575.36
Rate per cum = (a+b+c+d+e)/300 2046.84
say 2047.00
Note Quantities of aggregates provided under 'c' above are
uncompacted quantities.
4.12 406 Providing, laying, spreading and compacting graded stone
aggregate to wet mix macadam specification including
premixing the Material with water at OMC in mechanical mix
plant carriage of mixed Material by tipper to site, laying in
uniform layers with paver in sub- base / base course on well
prepared surface and compacting with vibratory roller to
achieve the desired density.
Unit = cum
Taking output = 225 cum (495 tonnes)
a) Labour
Mate day 0.480 451.00 216.48
Mazdoor skilled day 2.000 515.00 1030.00
Mazdoor day 10.000 400.00 4000.00
b) Machinery
Wet mix plant of 75 tonne hourly capacity hour 6.600 1679.70 11086.02
Electric generator 125 KVA hour 6.000 1543.10 9258.60
Front end loader 1 cum capacity hour 6.000 1594.70 9568.20
Paver finisher hour 6.000 2290.60 13743.60
Vibratory roller 8 - 10 tonne hour 6x0.65 2736.20 10671.18
or
Smooth 3 wheeled steel roller @ 8-10 tonnes. hour 12.000
Water tanker 6 KL capacity hour 3.000 655.20 1965.60
Tipper tonne.km 495 x L 6.56 25966.00

Add 10 per cent of cost of carriage to cover cost of 2596.60


loading and unloading

SOR 2018-19 Roads-Sub Base

RA - 22
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
c) Material ( Table 400-11)
45 mm to 22.4 mm@ 30 per cent cum 89.100 1068.42 95196.22
22.4 mm to 2.36 mm @ 40 per cent cum 118.800 839.53 99736.16
2.36 mm to 75 micron@ 30 per cent cum 89.100 333.00 29670.30
Cost of water KL 18.000 77.00 1386.00
d) Overhead charges @ 2.615% on (a+b+c) 8265.78
e) Contractor's profit @ 10% on (a+b+c+d) 32435.67
Add seignorage charges cum 297.000 75.00 22275.00
Add District Mineral Fund (DMF) 30% on Seinorage 0.300 22275.00 6682.50
charges
Cost for 225 cum = a+b+c+d+e 385749.92
Rate per cum = (a+b+c+d+e)/225 1714.44
say 1714.00
a) Add Lead charges for metal 25.00 Km 593.34
2307.78
say 2308.00
Note 1. Though vibratory roller is required only for 3 hours as per
norms, the same is required to be available at site for 6 hours
to match with other machines. The usage rates of vibratory
roller may be multiplied with a factor of 0.65
2. As three wheeled smooth steel rollers are commonly in use,
the same has been provided as an alternative which can be
used if the thickness of individual layer does not exceed 100
mm..
4.13 407 Construction of Median and Island with Soil Taken from
Roadway Cutting
Construction of Median and Island above road level with
approved material deposited at site from roadway cutting and
excavation for drain and foundation of other structures, spread,
graded and compacted as per clause 407

Unit = cum
Taking output =21 cum
a) Labour
Mate day 0.240 451.00 108.24
Mazdoor day 6.000 400.00 2400.00
b) Machinery
Water tanker 6 KL with 5 km lead and 1 trip per hour hour 1.000 655.20 655.20
Plate compactor @ 3.5 cum per hour hour 6.000 59.10 354.60
c) Material
Cost of water KL 6.000 77.00 462.00
d) Overhead charges @ 2.615% on (a+b+c) 104.08
e) Contractor's profit @ 10% on (a+b+c+d) 408.41
Cost for 21 cum = a+b+c+d+e 4492.53
Rate per cum = (a+b+c+d+e)/21 213.93
say 214.00
Note This analysis provides for median and island with earthen top.
In case the surface is required to be turfed or planted with
shrubs, the same is required to be provided separately as per
analysis given in the chapter on horticulture. In case granular
fill is required to be paved, quantities of paving are required to
be calculated as per approved design and paid separately.

4.14 407 Construction of Median and Island with Soil Taken from
Borrow Areas
Construction of median and Island above road level with
approved material brought from borrow pits, spread, sloped
and compacted as per clause 407
Unit = cum
Taking output = 21 cum
a) Labour
Mate day 0.160 451.00 72.16

SOR 2018-19 Roads-Sub Base

RA - 23
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Mazdoor day 4.000 400.00 1600.00
b) Machinery
Water tanker with 5 km lead hour 1.000 655.20 655.20
Plate Compactor @ 3.5 cum per hour hour 6.000 59.10 354.60
Hydraulic Excavator1.0 cum bucket capacity @60 cum hour 0.500 2791.60 1395.80
per hour
Tipper 10 tonne capacity tonne.km 52.5 x L 6.56 1721.23

Add 10 per cent of cost of transportation to cover cost of 172.12


loading and unloading
c) Material
Cost of water KL 6.000 77.00 462.00
d) Overhead charges @ 2.615% on (a+b+c) 168.23
e) Contractor's profit @ 10% on (a+b+c+d) 660.13
Cost for 21 cum = a+b+c+d+e 7261.47
Rate per cum = (a+b+c+d+e)/ 21 345.78
say 346.00
say 346.00
Note This analysis provides for median and island with earthen top.
In case the surface is required to be turfed or planted with
shrubs, the same is required to be provided separately as per
analysis given in the chapter on horticulture. In case surface
finish is of hard type, the same may be provided separately as
per approved design.

4.16 409 Footpaths and Separators


Construction of footpath/separator by providing a 150 mm
compacted granular sub base as per clause 401 and 25 mm
thick cement concrete grade M15, over laid with pre-cast
concrete tiles in cement mortar 1:3 including provision of all
drainage arrangements but excluding kerb channel..

Unit = sqm
Taking output = 300 sqm
a) Labour
Mate day 1.360 451.00 613.36
Mason day 4.000 455.00 1820.00
Mazdoor day 30.000 400.00 12000.00
b) Machinery
Vibratory road roller 8 -10 tonnes @60 cum per hour hour 0.750 2736.20 2052.15
Water tanker 6 KL capacity @ 1 trip per hour hour 2.000 655.20 1310.40
Concrete mixer 0.4/0.28 cum per hour hour 6.000 525.50 3153.00
c) Material
i) For Granular sub base material
53 mm to 26.5 mm @ 35 per cent cum 20.790 858.90 17856.53
26.5 mm to 4.75 mm @ 45 per cent cum 26.730 990.95 26488.09
2.36 mm below @ 20 per cent cum 11.880 333.00 3956.04
ii) For cement concrete grade M157.5 cum
Aggregate 12 mm crushed @ 0.9 cum of concrete cum 6.750 998.56 6740.30
Sand @ 0.45 cum/cum of concrete cum 3.380 182.00 615.16
Cement tonne 1.880 3900.00 7332.00

SOR 2018-19 Roads-Sub Base

RA - 24
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
iii) For cement plaster 1:3
Sand cum 3.840 182.00 698.88
Cement tonne 1.830 3900.00 7137.00
iv) Pre-cast cement concrete tiles
Tiles size 300 x 300 mm and 25 mm thick each 3300.000 23.49 77524.75
v) RCC pipes
Pipes 200 mm dia,2.5 m long for drainage metre 22.500 263.00 5917.50
vi) Cost of water KL 12.000 77.00 924.00
d) Overhead charges @ 2.615% on (a+b+c) 4606.04
e) Contractor's profit @ 10% on (a+b+c+d) 18074.52
Add Seigniorage Fee on Sand Cum 7.220 50.00 361.00
Add Seigniorage Fee on Road Metal Cum 66.150 75.00 4961.25
Add District Mineral Fund (DMF) 30% on Seinorage 0.300 5322.25 1596.68
charges
Cost for 300 sqm = a+b+c+d+e 205738.65
Rate per sqm = (a+b+c+d+e)/300 685.80
say 686.00
Add lead charges of metal 25.00 Km 0.221 449.50 99.11
Add lead charges of sand 41.00 Km 0.012 718.12 8.64
Add lead charges of Manufactured Sand 25.00 Km 0.012 505.00 6.08
say 799.83
say 800.00

SOR 2018-19 Roads-Sub Base

RA - 25
CHAPTER - 5
BASES AND SURFACE COURSES (BITUMINOUS)
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
5.1 502 Prime Coat
Providing and applying primer coat with bitumen
emulsion on prepared surface of granular Base
including clearing of road surface and spraying primer
at the rate of 0.70 kg/sqm using mechanical means.

Unit = sqm
Taking output = 3500 sqm
a) Labour
Mate day 0.080 451.00 36.08
Mazdoor day 2.000 400.00 800.00
b) Machinery
Mechanical broom @ 1250 sqm per hour hour 2.800 381.80 1069.04
Air compressor 250 cfm hour 2.800 556.50 1558.20
Emulsion pressure distributor @ 1750 sqm per hour hour 2.000 875.60 1751.20

Water tanker 6 KL capacity @ 1 trip per hour hour 1.000 655.20 655.20
c) Material
Bitumen emulsion @ 0.6 kg per sqm (SS1) tonne 2.100 44730.00 93933.00
Cost of water KL 6.000 77.00 462.00
d) Overhead charges @ 2.615% on (a+b+c) 2621.92
e) Contractor's profit @ 10% on (a+b+c+d) 10288.66
Cost for 3500 sqm = a+b+c+d+e 113175.31
Rate per sqm = (a+b+c+d+e)/3500 32.34
say 32.30
add lead charges of bitumen 250.00 Km 0.28
total rate per sqm 32.62
say 32.60
Note Bitumen primer has been provided @ 0.60 kg per sqm as per
clause 502.8. Payment shall be made with adjustment, plus
or minus, for the variation between this quantity and the
actual quantity approved by the Engineer after the
preliminary trials referred to in clause No. 502.4.3.
5.2 503 Tack Coat
Providing and applying tack coat with bitumen emulsion
using emulsion pressure distributor at the rate of 0.25
kg per sqm on the prepared bituminous/granular
surface cleaned with mechanical broom.

Unit = sqm
Taking output = 3500 sqm
a) Labour
Mate day 0.080 451.00 36.08
Mazdoor day 2.000 400.00 800.00
b) Machinery
Mechanical broom @ 1250 sqm per hour hour 2.800 381.80 1069.04
Air compressor 250 cfm hour 2.800 556.50 1558.20
Emulsion pressure distributor @ 1750 sqm per hour hour 2.000 875.60 1751.20

c) Material
Bitumen emulsion @ 0.25kg per sqm (RS) tonne 0.875 35790.00 31316.25
d) Overhead charges @ 2.615% on (a+b+c) 955.28
e) Contractor's profit @ 10% on (a+b+c+d) 3748.60
Cost for 3500 sqm = a+b+c+d+e 41234.65
Rate per sqm = (a+b+c+d+e)/3500 11.78
say 11.80
add lead charges of bitumen 250.00 Km 0.12
total rate per sqm 11.90
say 11.90

SOR 2018-19 Roads-Base Courses

RA - 26
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Note 1. Bitumen emulsion has been provided @ 0.20 kg per sqm
as per clause 503.8. Payment shall be made with
adjustment, plus or minus, for the variation between this
quantity and actual quantity approved by the Engineer after
preliminary trials referred to in clause No. 503.4.3
2. An output of 3500 sqm has been considered in case of
prime coat and tack coat which can be covered by
bituminous courses on the same day.
5.6 507 Dense Graded Bituminous Macadam
Providing and laying dense graded bituminous
macadam with 100-120 TPH batch type HMP producing
an average output of 75 tonnes per hour using crushed
aggregates of specified grading, premixed with
bituminous binder @ 4.0 to 4.5 per cent by weight of
total mix and filler, transporting the hot mix to work site,
laying with a hydrostatic paver finisher with sensor
control to the required grade, level and alignment,
rolling with smooth wheeled, vibratory and tandem
rollers to achieve the desired compaction as per MoRTH
specification clause No. 507 complete in all respects.

Unit = cum
Taking output = 195 cum (450 tonnes)
a) Labour
Mate day 0.840 451.00 378.84
Mazdoor working with HMP, mechanical broom, paver, day 14.000 400.00 5600.00
roller, asphalt cutter and assistance for setting out lines,
levels and layout of construction
Skilled mazdoor for checking line & levels day 5.000 515.00 2575.00
b) Machinery
Batch mix HMP @ 75 tonne per hour hour 6.000 24636.00 147816.00
Paver finisher hydrostatic with sensor control @ 75 cum hour 6.000 3115.20 18691.20
per hour
Generator 250 KVA hour 6.000 2162.60 12975.60
Front end loader 1 cum bucket capacity hour 6.000 1594.70 9568.20
Tipper 10 tonne capacity tonne.km 450 x L 6.56 23605.45

Add 10 per cent of cost of carriage to cover cost of loading 2360.55


and unloading
smooth wheeled roller 8-10 tonnes for initial break down hour 6.00x0.65* 1329.90 5186.61
rolling.
Vibratory roller 8 tonnes for intermediate rolling. hour 6.00x0.65* 2736.20 10671.18
Finish rolling with 6-8 tonnes smooth wheeled tandem hour 6.00x0.65* 1856.50 7240.35
roller.
c) Materials for Grade I
Bitumen @ 4.0 per cent of weight of mix tonne 18.000 33760.00 607680.00
Aggregate
Total weight of mix = 450 tonnes
Weight of bitumen = 18 tonnes
Weight of aggregate = 450 -18 = 432 tonnes
Taking density of aggregate = 1.5 ton/cum
Volume of aggregate = 288 cum
Grading - I40 mm (Nominal Size)
37.5 - 25 mm 22 per cent cum 63.360 981.91 62213.82
25 - 10 mm 13 per cent cum 37.440 1071.19 40105.35
10 -4.75 mm 19 per cent cum 54.720 760.47 41612.92
4.75 mm and below 44 per cent cum 126.720 384.84 48766.92
Filler @ 2 per cent of weight of aggregates. tonne 8.640 2491.00 21522.24
(i) For Grading I ( 40 mm nominal size )
d) Overhead charges @ 2.615% on (a+b+c) 27943.11
e) Contractor's profit @ 10% on (a+b+c+d) 109651.33

SOR 2018-19 Roads-Base Courses

RA - 27
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Add seignorage charges for metal cum 282.240 75.00 21168.00
Add seignorage charges for filler tonne 8.640 88.00 760.32
Add District Mineral Fund (DMF) 30% on Seinorage 0.300 21928.32 6578.50
charges
Cost for 195 cum = a+b+c+d+e 1234671.49
Rate per cum = (a+b+c+d+e)/195 (For Grading I) 6331.65
say 6332.00
a) Add Lead charges for metal 25.00 Km 650.60
b) Add lead charges for Bitumen 250.00 Km 42.98
7025.23
Say 7025.00
c) Materials for Grade II
Bitumen @ 4.5 per cent of weight of mix tonne 20.250 33760.00 683640.00
Aggregate
Total weight of mix = 450 tonnes
Weight of bitumen = 20.25 tonnes
Weight of aggregate = 450 -20.25 = 429.75 tonnes
Taking density of aggregate = 1.5 ton/cum
Volume of aggregate = 286.5 cum
Grading - II19 mm (Nominal Size)
25 - 10 mm 30 per cent cum 85.950 1071.19 92068.78
10 - 5 mm 28 per cent cum 80.220 760.47 61004.90
5 mm and below 40 per cent cum 114.600 384.84 44102.66
Filler @ 2 per cent of weight of aggregates. tonne 8.595 2491.00 21410.15
* Any one of the alternative may be adopted as per approved
design
(ii) For GradingII(19 mm nominal size)
d) Overhead charges @ 2.615% on (a+b+c) 30043.62
e) Contractor's profit @ 10% on (a+b+c+d) 117893.91
Add seignorage charges for metal cum 280.770 75.00 21057.75
Add seignorage charges for filler tonne 8.595 88.00 756.36
Add District Mineral Fund (DMF) 30% on Seinorage 0.300 21814.11 6544.23
charges
Cost for195 cum = a+b+c+d+e 1325191.34
Rate per cum = (a+b+c+d+e)/195 (For Grading-II) 6795.85
say 6796.00
a) Add Lead charges for metal 25.00 Km 647.21
b) Add lead charges for Bitumen 250.00 Km 48.35
7491.42
Say 7491.00
Note *1. Although the roller are required only for 3 hours as per
norms of output, but the same have to be available at site for
six hours as the hot mix plant and paver will take six hours
for mixing and paving the output of 450 tonnes considered in
this analysis. To cater for the idle period of these rollers, their
usage rates have been multiplied by a factor of 0.65.

2.Quantity of Bitumen has been taken for analysis purpose.


The actual quantity will depend upon job mix formula.

3. Labour for traffic control, watch and ward and other


miscellaneous duties at site including sundries have been
included in administrative overheads of the contractor.

4. In case DBM is laid over freshly laid tack coat, provision of


mechanical broom and 2 mazdoors shall be deleted as the
same has been included in the cost of tack coat.

SOR 2018-19 Roads-Base Courses

RA - 28
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
5. The individual density for each size of aggregates to be
used for construction I.e. 37.5-25 mm, 25-10 mm etc. should
be found in the laboratory and accordingly the quantities
should be ammended for use in field. The average density of
1.5 tonne/cum is only a reference density in this Data Book.

6. The individual percentage of aggregates should be


calculated from the total weight of dry aggregates i.e..
excluding the weight of bitumen. The weight of filler will also
be 2 per cent by weight of dry aggregates.
5.8 509 Bituminous Concrete
Providing and laying bituminous concrete with 100-120
TPH batch type hot mix plant producing an average
output of 75 tonnes per hour using crushed aggregates
of specified grading, premixed with bituminous binder
@ 5.2 to 5.4 per cent of mix and filler, transporting the
hot mix to work site, laying with a hydrostatic paver
finisher with sensor control to the required grade, level
and alignment, rolling with smooth wheeled, vibratory
and tandem rollers to achieve the desired compaction as
per MORTH specification clause No. 509 complete in all
respects
Unit = cum
Taking output = 191 cum (450 tonnes)
a) Labour
Mate day 0.840 451.00 378.84
Mazdoor working with HMP, mechanical broom, paver, day 14.000 400.00 5600.00
roller, asphalt cutter and assistance for setting out lines,
levels and layout of construction
Skilled mazdoor for checking line & levels day 5.000 515.00 2575.00
b) Machinery
Batch mix HMP @ 75 tonne per hour hour 6.000 24636.00 147816.00
Paver finisher hydrostatic with sensor control @ 75 cum hour 6.000 3115.20 18691.20
per hour
Generator 250 KVA hour 6.000 2162.60 12975.60
Front end loader 1 cum bucket capacity hour 6.000 1594.70 9568.20
Tipper 10 tonne capacity tonne.km 450 x L 6.56 23605.45

Add 10 per cent of cost of carriage to cover cost of loading 2360.55


and unloading
Smooth wheeled roller 8-10 tonnes for initial break hour 6.00x0.65* 1329.90 5186.61
down rolling.
Vibratory roller 8 tonnes for intermediate rolling. hour 6.00x0.65* 2736.20 10671.18
Finish rolling with 6-8 tonnes smooth wheeled tandem hour 6.00x0.65* 1856.50 7240.35
roller.
c) Material for Grade I
i) Bitumen@ 5.2 per cent of weight of mix tonne 23.400 33670.00 787878.00
ii) Aggregate
Total weight of mix = 450 tonnes
Weight of bitumen = 23.4 tonnes
Weight of aggregate = 450 -23.40 = 426.6 tonnes
Taking density of aggregate = 1.5 ton/cum
Volume of aggregate = 284.4 cum
* Grading - I-19 mm (Nominal Size)
20 - 10 mm 35 per cent cum 99.540 1030.31 102557.06
10 - 5 mm 23 per cent cum 65.412 760.47 49743.86
5 mm and below 40 per cent cum 113.760 384.84 43779.40
Filler @ 2 per cent of weight of aggregates. tonne 8.532 2491.00 21253.21
(i) for Grading-I ( 19 mm nominal size )
d) Overhead charges @ 2.615% on (a+b+c) 32736.68
e) Contractor's profit @ 10% on (a+b+c+d) 128461.72

SOR 2018-19 Roads-Base Courses

RA - 29
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Add seignorage charges for metal cum 278.712 75.00 20903.40
Add seignorage charges for filler tonne 8.532 88.00 750.82
Add District Mineral Fund (DMF) 30% on Seinorage 0.300 21654.22 6496.26
charges
Cost for 191 cum = a+b+c+d+e 1441229.38
Rate per cum = (a+b+c+d+e)/191 7545.70
say 7546.00
a) Add Lead charges for metal 25.00 Km 655.92
b) Add lead charges for Bitumen 250.00 Km 57.04
8258.67
Say 8259.00
c) Material for Grade II
i) Bitumen@ 5.4 per cent of weight of mix tonne 24.300 33670.00 818181.00
ii) Aggregate
Total weight of mix = 450 tonnes
Weight of bitumen = 24.3 tonnes
Weight of aggregate = 450 -24.30 = 425.70 tonnes
Taking density of aggregate = 1.5 ton/cum
Volume of aggregate = 284.4 cum
Grading - II-13 mm (Nominal Size)
13.2 - 10 mm30 per cent cum 85.140 924.75 78733.22
10 - 5 mm 25 per cent cum 70.950 760.47 53955.35
5 mm and below43 per cent cum 122.034 384.84 46963.56
Filler @ 2 per cent of weight of aggregates. tonne 8.514 2491.00 21208.37
*Any one of the alternative may be adopted as per
approved design
5.8 (ii) for Grading-II(13 mm nominal size)
d) Overhead charges @ 2.615% on (a+b+c) 33098.33
e) Contractor's profit @ 10% on (a+b+c+d) 129880.88
Add seignorage charges for metal cum 278.124 75.00 20859.30
Add seignorage charges for filler tonne 8.514 88.00 749.23
Add District Mineral Fund (DMF) 30% on Seinorage 0.300 21608.53 6482.56
charges
Cost for 191 cum = a+b+c+d+e 1456780.78
Rate per cum = (a+b+c+d+e)/191 (For Grading-II) 7627.12
say 7627.00
a) Add Lead charges for metal 25.00 Km 654.54
b) Add lead charges for Bitumen 250.00 Km 59.24
8340.90
Say 8341.00

Note *1. Although the rollers are required only for 3 hours as per
norms of output, but the same have to be available at site for
six hours as the hot mix plant and paver will take six hours
for mixing and paving the output of 450 tonnes considered in
this analysis. To cater for the idle period of these rollers, their
usage rates have been multiplied by a factor of 0.65

2.Quantity of Bitumen has been taken for analysis purpose.


The actual quantity will depend upon job mix formula.

3. Labour for traffic control, watch and ward and other


miscellaneous duties at site including sundries have been
included in administrative overheads of the contractor.

4. In case BC is laid over freshly laid tack coat, provision of


mechanical broom and 2 mazdoors shall be deleted as the
same has been included in the cost of tack coat.

SOR 2018-19 Roads-Base Courses

RA - 30
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
5. The individual density for each size of aggregates to be
used for construction i.e. 37.5-25 mm, 25-10 mm etc. should
be found in the laboratory and accordingly the quantities
should be ammended for use in field. The average density of
1.5 tonne/cum is only a reference density in this Data Book.

6. The individual percentage of aggregates should be


calculated from the total weight of dry aggregates i.e..
excluding the weight of bitumen. The weight of filler will also
be 2 per cent by weight of dry aggregates.
5.14 515 Mastic Asphalt
Providing and laying 25 mm thick mastic asphalt
wearing course with paving grade bitumen meeting the
requirements given in table 500-29, prepared by using
mastic cooker and laid to required level and slope after
cleaning the surface, including providing antiskid
surface with bitumen precoated finegrained hard stone
chipping of 13.2 mm nominal size at the rate of
0.005cum per 10 sqm and at an approximate spacing of
10 cm center to center in both directions, pressed into
surface when the temperature of surfaces is not less
than 1000C, protruding 1 mm to 4 mm over mastic
surface, all complete as per clause 515.

Unit = sqm
Taking output = 35.00 sqm (0.87 cum ) assuming a
density of 2.3 tonnes/cum.-2 tonnes
a) Labour
Mate day 0.440 451.00 198.44
Mazdoor day 10.000 400.00 4000.00
Mazdoor skilled day 1.000 515.00 515.00
b) Machinery
Mechanical broom @ 1250 sqm per hour hour 0.060 381.80 22.91
Air compressor 250 cfm hour 0.060 556.50 33.39
Mastic cooker 1 tonne capacity hour 6.000 79.50 477.00
Bitumen boiler 1500 litres capacity hour 6.000 223.00 1338.00
Tractor for towing and positioning of mastic cooker and hour 1.000 413.60 413.60
bitumen boiler
c) Material
Base mastic (without coarse aggregates) = 60 per cent
Coarse aggregate (6.3mm to 13.2 mm) = 40 per cent .
Proportion of material required for mastic asphalt with coarse
aggregates (based on mix design done by CRRI for a
specific case)
I) Bitumen 85/25 or 30/40 @ 10.2 per cent by weight of tonne 0.204 33760.00 6887.04
mix. 2 x 10.2/100 = 0.204
ii) Fine aggregate passing 2.36mm and retained on cum 0.390 333.00 129.87
0.075mm sieve @ 31.9 per cent by weight of mix = 2 x
31.9/100 = 0.638 tonnes = 0.638/1.625 = 0.39

iii) Lime stone dust filler with calcium content not less tonne 0.360 2491.00 896.76
than 80 per cent by weight @ 17.92 per cent by weight
of mix = 2 x 17.92/100 = 0.36
iv) Coarse aggregates 6.3 mm to 13.2 mm @ 40 per cum 0.550 839.83 461.91
cent by weight of mix = 2 x 40/100 = 0.8 MT =
0.8/1.456 = 0.55
v) Pre-coated stone chips of 13.2 mm nominal size for cum 0.018 333.00 5.99
skid resistance = 35 x 0.005/10 = 0.018
vi) Bitumen for coating of chips @ 2 per cent by weight kg 0.500 33.76 16.88
= 0.018 x 1.456 x 2/100 = 0.0005 MT = 0.5kg

d) Overhead charges @ 2.615% on (a+b+c) 402.63

SOR 2018-19 Roads-Base Courses

RA - 31
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
e) Contractor's profit @ 10% on (a+b+c+d) 1579.94
Add seignorage charges for metal cum 0.958 75.00 71.85
Add seignorage charges for filler tonne 0.360 88.00 31.68
Add District Mineral Fund (DMF) 30% on Seinorage 0.300 103.53 31.06
charges
Cost for 35.00 sqm = a+b+c+d+e 17513.94
Rate per sqm = (a+b+c+d+e)/35 500.40
say 500.00
a) Add Lead charges for metal 25.00 Km 12.30
b) Add lead charges for Bitumen 250.00 Km 2.71
515.02
say 515.00

Note 1.The rates for 50 mm & 40 mm thick layers may be worked


out on pro-rata basis.
2.Where tack coat is required to be provided before laying
mastic asphalt, the same is required to be measured and
paid separately.
3.The quantities of binder, filler and aggregates are for
estimating purpose. Exact quantities shall be as per mix
design.
4.This rate analysis is based on design made by CRRI for a
specific case and is meant for estimating purposes only.
Actual design is required to be done for each case.

SOR 2018-19 Roads-Base Courses

RA - 32
CHAPTER - 5
BASES AND SURFACE COURSES (BITUMINOUS)
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
5.12 513 Stress Absorbing Membrane Interlayer (SAMI)
Providing and laying of Stress Absorbing Membrane
Interlayer (SAMI) on a WMM surface laid to the specified
levels, grade and cross fall using Type A and B

Unit = sqm
Taking output = 10250 sqm (92.25 cum)
(i) Case - I : Type A
a) Labour
Mate day 0.240 451.00 108.24
Mazdoor day 6.000 400.00 2400.00
b) Machinery
Hydraulic self propelled chip spreader hour 6.000 2743.70 16462.20
Tipper 5.5 cum capacity hour 6.000 950.30 5701.80
Front end loader 1 cum bucket capacity hour 6.000 1594.70 9568.20
Bitumen pressure distributor @ 1750 sqm per hour hour 6.000 1527.10 9162.60
Smooth wheeled roller 8 -10 tonne weight hour 6.000 1329.90 7979.40
c) Material
Modified Bitumen @ 11.00 kg per 10 sqm (IRC 37-
tonne 11.275 33670.00 379629.25
2018, Cl. 8.3)
Crushed stone chipping of 6.7 mm size defined as 100
per cent passing 11.2 mm sieve and retained on 2.36
cum 102.500 850.94 87221.09
mm sieve applied @ 0.1 cum per 10 sqm (IRC 37-
2018, Cl. 8.3)
d) Overhead charges @ 2.615% on (a+b+c) 13551.79
e) Contractor's profit @ 10% on (a+b+c+d) 53178.46
Add Seigniorage Fee cum 102.500 75.00 7687.50
Add District Mineral Fund (DMF) 30% on Seinorage 0.300 7687.50 2306.25
charges
Cost for 10250 sqm = a+b+c+d+e 594956.78
Rate per sqm = (a+b+c+d+e)/10250 58.04
a) Add Lead charges for metal 25.00 Km 4.50
b) Add lead charges for Bitumen 250.00 Km 0.51
say 63.00
Note Since seal coat is provided immediately over the bituminous
layers, mechanical broom for clearing has not been catered.

SOR 2018-19 Roads-Base Courses

RA - 33
CEMENT CONCRETE PAVEMENTS
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
6.1 601 Dry Lean Cement Concrete Sub- base
Construction of dry lean cement concrete Sub- base over a
prepared sub-grade with coarse and fine aggregate
conforming to IS: 383, the size of coarse aggregate not
exceeding 25 mm, aggregate cement ratio not to exceed
15:1, aggregate gradation after blending to be as per table
600-1, cement content not to be less than 150 kg/ cum,
optimum moisture content to be determined during trial
length construction, concrete strength not to be less than 10
Mpa at 7 days, mixed in a batching plant, transported to site,
laid with a paver with electronic sensor, compacting with 8-
10 tonnes vibratory roller, finishing and curing.

Unit = cum
Taking output = 450 cum (990 tonne)
a) Labour
Mate day 1.120 451.00 505.12
Mazdoor skilled day 6.000 515.00 3090.00
Mazdoor day 22.000 400.00 8800.00
b) Machinery
Front end loader 1 cum bucket capacity hour 6.000 1594.70 9568.20
Cement concrete batch mix plant @ 75 cum per hour hour 6.000 1310.90 7865.40

Electric generator 100 KVA hour 6.000 1316.30 7897.80


Paver with electronic sensor hour 6.000 3115.20 18691.20
Vibratory roller 8-10 t capacity hour 8.000 2736.20 21889.60
Water tanker6 KL capacity hour 8.000 655.20 5241.60
Tipper tonne.km 990 x L 6.56 51931.99

Add 10 per cent of cost of carriage to cover cost of loading 5193.20


and unloading
c) Material
Crushed stone coarse aggregate of 25 mm and 12.5 cum 405.000 1096.00 443880.00
mm nominal sizes graded as per table 600-1 @ 0.90
cum/cum of concrete conforming to clause 602.2.4.

Coarse Sand as per IS: 383 @ 0.45 cum/cum of cum 203.000 182.00 36946.00
concrete
Cement @ 150 kg/cum of concrete tonne 67.500 3900.00 263250.00
Cost of water KL 48.000 77.00 3696.00
d) Overhead charges @ 2.615% on (a+b+c) 23232.87
e) Contractor's profit @ 10% on (a+b+c+d) 91167.90
Add seignorage charges for metal cum 405.000 75.00 30375.00
Add seignorage charges for sand cum 203.000 50.00 10150.00
Add District Mineral Fund (DMF) 30% on Seinorage 0.300 40525.00 12157.50
charges
Cost for 205 cum = a+b+c+d+e 1055529.38
Rate per cum = (a+b+c+d+e)/450 2345.62
say 2346.00
Add lead charges of metal 25.00 Km 0.900 449.50 404.55
Add lead charges of sand 41.00 Km 0.451 718.12 323.95
Add lead charges of Manufactured Sand 25.00 Km 0.000 505.00 0.00
3074.50
Say 3075.00
Note Quantity provided for aggregate is for estimating purpose.
Exact quantity shall be as per mix design.

SOR 2018-19 Roads-CC Pavement

RA - 34
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
6.2 602 Cement Concrete Pavement
Construction of un-reinforced, dowel jointed, plain cement
concrete pavement over a prepared sub base with 43 grade
cement @ 400 kg per cum, coarse and fine aggregate
conforming to IS 383, maximum size of coarse aggregate
not exceeding 25 mm, mixed in a batching and mixing plant
as per approved mix design, transported to site, laid with a
fixed form or slip form paver, spread, compacted and
finished in a continuous operation including provision of
contraction, expansion, construction and longitudinal joints,
joint filler, separation membrane, sealant primer, joint
sealant, debonding strip, dowel bar, tie rod, admixtures as
approved, curing compound, finishing to lines and grades as
per drawing
Unit = cum
Taking output = 1050 cum (2415 tonne)
a) Labour
Mate day 2.000 451.00 902.00
Mazdoor skilled day 15.000 515.00 7725.00
Mazdoor day 35.000 400.00 14000.00
b) Machinery
Road Sweeper @ 1250 sqm per hour hour 2.800 381.80 1069.04
Front end loader 1 cum bucket capacity hour 18.000 1594.70 28704.60
Cement concrete batch mix plant @ 175 cum per hour hour 6.000 1310.90 7865.40
(effective output)
Electric generator 250 KVA hour 6.000 2162.60 12975.60
Slip form paver with electronic sensor hour 6.000 3247.20 19483.20
Water tanker6 KL capacity hour 36.000 655.20 23587.20
Transit truck agitator 5 cum capacity. tonne.km 2415xL 6.56 126682.59

Add 10 per cent of cost of carriage to cover cost of loading 12668.26


and unloading
Concrete joint cutting machine . hour 12.000 332.00 3984.00
Texturing machine . hour 12.000 450.00 5400.00
c) Material
Crushed stone coarse aggregates of 25mm and cum 945.000 1096.00 1035720.00
12.5mm nominal size @ 0.90 cum/cum of concrete
conforming to clause 602.2.4. .
Sand as per IS: 383 and conforming to clause 602.2.4 cum 473.000 182.00 86086.00
@ 0.45 cum/cum of concrete
Cement 43 grade @ 400 kg/cum of concrete tonne 414.000 3900.00 1614600.00
32 mm mild steel dowel bars of grade S 240 tonne 9.450 39674.00 374919.30
16 mm deformed steel tie bars of grade S 415 tonne 1.170 42500.00 49725.00
Separation Membrane of impermeable plastic sheeting sqm 3675.000 14.35 52736.25
125 micron thick
Pre moulded Joint filler, 25 mm thick for expansion sqm 16.330 262.00 4278.46
joint.
Joint sealant kg 875.000 58.00 50750.00
Sealant primer kg 116.670 476.00 55534.92
Plastic sheath,1.25 mm thick for dowel bars sqm 46.670 47.00 2193.49
Curing compound liter 1850.000 101.00 186850.00
Super plastisizer admixture IS marked as per 9103- kg 2070.000 43.00 89010.00
1999 @ 0.5 per cent by weight of cement
Cost of water KL 216.000 77.00 16632.00

SOR 2018-19 Roads-CC Pavement

RA - 35
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Add 1 per cent of material for cost of miscellaneous 36190.35
materials like tarpauline, Hessian cloth, metal cap, cotton /
compressible sponge and cradle for dowel bars, work
bridges for men to approach concrete surface without
walking over it, cutting blades and bites, minor equipments
like scabbling machine, threads, ropes, guide wires and any
other unforeseen items.
d) Overhead charges @ 2.615% on (a+b+c) 102515.13
e) Contractor's profit @ 10% on (a+b+c+d) 402278.78
Add seignorage charges for metal cum 945.000 75.00 70875.00
Add seignorage charges for sand cum 473.000 50.00 23650.00
Add District Mineral Fund (DMF) 30% on Seinorage 0.300 94525.00 28357.50
charges
Cost for 1050cum = a+b+c+d+e 4547949.08
Rate per cum = (a+b+c+d+e)/1050 4331.38
say 4331.00
Add lead charges of metal 25.00 Km 0.900 449.50 404.55
Add lead charges of sand 41.00 Km 0.450 718.12 323.50
Add lead charges of Manufactured Sand 25.00 Km 0.000 505.00 0.00
728.05
Say 5059.00
Note The quantities for cement, coarse aggregate and fine
aggregates are for estimating only .The exact quantities will
be as per mix design.

SOR 2018-19 Roads-CC Pavement

RA - 36
CHAPTER-7
GEOSYNTHETICS AND REINFORCED EARTH
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
7.5 3100 Reinforced Earth Structures
Reinforced earth Structures have four main components as
under:
a) Excavation for foundation, foundation concrete and
cement concrete grooved seating in the foundation for facing
elements (facia material).
b) Facia material and its placement.
c) Assembling, joining with facing elements and laying of
the reinforcing elements.
d) Earth fill with granular material which is to be retained
by the wall.
Each component is analysed separately as under:
considering Average height of wall = 8 m.
7.5(i) B With reinforcing elements of synthetic geogrids
Unit = sqm
Taking output = 300 sqm
a) Labour
Mate day 0.360 451.00 162.36
Mazdoor day 6.000 400.00 2400.00
Mazdoor skilled day 3.000 515.00 1545.00
b) Material
Synthetic Geogrids as per clause 3102.8 and approved
sqm 300.000 500.00 150000.00
design and specifications.
Add 10 per cent of the cost of reinforcing elements
(synthetic geogrids) for accessories like tie-strips, nuts
and bolts and loops/lugs for joining reinforcing elements 15000.00
with the facia panels, overlaps and other protective
elements for synthetic geogrids.
c) Overhead charges @ 2.615% on (a+b) 4422.16
d) Contractor's profit @ 10% on (a+b+c) 17352.95
Cost of 300 sqm of Synthetic geogrids = a+b+c+d 190882.47
Rate per sqm = (a+b+c+d)/ 300 636.27
say 636.00
7.5 3104 (ii) Facing elements of RCC
Unit = sqm
Taking output = 75 sqm
a) Labour
Mate day 0.180 451.00 81.18
Mazdoor day 3.000 400.00 1200.00
Mazdoor skilled day 1.500 515.00 772.50
b) Machinery
Light crane with lifting capacity up to 3 tonne hour 6.000 429.60 2577.60
c) Material
Pre-cast RCC M-35 facing elements of size as per
design and 18 cm thick for 75 sqm. (Refer Item 12.8 (H)) cum 13.500 4796.00 64746.00

HYSD steel @ 5 kg / sqm (Refer Item 13.6) tonnes 0.380 54927.00 20872.26
Add 2 per cent of cost of facia panels, for all necessary
temporary form work, scaffolding and provision of loops/lugs
1712.37
for lifting of panels and joining the reinforcing elements.

SOR 2018-19 Roads-Summary


RA - 37
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
d) Overhead charges @ 2.615% on (a+b) 121.11
e) Contractor's profit @ 10% on (a+b+c) 475.24
Cost for 75 sqm = a+b+c+d+e 92558.25
Rate per sqm = (a+b+c+d+e)/ 75 1234.11
say 1234.00

Consiolidated Rate Analysis for Fascia & Reinforcement

Unit = sqm
Taking output = 1 sqm
c) Material
Facing elements of RCC Sq.m 1.000 1234.00 1234.00
Synthetic Geogrids as per clause 3102.8 and approved Sq.m 5.517 636.00 3508.81
design and specifications.
d) Overhead charges @ 3% on (a+b) 124.02
e) Contractor's profit @ 10% on (a+b+d) 486.68
Cost for 1 sqm = c+d+e 5353.52
Rate per sqm = (c+d+e)/1Sqm say 5354.00

Note 1.The specification and construction details to be adopted


shall be as per section 3100 of MoRTH Specification.

2. Drainage arrangement shall be made as per approved


design and drawings.
3.The quantity of filler media shall be calculated as per
approved design and specifications and shall be priced
separately. The rate for same to be adopted from chapter 15.

4.Excavation for foundation including foundation concrete


and groove in the foundation for seating of bottom most facia
panel and capping beam to be calculated as per design and
priced separately. The rates for excavation and foundation
concrete shall be taken from the chapter 12 & 13 in bridge
section.
5.The earth fill to be retained is not included in this analysis.
The same is to be worked out and provided separately
complete as per clause 305.
, 6.For compaction of Earthwork, attention is invited to clause
3105.5 of MoRTH Specification.
7.Length of reinforcing strips will vary with the height of wall
and will be as per approved design and drawings.
8.The type of reinforcing elements to be adopted shall be as
per approved design and specifications.
9.The market rate for supply of reinforcing elements and their
accessories are to be ascertained from reputed firms in the
field of earth reinforcement.
10.The earth fill material shall be clean, free draining,
granular with high friction and low cohesion, non-corrosive,
coarse grained with not 10 per cent of particles passing 75
micron sieve, free of any deleterious matter, chlorides, salts,
acids, alkalies, mineral oil, fungus and microbes and shall be
of specified PH value.

SOR 2018-19 Roads-Summary


RA - 38
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
11.Capping beam is to be priced separately as per approved
design. The rate for cement concrete shall be taken from the
chapter of sub-structure in bridge section.

12.The cost of reinforced earth retaining wall shall include


following:
(I) Excavation for foundation including backfilling.
(ii) Foundation concrete as per approved design.
(iii) Cost of facial panels and their erection .
(iv) Cost of reinforcing elements including their fixing and
joining with the facial panels.
(v) Drainage arrangement including filter media as per
approved design and drawings.
13. The compacted earth filling to be retained shall form part
of embankment.

3.18 305 Construction of Subgrade and Earthen Shoulders


Construction of sub-grade and earthen shoulders with
approved material obtained from borrow pits with all lifts &
leads, transporting to site, spreading, grading to required
slope and compacted to meet requirement of table No. 300-2

Unit = cum
Taking output = 100 cum
a) Labour
Mate day 0.040 451.00 18.04
Mazdoor day 1.000 400.00 400.00
b) Machinery
Hydraulic excavator1 cum bucket capacity @ 60 cum hour 1.670 2791.60 4661.97
per hour
Tipper 10 tonne capacity tonne.km 175xL 6.56 5737.44

Add 10 per cent of cost of carriage to cover cost of 573.74


loading and unloading
Dozer 80 HP for spreading @ 200 cum per hour hour 0.500 2454.60 1227.30
Motor grader for grading @ 100 cum per hour hour 1.000 3020.40 3020.40
Water tanker with 6 km lead hour 4.000 655.20 2620.80
Vibratory roller 8-10 tonnes @ 80 cum per hour hour 1.250 2736.20 3420.25
c) Material
Cost of water KL 24.000 77.00 1848.00
Compensation for earth taken from private land cum 100.000 110.00 11000.00
d) Overhead charges @ 2.615% on (a+b+c) 902.91
e) Contractor's profit @ 10% on (a+b+c+d) 3543.08
add Seigniorage charges cum 100.000 30.00 3000.00
Add District Mineral Fund (DMF) 30% on Seinorage 0.300 3000.00 900.00
charges
Cost for 100 cum = a+b+c+d+e 42873.93
Rate per cum = (a+b+c+d+e)/100 428.74
say 429.00

SOR 2018-19 Roads-Summary


RA - 39
8.23 810 Metal Beam Crash Barrier
A Type - A, "W" : Metal Beam Crash Barrier

Providing and erecting a "W" metal beam crash barrier


comprising of 3 mm thick corrugated sheet metal beam rail,
70 cm above road/ground level, fixed on ISMC series
channel vertical post, 150 x 75 x 5 mm spaced 2 m centre to
centre, 1.8 m high, 1.1 m below ground/road level, all steel
parts and fitments to be galvanised by hot dip process, all
fittings to conform to IS:1367 and IS:1364, metal beam rail to
be fixed on the vertical post with a spacer of channel section
150 x 75 x 5 mm, 330 mm long complete as per clause 810

Unit = Running metre


Taking output = 4.5 metre length
a) Labour
Mate day 0.060 451.00 27.06
Blacksmith day 0.500 482.20 241.10
Mazdoor day 1.000 400.00 400.00
b) Machinery
Tractor-trolley hour 0.100 413.60 41.36
c) Material
Corrugated sheet,3 mm thick, "W" beam section 61.00 2513.81
kg 41.210
railing,4.5 m in length
Channel post 150 x 75 x 5 mm,1.8 m long,3 Nos @ 42.00 3719.52
kg 88.560
16.4 kg per metre
Spacer 150 x 75 x 5 mm channel 0.33 m long,3 Nos @ 42.00 682.08
kg 16.240
16.4 kg per metre
Nuts and bolts kg 20.000 85.00 1700.00
Add 25 per cent of the cost of material for fabrication, nuts,
2153.85
bolts and washers etc.)
d) Overhead charges @ 2.615% on (a+b+c) 300.17
e) Contractor's profit @ 10% on (a+b+c+d) 1177.90
Cost for 4.5 metre = a+b+c+d+e 12956.85

Earth work Excavation of pits of 1.1m depth


Add Cum 0.198 177.00 35.05
(2*0.300*0.300*1.1= 0.198) for 4.5m beam
Add PCC M15 for pits (2*0.3*0.3*1.1=0.198) for 4.5m beam cum 0.198 4729.00 936.34
Total Cost for 4.5m beam 13928.24
Rate per metre = (a+b+c+d+e)/4.5 3095.164
say 3095.00

RA - 40
Rate Analysis as per approved SOR 2018-19

Fencing With Welded Steel Wire Fabric 75


8.19 Suggestiv
mm x 50 mm
e
Providing 2.50 metre high fencing with angle
iron posts 50 mm x 50 mm x 5 mm at 2 metre
center to center with 0.90 metre embedded in
M15 grade cement concrete, corner, end and
every 15th post to be strutted, provided with
welded steel wire fabric of 75 mm x 50 mm
mesh and fixed to iron posts by flat iron 50 x 5
mm and bolts etc. complete in all respects.

Unit = Running metre


Taking output = 30 metres
i)Excavation for foundation of MS steel wire
fencing (16 Nos) cum 3.240 176.00 570.24
16 x 0.45 x 0.45 x 1.0
ii)PCC M-15 for foundation of MS fencing
cum 3.240 4729.00 15321.96
concrete 16 x 0.45 x 0.45 x 1.0
iii)Enamel Painting over MS Fencing
i) 30 Nos of 50mm x 50mmx5mm ISA (4.5
kg/m) of 3.5m length for vertical members sqm 22.050
(3.5x30)x(4x0.050+2x0.005)
ii) 30 Nos of 50mmx5mm flat of 3m length
for horizontal members & 10 Nos of
50mmx6mm flat of 2.5m length for
sqm 12.650
Vertical members
(3x30)x(2x0.050+2x0.005)+(2.5x10)x(4x0
.05+2x.005)
Total area of painting over MS Fencing 68.00
sqm 34.700 2359.60
(Exclusing steel wire)
a) Labour (For fixing at site)
Mate day 0.25 451.00 112.75
Welder day 2.08 482.20 1004.58
Mazdoor day 4.17 400.00 1666.67
b) Material
Structural Steel
i) Welded steel wire fabric 75x50 mm
mesh @ 4 kg/sqm,4 x 30 x 2.5 + 5 per Kg 315.000 131.00 41265.00
cent wastage
ii) 30 Nos of 50mm x 50mmx6mm ISA
(4.5 kg/m) of 3.5m length for vertical Kg 472.500 42.00 19845.00
members (3.5x21)x4.5
ii) Runner flat 50 x 5 mm Kg 196.000 42.00 8232.00
iv) 11 Nos of 20mm dia & 50mm lengthy
Bolts and Nuts @0.743 kg/each Kg 8.173 85.00 694.71
(6x0.743 kg/each)
Add 2.5 per cent of cost of material for
drilling holes in angles, flats, splitting
1750.92
angle at bottom, nuts and bolts and
welded consumables
c) Machinery
Tractor-trolley hour 0.040 413.60 16.54
d) Overhead charges @ 3% on (a+b+c) 1950.48

e) Contractor's profit @ 10% on (a+b+c+d) 7889.82


Cost for 9 metre =i+ii+iii+ a+b+c+d+e 102680.27
Rate per metre = (i+ii+iii+iv+a+b+c+d+e)/9 3422.68
say 3423.00

RA - 41
CHAPTER-8
TRAFFIC SIGNS, MARKINGS & OTHER ROAD APPURTENANCES
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
8.1 408 Cast in Situ Cement Concrete M20 Kerb
Construction of cement concrete kerb with top and bottom
width 115 and 165 mm respectively, 250 mm high in M 20
grade PCC on M-10 grade foundation 150 mm thick,
foundation having 50 mm projection beyond kerb stone, kerb
stone laid with kerb laying machine, foundation concrete laid
manually, all complete as per clause 408
Unit = Running metre
Taking output = 360 metre
A. Using Concrete Mixer
Cement Concrete
Cement concrete of grade M20 = 12.60 cum
Cement concrete of grade M10 for base= 11.61 cum
Total Concrete = 24.21 cu.m
a) Labour
Mate day 0.720 451.00 324.72
Mason day 2.000 455.00 910.00
Mazdoor day 16.000 400.00 6400.00
b) Machinery
Kerb casting machine @ 60 metres/hour hour 6.000 671.90 4031.40
Concrete mixer 0.48/0.28 cum capacity hour 12.000 525.50 6306.00
Water tanker6 KL capacity hour 5.000 655.20 3276.00
c) Material
Crushed stone aggregate 20 mm nominal size 59 per 1303.00 28392.37
cum 21.790
cent
Coarse sand 30 per cent cum 10.900 182.00 1983.80
Cement 11 per cent tonne 5.700 3900.00 22230.00
Cost of water KL 30.000 77.00 2310.00
d) Overhead charges @ 2.615% on (a+b+c) 1991.70
e) Contractor's profit @ 10% on (a+b+c+d) 7815.60
Add seignorage charges for metal cum 21.790 75.00 1634.25
Add seignorage charges for sand cum 10.900 50.00 545.00
Add District Mineral Fund (DMF) 30% on Seinorage 0.300 2179.25 653.78
charges
Cost for 360 meter = a+b+c+d+e 88804.61
Rate per metre = (a+b+c+d+e)/360 246.68
Add lead charges of metal 25.00 Km 0.061 449.50 27.21
Add lead charges of sand 41.00 Km 0.030 718.12 21.74
Add lead charges of Manufactured Sand 25.00 Km 0.000 505.00 0.00
295.63
say 296.00
B Using Concrete Batching and Mixing Plant
Cement Concrete
Cement concrete of grade M20 = 12.60 cum
Cement concrete of grade M10 for base = 11.61 cum
Total Concrete = 24.21 cu.m
a) Labour
Mate day 0.120 451.00 54.12
Mason day 1.000 455.00 455.00
Mazdoor day 2.000 400.00 800.00
b) Machinery
Kerb casting machine @ 60 metres/hour hour 6.000 671.90 4031.40
Concrete batching and mixing plant @ 15 cum/hr. hour 1.600 1083.10 1732.96
Water tanker6 KL capacity hour 5.000 655.20 3276.00
Tipper 5.5 cum capacity hour 6.000 950.30 5701.80
c) Material
Crushed stone aggregate 20 mm nominal size 59 per 1303.00 28392.37
cum 21.790
cent
Coarse sand 30 per cent cum 10.900 182.00 1983.80
Cement 11 per cent tonne 5.700 3900.00 22230.00

SOR 2018-19 Roads-Traffic Signs

RA - 42
CHAPTER-8
TRAFFIC SIGNS, MARKINGS & OTHER ROAD APPURTENANCES
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Cost of water KL 30.000 77.00 2310.00
d) Overhead charges @ 2.615% on (a+b+c) 1855.80
e) Contractor's profit @ 10% on (a+b+c+d) 7282.32
Add seignorage charges for metal cum 21.790 75.00 1634.25
Add seignorage charges for sand cum 10.900 50.00 545.00
Add District Mineral Fund (DMF) 30% on Seinorage 0.300 2179.25 653.78
charges
Cost for 360 meter = a+b+c+d+e 82938.60
Rate per metre = (a+b+c+d+e)/360 230.38
say 230.00
Add lead charges of metal 25.00 Km 0.061 449.50 27.21
Add lead charges of sand 41.00 Km 0.030 718.12 21.74
Add lead charges of Manufactured Sand 25.00 Km 0.000 505.00 0.00
278.95
say 279.00
8.4 801 Retro-Reflectorised Traffic Signs

Providing and fixing of retro- reflectorised cautionary,


mandatory and informatory sign as per IRC :67 made of high
intensity grade sheeting vide clause 801.3, fixed over
aluminium sheeting, 1.5 mm thick supported on a mild steel
angle iron post 75 mm x 75 mm x 6 mm firmly fixed to the
ground by means of properly designed foundation with M15
grade cement concrete 45 cm x 45 cm x 60 cm, 60 cm below
ground level as per approved drawing

Unit = Each
Taking output = one traffic sign
416.00 89.86
i) Excavation for foundation cum 0.216
4729.00 567.48
ii) Cement concrete M15 grade cum 0.120
iii) Painting angle iron post two coats sqm 0.430 68.00 29.24
a) Labour (For fixing at site)
Mate day 0.010 451.00 4.51
Mazdoor day 0.250 400.00 100.00
b) Material
42.00 798.00
Mild steel angle iron 75 x 75 x 6 mm kg 19.000
Aluminium sheeting fixed with encapsulated lens type
reflective sheeting of size including lettering and signs as
applicable
Add 2 per cent of cost of angle iron towards cost of drilling
holes, nuts, bolts etc.
(i) 90 cm equilateral triangle sqm 0.350 819.00 286.65
or
( ii ) 60 cm equilateral triangle sqm 0.156 819.00 127.76
or
( iii ) 60 cm circular sqm 0.283 819.00 231.78
or
( iv ) 80 mm x 60 mm rectangular sqm 0.480 819.00 393.12
or
(v) 60 cm x 45 cm rectangular sqm 0.270 819.00 221.13
or
(vi ) 60 cm x 60 cm square sqm 0.360 819.00 294.84
or
( vii ) 90 cm high octagon sqm 0.672 819.00 550.37
c) Machinery
Tractor-trolley hour 0.010 413.60 4.14
(i) 90 cm equilateral triangle
d) Overhead charges @ 2.615% on (a+b+c) 31.20

SOR 2018-19 Roads-Traffic Signs

RA - 43
CHAPTER-8
TRAFFIC SIGNS, MARKINGS & OTHER ROAD APPURTENANCES
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
e) Contractor's profit @ 10% on (a+b+c+d) 122.45
Rate per traffic sign = ( i+ii+iii+a+b+c+d+e) 2033.53
say 2034.00
( ii ) 60 cm equilateral triangle
d) Overhead charges @ 2.615% on (a+b+c) 27.05
e) Contractor's profit @ 10% on (a+b+c+d) 106.15
Rate per traffic sign = ( i+ii+iii+a+b+c+d+e) 1854.18
say 1854.00
( iii ) 60 cm circular
d) Overhead charges @ 2.615% on (a+b+c) 29.77
e) Contractor's profit @ 10% on (a+b+c+d) 116.82
Rate per traffic sign = ( i+ii+iii+a+b+c+d+e) 1971.59
say 1972.00
( iv ) 80 mm x 60 mm rectangular
d) Overhead charges @ 2.615% on (a+b+c) 33.99
e) Contractor's profit @ 10% on (a+b+c+d) 133.38
Rate per traffic sign = ( i+ii+iii+a+b+c+d+e) 2153.71
say 2154.00
(v) 60 cm x 45 cm rectangular
d) Overhead charges @ 2.615% on (a+b+c) 29.49
e) Contractor's profit @ 10% on (a+b+c+d) 115.73
Rate per traffic sign = ( i+ii+iii+a+b+c+d+e) 1959.57
say 1960.00
(vi ) 60 cm x 60 cm square
d) Overhead charges @ 2.615% on (a+b+c) 31.42
e) Contractor's profit @ 10% on (a+b+c+d) 123.29
Rate per traffic sign = ( i+ii+iii+a+b+c+d+e) 2042.77
say 2043.00
( vii ) 90 cm high octagon
d) Overhead charges @ 2.615% on (a+b+c) 38.10
e) Contractor's profit @ 10% on (a+b+c+d) 149.51
Rate per traffic sign = ( i+ii+iii+a+b+c+d+e) 2331.20
say 2331.00
1.Any one area of aluminium sheeting given at (i) to (vii) may
Note be adopted as per site requirement and in accordance with
IRC : 67
2.Rate for excavation, cement concrete M-15 and painting
may be taken from respective chapters
3. The depth of foundation and quantity of cement concrete
in the foundation are indicative. These may be increased for
areas having higher wind velocities like in coastal areas. This
is applicable to all road signs and directions boards.
Direction and Place Identification Signs upto 0.9 sqm
8.5 801
Size Board.

Providing and erecting direction and place identification retro-


reflectorised sign as per IRC:67 made of high intensity grade
sheeting vide clause 801.3, fixed over aluminium sheeting, 2
mm thick with area not exceeding 0.9 sqm supported on a
mild steel single angle iron post 75 x 75 x 6 mm firmly fixed
to the ground by means of properly designed foundation with
M15 grade cement concrete 45 x 45 x 60 cm, 60 cm below
ground level as per approved drawing
Unit = sqm
Taking output = 0.9 sqm
416.00 89.86
i) Excavation for foundation cum 0.216
4729.00 567.48
ii) Cement concrete M15 grade cum 0.120

SOR 2018-19 Roads-Traffic Signs

RA - 44
CHAPTER-8
TRAFFIC SIGNS, MARKINGS & OTHER ROAD APPURTENANCES
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
iii) Painting angle iron post two coats sqm 0.430 68.00 29.24
a) Labour (For fixing at site)
Mate day 0.010 451.00 4.51
Mazdoor day 0.200 400.00 80.00
b) Material
Mild steel angle iron 75 mm x 75 mm x 6 mm,2.85 42.00 798.00
kg 19.000
metres long
Aluminium sheeting fixed with encapsulated lens type 819.00 737.10
sqm 0.900
reflective sheeting of size 0.9 sqm
Add 2 per cent of cost of materials for drilling holes, nuts,
bolts, fabrication etc.
c) Machinery
Tractor-trolley hour 0.020 413.60 8.27
d) Overhead charges @ 2.615% on (a+b+c) 42.57
e) Contractor's profit @ 10% on (a+b+c+d) 167.05
Cost for 0.9 sqm =I+ii+ii+ a+b+c+d+e 2524.07
Rate per sqm (for sign having area upto 0.9 sqm) =
2804.52
(I+ii+iii+a+b+c+d+e)/0.90
say 2805.00
I) Lettering and arrow marks on sign board to be provided
Note separately as per actual requirement. Rates for these items
have been analysed separately
ii) Rate for excavation, cement concrete M-15 and painting
may be taken from respective chapters
Direction and Place Identification Signs with size more
8.6 801
than 0.9 sqm size Board.

Providing and erecting direction and place identification retro-


reflectorised sign as per IRC :67 made of high intensity grade
sheeting vide clause 801.3, fixed over aluminium sheeting, 2
mm thick with area exceeding 0.9 sqm supported on a mild
steel angle iron post 75 mm x 75 mm x 6 mm, 2 Nos. firmly
fixed to the ground by means of properly designed foundation
with M 15 grade cement concrete45 cm x 45 cm x 60 cm, 60
cm below ground level as per approved drawing

Unit = sqm
Taking output = 1.50 sqm
416.00 178.88
i) Excavation for foundation cum 0.430
4729.00 1134.96
ii) Cement concrete M15 grade cum 0.240
iii) Painting angle iron post 2 coats sqm 0.860 68.00 58.48
a) Labour (For fixing at site)
Mate day 0.010 451.00 4.51
Mazdoor day 0.300 400.00 120.00
b) Material
Mild steel angle iron 75 mm x 75 mm x 6 mm, 2.85 42.00 1596.00
kg 38.000
metres long, 2 nos
Aluminium sheeting fixed with encapsulated lens type 819.00 1228.50
sqm 1.500
reflective sheeting
Add 2 per cent of cost of materials for drilling holes, nuts,
bolts, fabrication etc.
c) Machinery
Tractor-trolley hour 0.020 413.60 8.27
d) Overhead charges @ 2.615% on (a+b+c) 74.08
e) Contractor's profit @ 10% on (a+b+c+d) 303.14
Cost for 1.5 sqm =I+ii+ii+ a+b+c+d+e 4706.81
Rate per sqm ( for sign having area more than 0.9 sqm)
5229.79
= ( i+ii+iii+a+b+c+d+e)/1.50
say 5230.00

SOR 2018-19 Roads-Traffic Signs

RA - 45
CHAPTER-8
TRAFFIC SIGNS, MARKINGS & OTHER ROAD APPURTENANCES
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
i) Lettering and arrow marks on sign board to be provided
Note separately as per actual requirement. Rates for these items
have been analysed separately
ii) Rate for excavation, cement concrete M-15 and painting
may be taken from respective chapters
8.7 802 Overhead Signs

Providing and erecting overhead signs with a corrosion


resistant 2mm thick aluminium alloy sheet reflectorised with
high intensity retro-reflective sheeting of encapsulated lense
type with vertical and lateral clearance given in clause 802.2
and 802.3 and installed as per clause 802.7 over a designed
support system of aluminium alloy or galvanised steel
trestles and trusses of sections and type as per structural
design requirements and approved plans

A Truss and Vertical Support


Unit = tonne
Taking output = 1 tonne
a) Labour
Mate day 0.240 451.00 108.24
Blacksmith day 2.000 482.20 964.40
Mazdoor including for handling & fixing at site. day 4.000 400.00 1600.00
b) Material
Aluminium alloy/galvanised steel including 5 per cent 42000.00 44100.00
tonne 1.050
wastage
Add 1 per cent on cost of material for nuts, bolts and drilling
441.00
and welding consumables
Add 15 per cent on cost of material for fabrication of trusses
6681.15
as per approved design
c) Machinery
Crane 3 tonne capacity hour 3.000 429.60 1288.80
Truck hour 0.500 950.30 475.15
d) Overhead charges @ 2.615% on (a+b+c) 1455.48
e) Contractor's profit @ 10% on (a+b+c+d) 5711.42
Rate per tonne = (a+b+c+d+e) 62825.64
say 62826.00
8.7 B Aluminium Alloy Plate for Over Head Sign
Unit = sqm
Taking output = 1 sqm
a) Labour
Mate day 0.020 451.00 9.02
Blacksmith day 0.100 482.20 48.22
Mazdoor day 0.150 400.00 60.00
b) Material
Aluminium alloy plate,2 mm thick, fixed with high 323.00 323.00
sqm 1.000
intensity grade sheeting vide clause 801.3
Miscellaneous
Add 1 per cent of cost of labour for lifting arrangement, like
1.17
ladders, pulleys, ropes etc
c) Overhead charges @ 2.615% on (a+b) 11.54
d) Contractor's profit @ 10% on (a+b+c) 45.30
Rate per sqm = (a+b+c+d) 498.25
say 498.00
1. The cost of excavation and foundation concrete for fixing
of vertical support system to be worked out separately as per
Note
the approved drawing/design and to be included in the
estimate.

SOR 2018-19 Roads-Traffic Signs

RA - 46
CHAPTER-8
TRAFFIC SIGNS, MARKINGS & OTHER ROAD APPURTENANCES
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.

2. Lettering and arrow marks on sign board to be provided


separately as per actual requirement. Rates for these items
have been included separately in this chapter.
8.8 803 Painting Two Coats on New Concrete Surfaces
Painting two coats after filling the surface with synthetic
enamel paint in all shades on new plastered concrete
surfaces
Unit = sqm
Taking output = 40 sqm
a) Labour
Mate day 0.120 451.00 54.12
Painter day 2.000 473.00 946.00
Mazdoor day 1.000 400.00 400.00
b) Material
Paint conforming to requirement of clause 803.3. Litre 6.000 198.00 1188.00
Add for scaffolding @ 1 per cent of labour cost where
11.88
required
Add @ 5 per cent cost of labour and materials to 129.41
prepare the surface by filling minuts roughness on the
surface and priming the surface before laying 2 coats of
painting.
c) Overhead charges @ 2.615% on (a+b) 71.37
d) Contractor's profit @ 10% on (a+b+c) 280.08
Cost for 40 sqm = a+b+c+d 3080.86
Rate per sqm = (a+b+c+d)/40 77.02
say 77.00
8.9 803 Painting on Steel Surfaces
Providing and applying two coats of ready mix paint of
approved brand on steel surface after through cleaning of
surface to give an even shade
Unit = sqm
Taking output = 10 sqm
a) Labour
Mate day 0.030 451.00 13.53
Painter day 0.450 473.00 212.85
Mazdoor day 0.250 400.00 100.00
b) Material
Paint ready mixed approved brand. Litre 1.250 198.00 247.50
Add @ 1 per cent on cost of material for scaffolding 2.48
Add @ 5 per cent cost of labour and materials to 28.69
prepare the surface by filling minuts roughness on the
surface and priming the surface before laying 2 coats of
painting.
c) Overhead charges @ 2.615% on (a+b) 15.82
d) Contractor's profit @ 10% on (a+b+c) 62.09
Cost for 10 sqm = a+b+c+d 682.96
Rate per sqm= (a+b+c+d)/10 68.30
say 68.00
Road Marking with Hot Applied Thermoplastic
8.13 803 Compound with Reflectorising Glass Beads on
Bituminous Surface

Providing and laying of hot applied thermoplastic compound


2.5 mm thick including reflectorising glass beads @ 250 gms
per sqm area, thickness of 2.5 mm is exclusive of surface
applied glass beads as per IRC:35 .The finished surface to
be level, uniform and free from streaks and holes.
Unit = sqm
Taking output = 600 sqm

SOR 2018-19 Roads-Traffic Signs

RA - 47
CHAPTER-8
TRAFFIC SIGNS, MARKINGS & OTHER ROAD APPURTENANCES
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
a) Labour
Mate day 0.030 451.00 13.53
Mazdoor day 0.750 400.00 300.00
b) Machinery
Road marking machine @ 60 sqm per hour hour 10.000 135.50 1355.00
Tractor-trolley hour 0.500 413.60 206.80
c) Material
Hot applied thermoplastic compound Litre 1500.000 229.64 344460.00
Reflectorising glass beads kg 150.000 80.30 12045.00
d) Overhead charges @ 2.615% on (a+b+c) 9371.65
e) Contractor's profit @ 10% on (a+b+c+d) 36775.20
Cost for 600 sqm = a+b+c+d+e 404527.17
Rate per sqm = a+b+c+d+e)/600 674.21
say 674.00
1. A sealing primer may be applied in advance on cement
concrete pavement to ensure proper bonding. Any laitance
Note
and/or curing compound to be removed where paint is
required to be applied on concrete surface.
2.Cost of painter is already included in hire charges of road
marking machine.
8.14 804 Kilometre Stone
Reinforced cement concrete M15grade kilometre stone of
standard design as per IRC:8-1980, fixing in position
including painting and printing etc
(i) 5th kilometre stone (precast)
Unit = Nos.
Taking output = 6 Nos.
4729.00 11113.15
a) M-15 grade of concrete cum 2.350
54.93 1212.79
b) Steel reinforcement @ 5 kg per sqm kg 22.080
416.00 698.88
c) Excavation in soil for foundation cum 1.680
d) Painting two coats on concrete surface sqm 9.850 76.00 748.60
e) Lettering on km post (average 30 letters of 10 per cm per 0.70 1260.00
1800.000
cm height each) letter
Transportation and fixing
f) Labour
Mate day 0.260 451.00 117.26
Mason day 0.600 455.00 273.00
Mazdoor including loading/unloading day 6.000 400.00 2400.00
g) Machinery
Tractor-trolley hour 6.000 413.60 2481.60
h) Overhead charges @ 2.615% on (f+g) 137.86
i) Contractor's profit @ 10% on (f+g+h) 540.97
Cost for 6 Nos. 5th km stone = a+b+c+ d+e +f+g+h +i 20984.11
Rate for each 5th km stone = (a+b+c+ d+e +f+g+h +i )
3497.35
/6
say 3497.00
8.14 (ii) Ordinary kilometer stone (precast)
Unit = Nos.
Taking output = 14 Nos.
4729.00 17828.33
a) M-15 grade of concrete cum 3.770
54.93 1445.68
b) Steel reinforcement @ 5 kg per sqm kg 26.320
416.00 1152.32
c) Excavation in soil for foundation cum 2.770
d) Painting two coats on concrete surface sqm 11.410 76.00 867.16

SOR 2018-19 Roads-Traffic Signs

RA - 48
CHAPTER-8
TRAFFIC SIGNS, MARKINGS & OTHER ROAD APPURTENANCES
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
e) Lettering on km post ( average 12 letters of 10 per cm per 0.70 1176.00
1680.000
cm height each) letter
Transportation and fixing
f) Labour
Mate day 0.320 451.00 144.32
Mason day 1.000 455.00 455.00
Mazdoor day 7.000 400.00 2800.00
g) Machinery
Tractor-trolley hour 6.000 413.60 2481.60
h) Overhead charges @ 2.615% on (f+g) 153.79
i) Contractor's profit @ 10% on (f+g+h) 603.47
Cost for 14 Nos. ordinary km stone = (a+b+ c +d+e+f+g+h+i) 29107.67
Rate for each ordinary km stone = (a+b+ c
2079.12
+d+e+f+g+h+j) /14
say 2079.00
8.14 (iii) Hectometer stone (precast)
Unit = Nos.
Taking output = 33 Nos.
4729.00 7471.82
a) M-15 grade of concrete cum 1.580
54.93 3625.18
b) Steel reinforcement @ 5 kg per sqm kg 66.000
416.00 578.24
c) Excavation in soil for foundation cum 1.390
d) Painting two coats on concrete surface sqm 6.270 76.00 476.52
e) Lettering on km post (average 1 letter of 10 cm per cm per 0.70 231.00
330.000
height each) letter
Transportation and fixing
f) Labour
Mate day 0.340 451.00 153.34
Mason day 1.500 455.00 682.50
Mazdoor day 7.000 400.00 2800.00
g) Machinery
Tractor-trolley hour 6.000 413.60 2481.60
h) Overhead charges @ 2.615% on (f+g) 159.97
i) Contractor's profit @ 10% on (f+g+h) 627.74
Cost for 33 Nos. Hectometer stone = (a+b +c +d+e+f+ g+h+i) 19287.91
Rate for each Hectometer stone = (a+b +c +d+e+f+
584.48
g+h+i) 33
say 584.00
The rate for excavation, cement concrete, steel
Note reinforcement, painting and lettering may be taken from
respective chapters.
8.15 805 Road Delineators
Supplying and installation of delineators (road way indicators,
hazard markers, object markers), 80-100 cm high above
ground level, painted black and white in 15 cm wide strips,
fitted with 80 x 100 mm rectangular or 75 mm dia circular
reflectorised panels at the top, buried or pressed into the
ground and conforming toIRC-79 and the drawings.
Unit = Each
Taking output= 30 Nos.
a) Labour
Mate day 0.040 451.00 18.04
Mazdoor for fixing day 1.000 400.00 400.00
b) Material

SOR 2018-19 Roads-Traffic Signs

RA - 49
CHAPTER-8
TRAFFIC SIGNS, MARKINGS & OTHER ROAD APPURTENANCES
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
750.00 22500.00
Cost of approved type of delineators from ISI certified
each 30.000
firm as per the standard drawing given in IRC - 79
Add 10 per cent cost of material for installation 2250.00
c) Overhead charges @ 2.615% on (a+b) 658.14
d) Contractor's profit @ 10% on (a+b+c) 2582.62
Cost for 30 Nos. delineators = (a+b+ c+d) 28408.80
Rate per delineators = (a+b+c+d) /30 946.96
say 947.00
In case of soft ground, a proper foundation may be provided
as per approved design. In case foundation is required to be
Note
provided, the items of excavation and foundation concrete
are required to be measured and paid separately.
Tubular Steel Railing on Medium Weight Steel Channel (
8.20 808
ISMC series) 100 mm x 50 mm
Providing, fixing and erecting 50 mm dia steel pipe railing in
3 rows duly painted on medium weight steel channels (ISMC
series) 100 mm x 50 mm, 1.2 metres high above ground, 2 m
centre to centre, complete as per approved drawings
Unit = Running metre
Taking output = 10metres
i) Excavation for foundation (6 Nos)6 x 0.6 x 0.6 x 416.00 539.14
cum 1.296
0.6
ii) Foundation concrete M-15 grade PCC 6 x 0.6 x 4729.00 3064.39
cum 0.648
0.6 x 0.3
iii) Painting of pipe sqm 4.710 68.00 320.28
iv) Painting of channel section 6 nos,1.8 metres 68.00 146.88
sqm 2.160
each 0.2 x 1.8 x 6 = 2.16
a) Labour (For fixing at site)
Mate day 0.010 451.00 4.51
Mazdoor day 0.250 400.00 100.00
Plumber day 0.010 482.20 4.82
b) Material
Steel pipe 50 mm external dia as per IS:1239 metre 30.000 475.00 14250.00
42.00 4173.12
Medium weight steel channel (ISMC series) 100 mm x
kg 99.360
50 mm,10.8 metres length @ 9.2 kg per metre
Add for drilling holes @ 2 per cent of cost of channels 83.46
c) Machinery
Tractor-trolley hour 0.040 413.60 16.54
d) Overhead charges @ 2.615% on (a+b+c) 593.25
e) Contractor's profit @ 10% on (a+b+c+d) 2327.99
Cost for 10 metre =i+ii+iii+iv+ a+b+c+d+e 25624.39
Rate per metre = (i+ii+iii+iv+a+b+c+d+e)/10 2562.44
say 2562.00
Tubular Steel Railing on Precast RCC Posts, 1.2 m High
8.21 808
Above Ground Level
Providing, fencing and erecting 50 mm dia painted steel pipe
railing in 3 rows on precast M20 grade RCC vertical posts1.8
metres high (1.2 m above GL) with 3 holes 50 mm dia for
pipe, fixed 2 metres centre to, complete as per approved
drawing
Unit = Running metre
Taking output = 10metres
i) Excavation for foundation (6 Nos)6 x 0.6 x 0.6 x 416.00 539.14
cum 1.296
0.6
ii) Foundation concrete M - 15 grade PCC 6 x 0.6 x 4729.00 3064.39
cum 0.648
0.6 x 0.3

SOR 2018-19 Roads-Traffic Signs

RA - 50
CHAPTER-8
TRAFFIC SIGNS, MARKINGS & OTHER ROAD APPURTENANCES
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
iii) RCC M - 20 for pre cast posts 6 nos of 1.8 4922.00 1575.04
cum 0.320
metres each
iv) Painting of pipe sqm 4.710 68.00 320.28
a) Labour
Mate day 0.014 451.00 6.31
Mazdoor day 0.350 400.00 140.00
Plumber day 0.010 482.20 4.82
b) Material
Steel pipe 50 mm dia as per IS:1239 metre 30.000 475.00 14250.00
c) Machinery
Tractor-trolley hour 0.250 413.60 103.40
d) Overhead charges @ 2.615% on (a+b+c) 379.29
e) Contractor's profit @ 10% on (a+b+c+d) 1488.38
Cost for 10 metre =i+ii+iii+iv+ a+b+c+d+e 21871.06
Rate per metre = (i+ii+iii+iv+a+b+c+d+e)/10 2187.11
say 2187.00
8.22 809 Reinforced Cement Concrete Crash Barrier

Provision of an Reinforced cement concrete crash barrier at


the edges of the road, approaches to bridge structures and
medians, constructed with M-40 grade concrete with HYSD
reinforcement conforming to IRC:21 and dowel bars 25 mm
dia, 450 mm long at expansion joints filled with pre-moulded
asphalt filler board, keyed to the structure on which it is built
and installed as per design given in the enclosure to MOST
circular No. RW/NH - 33022/1/94-DO III dated 24 June 1994
as per dimensions in the approved drawing and at locations
directed by the Engineer, all as specified

Unit = Linear metre


Taking output = 10 m
(i) a) M 40 grade concrete
5427.00 16281.00
M 40 grade concrete cum 3.000
b) Labour
Mate day 0.040 451.00 18.04
Mazdoor day 1.000 400.00 400.00
c) Material
HYSD steel reinforcement including dowel bars tonne 0.280 42500.00 11900.00
Pre-moulded asphalt filler board sqm 0.320 580.00 185.60
d) Overhead charges @ 2.615% on (b+c) 326.97
e) Contractor's profit @ 10% on (b+c+d) 1283.06
Cost for 10 metre = a+b+c+d+e 30394.67
Rate per metre = (a+b+c+d+e)/10 3039.47
say 3039.00
i) Excavation and backfilling are incidental to work and not to
Note
be measured separately.
ii) Rate for RCC M 40 may be taken from chapter on super
structure.
8.23 810 Metal Beam Crash Barrier
A Type - A, "W" : Metal Beam Crash Barrier

Providing and erecting a "W" metal beam crash barrier


comprising of 3 mm thick corrugated sheet metal beam rail,
70 cm above road/ground level, fixed on ISMC series
channel vertical post, 150 x 75 x 5 mm spaced 2 m centre to
centre, 1.8 m high, 1.1 m below ground/road level, all steel
parts and fitments to be galvanised by hot dip process, all
fittings to conform to IS:1367 and IS:1364, metal beam rail to
be fixed on the vertical post with a spacer of channel section
150 x 75 x 5 mm, 330 mm long complete as per clause 810

SOR 2018-19 Roads-Traffic Signs

RA - 51
CHAPTER-8
TRAFFIC SIGNS, MARKINGS & OTHER ROAD APPURTENANCES
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Unit = Running metre
Taking output = 4.5 metre length
a) Labour
Mate day 0.060 451.00 27.06
Blacksmith day 0.500 482.20 241.10
Mazdoor day 1.000 400.00 400.00
b) Machinery
Tractor-trolley hour 0.100 413.60 41.36
c) Material
Corrugated sheet,3 mm thick, "W" beam section 61.00 2513.81
kg 41.210
railing,4.5 m in length
Channel post 150 x 75 x 5 mm,1.8 m long,3 Nos @ 42.00 3719.52
kg 88.560
16.4 kg per metre
Spacer 150 x 75 x 5 mm channel 0.33 m long,3 Nos @ 42.00 682.08
kg 16.240
16.4 kg per metre
Nuts and bolts kg 20.000 85.00 1700.00
Add 25 per cent of the cost of material for fabrication, nuts,
2153.85
bolts and washers etc.)
d) Overhead charges @ 2.615% on (a+b+c) 300.17
e) Contractor's profit @ 10% on (a+b+c+d) 1177.90
Cost for 4.5 metre = a+b+c+d+e 12956.85
Rate per metre = (a+b+c+d+e)/4.5 2879.30
say 2879.00
Suggesti
8.27 Street Lighting
ve
Providing and erecting street light mounted on a steel circular
hollow pole of standard specifications for street lighting, 9 m
high spaced 40 m apart, 1.8 m overhang on both sides if
fixed in the median and on one side if fixed on the footpath,
fitted with sodium vapour lamp and fixed firmly in concrete
foundation.
Unit = Each
Taking output = one light
a) Labour
Mate day 0.030 451.00 13.53
Mazdoor day 0.500 400.00 200.00
Electrician day 0.250 482.20 120.55
b) Material
i) Steel circular hollow pole of standard specification for 16876.00 16876.00
street lighting to mount light at 9 m height above road each 1.000
level
ii) Sodium vapour lamp each 1.000 3500.00 3500.00
Add 5 per cent of cost of material for holder, electric cable,
1018.80
insulation, ladder, scaffolding etc
c) Painting
For Fixing in Median
Providing two coats of alluminium paint over steel 68.00 391.00
sqm 5.750
circular hollow pipe with overhang on both sides
For fixing in Footpath
Providing two coats of alluminium paint over steel 68.00 314.84
sqm 4.630
circular hollow pipe with overhang on one side
(i) For Fixing in Median
d) Overhead charges @ 2.615% on (a+b) 568.21
e) Contractor's profit @ 10% on (a+b+d) 2229.71
Rate per light for fixing in Median= a+b+c+d+e 24917.80
say 24918.00
(ii) For fixing in Footpath
Rate per light for Fixing in Footpath = a+b+c+d+e 24841.64
say 24842.00

SOR 2018-19 Roads-Traffic Signs

RA - 52
CHAPTER-8
TRAFFIC SIGNS, MARKINGS & OTHER ROAD APPURTENANCES
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
The items of excavation and cement concrete foundation will
be measured and included separately in the estimate as per
Note
approved design and drawing. The rate for painting has been
analysed in this chapter.
Suggesti
8.28 Lighting on Bridges
ve
Providing and fixing lighting on bridges, mounted on steel
hollow circular poles of standard specifications, 5 m high
fixed on parapets with cement concrete, 20 m apart and fitted
with sodium vapour lamp
Unit = Each
Taking output = one light
a) Labour
Mate day 0.020 451.00 9.02
Mazdoor day 0.400 400.00 160.00
Electrician day 0.200 482.20 96.44
b) Material
7619.33 7619.33
i) Steel circular hollow pole of standard specification for
each 1.000
street lighting to mount light at 5 m above deck level
ii) Sodium vapour lamp 70 watt each 1.000 3500.00 3500.00
Add 1 per cent of cost of material for holder, electric cable,
111.19
insulation, ladder, scaffolding etc
c) Painting
Providing two coats of alluminium paint over steel 68.00 187.68
sqm 2.760
circular hollow pipe
d) Overhead charges @ 2.615% on (a+b) 300.62
e) Contractor's profit @ 10% on (a+b+d) 1179.66
Rate per light = a+b+c+d+e 13163.95
say 13164.00
The items of cement concrete to be measured and paid
Note separately as per approved design. The rate for painting has
already been analysed in this chapter.
Suggesti
8.35 Road Markers/Road Stud with Lense Reflector
ve
Providing and fixing of road stud 100x 100 mm, die-cast in
aluminium, resistant to corrosive effect of salt and grit, fitted
with lense reflectors, installed in concrete or asphaltic surface
by drilling hole 30 mm upto a depth of 60 mm and bedded in
a suitable bituminous grout or epoxy mortar, all as per BS
873 part 4:1973
Unit = Nos
Taking output = 50Nos
a) Labour
Mate day 0.040 451.00 18.04
Mazdoor day 1.000 400.00 400.00
b) Material
Aluminium studs 100 x 100 mm fitted with lense 200.00 10000.00
each 50.000
reflectors
Add 10 per cent of cost of material for fixing and installation 1000.00
c) Overhead charges @ 2.615% on (a+b) 298.58
d) Contractor's profit @ 10% on (a+b+c) 1171.66
Cost for 50 studs = a+b+c+d 12888.28
Rate per studs = (a+b+c+d)/50 257.77
say 258.00
Suggesti
8.38 Rumble Strips
ve

SOR 2018-19 Roads-Traffic Signs

RA - 53
CHAPTER-8
TRAFFIC SIGNS, MARKINGS & OTHER ROAD APPURTENANCES
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.

Provision of 15 nos rumble strips covered with premix


bituminous carpet, 15-20 mm high at center, 250 mm wide
placed at 1 m center to center at approved locations to
control speed, marked with white strips of road marking paint.
Unit = sqm
Taking output = 100 sqm (including gaps)
The rate per sqm of premix carpet and road marking may be
adopted from chapter 5 & 8 respectively for the quantities
calculated from approved drawings
The rate per sqm of premix carpet (chapter 5 ) Sqm 125.00
The rate per sqm of roadmarking (chapter 8) Sqm 674.00
Rate per Square metre = (a+b) 799.00

SOR 2018-19 Roads-Traffic Signs

RA - 54
CHAPTER-11
HORTICULTURE
Ref. to Remarks
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs / Input
H Spec. ref.
11.08 307 Planting and Maintaining of Flowering Plants
and Shrubs
(a) Planting flowering plants and shrubs in
central verge
Unit = Running metres 200 plants and 800
shrubs in two rows in one km length of road
where width of verge is 3m and above.
Taking output = 1000 metres
a) Labour
Mate day 1.200 451.00 541.20 L-12
Mazdoor day 12.000 400.00 4800.00 L-13
b) Machinery
Water tanker6 KL capacity hour 6.000 655.20 3931.20 P&M-060
c) Material
Plants each 200.000 40.00 8000.00 M-100
Shrubs each 800.000 15.00 12000.00 M-166
Manure sludge/Farm yard manure cum 63.640 150.00 9546.00 M-167
Pesticide kg 0.500 150.00 75.00 M-136
Cost of water KL 36.000 77.00 2772.00 M-189
d) Overhead charges @ 2.615% on (a+b+c)
1089.55
e) Contractor's profit @ 10% on (a+b+c+d)
4275.50
Rate per Km = (a+b+c+d+e) 47030.45
say 47030.00 km
11.08 (b) Maintenance of flowering plants and shrubs in
central verge for one year
Unit = km
Taking output = one km
a) Labour
Mate day 36.000 451.00 16236.00 L-12
Mazdoor day 365.000 400.00 146000.00 L-13
b) Machinery
Water tanker6 KL capacity hour 90.000 655.20 58968.00 P&M-060
c) Material
Manure Sludge / farm yard manure at site cum 10.000 150.00 1500.00 M-167
Cost of water KL 180.000 77.00 13860.00 M-189
Replacement of casualties @ 10 per cent
Plants each 20.000 40.00 800.00 M-100
Shrubs each 80.000 15.00 1200.00 M-166
Pesticides kg 1.500 150.00 225.00 M-136
d) Overhead charges @ 2.615% on (a+b+c) 6244.33
e) Contractor's profit @ 10% on (a+b+c+d)
24503.33
Rate per Km for one year = (a+b+c+d+e) 269536.67
say 269537.00 km
11.09 307 Planting of Trees and their Maintenance for
one Year
Planting of trees by the road side (Avenue trees)
in 0.60 m dia holes, 1 m deep dug in the ground,
mixing the soil with decayed farm yard/sludge
manure, planting the saplings, backfilling the
trench, watering, fixing the tree guard and
maintaining the plants for one year
Unit = Each
Taking output = 10 trees
a) Labour
Mate day 1.700 451.00 766.70 L-12
SOR 2018-19 Roads-Horticulture

RA - 55
CHAPTER-11
HORTICULTURE
Ref. to Remarks
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs / Input
H Spec. ref.
Mazdoor for planting day 2.000 400.00 800.00 L-13
Mazdoor for maintenance for one year day 15.000 400.00 6000.00 L-13
b) Machinery
Water tanker6 KL capacity hour 2.000 655.20 1310.40 P&M-060
c) Material
Sapling 2 m high 25 mm dia each 10.000 25.00 250.00 M-160
Farm yard manure cum 0.940 150.00 141.00 M-167
Pesticide kg 0.500 150.00 75.00 M-136
Cost of water KL 12.000 77.00 924.00 M-189
d) Overhead charges @ 2.615% on (a+b+c) 268.48
e) Contractor's profit @ 10% on (a+b+c+d) 1053.56
Cost for 10 trees = a+b+c+d+e 11589.14
Rate per trees = (a+b+c+d+e)/10 1158.91
say 1159.00 each
11.19 New Tree Guard with MS Iron
Providing and fixing MS iron tree guard 60 cm
dia and 2 metre high above ground level formed
of 4 Nos (25 x 6 mm) and 8 Nos (25 x 3 mm)
vertical MS riveted to 3 Nos (25 x 6 mm) iron
rings in two halves, bolted together with 8 mm
dia and 30 mm long bolts including painting two
coats with paint of approved brand over a coat of
priming, complete in all respects.
Unit = Each
Taking output = one tree guard
a) Labour
Mate day 0.050 451.00 22.55 L-12
Blacksmith day 0.250 440.00 110.00 L-01
Mazdoor day 0.250 400.00 100.00 L-13
b) Material
MS iron 25 x 6 mm M-179
kg 19.200 42.00 806.40
/1000
MS iron 25 x 3 mm M-179
kg 9.600 42.00 403.20
/1000
Add 5 per cent of cost of material for
riveting, bolting and welding accessories
c) Machinery
Tractor-trolley P&M-
hour 0.040 413.60 16.54
053
d) Painting
Painting two coats including priming sqm 1.770 68.00 120.36 Item 8.9
e) Overhead charges @ 2.615% on
41.29
(a+b+c+d)
f) Contractor's profit @ 10% on 162.03
(a+b+c+d+e)
Rate per tree guard =a+b+c+d+e+f 1782.38
say 1782.00 each
Note 1 The items of excavation and concreting to be
measured and paid separately as per design .
2 . Rate of painting may be adopted from the
chapter as Traffic signs.

SOR 2018-19 Roads-Horticulture

RA - 56
(A) Usage Rates of Plant and Machinery
Output of
Sl. No. Description of Machine Activity Output Unit Rate
Machine
P&M-001 Air Compressor General Purpose capacity in cfm 170/250 hour 556.50

P&M-002 Batching and Mixing Plant (a) 30 cum capacity Concrete Mixing cum/hour 20 hour 1343.30

P&M-003 Batching and Mixing Plant (b) 15 - 20 cum capacity Concrete Mixing cum/hour 13 hour 1083.10

P&M-004 Bitumen Pressure Distributor Applying bitumen tack coat sqm/hour 1750 hour 1527.10
P&M-005 Bitumen Boiler oil fired Bitumen Spraying capacity in litre 1500 hour 223.00
P&M-006 Concrete Paver Finisher with 40 HP Motor Paving of concrete surface cum / hour 20 hour 3247.20
P&M-007 Concrete Pump of 45 & 30 cum capacity Pumping of concrete cum / hour 33 / 22 hour 1508.80
P&M-008 Concrete Bucket For Pouring concrete capacity in cum 1 hour 12.90
P&M-009 Concrete Mixer (a) 0.4/0.28 cum Concrete Mixing cum/hour 2.5 hour 525.50
P&M-010 Concrete Mixer (b) 1 cum Concrete Mixing cum/hour 7.5 hour 661.50
P&M-011 Crane (a) 80 tonnes Lifting Purpose hour 1311.20
P&M-012 Cranes b) 35 tonnes Lifting Purpose hour 885.70
P&M-013 Cranes c) 3 tonnes Lifting Purpose hour 429.60
P&M-014 Dozer D - 80 - A 12 ( as per MORTH data ) Spreading /Cutting / Clearing cum/hour 300/ 150/250 hour 2454.60
P&M-015 Dozer D - 50 - A 15( as per MORTH data ) Spreading /Cutting / Clearing cum/hour 200/ 100/150 hour 1546.80
P&M-016 Emulsion Pressure Distributor Applying emulsion tack coat sqm/hour 1750 hour 875.60
P&M-017 Front End loader 1 cum bucket capacity Soil loading / Aggregate loading cum/hour 60 /25 hour 1594.70
P&M-018 Generator (a) 125 KVA Genration of electric Energy KVA 100 hour 1543.10
P&M-019 Generator( b) 63 KVA Genration of electric Energy KVA 50 hour 1,174.15
P&M-020 GSB Plant 50 cum Producing GSB cum/hour 40 hour 1279.70
P&M-021 Hotmix Plant - 120 TPH capacity DBM/BM/SDC/ Premix cum/hour 40 hour 28708.00
P&M-022 Hotmix Plant - 100 TPH capacity DBM/BM/SDC/ Premix cum/hour 30 hour 24636.00
P&M-023 Hotmix Plant - 60 to 90 TPH capacity DBM/BM/SDC/ Premix cum/hour 25 hour 22092.00
P&M-024 Hotmix Plant - 40 to 60 TPH capacity DBM/BM/SDC/ Premix cum/hour 17 hour 19546.00
P&M-025 Hydraulic Chip Spreader Surface Dressing sqm/hour 1500 hour 2743.70

P&M-026 Hydraulic Excavator of 1 cum bucket Soil Ordinary/Soil Marshy / Soil Unsuitable cum/hour 60 /60 /60 hour 2791.60

P&M-027 Integrated Stone Crusher 100TPH Crushing of Spalls TPH 100 hour 9755.20
P&M-028 Integrated Stone Crusher 200 TPH Crushing of Spalls TPH 200 hour 20570.00
P&M-029 Kerb Casting Machine Kerb Making Rm/hour 80 hour 671.90
P&M-030 Mastic Cooker Mastic Wearing coat capacity in tonne 1 hour 79.50
P&M-031 Mechanical Broom Hydraulic Surface Cleaning sqm/hour 1250 hour 381.80
P&M-032 Motor Grader 3.35 mtr blade Clearing /Spreading /GSB /WBM cum/hour 200/200/50/50 hour 3020.40
P&M-033 Mobile slurry seal equipment Mixing and laying slurry seal sqm/hour 2700 hour 1261.40
Paver Finisher Hydrostatic with sensor control 100
P&M-034 Paving of DBM/ BM/SDC/ Premix cum/hour 40 hour 3115.20
TPH
P&M-035 Paver Finisher Mechanical 100 TPH Paving of WMM /Paving of DLC cum/hour 40/30 hour 2290.60

P&M-036 Piling Rig with Bantonite Pump 0.75 m dia to 1.2 m dia Boring attachment Rm/hour 2 to 3 hour 6131.70

P&M-037 Pneumatic Road Roller Rolling of Asphalt Surface cum/hour 25 hour 1515.60
P&M-038 Pneumatic Sinking Plant Pneumatic Sinking of wells cum/hour 1.5 to 2.00 hour 5701.00
P&M-039 Pot Hole Repair Machine Repair of potholes cum/hour 4 hour 903.00
P&M-040 Prestressing Jack with Pump & access Stressing of steel wires/stands hour 157.80
P&M-041 Ripper Scarifying cum/hour 60 hour 423.60
P&M-042 Rotavator Scarifying cum/hour 25 hour 423.60
P&M-043 Road marking machine Road marking Sqm/hour 100 hour 135.50
P&M-044 Smooth Wheeled Roller 8 tonne(Adopted 10T) Soil Compaction /BM Compaction cum/hour 70/25 hour 1329.90
P&M-045 Tandem Road Roller Rolling of Aspalt Surface cum/hour 30 hour 1856.50
Transportation of soil, GSB, WMM, Hotmix
P&M-046 Tipper - 5 cum Capacity in cum 5.5 km input
etc.

SOR 2018-19 Roads-Input

RA - 57
Transportation of soil, GSB, WMM, Hotmix
P&M-047 Tipper - 5 cum Capacity in cum 5.5 tonne.km 6.56
etc.
Transportation of soil, GSB, WMM, Hotmix
P&M-048 Tipper - 5 cum Capacity in cum 5.5 hour 950.30
etc.
P&M-049 Transit Mixer 4.0/4.5 cum Transportation of Concrete Mix to site cum/hour 4.5 hour 2071.70

P&M-050 Transit Mixer 4/4.5 cum Transportation of Concrete Mix to site cum/hour 4.5 tonne.km 13.18

P&M-051 Transit Mixer 3.0 cum (adopted 2cum) Transportation of Concrete Mix to site cum/hour 3 hour 2071.70

P&M-052 Transit Mixer 3.0 cum Transportation of Concrete Mix to site cum/hour 3 tonne.km input

P&M-053 Tractor Pulling capacity in HP 50 hour 413.60


P&M-054 Tractor with Rotevator Rate of Tractor + Rotevator hour 423.60
P&M-055 Tractor with Ripper Rate of Tractor 6+ Ripper hour 423.60
P&M-056 Truck 5.5 cum per 10 tonnes Material Transport capacity/cum 4.5 km input

P&M-057 Truck 5.5 cum per 10 tonnes Material Transport capacity/cum 4.5 hour 950.30

P&M-058 Truck 5.5 cum per 10 tonnes Material Transport capacity/cum 4.5 tonne.km 6.56
P&M-059 Vibratory Roller 8 tonne Earth or soil / GSB / WBM cum/hour 100/60/60 hour 2736.20

P&M-060 Water Tanker Water Transport capacity in KL 6 hour 655.20

P&M-061 Water Tanker Water Transport capacity in KL 6 km input


P&M-062 Wet Mix Plant 60 TPH Wet Mix cum/hour 25 hour 1679.70

Sl. No. Description of Machine Unit Rate


P&M-063 Air compressor with pneumatic chisel attachment for cutting hard clay. hour 886.00
P&M-064 Batch type cold mixing plant 100-120 TPH capacity producing an average output of 75 tonne per hour hour 3540.00
P&M-065 Belt conveyor system hour input
P&M-066 Boat to carry atleast 20 persons hour input
P&M-067 Cement concrete batch mix plant @ 175 cum per hour (effective output) hour 1310.90
P&M-068 Cement concrete batch mix plant @ 75 cum per hour hour 1310.90
P&M-069 Cold milling machine @ 20 cum per hour hour 1327.00
P&M-070 Crane 5 tonne capacity (Rate adopted for 3 tonnes capacity ) hour 429.60
P&M-071 Crane 10 tonne capacity hour 1217.00
P&M-072 Crane 15 tonne capacity hour 1217.00
P&M-073 Crane 20 tonne capacity hour 1217.00
P&M-074 Crane 40 T capacity (Rate adopted for 35tonnes capacity ) hour 885.70
P&M-075 Crane with grab 0.75 cum capacity hour 2308.90
P&M-076 Compressor with guniting equipment along with accessories hour 222.00
P&M-077 Drum mix plant for cold mixes of appropriate capacity but not less than 75 tonnes/hour. hour 1720.00
P&M-078 Epoxy Injection gun hour 165.00
P&M-079 Generator 33 KVA (Rate of 30 KVA capacity) hour 1032.00
P&M-080 Generator 100 KVA hour 1316.30
P&M-081 Generator 250 KVA hour 2162.60

P&M-082 Induction, deinduction and erection of plant and equipment including all components and accessories for pneumatic method of well sinking. hour input

P&M-083 Joint Cutting Machine with 2-3 blades (for rigid pavement)… hour 332.00

P&M-084 Jack for Lifting 40 tonne lifting capacity. day input


P&M-085 Piling rig Including double acting pile driving hammer (Hydraulic rig) hrs input
P&M-086 Plate compactor hour 59.10
P&M-087 Snow blower equipment 140 HP @ 600 cum per hour hour input
P&M-088 Texturing machine (for rigid pavement) hour 450.00
P&M-089 Truck Trailor 30 tonne capacity hour 3540.00
P&M-090 Truck Trailor 30 tonne capacity t.km 3.29
P&M-091 Tunnel Boring machine hour input
P&M-092 Vibrating Pile driving hammer complete with power unit and accessories. hour 1623.30
P&M-093 Wet Mix Plant 100 TPH (Adopted the rate of 60TPH ) hour 1679.70
P&M-094 Wet Mix Plant 75 TPH (Adopted the rate of 60TPH hour 1679.70

SOR 2018-19 Roads-Input

RA - 58
(B) Labour

Sl. No. Description of Labour Unit Rate

L-01 Blacksmith (IInd class) (Fitter C-II) day 440.00

L-02 Blacksmith (Ist class)/ Welder/ Plumber/ Electrician day 482.20

L-03 Blaster (Stone cutter) day 550.00

L-04 Carpenter I Class day 473.00

L-05 Chiseller (Head Mazdoor) day 440.00

L-06 Driller (Jumper) day 550.00

L-07 Diver day 560.00

L-08 Fitter day 520.00

L-09 Mali (Assumed Mazdoor rate) day 440.00

L-10 Mason (IInd class) day 440.00

L-11 Mason (Ist class) day 455.00

L-12 Mate / Supervisor (Asphalt sprayer) day 451.00

L-13 Mazdoor day 400.00

L-14 Mazdoor (Semi Skilled) day 440.00

L-15 Mazdoor/Dresser/Sinker (Skilled) (blaster rate) day 515.00

L-16 Medical Officer(assumed as work inspectorwith BE qualification) day 935.00

L-17 Operator(grouting) day 490.00

L-18 Painter I class day 473.00

L-19 Para medical personnel(assumed as work inspector with I.T.I qualification) day 560.00

(C) Materials

Sl. No. Description Unit Rate

M-001 Stone Boulder of size 150 mm and below at Cruser Plant cum 160.50

M-002 Supply of quarried stone 150 - 200 mm size for Hand Broken at site cum 238.55

M-003 Boulder with minimum size of 300 mm for Pitching at Site cum 163.80

M-004 Coarse sand at Mixing Plant cum 182.00

M-005 Coarse sand at Site cum 182.00

M-006 Fine sand at Site cum 182.00

M-007 Moorum at Site cum 185.00

M-008 Gravel/Quarry spall at Site Cum 110.00

M-009 Granular Material or hard murrum for GSB works at Site Cum 110.00

M-010 Granular Material or hard murrum for GSB works at Mixing Plant Cum 110.00

M-011 Fly ash conforming to IS: 3812 ( Part II & I) at HMP Plant / Batching Plant / Crushing Plant Cum 61.00

M-012 Filter media/Filter Material as per Table 300-3 (MoRT&H Specification) (Assumed Average rate of 150mm and 40) Cum 390.30

SOR 2018-19 Roads-Input

RA - 59
Rate at Plant
Description Unit (HMP/Batching Rate at Site
)

M-013 Close graded Granular sub-base Material 53 mm to 9.5 mm cum 944.60 944.60

M-014 Close graded Granular sub-base Material 37.5 mm to 9.5 mm cum 811.80 811.80

M-015 Close graded Granular sub-base Material 26.5 mm to 9.5 mm cum 1071.19 1071.19

M-016 Close graded Granular sub-base Material 9.5 mm to 4.75 mm cum 760.47 760.47

M-017 Close graded Granular sub-base Material 9.5 mm to 2.36 mm cum 652.54 652.54

M-018 Close graded Granular sub-base Material 4.75mm to 2.36 mm cum 436.69 436.69

M-019 Close graded Granular sub-base Material 4.75mm to 75 micron mm cum 384.84 384.84

M-020 Close graded Granular sub-base Material 2.36 mm cum 333.00 333.00

M-021 Stone crusher dust finer than 3mm with not more than 10% passing 0.075 sieve. cum 333.00 333.00

M-022 Coarse graded Granular sub-base Material 2.36 mm & below cum 333.00 333.00

M-023 Coarse graded Granular sub-base Material 4.75mm to 75 micron mm cum 384.84 384.84

M-024 Coarse graded Granular sub-base Material 4.75 mm to 2.36 mm cum 436.69 436.69

M-025 Coarse graded Granular sub-base Material 9.5 mm to 4.75 mm cum 760.47 760.47

M-026 Coarse graded Granular sub-base Material 26.5 mm to 4.75 mm cum 990.95 990.95

M-027 Coarse graded Granular sub-base Material 26.5 mm to 9.5 mm cum 1071.19 1071.19

M-028 Coarse graded Granular sub-base Material 37.5 mm to 9.5 mm cum 811.80 811.80

M-029 Coarse graded Granular sub-base Material 53 mm to 26 .5mm cum 858.90 858.90

M-030 Aggregates below 5.6 mm cum 384.84 384.84

M-031 Aggregates 22.4 mm to 2.36 mm cum 839.53 839.53


M-032 Aggregates 22.4 mm to 5.6 mm cum 940.23 940.23
M-033 Aggregates 45 mm to 2.8 mm cum 880.21 880.21
M-034 Aggregates 45 mm to 22.4 mm cum 1068.42 1068.42
M-035 Aggregates 53 mm to 2.8 mm cum 846.79 846.79
M-036 Aggregates 53 mm to 22.4 mm cum 954.53 954.53
M-037 Aggregates 63 mm to 2.8 mm cum 815.90 815.90
M-038 Aggregates 63 mm to 45 mm cum 650.56 650.56
M-039 Aggregates 90 mm to 45 mm cum 650.56 650.56
M-040 Aggregates 10 mm to 5 mm cum 760.47 760.47
M-041 Aggregates 11.2 mm to 0.09 mm cum 572.66 572.66
M-042 Aggregates 13.2 mm to 0.09 mm cum 657.84 657.84
M-043 Aggregates 13.2 mm to 5.6 mm cum 839.83 839.83
M-044 Aggregates 13.2 mm to 10 mm cum 924.75 924.75
M-045 Aggregates 20 mm to 10 mm cum 1030.31 1030.31
M-046 Aggregates 25 mm to 10 mm cum 1071.19 1071.19
M-047 Aggregates 19 mm to 6 mm cum 940.23 940.23
M-048 Aggregates 37.5 mm to 19 mm cum 1068.42 1068.42
M-049 Aggregates 37.5 mm to 25 mm cum 981.91 981.91
M-050 Aggregates 6 mm nominal size cum 670.00 670.00
M-051 Aggregates 10 mm nominal size cum 850.94 850.94
M-052 Aggregates 13.2/12.5 mm nominal size cum 998.56 998.56
M-053 Aggregates 20 mm nominal size cum 1241.44 1241.44
M-054 Aggregates 25 mm nominal size cum 1193.81 1193.81
M-055 Aggregates 40 mm nominal size cum 770.00 770.00

Sl. No. Description Unit Rate


M-056 AC pipe 100 mm dia (Class-15) metre 253.00
M-057 Acrylic polymer bonding coat litre 451.00
M-058 Alluminium Paint litre 256.00
M-059 Aluminium alloy plate 2mm Thick sqm 323.00
M-060 Aluminium alloy/galvanised steel tonne 60047.00
Aluminium sheeting fixed with encapsulated lens type reflective sheeting including 2% towards lettering, cost of angle iron, cost of drilling holes,
M-061 sqm 819.00
nuts, bolts etc.and signs as applicable
M-062 Aluminium studs 100 x 100 mm fitted with lense reflectors nos 200
M-063 Barbed wire kg 68.00

SOR 2018-19 Roads-Input

RA - 60
M-064 Bearing (Cost of parts) nos 483.00
M-065 Bearing (Cast steel rocker bearing assembly of 250 tonne ) nos 665.00
Bearing (Elastomeric bearing assembly consisting of 7 internal layers of elastomer bonded to 6 nos. internal reinforcing steel laminates by the
M-066 nos 15310.00
process of vulcanisation,)
M-067 Bearing (Forged steel roller bearing of 250 tonne nos 125475.00

Bearing (Pot type bearing assembly consisting of a metal piston supported by a disc, PTFE pads providing sliding surfaces against stainless
M-068 nos 47355.00
steel mating together with cast steel assemblies/fabricated structural steel assemblies duly painted with all components

M-069 Bearing (PTFE sliding plate bearing assembly of 80 tonnes ) nos 15430.00
M-070 Bearing (Supply of sliding plate bearing of 80 tonne) nos 16201.50
M-071 Bentonite kg 7.00
M-072 Binding wire kg 53.00
M-073 Bitumen ( Cationic Emulsion ) tonne
M-074 Bitumen (30-40 grade) VG-40 as on 16.12.2018 tonne 33760.00
M-075 Bitumen (80-100 grade) VG-10 as on 16.12.2018 tonne 31690.00
M-076 Bitumen (Cutback ) tonne 45000.00
M-077 Bitumen (emulsion) RS as on 16.12.2018 tonne 35790.00
M-078 Bitumen (modified graded) (CRMB 55) as on 16.12.2018 tonne 33670.00
M-079 Brick (as SSR 2018-19 building materials S. No -1 (1) each 5.70
M-080 C.I.shoes for the pile kg 46.00
M-081 Cement tonne 3900.00
M-082 Cold twisted bars (HYSD Bars) FE 500 for the month of October 2018 tonne 42500.00
M-083 Coller for joints 300 mm dia nos 128.00
M-084 Compressible Fibre Board (20mm thick) sqm 473.00
M-085 Connectors/ Staples each 64.00
M-086 Copper Plate(12m long x 250mmwide) kg 254.00
M-087 Corrosion resistant Structural steel tonne 50138.00
M-088 Corrugated sheet, 3 mm thick, "Thrie" beam section railing kg 174.00
M-089 Credit for excavated rock found suitable for use cum 194.00
M-090 Curing compound . liter 101.00
M-091 Delineators from ISI certified firm as per the standard drawing given in IRC - 79 each 750.00
M-092 Earth Cost or compensation for earth taken from private land cum 55.00
Elastomeric slab seal expansion joint assembly manufactured by using chloroprene, elastomer for elastomeric slab unit conforming to clause
M-093 metre input
915.1 of IRC: 83 (part II),
M-094 Electric Detonators @ 1 detonator for 1/2 gelatin stick of 125 gms each 100 nos 900.00
M-095 Epoxy compound with accessories for preparing epoxy mortar kg 280.00
M-096 Epoxy mortar kg 92.00
M-097 Epoxy primer kg 476.00
M-098 Epoxy resin-hardner mix for prime coat kg 491.00
M-099 Flag of red color cloth 600 x 600 mm each 24.00
M-100 Flowering Plants each 40.00
M-101 Galvanised MS flat clamp nos 165.00
M-102 Galvanised steel wire crates of mesh size 100 mm x 100 mm woven with 4mm dia. GI wire in rolls of required size. sqm 152.00
M-103 Galvanised structural steel plate 200 mm wide, 6 mm thick, 24 m long kg 789.00
M-104 Gelatin 80% old rare kg 57.00
M-105 Geo grids sqm 825.00
M-106 Geomembrane - 750 micron sqm 114.00
M-107 Geonets sqm 58.00
M-108 Geotextile sqm 116.00
M-109 Geotextile filter fabric (250 gsm) sqm 116.00
M-110 GI bolt 10 mm Dia nos 19.00
M-111 Grouting pump with agitator hour 353.00
M-112 Grass (Doob) kg 6.00
M-113 Grass (Fine) kg 8.00
M-114 HDPE pipes 75mm dia metre 104.00
M-115 HDPE pipes 90mm dia metre 150.00
M-116 Hedge plants each 150.00
M-117 Helical pipes 600mm diameter metre input
M-118 Hot applied thermoplastic compound litre 229.64

SOR 2018-19 Roads-Input

RA - 61
M-119 HTS strand tonne 35556.00
M-120 Joint Sealant Compound kg 58.00
M-121 Jute netting, open weave, 2.5 cm square opening for seeding and Mulching sqm 76.00
M-122 LDO for steam curing litre 57.00
M-123 M.S. Clamps nos 0.00
M-124 M.S. Clamps (structural steel rate adopted ) kg 50.14
M-125 M.S.shoes @ 35 Kg per pile of 15 m (structural steel rate adopted ) kg 50.14
M-126 Mild Steel bars tonne 39674.00
Modular strip/box seal expansion joint including anchorage catering to a horizontal movement beyond 70 mm and upto 140mm assembly
M-127 comprising of edge beams, central beam,2 modules chloroprene seal, anchorage elements, support and control system, all steel sections metre input
protected against corrosion and installed by the manufacturer or his authorised representative

Modular strip/box seal expansion joint catering to a horizontal movement beyond 140mm and upto 210mm box/box seal joint assembly
M-128 containing 3 modules/cells and comprising of edge beams, two central beams, chloroprene seal, anchorage elements, support and control metre input
system, all steel sections protected against corrosion and installed by the manufacturer or his authorised representative

M-129 Nipples 12mm nos 17.00

M-130 Nuts and bolts kg 85.00

M-131 Paint litre 198.00


M-132 Pavement Marking Paint litre 190.00
M-133 Paving Fabric sqm 35.00
M-134 Perforated geosynthetic pipe 150 mm dia metre 24.84
M-135 Perforated pipe of cement concrete, internal dia 100 mm metre 103.87
M-136 Pesticide (assumed) kg 150.00
M-137 Pipes 200 mm dia, 2.5 m long for drainage (PH-Table-3, P.No-107) metre 263.00
M-138 Plastic sheath, 1.25 mm thick for dowel bars sqm 47.00
M-139 Plastic tubes 50 cm dia, 1.2 m high nos input
M-140 Polymer braids metre input

M-141 Pre moulded Joint filler,25 mm thick for expansion joint. sqm 262.00

M-142 Pre-coated stone chips of 13.2 mm nominal size cum 4513.00


Preformed continuous chloroprene elastomer or closed cell foam sealing element with high tear strength, vulcanised in a single operation for the
M-143 metre input
full length of a joint to ensure water tightness.
M-144 Pre-moulded asphalt filler board sqm 580.00
M-145 Pre-packed cement based polymer concrete of strength 45 Mpa at 28 days kg 150.00
M-146 Primer (As per SSR of building items - rate of grade -I cement primer has been adopted ) kg 148.00
M-147 Quick setting compound kg 27.00
M-148 Random Rubble Stone cum 240.00
M-149 RCC Pipe NP 4 heavy duty non presure pipe 1000 mm dia metre input
M-150 RCC Pipe NP 4 heavy duty non presure pipe 1200 mm dia metre input
M-151 RCC Pipe NP 4 heavy duty non presure pipe 300 mm dia metre 1109.00
M-152 Reflectorising glass beads kg 80.30
M-153 Reinforcement strips 60 mm wide 5 mm thick as per clause 3102. (Copper Strips) metre 500.00
M-154 Reinforcement strips 60 mm wide 5 mm thick as per clause 3102. (Galvanised carbon steel strips) metre 500.00

M-155 Reinforcement strips 60 mm wide 5 mm thick as per clause 3102. (Glass reinforced polymer/fibre reinforced polymer/polymeric strips) metre 500.00

M-156 Reinforcement strips 60 mm wide 5 mm thick as per clause 3102. (Stainless steel strips) metre 500.00
M-157 Reinforcement strips 60 mm wide 5 mm thick as per clause 3102. Aluminium strips) metre 500.00
M-158 Rivets each 6.00
M-159 Sand bags (Cost of sand and Empty cement bag) nos 8.50
M-160 Sapling 2 m high 25 mm dia each 25.00
M-161 Scrap tyres of size 900 x 20 nos 68.00
M-162 Seeds (Assumed L.S rate) kg 18.00
M-163 Selected earth excluding seignorage cum 55.00
M-164 Separation Membrane of impermeable plastic sheeting 125 micron thick sqm 14.35
M-165 Sheathing duct metre 79.29
M-166 Shrubs(As per Old SSR)) each 15.00
M-167 Sludge / Farm yard manure @ 0.18 cum per 100 sqm at site of work for turfing (Assuming L.S rate of Rs 150/- per Cum) cum 150.00
M-168 Sodium vapour lamp of 250W (Market rate) each 3500.00
M-169 Square Rubble Coursed Stone cum 2130.00
M-170 Steel circular hollow pole of standard specification for street lighting to mount light at 5 m height above deck level each 7619.33
M-171 Steel circular hollow pole of standard specification for street lighting to mount light at 9 m height above road level each 16876.00

SOR 2018-19 Roads-Input

RA - 62
M-172 Steel drum 300 mm dia 1.2 m high/empty bitumen drum nos 114.17
M-173 Steel helmet and cushion block on top of pile head during driving. kg 36.58
M-174 Steel pipe 25 mm external dia as per IS:1239 metre 244.00
M-175 Steel pipe 50 mm external dia as per IS:1239 metre 475.00
M-176 Steel wire rope 20 mm kg 157.00
M-177 Steel wire rope 40 mm kg 179.00
M-178 Strip seal expansion joint metre 4200
M-179 Structural Steel for the month of October 2018 tonne 42000.00
M-180 Super plastisizer admixture IS marked as per 9103-1999 kg 43.00
M-181 Synthetic Geogrids as per clause 3102.8 and approved design and specifications. sqm 500.00
M-182 Through and bond stone (25 x 25x 40 cm) each 37.00
M-183 Tie rods 20mm diameter nos 46.00
M-184 Tiles size 300 x 300 mm and 25 mm thick (As per SSR buildings meterial S.No 87) each 261.00
M-185 Timber cum 59715.00
M-186 Traffic cones with 150 mm reflective sleeve nos 200.00
M-187 Tube anchorage set complete with bearing plate, permanent wedges etc nos 43.24
M-188 Unstaked lime ( as per I&C ) tonne 2491.00
M-189 Water (Rural) KL 77.00
M-190 Water based cement paint ( Buildng SOR) litre 51.00
M-191 Welded steel wire fabric kg 131.00
M-192 Wire mesh 50mm x 50mm size of 3mm wire kg 213.00
M-193 Wooden ballies 2" Dia for bracing each 21.21
M-194 Wooden ballies 8" Dia and 9 m long each 513.12
M-195 Wooden packing ( as per AP-2018-19 - M-195) cum 1071.00
M-196 Wooden staff for fastening of flag 25 mm dia, one m long ( as per AP-2018-19 - M-196) each 67.00

Overheads for Road Works 2.615%

Contractors profit for Road Works 10%

Overheads for Bridge Works 2.615% for input of Overheads or Contractors profit please type in collum C as like below

Type symble of apostrope(') then input value then one space then symble of
Overheads for Bridge Works (Rehabilitation) 10 %
percentage (%) for example '08 %

Contractors profit for Bridge Works 10%

Lead from Mixing Plant to working site 8 km

Lead for E/W borow area to site 5 km

Lead for fly ash from source to site 27.00 Km km

Items No. Summary of Rates calculated and used for analysis of rates of other items Unit Rate
per cm height
Item 8.3 Printing new letter and figures of any shade (ii) English Roman 0.70
per letter
Item 8.8 Painting Two Coats on New Concrete Surfaces sqm 76.00
Item 8.9 Painting angle iron post two coats sqm 68.00
Item 12.6 (B) Cement mortor 1:2 (Excluding OH & CP) cum 3900.00
Item 12.6 (A) Cement mortor 1:3 (Excluding OH & CP) cum 2558.00
Item 12.6 (D) Cement mortor 1:6 (Excluding OH & CP) cum 1720.00
Item 12.7 (A ) Course Rubble masonary in cement mortor 1:3 (including OH & CP) cum 5454.00
Item 12.7 (Addl) B) Random Rubble masonary in cement mortor 1:6 (including OH & CP) cum 4226.00
Item 12.8 (A) PCC Grade M15 including OH & CP for Open Foundation by Mixer cum 4729.00
Item 12.8 (A) PCC Grade M15 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by Mixer cum 3309.00
Item 12.8 (B) PCC PCC Grade M20 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by Mixer cum 3573.00
Item 12.8 (C) RCC Grade M20 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by Mixer cum 3690.00
Item 12.8 (C) RCC RCC Grade M20 including OH & CP for Open Foundation by Batching Plant cum 4407.00
Item 12.8 (C) RCC Grade M20 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by Batching Plant cum 3035.00
Item 12.8 (D) PCC Grade M25 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by Mixer cum 3788.00
Item 12.8 (D) PCC Grade M25 including OH & CP for Open Foundation by Batching Plant cum 4494.00

SOR 2018-19 Roads-Input

RA - 63
Item 12.8 (D) PCC Grade M25 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by Batching Plant cum 3140.00
Item 12.8 (E) RCC Grade M25 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by Mixer cum 3909.00
Item 12.8 (E) RCC Grade M25 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by Batching Plant cum 3322.00
Item 12.8 (F) PCC Grade M30 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by Mixer cum 3812.00
Item 12.8 (F) PCC Grade M30 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by Batching Plant cum 3161.00
Item 12.8 (G) RCC Grade M30 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by Mixer cum 3922.00
Item 12.8 (G) RCC Grade M30 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by Batching Plant cum 3267.00
Item 12.8 (H) RCC Grade M35 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by Mixer cum 3981.00
Item 12.8 (H) RCC Grade M35 including OH & CP for Open Foundation by Batching Plant cum 4796.00
Item 12.8 (H) RCC Grade M35 excluding OH & CP for Open Foundation by Batching Plant cum 3501.00
Item 12.8 (H) RCC Grade M35 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by Batching Plant cum 3399.00
Item 12.11 (C) i PCC Grade M20 for Open Foundation (Bottom Plug) Per Cum Basic Cost of Labour, Material & Mechinery by Mixer cum 3900.00
PCC Grade M20 for Open Foundation (Bottom Plug) Per Cum Basic Cost of Labour, Material & Mechinery by
Item 12.11 (C) i cum 3177.00
Batching Plant
Item 12.11 (C) ii PCC Grade M25 for Open Foundation (Bottom Plug) Per Cum Basic Cost of Labour, Material & Mechinery by Mixer cum 4023.00
PCC Grade M25 for Open Foundation (Bottom Plug) Per Cum Basic Cost of Labour, Material & Mechinery by
Item 12.11 (C) ii cum 3299.00
Batching Plant
Item 12.11 (C) iii PCC Grade M30 for Open Foundation (Bottom Plug) Per Cum Basic Cost of Labour, Material & Mechinery by Mixer cum 4047.00
PCC Grade M30 for Open Foundation (Bottom Plug) Per Cum Basic Cost of Labour, Material & Mechinery by
Item 12.11 (C) iii cum 3324.00
Batching Plant
Item 12.11 (C) iv PCC Grade M35 for Open Foundation (Bottom Plug) Per Cum Basic Cost of Labour, Material & Mechinery by Mixer cum 4101.00
Item 12.11 (C) iv PCC Grade M35 including OH & CP for Well Foundation (Bottom Plug) by Batching Plant cum 4789.00
PCC Grade M35 for Open Foundation (Bottom Plug) Per Cum Basic Cost of Labour, Material & Mechinery by
Item 12.11 (C) iv cum 3518.00
Batching Plant
Item 12.11 (F) iv PCC Grade M35 including OH & CP for Well Foundation (Well Cap) by Batching Plant cum 3867.00
Item No. 3.13 Excavation for Structures (Manual Means) cum 416.00
Item No. 3.13 Excavation for Structures (Mechenical Meanse) cum 115.00
Item 14.1(A) RCC Grade M20 for super-structure including OH & CP by Batching Plant cum 4922.00
Item 14.1(B) RCC Grade M20 for super-structure including OH & CP by Batching Plant cum 5205.00
Item 14.1(E) RCC Grade M20 for super-structure including OH & CP by Batching Plant cum 5427.00
Item 14.1(C) RCC Grade M30 for super-structure including formwork and excluding OH & CP by Batching Plant cum 3924.00
Item 14.1(C) RCC Grade M30 for super-structure excluding formwork and excluding OH & CP by Batching Plant cum 3270.00
Item 14.2 A Supplying ,fitting and placing HYSD bar reinforcement in super-structure exncluding OH & CP tonne 49895.00
Item 13.6 Supplying, fitting and placing HYSD including OH & CP for sub-structure tonne 54927.00
Item 5.17 Fog Seal sqm 36.00
Item 5.21 Case-I Crack Prevention courses. Case-I Stress Absorbing Membrane (SAM) crack width less than 6 mm sqm 46.00
Item 5.21 Case-II Crack Prevention courses. Case-II Stress Absorbing Membrane (SAM) with crack width 6 mm to 9 mm sqm 56.00
Crack Prevention courses. Case-III Stress Absorbing Membrane (SAM) crack width above 9 mm and cracked area
Item 5.21 Case-IV sqm 73.00
above 50 %
Item 5.21 Case-IV Crack Prevention courses. Case-IV Bitumen Impregnated Geotextile sqm 186.00
Item 5.15 Case-I Slurry Seal Case-I 5 mm thickness sqm 54.00
Item 5.15 Case-II Slurry Seal Case-II 3 mm thickness sqm 38.00
Item 5.15 Case-III Slurry Seal Case III 1.5 mm thickness sqm 24.00
Item 5.9 Case-I Surface Dressing Case-I 19 mm nominal chipping size sqm 74.00
Item 5.9 Case-II Surface Dressing Case-II 13 mm nominal size chipping sqm 58.00
Rate at Plant
Description (HAND BROKEN) Unit Rate at Site
(HMP/Batching
M-197 Aggregates 60 mm to 63 mm CUM 459.15 459.15

M-198 Aggregates 50mm to 55 mm CUM 494.40 494.40

M-199 Aggregates 40 mm to45 mm CUM 620.10 620.10

M-200 Aggregates 25 mm to27 mm CUM 959.15 959.15

M-201 Aggregates 20 mm to 22 mm CUM 997.25 997.25

M-202 Aggregates 90mm to 45 mm CUM 458.82 458.82

M-203 Aggregates 63mm to 45 mm CUM 524.55 524.55

M-204 Aggregates 53 mm to 22.4 mm CUM 767.73 767.73

Crushed metal
M-205 Aggregates 53 mm to 26.5 mm CUM 858.90 858.90

M-206 Aggregates 26.5 mm to 4.75 mm CUM 990.95 990.95

M-207 Aggregates 9.5mm to 4.75 mm CUM 760.47 760.47

M-208 Aggregates 2.36 mm below CUM 333.00 333.00

M-209 Aggrgates 53 to 9.5 mm CUM 944.60 944.60

SOR 2018-19 Roads-Input

RA - 64
M-210 Aggrgates 26.5 to 9.5 mm CUM 1071.19 1071.19

M-211 Aggrgates 9.5 mm to 2.36 mm CUM 652.54 652.54

M-212 Aggrgates 4.75mm to 2.36 mm CUM 436.69 436.69

FOR cement treated sub base/ base


for item 4.6 of SDB

M-213 Aggregates 37.5mm to 9.5 mm cum 811.80 0.00

M-214 Aggregates 9.5 mm to 4.75 mm cum 760.47 0.00

M-215 Aggregates 4.75mm to 75 micron cum 384.84 0.00

M-216 sand for filling cum 100.00 100.00

M-217 Stone dust (2.36 mm to 75 microns ) for WMM cum 333.00 333.00

M-218 bitumen grade 30/40 (Bulk) ( 60/70 grade adopted) tonne 33760.00 33760.00

M-219 stone chips size 13.2 mm cum 333.00 333.00

M-220 Seignorage for earth cum 30.00 30.00


20 mm SS 5 crushed Hard broken granite
M-221 cum 1303.00 1303.00
metal
40 mm SS 5 crushed Hard broken granite
M-222 cum 808.00 808.00
metal
10 mm SS 5 crushed Hard broken granite
M-223 cum 894.00 894.00
metal
M-224 stone for rubble masonary cum 310.00 310.00

M-225 Bond stone for rubble masonery each 47.60 47.60

SOR 2018-19 Roads-Input

RA - 65
Rates for carraiage of meterials including loading & unloading on surface and
unsurfaced roads( FOR RCC ITEMS with 3% O.H charges) - CC Pavement

SURFACED ROADS UNSURFACED ROADS

LEAD CHARGES LEAD CHARGES LEAD CHARGES


LEAD CHARGES BEYOND
S.NO DESCRIPTION OF THE ITEM UPTO 1 KM BEYOND 1 KM UPTO 1 KM
1 KM INCLUDING CP & OH
INCLUDING CP & INCLUDING CP & INCLUDING CP &
PER CUM
OH PER CUM OH PER CUM OH PER CUM

1 METAL / STONE / RUBBLE STONE 183.10 11.10 185.35 13.35

2 EARTH / GRAVEL / SAND 185.32 13.32 188.02 16.02

SOR 2018-19 Roads-Conveyance

RA - 66
Rates for carraiage of meterials including loading & unloading on surface roads

Description Metal Bitumen Gravel / Earth / Sand


Spn.No Unit
quantity Lead Lead charges quantity Lead quantity Lead Lead
in Cum charges beyond 1Km in Cum charges in Cum charges charges
upto 1Km & above per Km upto 1Km beyond
including including including including 1Km &
S.No O.H & C.P O.H & C.P O.H & C.P O.H & C.P above
(Rate/Km) including
(6) O.H & C.P
(5) (10) (Rate/Km)
(8) (11)
(2) (3)
(1) (4) (7) (9)
1 Prime caot @0.7kg/sqm 502 Sqm --- --- --- 0.00060 0.00112 --- --- ---
2 Tack caot @ 0.2kg/sqm 503 Sqm --- --- --- 0.00025 0.00047 --- --- ---
3 Bituminuous Macadam for
504 Cum 1.4151 259.11 15.7079 0.07244 0.13491 --- --- ---
Grade I
Bituminuous Macadam for
504 cum 1.4137 258.84 15.6916 0.07463 0.13900
Grade II
Bitumen Penetration
Macadam
(A) 50mm 505 Sqm 0.0750 13.73 0.8325 0.00500 0.00931

(B) 75mm 505 Sqm 0.1080 19.77 1.1988 0.00680 0.01266


4 Built-up Spray grout 506 Sqm 0.1130 20.69 1.2543 0.00300 0.00559 --- --- ---
5 Dense graded Bituminuous
505 Cum 1.4474 265.02 16.0660 0.09231 0.17192 --- --- ---
Macadam (Grade I )
Dense graded Bituminuous
505 Cum 1.4398 263.64 15.9823 0.10385 0.19341
Macadam (Grade II)
6 Semi Dense Bituminuous
Concrete (Grade- I:13mm 508 Cum 1.4398 263.64 15.9823 0.10385 0.19341 --- --- ---
nominal size)
7 Semi Dense Bituminuous
Concrete (Grade- II:10mm 508 Cum 1.4323 262.26 15.8986 0.11538 0.21490 --- --- ---
nominal size)
8 Bituminuous Concrete
509 Cum 1.4592 267.18 16.1974 0.12251 0.22818 --- --- ---
(Grade I )
Bituminuous Concrete
509 Cum 1.4561 266.62 16.1632 0.12723 0.23695
(Grade II)
9 Surface dressing ( Case
510 Sqm 0.0150 2.75 0.1665 0.00120 0.00223 --- --- ---
I:19mm chipping size)
10 Surface dressing ( Case
510 Sqm 0.0100 1.83 0.1110 0.00100 0.00186 --- --- ---
II:13mm chipping size)
Surface dressing ( Case
510 Sqm 0.0040 0.73 0.0444 0.00075 0.00140
III:6mm chipping size)
Open - Graded Premix
511 Sqm 0.0270 4.94 0.2997 0.00146 0.00272
Surfacing (case-i)
Open - Graded Premix
511 Sqm 0.0270 4.94 0.2997 0.00216 0.00401
Surfacing (case-ii)
11 Closed graded Premix
surfacing / Mix seal 512 Sqm 0.0270 4.94 0.2997 0.00220 0.00409 --- --- ---
surfacing ( case I / Type A)
12 Closed graded Premix
surfacing / Mix seal 512 Sqm 0.0270 4.94 0.2997 0.00190 0.00354 --- --- ---
surfacing ( case I I/ Type B)

Seal Coat (Case-I, Type A) 513 Sqm 0.0090 1.65 0.0999 0.00098 0.00183

Seal Coat (Case-II, Type B) 513 Sqm 0.0060 1.10 0.0666 0.00068 0.00127

13 Mastic asphalt 516 Sqm 0.0274 5.01 0.3038 0.00583 0.01086 --- --- ---
14 GSB with closely graded
401 Cum 1.2773 233.88 14.1784 --- --- 1.2773 236.72 17.0141
material Grade I
15 GSB with closely graded
401 Cum 1.2800 234.37 14.2080 --- --- 1.2800 237.21 17.0496
material Grade II and III
16 GSB with coarse graded
401 Cum 1.2800 234.37 14.2080 --- --- 1.2800 237.21 17.0496
material ( Grade I ,II, III )

SOR 2018-19 Roads-Lead Statement

RA - 67
Rates for carraiage of meterials including loading & unloading on surface roads

Description Metal Bitumen Gravel / Earth / Sand


Spn.No Unit
quantity Lead Lead charges quantity Lead quantity Lead Lead
in Cum charges beyond 1Km in Cum charges in Cum charges charges
upto 1Km & above per Km upto 1Km beyond
including including including including 1Km &
S.No O.H & C.P O.H & C.P O.H & C.P O.H & C.P above
(Rate/Km) including
(6) O.H & C.P
(5) (10) (Rate/Km)
(8) (11)
(2) (3)
(1) (4) (7) (9)
17
Inverted Choke Cum --- --- --- 1.2 222.38 15.9840
18 WBM ( Aggregates Gr-I
404 Cum 1.2100 221.55 13.4310 --- --- 0.35 64.86 4.6620
and Gravel Gr-I )
19 WBM ( Aggregates Gr-
404 Cum 1.2100 221.55 13.4310 --- --- 0.37 68.57 4.9284
II,III and Gravel Gr-II,III )
20
Wet Mix Macadam 406 Cum 1.3200 241.69 14.6520 --- --- --- --- ---

SAMI 513 Sqm 0.0100 1.83 0.1110 0.00110 0.00205

SOR 2018-19 Roads-Lead Statement

RA - 68
Rates of Material for the Year 2018-19

Machine
Initial rate after Total Rate as per
crushing Blasting
S.NO Description of Material Unit deducting stcaking SSR 2018-19
charges @ charges
charges excluding taxes
25%
1 75mm metal (IS 383,1970) Cum 289.50 ---- 0.00 289.50
2 65mm metal (IS 383,1970) Cum 360.95 ---- 70.00 430.95
3 60 - 63 mm metal (IRC-MORTH)
Cum 399.05 99.76 70.00 568.81
4 60 - 63 mm metal (Hand broken) Cum 389.15 70.00 459.15
5 50 - 55 mm metal (IRC-MORTH)
Cum 434.30 108.58 70.00 612.88
6 50 - 55 mm metal (Hand broken) Cum 424.40 70.00 494.40
7 40 - 45 mm metal (IRC-MORTH)Cum 560.00 140.00 70.00 770.00
8 40 -45 mm metal (Hand broken) Cum 550.10 70.00 620.10
9 25 - 27 mm metal (IRC-MORTH)Cum 899.05 224.76 70.00 1193.81
10 25 - 27 mm metal (Hand Broken) Cum 889.15 70.00 959.15
11 20 - 22 mm metal (IRC-MORTH)Cum 937.15 234.29 70.00 1241.44
12 20 - 22 mm metal (Hand broken) Cum 927.25 70.00 997.25
13 12 - 14 mm metal (IRC-MORTH)Cum 742.85 185.71 70.00 998.56
14 10 - 11.2 mm metal (IRC-MORTH)
Cum 624.75 156.19 70.00 850.94
15 5mm to 7mm metal (IRC-MORTH)
Cum 480.00 120.00 70.00 670.00
16 2.36mm to 5mm metal (IRC-MORTH)
Cum 293.35 73.34 70.00 436.69
17 Stone dust(HBG stone chips
Cum 333.00 ---- ----
2.36 mm and below ) 333.00
18 Stone boulders of size 150mm Cum 90.50 ---- 70.00 160.50
Supply of stone 150 -200 mm
Cum 168.55 ---- 70.00
19 size 238.55
Boulder with minimum size of
Cum 163.80 ----
20 300 mm for Pitching at Site 163.80
21 Lime Cum 940.00 ---- 940.00
22 Gravel Cum 110.00 ---- ---- 110.00
23 Sand for mortar (Concrete) Cum 182.00 ---- ---- 182.00
24 Sand for filling, blindage Cum 100.00 ---- ---- 100.00
25 Bulk Bitumen Grade 30/40 MT 33760.00 ---- ---- 33760.00
26 Bulk Bitumen Grade 80/100 MT 31690.00 ---- ---- 31690.00
27 Modified Bitumen CRMB55 MT 33670.00 ---- ---- 33670.00
28 Bitumen emulsion (Bulk) MT 35790.00 ---- ---- 35790.00
29 Cement MT 3900.00 ---- ---- 3900.00
30 20 mm metal SS 5 (IS383,1970) Cum 986.40 246.60 70.00 1303.00
31 40 mm metal ss5 (IS383,1970) Cum 590.40 147.60 70.00 808.00
32 10 mm metal ss5 (IS383,1970) Cum 659.20 164.80 70.00 894.00
33 RR masonary (Granite) Cum 240.00 70.00 310.00
34 CR masonary Cum 274.30 70.00 344.30
35 Bond stone each 47.60 ---- ---- 47.60
36 Fe 500 steel MT 42500.00 42500.00
37 Mild steel rods MT 39674.00 39674.00
38 Structural steel MT 42000.00 42000.00
39 HT wire 4mm MT 35556.00 35556.00
40 Murrum Cum 185.00 185.00

RA - 69
SOR 2018- 19 RMR
Average rates of material
S.No Description Unit Average Rate
1 Aggregates below 5.6mm Cum 384.84
2 Aggregates 22.4 mm to 2.36 mm Cum 839.53
3 Aggregates 22.4 mm to 5.6 mm Cum 940.23
4 Aggregates 45 mm to 2.8 mm Cum 880.21
5 Aggregates 45 mm to 22.4 mm Cum 1068.42
6 Aggregates 53 mm to 2.8 mm Cum 846.79
7 Aggregates 53 mm to 22.4 mm Cum 954.53
8 Aggregates 63 mm to 2.8 mm Cum 815.90
9 Aggregates 63 mm to 45 mm Cum 650.56
10 Aggregates 10 mm to 5 mm Cum 760.47
11 Aggregates 11.2 mm to 0.99 mm Cum 572.66
12 Aggregates 13.2 mm to 0.99 mm Cum 657.84
13 Aggregates 13.2mm to 5.60 mm Cum 839.83
14 Aggregates 13.2 mm to 10 mm Cum 924.75
15 Aggregates 20 mm to 10 mm Cum 1030.31
16 Aggregates 25 mm to 10 mm Cum 1071.19
17 Aggregates 19 mm to 6 mm Cum 940.23
18 Aggregates 37.5 mm to 19 mm Cum 1068.42
19 Aggregates 37.5 mm to 25 mm Cum 981.91
20 Aggregates 6mm nominal size Cum 670.00
21 Aggregates 10 mm nominal size Cum 850.94
22 Aggregates 13.2/12.5 mm nominal size Cum 998.56
23 Aggregates 20 mm nominal size Cum 1241.44
24 Aggregates 25 mm nominal size Cum 1193.81
25 Aggregates 40 mm nominal size Cum 770.00
26 Filter media avg of 150mm & 40mm) (Hand broken) Cum 390.30
27 Aggregates 45 mm to 22.4 mm (Hand Broken) Cum 858.83
28 Aggregates 53 mm to 22.4 mm (Hand Broken) Cum 767.73
29 Aggregates 90 mm to 45 mm (Hand Broken) Cum 458.82
30 Aggregates 63 mm to 45 mm (Hand Broken) Cum 524.55
31 Aggregates 4.75 mm to 75 microns Cum 384.84
32 Aggregates 37.5 mm to 9.5 microns Cum 811.80
33 Aggregates 9.5 mm to 75 microns Cum 572.66
34 Aggregates 53 to 26.5 Cum 858.90
35 Aggregates 26.5 to 4.75 Cum 990.95
36 Aggergates 9.5 mm to 4.75 mm Cum 760.47
37 Aggregates 2.36 mm and below (stone dust) Cum 333.00
38 Aggregates 53mm to 9.5 mm Cum 944.60
39 Aggregates 26.5mm to 9.5 mm Cum 1071.19
40 Aggregates 9.5 mm to 2.36 mm Cum 652.54
41 Aggregates 4.75mm to 2.36 mm Cum 436.69
42 Aggregates 20mm SS 5 Cum 1303.00

SOR 2018- 19 RA - 70 RMR


CHAPTER-9
PIPE CULVERTS
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
9.1 408 PCC 1:3:6 in Foundation
Plain cement concrete 1:3:6 mix with crushed stone
aggregate 40 mm nominal size mechanically mixed, placed
in foundation and compacted by vibration including curing for
14 days.
Unit = cum
Taking output = 15 cum
a) Labour
Mate day 0.640 451.00 288.64
Mason day 1.000 455.00 455.00
Mazdoor day 15.000 400.00 6000.00
b) Material
40mm Aggregate at site cum 13.800 805.00 11109.00
Sand at site cum 6.900 182.00 1255.80
Cement at site tonne 3.300 3900.00 12870.00
Cost of water KL 18.000 77.00 1386.00
c) Machinery
Concrete mixer0.4/ 0.28 cum hour 6.000 525.50 3153.00
Generator set 33 KVA hour 6.000 1032.00 6192.00
Water tanker6 KL capacity hour 3.000 655.20 1965.60
d) Overhead charges @ 2.615% on (a+b+c) 1168.25
e) Contractor's profit @ 10 % on (a+b+c+d) 4584.33
Cost for 15 cum = a+b+c+d+e 50427.62
Rate per cum = (a+b+c+d+e)/15 3361.84
say 3362.00
e) seigniorage charges per cum
Aggregate cum 0.92 75.00 69.00
Coarse Sand cum 0.46 50.00 23.00
Add District Mineral Fund (DMF) 30% on Seinorage 0.300 92.00 27.60
charges
Rate per cum say 119.60
Add Lead Charges for metal 25.00 Km 0.92 413.54 380.46
Add Lead Charges for sand 41.00 Km 0.46 330.94 152.23
Add lead charges of Manufactured Sand 25.00 Km 0.000 232.67 0.00
Say 4014.00
Note Vibrator is a part of minor T & P which is already included in
overhead charges of the contractor.
9.2 2900 Laying Reinforced Cement Concrete Pipe NP4 /
Prestressed Concrete Pipe on First Class Bedding in
Single Row .
Laying Reinforced cement concrete pipe NP4/prestressed
concrete pipe for culverts on first class bedding of granular
material in single row including fixing collar with cement
mortar 1:2 but excluding excavation, protection works,
backfilling, concrete an
Unit = metre
Taking output = 12.5 metres ( 5 pipes of 2.5 m length
each )
A 1000 mm dia
a) Labour
Mate day 0.180 451.00 81.18
Mason day 0.500 455.00 227.50
Mazdoor day 4.000 400.00 1600.00
b) Material
Sand at site cum 0.070 182.00 12.74
Cement at site tonne 0.050 3900.00 195.00
RCC pipe NP-4 /prestressed concrete pipe including metre 12.500 7578.00 94725.00
collar at site
Granular material passing 5.6 mm sieve for bedding cum 4.500 110.00 495.00

c) Overhead charges @ 2.615% on (a+b) 2545.35


d) Contractor's profit @ 10% on (a+b+c) 9988.18

SOR 2018-19 (3% OH) Pipe Culverts

RA - 71
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Cost for 12.5 metres = a+b+c+d 109869.94
Rate per metre = (a+b+c+d)/12.5 8789.60
say 8790.00
e) seigniorage charges per cum
Coarse Sand cum 0.01 50.00 0.28
Granular material cum 0.36 30.00 10.80
Add District Mineral Fund (DMF) 30% on Seinorage 0.300 11.08 3.32
charges
Rate per cum say 14.40
a) Add lead charges for NP-4 class 1000mm dia pipes in 41.00 Km 691.92
single row.
b) Add lead charges for Granular Material 25.00 Km 0.36 181.80 65.45
c) Add lead charges for Sand 41.00 Km 0.01 4.02 0.02
d) Add lead charges of Manufactured Sand 25.00 Km 0.000 2.83 0.00
say 757.39
Total rate 9561.79
Say 9562.00
Note 1. In case of cement craddle bedding, quantity of PCC M15
is to be calculated as per design and priced separately and
added .
2. The rate analysis does not include excavation, cement
/masonry works in head walls, backfilling, protection works
and parapet walls. The same are to be calculated as per
approved design and drawings and priced separately on
rates available under respective sections

9.2 B 1200 mm dia


a) Labour
Mate day 0.280 451.00 126.28
Mason day 1.000 455.00 455.00
Mazdoor day 6.000 400.00 2400.00
b) Material
Sand at site cum 0.090 182.00 16.38
Cement at site tonne 0.070 3900.00 273.00
RCC pipe NP-4/prestressed concrete pipe including metre 12.500 10340.00 129250.00
collar at site
Granular material passing 5-6 mm sieve for class cum 5.000 110.00 550.00
bedding
c) Overhead charges @ 2.615% on (a+b) 3479.80
d) Contractor's profit @ 10% on (a+b+c) 13655.05
Cost for 12.5 metres = a+b+c+d 150205.50
Rate per metre= (a+b+c+d)/12.5 12016.44
say 12016.00
e) seigniorage charges per cum
Coarse Sand cum 0.01 50.00 0.36
Granular material cum 0.40 30.00 12.00
Add District Mineral Fund (DMF) 30% on Seinorage 0.300 12.36 3.71
charges
Rate per cum say 16.07
a) Add lead charges for NP-4 class 1200mm dia pipes in 41.00 Km 753.58
single row.
b) Add lead charges for Granular Material 25.00 Km 0.40 202.00 80.80
c) Add lead charges for Sand 41.00 Km 0.01 5.17 0.04
d) Add lead charges of Manufactured Sand 25.00 Km 0.00 3.64 0.00
say 834.42
Total rate 12866.93
Say 12867.00
Note 1. In case of cement craddle bedding, quantity of PCC M15
is to be calculated as per design and priced separately and
added .

SOR 2018-19 (3% OH) Pipe Culverts

RA - 72
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
2. The rate analysis does not include excavation, cement
/masonry works in head walls, backfilling, protection works
and parapet walls. The same are to be calculated as per
approved design and drawings and priced separately on
rates available under respective sections
9.3 2900 Laying Reinforced Cement Concrete Pipe NP4 /
Prestressed Concrete Pipe on First Class Bedding in
Double Row .
Laying Reinforced cement concrete pipe NP4 / prestressed
concrete pipe for culverts on first class bedding of granular
material in double row including fixing collar with cement
mortar 1:2 but excluding excavation, protection works,
backfilling, concrete
Unit = metre
Taking output = 12.5 metres ( 10 pipes of 2.5 m length
each in two rows.)
A 1000 mm dia
a) Labour
Mate day 0.360 451.00 162.36
Mason day 1.000 455.00 455.00
Mazdoor day 8.000 400.00 3200.00
b) Material
Sand at site cum 0.140 182.00 25.48
Cement at site tonne 0.100 3900.00 390.00
RCC pipe NP-4/prestressed concrete pipe including metre 25.000 7578.00 189450.00
collar at site
Granular material passing 5.6 mm sieve for bedding cum 12.500 110.00 1375.00

c) Overhead charges @ 2.615% on (a+b) 5100.76


d) Contractor's profit @ 10% on (a+b+c) 20015.86
Cost for 12.5 metres = a+b+c+d 220174.46
Rate per metre = (a+b+c+d)/12.5 17613.96
say 17614.00
e) seigniorage charges per cum
Coarse Sand cum 0.01 50.00 0.56
Granular material cum 1.00 30.00 30.00
Add District Mineral Fund (DMF) 30% on Seinorage 0.300 30.56 9.17
charges
Rate per cum say 39.73
a) Add lead charges for NP-4 class 1000mm dia pipes in 41.00 Km 1383.84
double row.
b) Add lead charges for Granular Material 25.00 Km 1.00 505.00 505.00
c) Add lead charges for Sand 41.00 Km 0.01 8.04 0.09
d) Add lead charges of Manufactured Sand 25.00 Km 0.00 5.66 0.00
say 1888.93
Total rate 19542.62
Say 19543.00
Note 1. In case of cement craddle bedding, quantity of PCC M15
is to be calculated as per design and priced separately and
added .
2. The rate analysis does not include excavation, cement
/masonry works in head walls, backfilling, protection works
and parapet walls. The same are to be calculated as per
approved design and drawings and priced separately on
rates available under respective sections
9.3 B 1200 mm dia
a) Labour
Mate day 0.560 451.00 252.56
Mason day 2.000 455.00 910.00
Mazdoor day 12.000 400.00 4800.00
b) Material
Sand at site cum 0.180 182.00 32.76
Cement at site tonne 0.140 3900.00 546.00

SOR 2018-19 (3% OH) Pipe Culverts

RA - 73
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
RCC pipe NP-4 /prestressed concrete pipe including metre 25.000 10340.00 258500.00
collar at site
Granular material passing 5-6 mm sieve for class cum 13.750 110.00 1512.50
bedding
c) Overhead charges @ 2.615% on (a+b) 6970.38
d) Contractor's profit @ 10% on (a+b+c) 27352.42
Cost for 12.5 metres = a+b+c+d 300876.62
Rate per metre= (a+b+c+d)/12.5 24070.13
Note 1. In case of cement craddle bedding, quantity of PCC M15 say 24070.00
is to be calculated as per design and priced separately and
added .
e) seigniorage charges per cum
Coarse Sand cum 0.01 50.00 0.72
Granular material cum 1.10 30.00 33.00
Add District Mineral Fund (DMF) 30% on Seinorage 0.300 33.72 10.12
charges
Rate per cum say 43.84
a) Add lead charges for NP-4 class 1200mm dia pipes in 41.00 Km 1507.16
double row.
b) Add lead charges for Granular Material 25.00 Km 1.10 555.50 611.05
c) Add lead charges for Sand 41.00 Km 0.01 10.34 0.15
d) Add lead charges of Manufactured Sand 25.00 Km 0.00 7.27 0.00
say 2118.36
Total rate 26232.32
Say 26232.00
Note 1. In case of cement craddle bedding, quantity of PCC M15
is to be calculated as per design and priced separately and
added .
2. The rate analysis does not include excavation, cement
/masonry works in head walls, backfilling, protection works
and parapet walls. The same are to be calculated as per
approved design and drawings and priced separately on
rates available under respective sections
9.2 a 2900 Laying Reinforced Cement Concrete Pipe NP4 /
Prestressed Concrete Pipe on First Class Bedding in
Single Row .
Laying Reinforced cement concrete pipe NP4/prestressed
concrete pipe for culverts on first class bedding of granular
material in single row including fixing collar with cement
mortar 1:2 but excluding excavation, protection works,
backfilling, concrete an
Unit = metre
Taking output = 12.5 metres ( 5 pipes of 2.5 m length
each )
A 600 mm dia
a) Labour
Mate day 0.180 451.00 81.18
Mason day 0.500 455.00 227.50
Mazdoor day 4.000 400.00 1600.00
b) Material
Sand at site cum 0.070 182.00 12.74
Cement at site tonne 0.050 3900.00 195.00
RCC pipe NP-4 /prestressed concrete pipe including metre 12.500 2545.00 31812.50
collar at site
Granular material passing 5.6 mm sieve for bedding cum 4.500 110.00 495.00

c) Overhead charges @ 2.615% on (a+b) 900.19


d) Contractor's profit @ 10% on (a+b+c) 3532.41
Cost for 12.5 metres = a+b+c+d 38856.52
Rate per metre = (a+b+c+d)/12.5 3108.52
say 3109.00
e) seigniorage charges per cum
Coarse Sand cum 0.01 50.00 0.28

SOR 2018-19 (3% OH) Pipe Culverts

RA - 74
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Granular material cum 0.36 30.00 10.80
Add District Mineral Fund (DMF) 30% on Seinorage 0.300 11.08 3.32
charges
Rate per cum say 14.40
a) Add lead charges for NP-4 class 600mm dia pipes in 41.00 Km 352.39
single row.
b) Add lead charges for Granular Material 25.00 Km 0.36 181.80 65.45
c) Add lead charges for Sand 41.00 Km 0.01 4.02 0.02
d) Add lead charges of Manufactured Sand 25.00 Km 0.00 2.83 0.00
say 417.86
Total rate 3540.79
Say 3541.00

SOR 2018-19 (3% OH) Pipe Culverts

RA - 75
Rates for conveyance of R.C.C. NP-4 plain ended pipes

Rate up to 5 kms lead including Rate for every additional 1 km


Sl. No. Description
loading, unloading & stocking lead or part thereof

1 600 mm dia NP-4 class pipes in single row 131.71 6.13


2 1000 mm dia NP-4 class pipes in single row 255.60 12.12

3 1200 mm dia NP-4 class pipes in single row 306.46 12.42

4 1000 mm dia NP-4 class pipes in double row 511.20 24.24

5 1200 mm dia NP-4 class pipes in double row 612.92 24.84

SOR 2018-19 (3% OH) Pipe Culverts


RA - 76
Rates of materials for the year 2018 - 2019 for Pipe Culverts
Rate of Machine
Deduct
Sl. material after crushing Seigniorage Blasting Total rate in
Description Unit Initial rate stocking
No. deducting charges @ charges Charges Rs.
charges
stocking 25%
1 40 mm SS5 metal cum 590.40 590.40 147.60 67.00 805.00
2 Sand for mortar cum 182.00 182.00 -- -- 182.00
3 Gravel cum 110.00 110.00 -- -- 110.00

SOR 2018-19 Culverts

RA - 77
Rates for carriage of materials including loading and unloading on surfaces and un-
surface roads

Spn. Unit Granular Material Sand


No.
Quan Lead Lead Quantit Lead Lead
tity in charges charges y in charges charges
Cum upto 1 beyond Cum upto 1 beyond 1
Sl. Km 1 Km & Km Km &
Description
No. includin above includin above
g O.H. includin g O.H. & including
& C.P. g O.H & C.P. O.H & C.P.
C.P. (Rate /
(Rate / Km)
Km)
1 2 3 4 5 6 7 8 9 10
1 Laying reinforced cement 2900 Mtr 0.36 66.72 4.80 0.0056 1.038 0.075
concrete pipe NP4/Pre
stressed concrete pipe on
first class bedding in single
row 1000 mm dia (Surface
roads)

2 Laying reinforced cement 2900 Mtr 0.36 67.69 5.77 0.0056 1.053 0.090
concrete pipe NP4/Pre
stressed concrete pipe on
first class bedding in single
row 1000 mm dia (Un-
Surface roads)

3 Laying reinforced cement 2900 Mtr 0.40 74.13 5.33 0.0072 1.334 0.096
concrete pipe NP4/Pre
stressed concrete pipe on
first class bedding in single
row 1200 mm dia (Surface
roads)

4 Laying reinforced cement 2900 Mtr 0.40 75.21 6.41 0.0072 1.354 0.115
concrete pipe NP4/Pre
stressed concrete pipe on
first class bedding in single
row 1200 mm dia (Un-
Surface roads)

5 Laying reinforced cement 2900 Mtr 1.00 185.32 13.32 0.0112 2.076 0.149
concrete pipe NP4/Pre
stressed concrete pipe on
first class bedding in double
row 1000 mm dia (Surface
roads)

SOR 2018-19 Culverts


RA - 78
Spn. Unit Granular Material Sand
No.
Quan Lead Lead Quantit Lead Lead
tity in charges charges y in charges charges
Cum upto 1 beyond Cum upto 1 beyond 1
Sl. Km 1 Km & Km Km &
Description
No. includin above includin above
g O.H. includin g O.H. & including
& C.P. g O.H & C.P. O.H & C.P.
C.P. (Rate /
(Rate / Km)
Km)
6 Laying reinforced cement 2900 Mtr 1.00 188.02 16.02 0.0112 2.106 0.179
concrete pipe NP4/Pre
stressed concrete pipe on
first class bedding in double
row 1000 mm dia (Un-
Surface roads)

7 Laying reinforced cement 2900 Mtr 1.10 203.85 14.65 0.0144 2.669 0.192
concrete pipe NP4/Pre
stressed concrete pipe on
first class bedding in double
row 1200 mm dia (Surface
roads)

8 Laying reinforced cement 2900 Mtr 1.10 206.82 17.62 0.0144 2.707 0.231
concrete pipe NP4/Pre
stressed concrete pipe on
first class bedding in double
row 1200 mm dia (Un-
Surface roads)

SOR 2018-19 Culverts


RA - 79
Conveyance rate including loading and un-loading for cement concrete (1:3:6) mix with crushed stone aggregate (40mm
nominal size)

Lead charges up Lead charges


Quantity in tons or
Sl. No. Description Sp. No. Unit to 1 km including beyond 1 km and Remarks
cum
L+UL+Haulage above

1 PCC (1:3:6) 408 cum 0.92 x 1.5 or 1.380 MT 168.452 10.212 Metal on surface roads

2 PCC (1:3:6) 408 cum 0.92 x 1.5 or 1.380 MT 170.522 12.282 Metal on un-surface roads
0.46 x 1.80 or 0.83
3 PCC (1:3:6) 408 cum 85.262 6.142 Sand on surface roads
cum
0.46 x 1.80 or 0.83
4 PCC (1:3:6) 408 cum 86.507 7.387 Sand on un-surface roads
cum

SOR 2018-19 Culverts


RA - 80
For Pipes of 1000 & 1200 mm dia
The weight of cement and steel for pipe
and collar are calculated as per
IS.458/2003.

Weight of Cement :(Wc) Weight ofSteel:(Ws)

For collar of 1000mmØ


(WC1)c = 3.14/4(1.388*1.388-1.23*1.23)*0.2*360 (Ws1)c=0.33kg/collar
23.38 kg/collar

For collar of 1200mmØ (Ws2)c=0.5 kg/collar

(WC2)c = 3.14/4*(1.638*1.638-1.45*1.45)*0.2*360
32.812 kg/collar
For pipe of 1000mmØ (Ws1)p=6.04 kg/m

(WC1)p = 3.14/4*(1.23*1.23-1*1)*360
144.95 kg/m
For pipe of 1200mmØ (Ws2)p=6.04 kg/m

(WC2)p = 3.14/4*(1.45*1.45-1.2*1.2)*360
187.22 kg/m

For pipe of 1000mm Ø

6 MM R1=[(44000-41500)/1000*6.04 = Rs 15.1
RODS Rs- 15.1

cement R2=[(3900-3882)/1000*144.945 = Rs 2.60901972


Rs per metre run 2.60901972

a Revised Cost=7257+R1+R2 = Rs 7274.70902


per metre 7274.70902

For pipe of 1200mmØ

6 MM R1=[(44000-41500)/1000*6.04 = Rs 15.1
RODS
R2=[(3900-3882)/1000*187.22 = Rs 3.370005
cement

Revised Cost=9839+R1+R2 = Rs 9857.470005


per metre 9857.470005

For collar of 1000mmØ

6 MM R1=[(44000-41500)/1000*0.33 = Rs 0.825
RODS per collar 0.825

cement R2=[(3900-3882)/1000*23.38 = Rs 0.42082486


per collar 0.42082486

RA - 81
b Revised Cost=947+R1+R2 = Rs 948.2458249
per collar 948.2458249

For collar of 1200mmØ

6 MM R1=[(44000-41500)/1000*0.50 = Rs 1.25
RODS
R2=[(3900-3882)/1000*32.812 = Rs 0.590622244
cement
Revised Cost=1505+R1+R2 = Rs 1506.840622
per collar 1506.840622

Input values for pipe:-


for 1000 mm=Rs 7578.15
a+4*b/12.5 per m 7578.00
for 1200 mm=Rs 10339.66
a+4*b/12.5 per m 10340.00

RA - 82
For Pipes of 300, 600 & 900 mm dia
The weight of cement and steel for pipe
and collar are calculated as per
IS.458/2003. Table 22 & 8

Weight of Cement :(Wc) Weight ofSteel:(Ws)

For collar of 300mmØ


(WC1)c = 3.14/4(0.492*0.492-0.4*0.4)*0.15*360 (Ws1)c=0.11kg/collar
3.479 kg/collar

For collar of 600mmØ


(WC1)c = 3.14/4(0.868*0.868-0.75*0.75)*0.2*360 (Ws1)c=0.23kg/collar
10.791 kg/collar

For collar of 900mmØ (Ws2)c=0.33 kg/collar


(WC2)c = 3.14/4*(1.248*1.248-1.10*1.10)*0.2*360
19.641 kg/collar

For pipe of 300mmØ (Ws1)p=0.78kg/m


(WC1)p = 3.14/4*(0.40*0.40-0.3*0.3)*360
19.782 kg/m

For pipe of 600mmØ (Ws1)p=2.34kg/m


(WC1)p = 3.14/4*(0.75*0.75-0.6*0.6)*360
57.227 kg/m

For pipe of 900mmØ (Ws2)p=3.44 kg/m


(WC2)p = 3.14/4*(1.1*1.1-0.9*0.9)*360
113.040 kg/m

For pipe of 300mm Ø

6 MM R1=[(44000-41500)/1000*0.78 = Rs 1.95
RODS Rs- 1.95

cement R2=[(3900-3882)/1000*19.782 = Rs 0.36


Rs per metre run 0.356076

a Revised Cost=846+R1+R2 = Rs 848.306076

For pipe of 600mm Ø

6 MM R1=[(44000-41500)/1000*2.34 = Rs 5.85
RODS Rs- 5.85

cement R2=[(3900-3882)/1000*57.227 = Rs 1.03


Rs per metre run 1.03

Revised Cost=2416+R1+R2 = Rs 2,422.88

RA - 83
For pipe of 900mmØ

R1=[(44000-41500)/1000*3.44 = Rs 8.6

R2=[(3900-3882)/1000*113.040 = Rs 58.55

Revised Cost=5285+R1+R2 = Rs 5,352.15

For collar of 300mmØ

R1=[(44000-41500)/1000*0.11 = Rs 0.28
per collar

R2=[(3900-3882)/1000*3.479 = Rs 1.80
per collar

b Revised Cost=126+R1+R2 = Rs 128.08


per collar

For collar of 600mmØ

R1=[(44000-41500)/1000*0.23 = Rs 0.58
per collar

R2=[(3900-3882)/1000*10.791 = Rs 0.19
per collar

Revised Cost=380+R1+R2 = Rs 380.77


per collar

For collar of 900mmØ

R1=[(44000-41500)/1000*0.33 = Rs 0.825

R2=[(3900-3882)/1000*19.641 = Rs 0.35

Revised Cost=759+R1+R2 = Rs 760.18

Input values for pipe:-


for300 mm=Rs 889.29
a+4*b/12.5 per m 889.00

for600 mm=Rs 2544.73


a+4*b/12.5 per m 2545.00

for 900 mm=Rs 5595.41


a+4*b/12.5 per m 5595.00

RA - 84
CHAPTER-12
FOUNDATIONS
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
12.1 304 Excavation for Structures
Earth work in excavation of foundation of structures as per
drawing and technical specification, including setting out,
construction of shoring and bracing, removal of stumps and
other deleterious matter, dressing of sides and bottom and
backfilling with
I Ordinary soil
Unit = cum
Taking output = 10 cum
A Manual Means
(i) Depth upto 3 m
a) Labour
Mate day 0.14 451.00 63.14
Mazdoor day 3.50 400.00 1400.00
b) Overhead charges @ 2.615% on (a) 38.26
c) Contractor's profit @ 10% on (a+b) 150.14
Cost for 10 cum = a+b+c 1651.54
Rate per cum = (a+b+c)/10 165.15
Total 165.00
Note 1. Cost of dewatering may be added where required upto, 10
per cent of labour cost Assessment for dewatering shall be
made as per site conditions.
2.The excavated earth can be used partially for backfilling of
foundation pit and partly for road work except for marshy soil.
Hence cost of disposal has not been added except for
marshy soil. This remark is common to all cases of item 12.1
excluding mars
3.The cost of shoring and shuttering, where needed, may be
added @ 1 per cent on cost of excavation for open
foundation.
12.1 (I) (ii) Depth 3 m to 6 m
A
a) Labour
Mate/Supervisor day 0.18 451.00 81.18
Mazdoor day 4.50 400.00 1800.00
b) Overhead charges @ 2.615% on (a) 49.19
c) Contractor's profit @ 10% on (a+b) 193.04
Cost for 10 cum = a+b+c 2123.41
Rate per cum = (a+b+c)/10 212.34
Total 212.00
Note Cost of dewatering may be added where required upto 15
per cent of labour cost. Assessment for dewatering shall be
done as per actual ground conditions.
12.1 (I) (iii) Depth above 6 m
A
a) Labour
Mate/Supervisor day 0.24 451.00 108.24
Mazdoor day 6.00 400.00 2400.00
b) Overhead charges @ 2.615% on (a) 65.59
c) Contractor's profit @ 10% on (a+b) 257.38
Cost for 10 cum = a+b+c 2831.21
Rate per cum = (a+b+c)/10 283.12
Total 283.00
Note 1. Cost of dewatering may be added where required upto 20
per cent of labour cost. Assessment for dewatering shall be
made as per site conditions..
12.1 (I) B Mechanical Means
(i) Depth upto 3 m
Unit = cum
Taking output = 240 cum
a) Labour

SOR 2018-19 (3% OH) Culverts - Foundation


RA - 85
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Mate day 0.32 451.00 144.32
Mazdoor day 8.00 400.00 3200.00
b) Machinery
Hydraulic excavator 1.0 cum bucket capacity hour 6.00 2791.60 16749.60
c) Overhead charges @ 2.615% on (a+b) 525.46
d) Contractor's profit @ 10% on (a+b+c) 2061.94
Cost for 240 cum = a+b+c+d 22681.31
Rate per cum = (a+b+c+d)/240 94.51
Total 95.00
Note Cost of dewatering upto 5 per cent of (a+b) may be added,
where required. Assessment for dewatering shall be made as
per site conditions..
12.1 (I) (ii) Depth 3 m to 6 m
B
Unit = cum
Taking output = 210 cum
a) Labour
Mate day 0.32 451.00 144.32
Mazdoor day 8.00 400.00 3200.00
b) Machinery
Hydraulic excavator 1.0 cum bucket capacity hour 6.00 2791.60 16749.60
c) Overhead charges @ 2.615% on (a+b) 525.46
d) Contractor's profit @ 10% on (a+b+c) 2061.94
Cost for 210 cum = a+b+c+d 22681.31
Rate per cum = (a+b+c+d)/210 108.01
Total 108.00
Note Cost of dewatering upto 7.5 per cent of (a+b) may be
added, where required. Assessment for dewatering shall be
made as per site conditions..
12.1 (I) (iii) Depth above 6m
B
Unit = cum
Taking output = 180 cum
a) Labour
Mate day 0.40 451.00 180.40
Mazdoor day 10.00 400.00 4000.00
b) Machinery
Hydraulic excavator 1.0 cum bucket capacity hour 6.00 2791.60 16749.60
c) Overhead charges @ 2.615% on (a+b) 547.32
d) Contractor's profit @ 10% on (a+b+c) 2147.73
Cost for 180 cum = a+b+c+d 23625.05
Rate per cum = (a+b+c+d)/180 131.25
Total 131.00
Note 1. Cost of dewatering upto 10 per cent of (a+b) may be
added, where required. Assessment for dewatering shall be
made as per site conditions..
2.Labour provided for excavation by mechanical means
includes that required for trimming of bottom and side slopes.

12.1 II Ordinary Rock (not requiring blasting)


A Manual Means
(i) Depth upto 3 m
Unit = cum
Taking output = 10 cum
a) Labour
Mate day 0.20 451.00 90.20
Mazdoor day 5.00 400.00 2000.00
b) Overhead charges @ 2.615% on (a) 54.66
c) Contractor's profit @ 10% on (a+b) 214.49
Cost for 10 cum = a+b+c 2359.34

SOR 2018-19 (3% OH) Culverts - Foundation


RA - 86
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Rate per cum = (a+b+c)/10 235.93
Total 236.00
Note Cost of dewatering upto 10 per cent of labour cost may be
added, where required. Assessment for dewatering shall be
made as per site conditions..
12.1(II) B Mechanical Means
Unit = cum
Taking output = 180 cum
a) Labour
Mate day 0.24 451.00 108.24
Mazdoor day 6.00 400.00 2400.00
b) Machinery
Hydraulic excavator 1.0 cum bucket capacity hour 6.00 2791.60 16749.60
c) Overhead charges @ 2.615% on (a+b) 503.59
d) Contractor's profit @ 10% on (a+b+c) 1976.14
Cost for 180 cum = a+b+c+d 21737.58
Rate per cum = (a+b+c+d)/180 120.76
Total 121.00
Note 1.Cost of dewatering upto 10 per cent of (a+b), may be
added, where required Assessment for dewatering shall be
made as per site conditions.
2.In case of rock, foundation beyond3 m is not dug and
hence not included.
12.8 1500, 1700 Plain/Reinforced Cement Concrete in Open Foundation
& 2100 complete as per Drawing and Technical Specifications.

A PCC Grade M15


Unit = cum
Taking output = 15 cum
a) Material
Cement tonne 4.13 3900.00 16107.00
Coarse sand cum 6.75 182.00 1228.50
40 mm Aggregate cum 8.10 808.00 6544.80
20 mm Aggregate cum 4.05 1303.00 5277.15
10 mm Aggregate cum 1.35 894.00 1206.90
b) Labour
Mate day 0.86 451.00 387.86
Mason day 1.50 455.00 682.50
Mazdoor day 20.00 400.00 8000.00
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 525.50 3153.00
Generator 63 KVA hour 6.00 1174.15 7044.90
Per Cum Basic Cost of Labour, Material & Machinery 3309.00
(a+b+c)
d) Formwork @ 4 per cent on cost of concrete i.e. cost 1985.30
of material, labour and machinery

e) Overhead charges @ 2.615% on (a+b+c+d) 1349.81


f) Contractor's profit @ 10% on (a+b+c+d+e) 5296.77
Cost for 15 cum = a+b+c+d+e+f 58264.50
Rate per cum = (a+b+c+d+e+f)/15 3884.30
say 3884.00
g) seigniorage charges per cum
Coarse Sand 0.45 50.00 22.50
Aggregate 0.90 75.00 67.50
Add District Mineral Fund (DMF) 30% on Seinorage 0.300 90.00 27.00
charges
Rate per cum say 117.00

SOR 2018-19 (3% OH) Culverts - Foundation


RA - 87
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Add lead charges of metal 25.00 Km 0.90 449.50 404.55
Add lead charges of sand 41.00 Km 0.45 718.12 323.15
Add lead charges of Manufactured Sand 25.00 Km 0.00 505.00 0.00
727.70
4729.00
TOTAL Rate Total 4729.00
Note Needle Vibrator is an item of minor T & P which is already
included in overhead charges. Hence not added in rate
analysis of cement concrete works.
12.8 B PCC Grade M20
Unit : cum
Taking output = 15 cum
a) Material
Cement tonne 5.16 3900.00 20124.00
Coarse sand cum 6.75 182.00 1228.50
40 mm Aggregate cum 5.40 808.00 4363.20
20 mm Aggregate cum 5.40 1303.00 7036.20
10 mm Aggregate cum 2.70 894.00 2413.80
b) Labour
Mate day 0.86 451.00 387.86
Mason day 1.50 455.00 682.50
Mazdoor day 20.00 400.00 8000.00
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 525.50 3153.00
Generator 33 KVA hour 6.00 1032.00 6192.00
Per Cum Basic Cost of Labour, Material & Machinery 3573.00
(a+b+c)
d) Formwork @ 4 per cent on cost of concrete i.e. cost 2143.24
of material, labour and machinery
e) Overhead charges @ 2.615% on (a+b+c+d) 1457.19
f) Contractor's profit @ 10% on (a+b+c+d+e) 5718.15
Cost for 15 cum = a+b+c+d+e+f 62899.64
Rate per cum = (a+b+c+d+e+f)/15 4193.31
say 4193.00
g) seigniorage charges per cum
Coarse Sand 0.45 50.00 22.50
Aggregate 0.90 75.00 67.50
Add District Mineral Fund (DMF) 30% on Seinorage 0.300 90.00 27.00
charges
Rate per cum say 117.00
Add lead charges of metal 25.00 Km 0.90 449.50 404.55
Add lead charges of sand 41.00 Km 0.45 718.12 323.15
Add lead charges of Manufactured Sand 25.00 Km 0.00 505.00 0.00
727.70
TOTAL Rate Total 5038.00
12.8 C RCC Grade M20
Case I Using Concrete Mixer
Unit = cum
Taking output = 15 cum
a) Material
Cement tonne 5.21 3900.00 20319.00
Coarse sand cum 6.75 182.00 1228.50
20 mm Aggregate cum 8.10 1303.00 10554.30
10 mm Aggregate cum 5.40 894.00 4827.60
b) Labour
Mate day 0.86 451.00 387.86
Mason day 1.50 455.00 682.50

SOR 2018-19 (3% OH) Culverts - Foundation


RA - 88
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Mazdoor day 20.00 400.00 8000.00
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 525.50 3153.00
Generator 33 KVA hour 6.00 1032.00 6192.00
Per Cum Basic Cost of Labour, Material & Machinery 3690.00
(a+b+c)
d) Formwork @ 4 per cent on (a+b+c) 2213.79
e) Overhead charges @ 2.615% on (a+b+c+d) 1505.16
f) Contractor's profit @ 10% on (a+b+c+d+e) 5906.37
Cost for 15 cum = a+b+c+d+e+f 64970.08
Rate per cum = ( a+b+c+d+e+f )/15 4331.34
say 4331.00
g) seigniorage charges per cum
Coarse Sand cum 0.45 50.00 22.50
Aggregate cum 0.90 75.00 67.50
Add District Mineral Fund (DMF) 30% on Seinorage 0.300 90.00 27.00
charges
Rate per cum say 117.00
Add lead charges of metal 25.00 Km 0.90 449.50 404.55
Add lead charges of sand 41.00 Km 0.45 718.12 323.15
Add lead charges of Manufactured Sand 25.00 Km 0.00 505.00 0.00
727.70
TOTAL Rate Total 5176.00
Case II With Batching Plant, Transit Mixer and Concrete Pump

Unit : cum
Taking Output = 120 cum
a) Material
Cement tonne 41.66 3900.00 162474.00
Coarse Sand cum 54.00 182.00 9828.00
20 mm Aggregate cum 64.80 1303.00 84434.40
10 mm Aggregate cum 43.20 894.00 38620.80
b) Labour
Mate day 0.84 451.00 378.84
Mason day 3.00 455.00 1365.00
Mazdoor day 18.00 400.00 7200.00
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1343.30 8059.80
Generator 100 KVA hour 6.00 1316.30 7897.80
Loader 1 cum capacity hour 6.00 1594.70 9568.20
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 2071.70 31075.50
Lead beyond 1 km, L-lead in km tonne.km 300L 13.18 31634.26

Concrete Pump hour 6 1508.80 9052.80


Per Cum Basic Cost of Labour, Material & Machinery 3347.00
(a+b+c)
d) Formwork @ 4 per cent on cost of concrete i.e. cost 16063.58
of material, labour and machinery
e) Overhead charges @ 2.615% on (a+b+c+d) 10921.63
f) Contractor's profit @ 10% on (a+b+c+d+e) 42857.46
Cost for 120 cum = a+b+c+d+e+f 471432.06
Rate per cum = ( a+b+c+d+e+f )/120 3928.60
say 3929.00
g) seigniorage charges per cum
Coarse Sand 0.45 50.00 22.50
Aggregate 0.90 75.00 67.50
Add District Mineral Fund (DMF) 30% on Seinorage 0.300 90.00 27.00
charges

SOR 2018-19 (3% OH) Culverts - Foundation


RA - 89
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Rate per cum say 117.00
Add lead charges of metal 25.00 Km 0.90 449.50 404.55
Add lead charges of sand 41.00 Km 0.45 718.12 323.15
Add lead charges of Manufactured Sand 25.00 Km 0.00 505.00 0.00
727.70
TOTAL Rate Total 4773.00
12.11 F Case II Using Batching Plant, Transit Mixer and Concrete Pump
(i)
Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 40.92 3900.00 159588.00
Coarse sand cum 54.00 182.00 9828.00
20 mm Aggregate cum 64.80 1303.00 84434.40
10 mm Aggregate cum 43.20 894.00 38620.80
b) Labour
Mate day 0.84 451.00 378.84
Mason day 3.00 455.00 1365.00
Mazdoor day 18.00 400.00 7200.00
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1343.30 8059.80
Generator 100 KVA hour 6.00 1316.30 7897.80
Loader (capacity 1 cum) hour 6.00 1594.70 9568.20
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 2071.70 31075.50
Lead beyond 1 Km, L - lead in Kilometer tonne.km 300L 13.18 31634.26

Concrete Pump hour 6.00 1508.80 9052.80


Formwork @ 4 per cent of (a+b+c) 15948.14
d) Overhead charges @ 2.615% on (a+b+c) 10843.14
e) Contractor's profit @ 10% on (a+b+c+d) 42549.47
cost of 120 cum = a+b+c+d+e 468044.14
Rate per cum = (a+b+c+d+e)/120 3900.37
g) seigniorage charges per cum
Coarse Sand cum 0.45 50.00 22.50
Aggregate cum 0.90 75.00 67.50
Add District Mineral Fund (DMF) 30% on Seinorage 0.300 90.00 27.00
charges
117.00
Add lead charges of metal 25.00 Km 0.90 449.50 404.55
Add lead charges of sand 41.00 Km 0.45 718.12 323.15
Add lead charges of Manufactured Sand 25.00 Km 0.00 505.00 0.00
727.70
Total 4745.00
12.40 1600 Supplying, Fitting and Placing un-coated HYSD bar
Reinforcement in Foundation complete as per Drawing
and Technical Specifications.
Unit = 1 MT
Taking output = 1 MT
a) Material
HYSD bars including5 per cent overlaps and wastage tonne 1.05 42500 44625.00

Binding wire Kg 6.00 53.00 318.00


b) Labour for cutting, bending, shifting to site, tying
and placing in position
Mate day 0.40 451.00 180.40
Blacksmith day 2.00 482.20 964.40
Mazdoor day 6.00 400.00 2400.00

SOR 2018-19 (3% OH) Culverts - Foundation


RA - 90
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
c) Overhead charges @ 2.615% on (a+b) 1267.96
d) Contractor's profit @ 10% on (a+b+c) 4975.58
Rate for per MT (a+b+c+d) 54731.33
Total 54731.00
12.41 1600 Supplying, fitting and placing un-coated Mild steel
reinforcement complete in foundation as per drawing
and technical specification
Unit = 1 MT
Taking output = 1 MT
a) Material
MS bars including 5 per cent overlaps and wastage tonne 1.05 39674.00 41657.70

Binding wire Kg 6.00 53.00 318.00


b) Labour for straightening, cutting, bending, shifting
to site, tying and placing in position
Mate day 0.43 451.00 193.93
Blacksmith day 2.25 482.20 1084.95
Mazdoor day 6.50 400.00 2600.00
c) Overhead charges @ 2.615% on (a+b) 1199.10
d) Contractor's profit @ 10% on (a+b+c) 4705.37
Rate for per MT (a+b+c+d) 51759.04
Total 51759.00

SOR 2018-19 (3% OH) Culverts - Foundation


RA - 91
CHAPTER-13
SUB-STRUCTURE
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
13.5 1500, Plain/Reinforced cement concrete in sub-structure
1700 & complete as per drawing and Technical Specifications
2200
Unit = cum
Taking output = 1 cum
13.5 F RCC Grade M25
(p) Height upto 5m
Same as Item 12.8 (E) upto 5m height, excluding formwork.
For cost of formwork, add 10 per cent of cost of material,
labour and machinery instead of 3.75 per cent .

Case Using concrete Mixer


I
Per Cum Basic Cost of Labour, Material & Machinery 3909.00
(a+b+c) of Item 12.8 (E) Case I
d) formwork
Add 10 per cent of cost of material, labour and 10.00 390.90
machinery (a+b+c) for Formwork
e) Overhead charges @ 2.615% on (a+b+c+d) 112.44
f) Contractor's profit @ 10% on (a+b+c+d+e) 441.23
Rate perm (a+b+c+d+e+f) 4853.58
say 4854
g) seinarage charges per cum
Coarse Sand 0.45 50.00 22.50
Aggregate 0.90 75.00 67.50
Add District Mineral Fund (DMF) 30% on Seinorage 0.300 90.00 27.00
charges
Rate per cum say 117.00
Add lead charges of metal 25.00 Km 0.90 449.50 404.55
Add lead charges of sand 41.00 Km 0.45 718.12 323.15
Add lead charges of Manufactured Sand 25.00 Km 0.00 505.00 0.00
TOTAL Rate Total 5698.00
13.5 F (p) Case With Batching Plant, Transit Mixer and Concrete Pump
II
Per Cum Basic Cost of Labour, Material & Machinery 3635.00
(a+b+c) of Item 12.8 (E) Case II
d) formwork
Add 10 per cent of cost of material, labour and 10.00 363.50
machinery (a+b+c) for Formwork
e) Overhead charges @ 2.615% on (a+b+c+d) 104.56
f) Contractor's profit @ 10% on (a+b+c+d+e) 410.31
Rate perm (a+b+c+d+e+f) 4513.37
say 4513
g) seinarage charges per cum
Coarse Sand 0.45 50.00 22.50
Aggregate 0.90 75.00 67.50
Add District Mineral Fund (DMF) 30% on Seinorage 0.300 90.00 27.00
charges
Rate per cum say 117.00
Add lead charges of metal 25.00 Km 0.90 449.50 404.55
Add lead charges of sand 41.00 Km 0.45 718.12 323.15
Add lead charges of Manufactured Sand 25.00 Km 0.00 505.00 0.00
TOTAL Rate Total 5358.00
13.5 F (q) Height 5m to 10m
For height, upto 10m, add 1.8 per cent of cost as above
excluding formwork. For cost of formwork add 11.8 per cent
of cost of material, labour and machinery
Case Using concrete Mixer
I
Per Cum Basic Cost of Labour, Material & Machinery 3909.00
(a+b+c) of Item 12.8 (E) Case I

SOR 2018-19 (3% OH) Culverts - Sub Structure


RA - 92
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
d) formwork
Add 11.8 per cent of cost of material, labour and 11.80 461.26
machinery (a+b+c) for Formwork
Add 1.8 per cent of cost of material, Labour and 1.80 70.36
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 2.615% on (a+b+c+d) 116.12
f) Contractor's profit @ 10% on (a+b+c+d+e) 455.67
Rate perm (a+b+c+d+e+f) 5012.42
say 5012
g) seinarage charges per cum
Coarse Sand 0.45 50.00 22.50
Aggregate 0.90 75.00 67.50
Add District Mineral Fund (DMF) 30% on Seinorage 0.300 90.00 27.00
charges
Rate per cum say 117.00
Add lead charges of metal 25.00 Km 0.90 449.50 404.55
Add lead charges of sand 41.00 Km 0.45 718.12 323.15
Add lead charges of Manufactured Sand 25.00 Km 0.00 505.00 0.00
TOTAL Rate Total 5857.00
13.5 F (q) Case With Batching Plant, Transit Mixer and Concrete Pump
II
Per Cum Basic Cost of Labour, Material & Machinery 3635.00
(a+b+c) of Item 12.8 (E) Case II
d) formwork
Add 11.8 per cent of cost of material, labour and 11.80 428.93
machinery (a+b+c) for Formwork
Add 1.8 per cent of cost of material, Labour and 1.80 65.43
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 2.615% on (a+b+c+d) 107.98
f) Contractor's profit @ 10% on (a+b+c+d+e) 423.73
Rate perm (a+b+c+d+e+f) 4661.08
say 4661
g) seinarage charges per cum
Coarse Sand 0.45 50.00 22.50
Aggregate 0.90 75.00 67.50
Add District Mineral Fund (DMF) 30% on Seinorage 0.300 90.00 27.00
charges
Rate per cum say 117.00
Add lead charges of metal 25.00 Km 0.90 449.50 404.55
Add lead charges of sand 41.00 Km 0.45 718.12 323.15
Add lead charges of Manufactured Sand 25.00 Km 0.00 505.00 0.00
TOTAL Rate Total 5506.00
13.5 F (r) Height above 10m
For height, above 10m, add 4 per cent of cost as above
excluding formwork. For cost of formwork add 15 per cent of
cost of material, labour and machinery
Case Using concrete Mixer
I
Per Cum Basic Cost of Labour, Material & Machinery 3909.00
(a+b+c) of Item 12.8 (E) Case I
d) formwork
Add 15 per cent of cost of material, labour and 15.00 586.35
machinery (a+b+c) for Formwork
Add 4 per cent of cost of material, Labour and 4.00 156.36
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 2.615% on (a+b+c+d) 121.64
f) Contractor's profit @ 10% on (a+b+c+d+e) 477.34
Rate perm (a+b+c+d+e+f) 5250.69
say 5251
g) seinarage charges per cum
Coarse Sand 0.45 50.00 22.50
Aggregate 0.90 75.00 67.50

SOR 2018-19 (3% OH) Culverts - Sub Structure


RA - 93
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Add District Mineral Fund (DMF) 30% on Seinorage 0.300 90.00 27.00
charges
Rate per cum say 117.00
Add lead charges of metal 25.00 Km 0.90 449.50 404.55
Add lead charges of sand 41.00 Km 0.45 718.12 323.15
Add lead charges of Manufactured Sand 25.00 Km 0.00 505.00 0.00
TOTAL Rate Total 6095.00
13.5 F (r) Case With Batching Plant, Transit Mixer and Concrete Pump
II
Per Cum Basic Cost of Labour, Material & Machinery 3635.00
(a+b+c) of Item 12.8 (E) Case II
d) formwork
Add 15 per cent of cost of material, labour and 15.00 545.25
machinery (a+b+c) for Formwork
Add 4 per cent of cost of material, Labour and 4.00 145.40
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 2.615% on (a+b+c+d) 113.12
f) Contractor's profit @ 10% on (a+b+c+d+e) 443.88
Rate perm (a+b+c+d+e+f) 4882.64
say 4883
g) seinarage charges per cum
Coarse Sand 0.45 50.00 22.50
Aggregate 0.90 75.00 67.50
Add District Mineral Fund (DMF) 30% on Seinorage 0.300 90.00 27.00
charges
Rate per cum say 117.00
Add lead charges of metal 25.00 Km 0.90 449.50 404.55
Add lead charges of sand 41.00 Km 0.45 718.12 323.15
Add lead charges of Manufactured Sand 25.00 Km 0.00 505.00 0.00
TOTAL Rate Total 5727.00
13.5 G RCC Grade M30
(p) Height upto 5m
Same as Item 12.8 (G) upto 5m height, excluding formwork.
For cost of formwork, add 10 per cent of cost of material,
labour and machinery instead of 3.5 per cent .

Case Using concrete Mixer


I
Per Cum Basic Cost of Labour, Material & Machinery 3922.00
(a+b+c) of Item 12.8 (G) Case I
d) formwork
Add 10 per cent of cost of material, labour and 10.00 392.20
machinery (a+b+c) for Formwork
e) Overhead charges @ 2.615% on (a+b+c+d) 112.82
f) Contractor's profit @ 10% on (a+b+c+d+e) 442.70
Rate perm (a+b+c+d+e+f) 4869.72
say 4870
g) seinarage charges per cum
Coarse Sand 0.45 50.00 22.50
Aggregate 0.90 75.00 67.50
Add District Mineral Fund (DMF) 30% on Seinorage 0.300 90.00 27.00
charges
Rate per cum say 117.00
Add lead charges of metal 25.00 Km 0.90 449.50 404.55
Add lead charges of sand 41.00 Km 0.45 718.12 323.15
Add lead charges of Manufactured Sand 25.00 Km 0.00 505.00 0.00
TOTAL Rate Total 5714.00
13.5 G (p) Case With Batching Plant, Transit Mixer and Concrete Pump
II
Per Cum Basic Cost of Labour, Material & Machinery 3649.00
(a+b+c) of Item 12.8 (G) Case II
d) formwork

SOR 2018-19 (3% OH) Culverts - Sub Structure


RA - 94
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Add 10 per cent of cost of material, labour and 10.00 364.90
machinery (a+b+c) for Formwork
e) Overhead charges @ 2.615% on (a+b+c+d) 104.96
f) Contractor's profit @ 10% on (a+b+c+d+e) 411.89
Rate perm (a+b+c+d+e+f) 4530.75
say 4531
g) seinarage charges per cum
Coarse Sand 0.45 50.00 22.50
Aggregate 0.90 75.00 67.50
Add District Mineral Fund (DMF) 30% on Seinorage 0.300 90.00 27.00
charges
Rate per cum say 117.00
Add lead charges of metal 25.00 Km 0.90 449.50 404.55
Add lead charges of sand 41.00 Km 0.45 718.12 323.15
Add lead charges of Manufactured Sand 25.00 Km 0.00 505.00 0.00
TOTAL Rate Total 5375.00
13.5 G (q) Height 5m to 10m
For height, upto 10m, add 1.6 per cent of cost as above
excluding formwork. For cost of formwork add 11.5 per cent
of cost of material, labour and machinery
Case Using concrete Mixer
I
Per Cum Basic Cost of Labour, Material & Machinery 3922.00
(a+b+c) of Item 12.8 (G) Case I
d) formwork
Add 11.5 per cent of cost of material, labour and 11.50 451.03
machinery (a+b+c) for Formwork
Add 1.6 per cent of cost of material, Labour and 1.60 62.75
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 2.615% on (a+b+c+d) 116.00
f) Contractor's profit @ 10% on (a+b+c+d+e) 455.18
Rate perm (a+b+c+d+e+f) 5006.96
say 5007
g) seinarage charges per cum
Coarse Sand 0.45 50.00 22.50
Aggregate 0.90 75.00 67.50
Add District Mineral Fund (DMF) 30% on Seinorage 0.300 90.00 27.00
charges
Rate per cum say 117.00
Add lead charges of metal 25.00 Km 0.90 449.50 404.55
Add lead charges of sand 41.00 Km 0.45 718.12 323.15
Add lead charges of Manufactured Sand 25.00 Km 0.00 505.00 0.00
TOTAL Rate Total 5852.00
13.5 G (q) Case With Batching Plant, Transit Mixer and Concrete Pump
II
Per Cum Basic Cost of Labour, Material & Machinery 3649.00
(a+b+c) of Item 12.8 (G) Case II
d) formwork
Add 11.5 per cent of cost of material, labour and 11.50 419.64
machinery (a+b+c) for Formwork
Add 1.6 per cent of cost of material, Labour and 1.60 58.38
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 2.615% on (a+b+c+d) 107.92
f) Contractor's profit @ 10% on (a+b+c+d+e) 423.49
Rate perm (a+b+c+d+e+f) 4658.43
say 4658
g) seinarage charges per cum
Coarse Sand 0.45 50.00 22.50
Aggregate 0.90 75.00 67.50
Add District Mineral Fund (DMF) 30% on Seinorage 0.300 90.00 27.00
charges
Rate per cum say 117.00
Add lead charges of metal 25.00 Km 0.90 449.50 404.55

SOR 2018-19 (3% OH) Culverts - Sub Structure


RA - 95
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Add lead charges of sand 41.00 Km 0.45 718.12 323.15
Add lead charges of Manufactured Sand 25.00 Km 0.00 505.00 0.00
TOTAL Rate Total 5503.00
13.5 G (r) Height above 10m
For height, above 10m, add 3.5 per cent of cost as above
excluding formwork. For cost of formwork add 14 per cent of
cost of material, labour and machinery
Case Using concrete Mixer
I
Per Cum Basic Cost of Labour, Material & Machinery 3922.00
(a+b+c) of Item 12.8 (G) Case I
d) formwork
Add 14 per cent of cost of material, labour and 14.00 549.08
machinery (a+b+c) for Formwork
Add 3.5 per cent of cost of material, Labour and 3.50 137.27
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 2.615% on (a+b+c+d) 120.51
f) Contractor's profit @ 10% on (a+b+c+d+e) 472.89
Rate perm (a+b+c+d+e+f) 5201.74
say 5202
g) seinarage charges per cum
Coarse Sand 0.45 50.00 22.50
Aggregate 0.90 75.00 67.50
Add District Mineral Fund (DMF) 30% on Seinorage 0.300 90.00 27.00
charges
Rate per cum say 117.00
Add lead charges of metal 25.00 Km 0.90 449.50 404.55
Add lead charges of sand 41.00 Km 0.45 718.12 323.15
Add lead charges of Manufactured Sand 25.00 Km 0.00 505.00 0.00
TOTAL Rate Total 6046.00
13.5 G (r) Case With Batching Plant, Transit Mixer and Concrete Pump
II
Per Cum Basic Cost of Labour, Material & Machinery 3649.00
(a+b+c) of Item 12.8 (G) Case II
d) formwork
Add 14 per cent of cost of material, labour and 14.00 510.86
machinery (a+b+c) for Formwork
Add 3.5 per cent of cost of material, Labour and 3.50 127.72
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 2.615% on (a+b+c+d) 112.12
f) Contractor's profit @ 10% on (a+b+c+d+e) 439.97
Rate perm (a+b+c+d+e+f) 4839.66
say 4840
g) seinarage charges per cum
Coarse Sand 0.45 50.00 22.50
Aggregate 0.90 75.00 67.50
Add District Mineral Fund (DMF) 30% on Seinorage 0.300 90.00 27.00
charges
Rate per cum say 117.00
Add lead charges of metal 25.00 Km 0.90 449.50 404.55
Add lead charges of sand 41.00 Km 0.45 718.12 323.15
Add lead charges of Manufactured Sand 25.00 Km 0.00 505.00 0.00
TOTAL Rate Total 5684.00
13.5 H RCC Grade M35
(p) Height upto 5m
Same as Item 12.8 (H) upto 5m height, excluding formwork.
For cost of formwork, add 10 per cent of cost of material,
labour and machinery instead of 3 per cent .
Case Using concrete Mixer
I
Per Cum Basic Cost of Labour, Material & Machinery 3981.00
(a+b+c) of Item 12.8 (H) Case I
d) formwork

SOR 2018-19 (3% OH) Culverts - Sub Structure


RA - 96
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Add 10 per cent of cost of material, labour and 10.00 398.10
machinery (a+b+c) for Formwork
e) Overhead charges @ 2.615% on (a+b+c+d) 114.51
f) Contractor's profit @ 10% on (a+b+c+d+e) 449.36
Rate perm (a+b+c+d+e+f) 4942.97
say 4943
g) seinarage charges per cum
Coarse Sand 0.45 50.00 22.50
Aggregate 0.90 75.00 67.50
Add District Mineral Fund (DMF) 30% on Seinorage 0.300 90.00 27.00
charges
Rate per cum say 117.00
Add lead charges of metal 25.00 Km 0.90 449.50 404.55
Add lead charges of sand 41.00 Km 0.45 718.12 323.15
Add lead charges of Manufactured Sand 25.00 Km 0.00 505.00 0.00
TOTAL Rate Total 5788.00
13.5 H (p) Case With Batching Plant, Transit Mixer and Concrete Pump
II
Per Cum Basic Cost of Labour, Material & Machinery 3712.00
(a+b+c) of Item 12.8 (H) Case II
d) formwork
Add 10 per cent of cost of material, labour and 10.00 371.20
machinery (a+b+c) for Formwork
e) Overhead charges @ 2.615% on (a+b+c+d) 106.78
f) Contractor's profit @ 10% on (a+b+c+d+e) 419.00
Rate perm (a+b+c+d+e+f) 4608.97
say 4609
g) seinarage charges per cum
Coarse Sand 0.45 50.00 22.50
Aggregate 0.90 75.00 67.50
Add District Mineral Fund (DMF) 30% on Seinorage 0.300 90.00 27.00
charges
Rate per cum say 117.00
Add lead charges of metal 25.00 Km 0.90 449.50 404.55
Add lead charges of sand 41.00 Km 0.45 718.12 323.15
Add lead charges of Manufactured Sand 25.00 Km 0.00 505.00 0.00
TOTAL Rate Total 5454.00
13.5 H (q) Height 5m to 10m
For height, upto 10m, add 1.4 per cent of cost as above
excluding formwork. For cost of formwork add 11 per cent of
cost of material, labour and machinery .
Case Using concrete Mixer
I
Per Cum Basic Cost of Labour, Material & Machinery 3981.00
(a+b+c) of Item 12.8 (H) Case I
d) formwork
Add 11 per cent of cost of material, labour and 11.00 437.91
machinery (a+b+c) for Formwork
Add 1.4 per cent of cost of material, Labour and 1.40 55.73
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 2.615% on (a+b+c+d) 117.01
f) Contractor's profit @ 10% on (a+b+c+d+e) 459.17
Rate perm (a+b+c+d+e+f) 5050.82
say 5051
g) seinarage charges per cum
Coarse Sand 0.45 50.00 22.50
Aggregate 0.90 75.00 67.50
Add District Mineral Fund (DMF) 30% on Seinorage 0.300 90.00 27.00
charges
Rate per cum say 117.00
Add lead charges of metal 25.00 Km 0.90 449.50 404.55
Add lead charges of sand 41.00 Km 0.45 718.12 323.15
Add lead charges of Manufactured Sand 25.00 Km 0.00 505.00 0.00

SOR 2018-19 (3% OH) Culverts - Sub Structure


RA - 97
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
TOTAL Rate Total 5896.00
13.5 H (q) Case With Batching Plant, Transit Mixer and Concrete Pump
II
Per Cum Basic Cost of Labour, Material & Machinery 3712.00
(a+b+c) of Item 12.8 (H) Case II
d) formwork
Add 11 per cent of cost of material, labour and 11.00 408.32
machinery (a+b+c) for Formwork
Add 1.4 per cent of cost of material, Labour and 1.40 51.97
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 2.615% on (a+b+c+d) 109.11
f) Contractor's profit @ 10% on (a+b+c+d+e) 428.14
Rate perm (a+b+c+d+e+f) 4709.53
say 4710
g) seinarage charges per cum
Coarse Sand 0.45 50.00 22.50
Aggregate 0.90 75.00 67.50
Add District Mineral Fund (DMF) 30% on Seinorage 0.300 90.00 27.00
charges
Rate per cum say 117.00
Add lead charges of metal 25.00 Km 0.90 449.50 404.55
Add lead charges of sand 41.00 Km 0.45 718.12 323.15
Add lead charges of Manufactured Sand 25.00 Km 0.00 505.00 0.00
TOTAL Rate Total 5554.00
13.5 H (r) Height above 10m
For height, above 10m, add 3 per cent of cost as above
excluding formwork. For cost of formwork add 13 per cent of
cost of material, labour and machinery
Case Using concrete Mixer
I
Per Cum Basic Cost of Labour, Material & Machinery 3981.00
(a+b+c) of Item 12.8 (H) Case I
d) formwork
Add 13 per cent of cost of material, labour and 13.00 517.53
machinery (a+b+c) for Formwork
Add 3 per cent of cost of material, Labour and 3.00 119.43
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 2.615% on (a+b+c+d) 120.76
f) Contractor's profit @ 10% on (a+b+c+d+e) 473.87
Rate perm (a+b+c+d+e+f) 5212.59
say 5213
g) seinarage charges per cum
Coarse Sand 0.45 50.00 22.50
Aggregate 0.90 75.00 67.50
Add District Mineral Fund (DMF) 30% on Seinorage 0.300 90.00 27.00
charges
Rate per cum say 117.00
Add lead charges of metal 25.00 Km 0.90 449.50 404.55
Add lead charges of sand 41.00 Km 0.45 718.12 323.15
Add lead charges of Manufactured Sand 25.00 Km 0.00 505.00 0.00
TOTAL Rate Total 6057.00
13.5 H (r) Case With Batching Plant, Transit Mixer and Concrete Pump
II
Per Cum Basic Cost of Labour, Material & Machinery 3712.00
(a+b+c) of Item 12.8 (H) Case II
d) formwork
Add 13 per cent of cost of material, labour and 13.00 482.56
machinery (a+b+c) for Formwork
Add 3 per cent of cost of material, Labour and 3.00 111.36
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 2.615% on (a+b+c+d) 112.60
f) Contractor's profit @ 10% on (a+b+c+d+e) 441.85
Rate perm (a+b+c+d+e+f) 4860.37

SOR 2018-19 (3% OH) Culverts - Sub Structure


RA - 98
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
say 4860
g) seinarage charges per cum
Coarse Sand 0.45 50.00 22.50
Aggregate 0.90 75.00 67.50
Add District Mineral Fund (DMF) 30% on Seinorage 0.300 90.00 27.00
charges
Rate per cum say 117.00
Add lead charges of metal 25.00 Km 0.90 449.50 404.55
Add lead charges of sand 41.00 Km 0.45 718.12 323.15
Add lead charges of Manufactured Sand 25.00 Km 0.00 505.00 0.00
TOTAL Rate Total 5705.00
Note The basic components of this analysis are the same as those
of items 13.8 (A to H). The only changes are as under:

a) Ramps/Stairs: Extra expenditure on structures which are


more than 5 m high @ 2 per cent of cost for height upto 10 m
and 4 per cent for heights above 10 m will be involved for
approaching the work spot by providing higher ramp/stair case
for use
b) The above mentioned percentages have been suitably
modified for different categories as cost for various categories
varies, whereas effort for access for same height will be
similar. As the cost of richer concrete is comparatively more,
the percent
13.6 1600 & Supplying, fitting and placing HYSD bar reinforcement in
2200 sub-structure complete as per drawing and Technical
Specifications
Output: MT
Taking output = 1 MT
a) Material
HYSD bars including 5 per cent overlaps and wastage tonne 1.05 42500 44625

Binding wire kg 6.00 53.00 318.00


b) Labour for cutting, bending, shifting to site, tying
and placing in position
Mate day 0.34 451.00 153.34
Blacksmith day 2.00 482.20 964.40
Mazdoor day 6.50 400.00 2600.00
c) Overhead charges @ 2.615% on (a+b) 1272.48
d) Contractor's profit @ 10% on (a+b+c) 4993.32
Rate for per MT (a+b+c+d) 54926.54
Total 54927
13.7 1600 & Supplying, fitting and placing Mild steel reinforcement
2200 complete in sub-structure as per drawing and Technical
Specification
Unit = MT
Taking output = 1 MT
a) Material
MS bars including 5 per cent overlaps and wastage tonne 1.05 39674 41657.70
Binding wire kg 6.00 53.00 318.00
b) Labour for straightening, cutting, bending, shifting
to site, tying and placing in position
Mate day 0.28 451.00 126.28
Blacksmith day 1.50 482.20 723.30
Mazdoor day 5.50 400.00 2200.00
c) Overhead charges @ 2.615% on (a+b) 1177.41
d) Contractor's profit @ 10% on (a+b+c) 4620.27
Rate for per MT (a+b+c+d) 50822.96
Total 50823

SOR 2018-19 (3% OH) Culverts - Sub Structure


RA - 99
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
13.8 2706 & Providing weep holes in Brick masonry/Plain/ Reinforced
2200 concrete abutment, wing wall/ return wall with 100 mm
dia AC pipe, extending through the full width of the
structure with slope of 1V :20H towards drawing foce.
Complete as per drawing and Technical

Unit = Nos.
Taking output = 30 Nos.
a) Material
AC pipe 100 mm dia. (including wastage @ 5 per cent ) metre 31.50 253.00 7969.50

Average length of weep hole is taken as one metre for the


purpose of estimating.
MS clamp each. 30.00 0.00 0.00
collar for AC pipe (average) taking 10% of above pipe each. 10.00 25.30 253.00
rate
Cement mortar 1:3 (Rate as in Item 12.6) cum 0.05 3380.00 169.00

b) Labour
Mate day 0.03 451.00 13.53
Mason day 0.50 455.00 227.50
Mazdoor day 0.25 400.00 100.00
c) Overhead charges @ 2.615% on (a+b) 228.36
d) Contractor's profit @ 10% on (a+b+c) 896.09
Cost for 30 m = a+b+c+d 9856.97
Rate per m (a+b+c+d)/30 328.57
Total 329
Note 1. In case of stone masonry, the size of the weep hole shall be
150 mm x 80 mm or circular with 150 mm diameter.

2. For structure in stone masonry, the weep holes shall be


deemed to be included in the item of stone masonry work and
shall not be paid separately.
13.9 710.1.4.of Back filling behind abutment, wing wall and return wall
IRC:78 & complete as per drawing and Technical Specification
2200
Unit = cum
Taking output = 10 cum
A Granular material
a) Labour
Mate day 0.28 451.00 126.28
Mazdoor day 7.00 400.00 2800.00
b) Material
Granular material cum 12.00 110.00 1320.00
c) Machinery
Plate compactor/power rammer hour 2.50 59.10 147.75
Water Tanker hour 0.05 655.20 32.76
d) Overhead charges @ 2.615% on (a+b+c) 115.76
e) Contractor's profit @ 10% on (a+b+c+d) 454.26
Cost for 10 cum of granular backfill = a+b+c+d+e 4996.81
Rate per cum = (a+b+c+d+e)/10 499.68
say 500
g) seinarage charges per cum
Granular material cum 1.20 30.00 36.00
Add District Mineral Fund (DMF) 30% on Seinorage 0.300 36.00 10.80
charges
Rate per cum say 46.80
Add Lead charges of gravel 5.00 Km 1.20 238.60 286.32
TOTAL Rate Total 822.00
13.9 B Sandy material
a) Labour
Mate day 0.28 451.00 126.28
Mazdoor for filling, watering, ramming etc. day 7.00 400.00 2800.00
b) Material

SOR 2018-19 (3% OH) Culverts - Sub Structure


RA - 100
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Sand cum 12.00 100.00 1200.00
c) Machinery
Plate compactor/power rammer hour 2.50 59.10 147.75
Water Tanker hour 0.06 655.20 39.31
d) Overhead charges @ 2.615% on (a+b+c) 112.79
e) Contractor's profit @ 10% on (a+b+c+d) 442.61
Cost for 10 cum of sandy backfill = a+b+c+d+e 4868.75
Rate per cum = (a+b+c+d+e)/10 486.87
say 487
g) seinarage charges per cum
Sand cum 1.20 50.00 60.00
Add District Mineral Fund (DMF) 30% on Seinorage 0.300 60.00 18.00
charges
Rate per cum 78.00
Add Lead charges of Sand 41.00 Km 1.20 718.12 861.74
Add lead charges of Manufactured Sand 25.00 Km 0.00 505.00 0.00
TOTAL Rate Total 1427.00
13.10 710.1.4.of Providing and laying of Filter media with granular
IRC:78 materials/stone crushed aggregates satisfying the
and 2200 requirements laid down in clause 2504.2.2. of MoRTH
specifications to a thickness of not less than 600 mm with
smaller size towards the soil and bigger si

Unit = cum
Taking output = 10 cum.
a) Labour
Mate day 0.32 451.00 144.32
Mazdoor for filling, watering, ramming etc. day 7.00 400.00 2800.00
Mazdoor (Skilled) day 1.00 515.00 515.00
b) Material
Filter media of stone aggregate conforming to clause cum 12.00 597.90 7174.80
2504.2.2. of MoRTH specifications.
c) Machinery
Water Tanker of 6 KL capacity hour 0.06 655.20 39.31
d) Overhead charges @ 2.615% on (a+b+c) 279.11
e) Contractor's profit @ 10% on (a+b+c+d) 1095.25
cost for 10 cum of Fiter Media = a+b+c+d+e 12047.80
Rate per cum = (a+b+c+d+e)/10 1204.78
say 1205
Add seignorage charges of metal cum 1.20 75.00 90.00
Add District Mineral Fund (DMF) 30% on Seinorage 0.300 90.00 27.00
charges
Add lead charges of metal 25.00 Km 1.20 449.50 539.40
TOTAL Rate Total 1861.00
13.14 2000 & Supplying, fitting and fixing in position true to line and
2200 level elastomeric bearing conforming to IRC: 83 (Part-II)
section IX and clause 2005 of MoRTH specifications
complete including all accessories as per drawing and
Technical Specifications.
Unit: one cubic centimetre
Considering an elastomeric bearing of size 500 x 400 x 96 mm
for this analysis.
Overall volume - 19200 cu.cm
Volume of 6 nos. 488 x 388 x 4 mm size reinforcing steel
plates = 4545 cu.cm.
Hence volume of elastometer = 14655 cu.cm.
a) Labour
Mate day 0.06 451.00 27.06
Mazdoor day 1.00 400.00 400.00
Mazdoor (Skilled) day 0.50 515.00 257.50
b) Material

SOR 2018-19 (3% OH) Culverts - Sub Structure


RA - 101
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Elastomeric bearing assembly consisting of 7 layers of each. 1.00 15310.00 15310.00
elastomer bonded to 6 nos. internal reinforcing steel
laminates by the process of vulcanisation, complete with
all components as per drawing and Technical
Specifications.
Add 1 per cent of cost of bearing assembly for 153.10
foundation anchorage bolts and consumables.
c) Overhead charges @ 2.615% on (a+b) 422.26
d) Contractor's profit @ 10% on (a+b+c) 1656.99
cost for 19200cc of elastomeric bearing = a+b+c+d 18226.91
Rate per cc of elastomeric bearing = (a+b+c+d)/19200 0.95

Total 1

SOR 2018-19 (3% OH) Culverts - Sub Structure


RA - 102
CHAPTER-14
SUPER-STRUCTURE
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
14.1 1500 Furnishing and Placing Reinforced/ Prestressed cement
&1600 concrete in super-structure as per drawing and
1700 Technical Specification
14.1 E PSC Grade M-40
Case 1 Using concrete mixer.
Unit = 1 cum
Taking output = 15 cum
a) Material
Cement tonne 6.45 3900.00 25155.00
Coarse sand cum 6.75 182.00 1228.50
20 mm Aggregate cum 8.10 1303.00 10554.30
10 mm Aggregate cum 5.40 894.00 4827.60
Admixture @ 0.4 per cent of cement kg 25.80 43.00 1109.40
b) Labour
Mate day 0.96 451.00 432.96
Mason day 2.00 455.00 910.00
Mazdoor day 22.00 400.00 8800.00
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 525.50 3153.00
Generator 33 KVA hour 6.00 1032.00 6192.00
Basic Cost of Labour, Material & Machinery (a+b+c) 62363.00
for 15 cum
For formwork and staging add the following:
14.1E (i) For solid slab super-structure, 20-30 per cent of (a+b+c)
Case I
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) for 62363.00
15 cum
d) Formwork and staging 20 per cent of (a+b+c) 20.00 12472.60

e) Overhead charges @ 2.615% on (a+b+c+d) 1956.95


f) Contractor's profit @ 10% on (a+b+c+d+e) 7679.26
Cost for 15 cum = a+b+c+d+e+f 84471.81
Rate per cum = (a+b+c+d+e+f)/15 5631.45
say 5631.00
g) seiniorage charges per cum
Coarse Sand cum 0.45 50.00 18.00
Aggregate cum 0.90 75.00 67.50
Add District Mineral Fund (DMF) 30% on Seinorage 0.300 85.50 25.65
charges
Rate per cum say 111.15
Add lead charges of metal 25.00 Km 0.90 449.50 404.55
Add lead charges of sand 41.00 Km 0.45 718.12 323.15
Add lead charges of Manufactured Sand 25.00 Km 0.00 505.00 0.00
say 727.70
Total 6470.00
14.1E (q) Height 5m to 10m
Case I (i)

Basic Cost of Labour, Material & Machinery (a+b+c) for 62363.00


15 cum
d) Formwork and staging 25 per cent of (a+b+c) 25.00 15590.75

SOR 2018-19 (3% OH) Culverts - Super Structure


RA - 103
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
e) Overhead charges @ 2.615% on (a+b+c+d) 2038.49
f) Contractor's profit @ 10% on (a+b+c+d+e) 7999.22
Cost for 15 cum = a+b+c+d+e+f 87991.46
Rate per cum = (a+b+c+d+e+f)/15 5866.10
say 5866.00
g) seiniorage charges per cum 111.15
Rate per cum say 111.15

f) Lead charges for Material say 727.70


TOTAL Rate 6704.95
Total 6705.00
14.1E (r) Height above 10m
Case I (i)

Basic Cost of Labour, Material & Machinery (a+b+c) for 62363.00


15 cum
d) Formwork and staging 30 per cent of (a+b+c) 30.00 18708.90

e) Overhead charges @ 2.615% on (a+b+c+d) 2120.03


f) Contractor's profit @ 10% on (a+b+c+d+e) 8319.19
Cost for 15 cum = a+b+c+d+e+f 91511.12
Rate per cum = (a+b+c+d+e+f)/15 6100.74
say 6101.00
g) seiniorage charges per cum 111.15
Rate per cum say 111.15

f) Lead charges for Material say 727.70


TOTAL Rate 6939.60
Total 6940.00
14.1E (ii) For T-beam & slab, 25-35 per cent of (a+b+c)
Case I
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) for 62363.00
15 cum
d) Formwork and staging 25 per cent of (a+b+c) 25.00 15590.75

e) Overhead charges @ 2.615% on (a+b+c+d) 2038.49


f) Contractor's profit @ 10% on (a+b+c+d+e) 7999.22
Cost for 15 cum = a+b+c+d+e+f 87991.46
Rate per cum = (a+b+c+d+e+f)/15 5866.10
say 5866.00
g) seiniorage charges per cum 111.15
Rate per cum say 111.15

f) Lead charges for Material say 727.70


TOTAL Rate 6704.95
Total 6705.00
14.1E (q) Height 5m to 10m
Case I
(ii)
Basic Cost of Labour, Material & Machinery (a+b+c) for 62363.00
15 cum
d) Formwork and staging 30 per cent of (a+b+c) 30.00 18708.90

e) Overhead charges @ 2.615% on (a+b+c+d) 2120.03


f) Contractor's profit @ 10% on (a+b+c+d+e) 8319.19

SOR 2018-19 (3% OH) Culverts - Super Structure


RA - 104
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Cost for 15 cum = a+b+c+d+e+f 91511.12
Rate per cum = (a+b+c+d+e+f)/15 6100.74
say 6101.00
g) seiniorage charges per cum 111.15
Rate per cum say 111.15

f) Lead charges for Material say 727.70


TOTAL Rate 6939.60
Total 6940.00
14.1E (r) Height above 10m
Case I
(ii)
Basic Cost of Labour, Material & Machinery (a+b+c) for 62363.00
15 cum
d) Formwork and staging 35 per cent of (a+b+c) 35.00 21827.05

e) Overhead charges @ 2.615% on (a+b+c+d) 2201.57


f) Contractor's profit @ 10% on (a+b+c+d+e) 8639.16
Cost for 15 cum = a+b+c+d+e+f 95030.78
Rate per cum = (a+b+c+d+e+f)/15 6335.39
say 6335.00
g) seiniorage charges per cum 111.15
Rate per cum say 111.15

f) Lead charges for Material say 727.70


TOTAL Rate 7174.24
Total 7174.00
14.1E Case II Using Batching Plant, Transit Mixer and Concrete Pump

Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 51.60 3900.00 201240.00
Coarse sand cum 54.00 182.00 9828.00
20 mm Aggregate cum 64.80 1303.00 84434.40
10 mm Aggregate cum 43.20 894.00 38620.80
Admixture @ 0.4 per cent of cement kg 206.40 43.00 8875.20
b) Labour
Mate day 0.94 451.00 423.94
Mason day 3.50 455.00 1592.50
Mazdoor day 20.00 400.00 8000.00
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1343.30 8059.80
Generator 100 KVA hour 6.00 1316.30 7897.80
Loader hour 6.00 1594.70 9568.20
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity lead upto1 Km hour 15.00 2071.70 31075.50
Lead beyond 1 Km, L - lead in Kilometer tonne.km 300L 13.18 31634.26

Concrete Pump hour 6.00 1508.80 9052.80


Basic Cost of Labour, Material & Machinery (a+b+c) for 450304.00
120 cum
For formwork and staging add the following:

SOR 2018-19 (3% OH) Culverts - Super Structure


RA - 105
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
14.1E (i) For solid/voided slab super-structure, 18-28 per cent of
Case II (a+b+c)
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) for 120 450304.00
cum
d) Formwork and staging 18 per cent of (a+b+c) 18.00 81054.72

e) Overhead charges @ 2.615% on (a+b+c+d) 13895.03


f) Contractor's profit @ 10% on (a+b+c+d+e) 54525.38
Cost for 15 cum = a+b+c+d+e+f 599779.13
Rate per cum = (a+b+c+d+e+f)/120 4998.16
say 4998.00
g) seiniorage charges per cum
Coarse Sand cum 0.45 50.00 18.00
Aggregate cum 0.90 75.00 67.50
Add District Mineral Fund (DMF) 30% on Seinorage 0.300 85.50 25.65
charges
Rate per cum say 111.15
Add lead charges of metal 25.00 Km 0.90 449.50 404.55
Add lead charges of sand 41.00 Km 0.45 718.12 323.15
Add lead charges of Manufactured Sand 25.00 Km 0.00 505.00 0.00
say 727.70
Total 5837.00
14.1E (q) Height 5m to 10m
Case II
(i)
Basic Cost of Labour, Material & Machinery (a+b+c) for 450304.00
120 cum
d) Formwork and staging 23 per cent of (a+b+c) 23.00 103569.92

e) Overhead charges @ 2.615% on (a+b+c+d) 14483.80


f) Contractor's profit @ 10% on (a+b+c+d+e) 56835.77
Cost for 120 cum = a+b+c+d+e+f 625193.50
Rate per cum = (a+b+c+d+e+f)/120 5209.95
say 5210.00
g) seiniorage charges per cum 111.15
Rate per cum say 111.15

f) Lead charges for Material say 727.70


TOTAL Rate 6048.80
Total 6049.00
14.1E (r) Height above 10m
Case II
(i)
Basic Cost of Labour, Material & Machinery (a+b+c) for 450304.00
120 cum
d) Formwork and staging 28 per cent of (a+b+c) 28.00 126085.12

e) Overhead charges @ 2.615% on (a+b+c+d) 15072.58


f) Contractor's profit @ 10% on (a+b+c+d+e) 59146.17
Cost for 120 cum = a+b+c+d+e+f 650607.87
Rate per cum = (a+b+c+d+e+f)/120 5421.73
say 5422.00
g) seiniorage charges per cum 111.15
Rate per cum say 111.15

SOR 2018-19 (3% OH) Culverts - Super Structure


RA - 106
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
f) Lead charges for Material say 727.70
TOTAL Rate 6260.59
Total 6261.00
14.1E (ii) For T-beam & slab, 23-33 per cent of (a+b+c)
Case II
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) for 450304.00
120 cum
d) Formwork and staging 23 per cent of (a+b+c) 23.00 103569.92

e) Overhead charges @ 2.615% on (a+b+c+d) 14483.80


f) Contractor's profit @ 10% on (a+b+c+d+e) 56835.77
Cost for 120 cum = a+b+c+d+e+f 625193.50
Rate per cum = (a+b+c+d+e+f)/120 5209.95
say 5210.00
g) seiniorage charges per cum 111.15
Rate per cum say 111.15

f) Lead charges for Material say 727.70


TOTAL Rate 6048.80
Total 6049.00
14.1E (q) Height 5m to 10m
Case II
(ii)
Basic Cost of Labour, Material & Machinery (a+b+c) for 450304.00
120 cum
d) Formwork and staging 28 per cent of (a+b+c) 28.00 126085.12

e) Overhead charges @ 2.615% on (a+b+c+d) 15072.58


f) Contractor's profit @ 10% on (a+b+c+d+e) 59146.17
Cost for 120 cum = a+b+c+d+e+f 650607.87
Rate per cum = (a+b+c+d+e+f)/120 5421.73
say 5422.00
g) seiniorage charges per cum 111.15
Rate per cum say 111.15

f) Lead charges for Material say 727.70


TOTAL Rate 6260.59
Total 6261.00
14.1E (r) Height above 10m
Case II
(ii)
Basic Cost of Labour, Material & Machinery (a+b+c) for 450304.00
120 cum
d) Formwork and staging 33 per cent of (a+b+c) 33.00 148600.32

e) Overhead charges @ 2.615% on (a+b+c+d) 15661.35


f) Contractor's profit @ 10% on (a+b+c+d+e) 61456.57
Cost for 120 cum = a+b+c+d+e+f 676022.23
Rate per cum = (a+b+c+d+e+f)/120 5633.52
say 5634.00
g) seiniorage charges per cum 111.15
Rate per cum say 111.15

f) Lead charges for Material say 727.70


TOTAL Rate 6472.37

SOR 2018-19 (3% OH) Culverts - Super Structure


RA - 107
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Total 6472.00
14.1E (iii) For cast-in-situ box girder, segment construction and
Case II balanced cantilever, 38-58 per cent of cost of concrete.

(p) Height upto 5m


Basic Cost of Labour, Material & Machinery (a+b+c) for 450304.00
120 cum
d) Formwork and staging 38 per cent of (a+b+c) 38.00 171115.52

e) Overhead charges @ 2.615% on (a+b+c+d) 16250.12


f) Contractor's profit @ 10% on (a+b+c+d+e) 63766.96
Cost for 120 cum = a+b+c+d+e+f 701436.60
Rate per cum = (a+b+c+d+e+f)/120 5845.31
say 5845.00
g) seiniorage charges per cum 111.15
Rate per cum say 111.15
f) Lead charges for Material say 727.70
TOTAL Rate 6684.16
Total 6684.00
14.1E (q) Height 5m to 10m
Case II
(iii)
Basic Cost of Labour, Material & Machinery (a+b+c) for 450304.00
120 cum
d) Formwork and staging 48 per cent of (a+b+c) 48.00 216145.92

e) Overhead charges @ 2.615% on (a+b+c+d) 17427.67


f) Contractor's profit @ 10% on (a+b+c+d+e) 68387.76
Cost for 120 cum = a+b+c+d+e+f 752265.34
Rate per cum = (a+b+c+d+e+f)/120 6268.88
say 6269.00
g) seiniorage charges per cum 111.15
Rate per cum say 111.15
f) Lead charges for Material say 727.70
TOTAL Rate 7107.73
Total 7108.00
14.1E (r) Height above 10m
Case II
(iii)
Basic Cost of Labour, Material & Machinery (a+b+c) for 450304.00
120 cum
d) Formwork and staging 58 per cent of (a+b+c) 58.00 261176.32

e) Overhead charges @ 2.615% on (a+b+c+d) 18605.21


f) Contractor's profit @ 10% on (a+b+c+d+e) 73008.55
Cost for 120 cum = a+b+c+d+e+f 803094.08
Rate per cum = (a+b+c+d+e+f)/120 6692.45
say 6692.00
g) seiniorage charges per cum 111.15
Rate per cum say 111.15
f) Lead charges for Material say 727.70
TOTAL Rate 7531.30
Total 7531.00

SOR 2018-19 (3% OH) Culverts - Super Structure


RA - 108
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
14.2 1600 Supplying, fitting and placing HYSD Fe 500 bar
reinforcement in super-structure complete as per
drawing and technical specifications
Unit = 1 MT
Taking output = 1 MT
a) Material
HYSD bars including 5 per cent for laps and wastage tonne 1.05 42500.00 44625.00

Binding wire Kg 8.00 53.00 424.00


b) Labour for cutting, bending, tying and placing in
position
Mate day 0.44 451.00 198.44
Blacksmith day 3.00 482.20 1446.60
Mazdoor day 8.00 400.00 3200.00
Basic Cost of Labour & Material (a+b) 49895.00
c) Overhead charges @ 2.615% on (a+b) 1304.73
d) Contractor's profit @ 10% on (a+b+c) 5119.88
Rate per MT = a+b+c+d 56318.65
Total 56319.00
14.16 800 Painting on concrete surface
Providing and applying 2 coats of water based cement
paint to unplastered concrete surface after cleaning the
surface of dirt, dust, oil, grease, efflorescence and
applying paint @ of 1 litre for 2 sqm.

Unit = sqm
Taking output = 10 sqm
a) Labour
Mate day 0.01 451.00 4.51
Painter day 0.25 473.00 118.25
Mazdoor (Skilled) day 0.25 515.00 128.75
b) Material
Water based paint of approved quality for cement Litres 5.00 51.00 255.00
concrete surface
c) Overhead charges @ 2.615% on (a+b) 13.25
d) Contractor's profit @ 10% on (a+b+c) 51.98
Cost for 10 sqm (a+b+c+d) 571.73
Rate per sqm (a+b+c+d)/10 57.17
Total 57.00

SOR 2018-19 (3% OH) Culverts - Super Structure


RA - 109
CHAPTER - 15
RIVER TRAINING AND PROTECTION WORKS
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
15.1 2503 Providing and laying boulders apron on river bed for
protection against scour with stone boulders weighing
not less than 40 kg each complete as per drawing and
Technical specification.
A Boulder Laid Dry Without Wire Crates.
Unit = cum
Taking output = 1 cum
a) Material
Stone cum 1.00 233.80 233.80
Stone Spalls cum 0.20 110.00 22.00
b) Labour
Mate day 0.04 451.00 18.04
Mason day 0.35 455.00 159.25
Mazdoor * day 0.75 400.00 300.00
c) Overhead charges @ 2.615% on (a+b) 19.17
d) Contractor's profit @ 10% on (a+b+c) 75.23
Rate per cum = (a+b+c+d) 827.49
say 827.00
e) seiniorage charges per cum
Stone cum 1.00 75.00 75.00
Stone Spalls cum 0.20 75.00 15.00
Add District Mineral Fund (DMF) 30% on Seinorage 0.300 90.00 27.00
charges
Add lead charges of metal 25.00 Km 1.20 449.50 539.40
Total rate 1483.89
Rate per cum Total 1484.00
* Including excavation for trimming for preparation of bed.
Note Nominal excavation required for preparation of bed has been
taken into account while making provision for labour.

15.5 2504 Providing and laying Filter material underneath pitching


in slopes complete as per drawing and Technical
specification
Unit = cum
Taking output = 1 cum
a) Material
Graded stone aggregate of required size cum 1.20 597.90 717.48
b) Labour
Mate day 0.05 451.00 22.55
Mazdoor (Skilled) day 0.25 515.00 128.75
Mazdoor * day 1.00 400.00 400.00
c) Overhead charges @ 2.615% on (a+b) 33.18
d) Contractor's profit @ 10% on (a+b+c) 130.20
Rate per cum = (a+b+c+d) 1432.15
say 1432.00
e) seiniorage charges per cum
Stone cum 1.20 75.00 90.00
Add District Mineral Fund (DMF) 30% on Seinorage 0.300 90.00 27.00
charges
Add lead charges of metal 25.00 Km 1.20 449.50 539.40
Total rate 2088.55
Rate per cum Total 2089.00

Includes Mazdoor required for trimming of slope to proper


profile and preparation of bed.

SOR 2018-19 (3% OH) Culverts - Protection works


RA - 110
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
15.10 2507.2 Curtain wall complete as per drawing and Technical
specification
A Stone masonry in cement mortar (1:3)
Coursed rubble masonry (1st sort) cum 1.00 6334.00 6334.00

Rate same as per item No. 12.7 (A) including OH & CP

Rate per cum total 6334.00


or
15.10 B Cement concrete Grade M15
Concrete Grade M15 Rate as per item No. 12.8 (A) cum 1.00 4729.00 4729.00
including OH & CP
Rate per cum say 4729.00
Total 4729.00
Note Other items like excavation for foundation, filling behind wall,
filter media, weep holes etc. shall be added separately as
per approved design.
15.11 2507.2 Flexible Apron :Construction of flexible apron 1 m thick
comprising of loose stone boulders weighing not less
than 40 kg beyond curtain wall.
Unit = cum
Taking Output = 1 cum
a) Material
Stone cum 1.00 233.80 233.80
Stone Spalls cum 0.20 110.00 22.00
b) Labour
Mate day 0.05 451.00 22.55
Mason day 0.25 455.00 113.75
Mazdoor day 1.00 400.00 400.00
Add 1 per cent of cost of (a+b) for trimming and 7.92
preparation of bed.
c) Overhead charges @ 2.615% on (a+b) 20.92
d) Contractor's profit @ 10% on (a+b+c) 82.09
Rate per cum = (a+b+c+d) 903.04
say 903.00
e) seiniorage charges per cum
Stone cum 1.00 75.00 75.00
Stone Spalls cum 0.20 75.00 15.00
Add District Mineral Fund (DMF) 30% on Seinorage 0.300 90.00 27.00
charges
Add lead charges of metal 25.00 Km 1.20 449.50 539.40
Total rate 1559.40
Rate per cum Total 1559.00

SOR 2018-19 (3% OH) Culverts - Protection works


RA - 111
Rates of Material for the Year 2018-19

DEDUC
INITIAL RATE T MACHINE SEIGNO Total Rate as
S. excluding STACK CRUSHING BLASTING RAGE per SSR 2018-
DESCRIPTION OF THE MATERIAL UNIT
NO stacking ING CHARGES CHARGES CHARGE 19 excluding
charges CHARG @ 25% S Taxes
ES
1 40 mm SS 5 metal (IS383,1970) Cum 590.4 147.60 70.00 808.00
2 20 mm SS 5 metal (IS383,1970) Cum 986.40 246.60 70.00 1303.00
3 25 mm SS 5 metal (IS383,1970) Cum 947.2 236.80 70.00 1254.00
4 10 mm SS 5 metal (IS383,1970) Cum 659.20 164.80 70.00 894.00
5 6 mm SS 5 metal (IS383,1970) Cum 506.4 126.60 70.00 703.00
6 Gravel Cum 110.00 110.00
7 Sand for mortar Cum 182 182.00
8 Sand for filling, blindage Cum 100 100.00
9 12 mm SS 5 metal (IS383,1970) Cum 782.4 195.60 70.00 1048.00
10 RR masonary (Granite) Cum 240 70.00 310.00
11 CR masonary (Granite) Cum 274.3 70.00 344.30
Stone boulder of size 150 mm size
90.50
12 Cum 70.00 160.50
Stone boulder of size 150-200mm
168.55
13 size Cum 70.00 238.55
163.80
14 Stone boulder of size 300 mm size Cum 70.00 233.80
Stone dust (HBG stone chips 2.36
333.00
15 mm and below) Cum 333.00
16 Sand for mortar Cum 182 182.00
17 Bulk Bitumen Grade 30/40 mt 33760.00 33760.00
18 Bulk Bitumen Grade 80/100 mt 31690.00 31690.00
19 Modified Bitumen CRMB55 mt 33670.00 33670.00
20 Bitumen emulsion (Bulk) mt 35790.00 35790.00
21 Cement mt 3900.00 3900.00
22 Fe 500 steel mt 42500.00 42500.00
23 Mild steel rods mt 39674.00 39674.00
24 Structural steel mt 42000.00 42000.00
25 HT wire 4mm mt 35556.00 35556.00
26 40 mm metal (hand broken) Cum 580.50 70.00 650.50
27 Moorum at Site Cum 185.00 185.00
28 2.36mm to 5mm metal (IRC-MORTH) Cum 293.35 73.3375 70.00 436.69

SOR 2018-19 (3% OH) Culverts - RMR


RA - 112
RATES OF CONVEYANCE OF MATERIALS INCLUDING LOADING AND UNLOADING -- CULVERT WORKS

SURFACED ROADS UNSURFACED ROADS KATCHA ROADS


BEYOND 1
UPTO 1 KM BEYOND 1 KM UPTO 1 KM BEYOND 1 KM UPTO 1 KM
KM
S.NO DESCRIPTION OF THE ITEM INCLUDING INCLUDING INCLUDING INCLUDING INCLUDING
INCLUDING
CP & OH CP & OH PER CP & OH CP & OH PER CP & OH PER
CP & OH
PER CUM CUM PER CUM CUM CUM
PER CUM

1 METAL / STONE / RUBBLE STONE 183.10 11.10 185.35 13.35 198.85 26.85

2 EARTH / GRAVEL / SAND 185.32 13.32 188.02 16.02 204.22 32.22

3 BITUMEN / LUBRICANTS 1.86 1.86 1.86 1.86 1.86 1.86

SOR 2018-19 (3% OH) Culverts - Conveyance


RA - 113
RA - 114
CHAPTER-12
FOUNDATIONS
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
12.1 304 Excavation for Structures
Earth work in excavation of foundation of structures as per
drawing and technical specification, including setting out,
construction of shoring and bracing, removal of stumps and
other deleterious matter, dressing of sides and bottom and
backfilling with
I Ordinary soil
Unit = cum
Taking output = 10 cum
A Manual Means
(i) Depth upto 3 m
a) Labour
Mate day 0.14 451.00 63.14
Mazdoor day 3.50 400.00 1400.00
b) Overhead charges @ 14.615% on (a) 213.84
c) Contractor's profit @ 10% on (a+b) 167.70
Cost for 10 cum = a+b+c 1844.68
Rate per cum = (a+b+c)/10 184.47
Total 184.00
Note 1. Cost of dewatering may be added where required upto,
10 per cent of labour cost Assessment for dewatering shall
be made as per site conditions.
2.The excavated earth can be used partially for backfilling of
foundation pit and partly for road work except for marshy
soil. Hence cost of disposal has not been added except for
marshy soil. This remark is common to all cases of item 12.1
excluding mars
3.The cost of shoring and shuttering, where needed, may be
added @ 1 per cent on cost of excavation for open
foundation.
12.1 (I) (ii) Depth 3 m to 6 m
A
a) Labour
Mate/Supervisor day 0.18 451.00 81.18
Mazdoor day 4.50 400.00 1800.00
b) Overhead charges @ 14.615% on (a) 274.93
c) Contractor's profit @ 10% on (a+b) 215.61
Cost for 10 cum = a+b+c 2371.73
Rate per cum = (a+b+c)/10 237.17
Total 237.00
Note Cost of dewatering may be added where required upto 15
per cent of labour cost. Assessment for dewatering shall be
done as per actual ground conditions.
12.1 (I) (iii) Depth above 6 m
A
a) Labour
Mate/Supervisor day 0.24 451.00 108.24
Mazdoor day 6.00 400.00 2400.00
b) Overhead charges @ 14.615% on (a) 366.58
c) Contractor's profit @ 10% on (a+b) 287.48
Cost for 10 cum = a+b+c 3162.30
Rate per cum = (a+b+c)/10 316.23
Total 316.00
Note 1. Cost of dewatering may be added where required upto 20
per cent of labour cost. Assessment for dewatering shall be
made as per site conditions..
12.1 (I) B Mechanical Means
(i) Depth upto 3 m
Unit = cum
Taking output = 240 cum
a) Labour
Mate day 0.32 451.00 144.32
Mazdoor day 8.00 400.00 3200.00
b) Machinery

SOR 2018-19 (15% OH) BRIDGES - FOUNDATIONS

RA - 115
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Hydraulic excavator 1.0 cum bucket capacity hour 6.00 2791.60 16749.60
c) Overhead charges @ 14.615% on (a+b) 2936.73
d) Contractor's profit @ 10% on (a+b+c) 2303.06
Cost for 240 cum = a+b+c+d 25333.71
Rate per cum = (a+b+c+d)/240 105.56
Total 106.00
Note Cost of dewatering upto 5 per cent of (a+b) may be added,
where required. Assessment for dewatering shall be made
as per site conditions..
12.1 (I) (ii) Depth 3 m to 6 m
B
Unit = cum
Taking output = 210 cum
a) Labour
Mate day 0.32 451.00 144.32
Mazdoor day 8.00 400.00 3200.00
b) Machinery
Hydraulic excavator 1.0 cum bucket capacity hour 6.00 2791.60 16749.60
c) Overhead charges @ 14.615% on (a+b) 2936.73
d) Contractor's profit @ 10% on (a+b+c) 2303.06
Cost for 210 cum = a+b+c+d 25333.71
Rate per cum = (a+b+c+d)/210 120.64
Total 121.00
Note Cost of dewatering upto 7.5 per cent of (a+b) may be
added, where required. Assessment for dewatering shall be
made as per site conditions..
12.1 (I) (iii) Depth above 6m
B
Unit = cum
Taking output = 180 cum
a) Labour
Mate day 0.40 451.00 180.40
Mazdoor day 10.00 400.00 4000.00
b) Machinery
Hydraulic excavator 1.0 cum bucket capacity hour 6.00 2791.60 16749.60
c) Overhead charges @ 14.615% on (a+b) 3058.92
d) Contractor's profit @ 10% on (a+b+c) 2398.89
Cost for 180 cum = a+b+c+d 26387.81
Rate per cum = (a+b+c+d)/180 146.60
Total 147.00
Note 1. Cost of dewatering upto 10 per cent of (a+b) may be
added, where required. Assessment for dewatering shall be
made as per site conditions..
2.Labour provided for excavation by mechanical means
includes that required for trimming of bottom and side
slopes.
12.1 II Ordinary Rock (not requiring blasting)
A Manual Means
(i) Depth upto 3 m
Unit = cum
Taking output = 10 cum
a) Labour
Mate day 0.20 451.00 90.20
Mazdoor day 5.00 400.00 2000.00
b) Overhead charges @ 14.615% on (a) 305.48
c) Contractor's profit @ 10% on (a+b) 239.57
Cost for 10 cum = a+b+c 2635.25
Rate per cum = (a+b+c)/10 263.53
Total 264.00
Note Cost of dewatering upto 10 per cent of labour cost may be
added, where required. Assessment for dewatering shall be
made as per site conditions..
12.1(II) B Mechanical Means

SOR 2018-19 (15% OH) BRIDGES - FOUNDATIONS

RA - 116
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Unit = cum
Taking output = 180 cum
a) Labour
Mate day 0.24 451.00 108.24
Mazdoor day 6.00 400.00 2400.00
b) Machinery
Hydraulic excavator 1.0 cum bucket capacity hour 6.00 2791.60 16749.60
c) Overhead charges @ 14.615% on (a+b) 2814.53
d) Contractor's profit @ 10% on (a+b+c) 2207.24
Cost for 180 cum = a+b+c+d 24279.61
Rate per cum = (a+b+c+d)/180 134.89
Total 135.00
Note 1.Cost of dewatering upto 10 per cent of (a+b), may be
added, where required Assessment for dewatering shall be
made as per site conditions.
2.In case of rock, foundation beyond3 m is not dug and
hence not included.
12.1 III Hard Rock ( requiring blasting )
A Manual Means
Unit = cum
Taking output = 10 cum
a) Labour
Mate day 0.35 451.00 157.85
Driller day 0.50 550.00 275.00
Blaster day 0.25 550.00 137.50
Mazdoor day 8.00 400.00 3200.00
b) Machinery
Air Compressor 250 cfm with 2 jack hammer for hour 1.00 556.50 556.50
drilling.
c) Material
Blasting Material kg 3.50 57.00 199.50
Detonator electric each 14.00 9.00 126.00
d) Overhead charges @ 14.615% on (a+b+c) 679.94
e) Contractor's profit @ 10% on (a+b+c+d) 533.23
Cost for 10 cum = a+b+c+d+e 5865.52
Rate per cum = (a+b+c+d+e)/10 586.55
Total 587.00
Note Cost of dewatering @ 10 per cent of (a+b) may be
added, where required Assessment for dewatering shall be
made as per site conditions.
12.8 1500, 1700 Plain/Reinforced Cement Concrete in Open Foundation
& 2100 complete as per Drawing and Technical Specifications.

A PCC Grade M15


Unit = cum
Taking output = 15 cum
a) Material
Cement tonne 4.13 3900.00 16107.00
Coarse sand cum 6.75 182.00 1228.50
40 mm Aggregate cum 8.10 808.00 6544.80
20 mm Aggregate cum 4.05 1303.00 5277.15
10 mm Aggregate cum 1.35 894.00 1206.90
b) Labour
Mate day 0.86 451.00 387.86
Mason day 1.50 455.00 682.50
Mazdoor day 20.00 400.00 8000.00
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 525.50 3153.00
Generator 63 KVA hour 6.00 1174.15 7044.90
Per Cum Basic Cost of Labour, Material & Machinery 3309.00
(a+b+c)

SOR 2018-19 (15% OH) BRIDGES - FOUNDATIONS

RA - 117
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
d) Formwork @ 4 per cent on cost of concrete i.e. cost 1985.30
of material, labour and machinery

e) Overhead charges @ 14.615% on (a+b+c+d) 7543.96


f) Contractor's profit @ 10% on (a+b+c+d+e) 5916.19
Cost for 15 cum = a+b+c+d+e+f 65078.06
Rate per cum = (a+b+c+d+e+f)/15 4338.54
say 4339.00
g) seigniorage charges per cum
Coarse Sand 0.45 50.00 22.50
Aggregate 0.90 75.00 67.50
Add District Mineral Fund (DMF) 30% on Seinorage 0.300 90.00 27.00
charges
Rate per cum say 117.00
Add lead charges of metal 25.00 Km 0.90 504.25 453.83
Add lead charges of sand 41.00 Km 0.45 805.54 362.49
Add lead charges of Manufactured Sand 25.00 Km 0.00 566.50 0.00
816.32
5271.86
TOTAL Rate Total 5272.00
Note Needle Vibrator is an item of minor T & P which is already
included in overhead charges. Hence not added in rate
analysis of cement concrete works.
12.8 B PCC Grade M20
Unit : cum
Taking output = 15 cum
a) Material
Cement tonne 5.16 3900.00 20124.00
Coarse sand cum 6.75 182.00 1228.50
40 mm Aggregate cum 5.40 808.00 4363.20
20 mm Aggregate cum 5.40 1303.00 7036.20
10 mm Aggregate cum 2.70 894.00 2413.80
b) Labour
Mate day 0.86 451.00 387.86
Mason day 1.50 455.00 682.50
Mazdoor day 20.00 400.00 8000.00
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 525.50 3153.00
Generator 33 KVA hour 6.00 1032.00 6192.00
Per Cum Basic Cost of Labour, Material & Machinery 3573.00
(a+b+c)
d) Formwork @ 4 per cent on cost of concrete i.e. cost 2143.24
of material, labour and machinery
e) Overhead charges @ 14.615% on (a+b+c+d) 8144.11
f) Contractor's profit @ 10% on (a+b+c+d+e) 6386.84
Cost for 15 cum = a+b+c+d+e+f 70255.25
Rate per cum = (a+b+c+d+e+f)/15 4683.68
say 4684.00
g) seigniorage charges per cum
Coarse Sand 0.45 50.00 22.50
Aggregate 0.90 75.00 67.50
Add District Mineral Fund (DMF) 30% on Seinorage 0.300 90.00 27.00
charges
Rate per cum say 117.00
Add lead charges of metal 25.00 Km 0.90 504.25 453.83
Add lead charges of sand 41.00 Km 0.45 805.54 362.49
Add lead charges of Manufactured Sand 25.00 Km 0.00 566.50 0.00
816.32
TOTAL Rate Total 5617.00
12.8 G RCC Grade M30

SOR 2018-19 (15% OH) BRIDGES - FOUNDATIONS

RA - 118
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
12.8 G Case II Using Batching Plant, Transit Mixer and Concrete Pump

Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 48.80 3900.00 190320.00
Coarse sand cum 54.00 182.00 9828.00
20 mm Aggregate cum 64.80 1303.00 84434.40
10 mm Aggregate cum 43.20 894.00 38620.80
Admixture Kg 195.20 43.00 8393.60
b) Labour
Mate day 0.84 451.00 378.84
Mason day 3.00 455.00 1365.00
Mazdoor day 18.00 400.00 7200.00
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1343.30 8059.80
Generator 100 KVA hour 6.00 1316.30 7897.80
Loader 1 cum capacity hour 6.00 1594.70 9568.20
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 2071.70 31075.50
Transit Mixer 4 cum capacity lead beyond 1 Km, L - tonne.km 300L 13.18 31634.26
lead in Kilometer
Concrete Pump hour 6.00 1508.80 9052.80
Per Cum Basic Cost of Labour, Material & Machinery 3649.00
(a+b+c)
d) Formwork @ 3.5 per cent of cost of concrete i.e. cost 15324.01
of material, labour and machinery
e) Overhead charges @ 14.615% on (a+b+c+d) 66228.31
f) Contractor's profit @ 10% on (a+b+c+d+e) 51938.13
cost of 120 cum = a+b+c+d+e+f 571319.46
Rate per cum (a+b+c+d+e+f )/120 4761.00
say 4761.00
g) seigniorage charges per cum
Coarse Sand 0.45 50.00 22.50
Aggregate 0.90 75.00 67.50
Add District Mineral Fund (DMF) 30% on Seinorage 0.300 90.00 27.00
charges
Rate per cum say 117.00
Add lead charges of metal 25.00 Km 0.90 504.25 453.83
Add lead charges of sand 41.00 Km 0.45 805.54 362.49
Add lead charges of Manufactured Sand 25.00 Km 0.00 566.50 0.00
816.32
TOTAL Rate Total 5694.00
12.8 H RCC Grade M35
12.8 H Case II Using Batching Plant, Transit Mixer and Concrete Pump

Unit ; cum
Taking Output = 120 cum
a) Material
Cement tonne 50.64 3900.00 197496.00
Coarse sand cum 54.00 182.00 9828.00
20 mm Aggregate cum 64.80 1303.00 84434.40
10 mm Aggregate cum 43.20 894.00 38620.80
Admixture Kg 202.56 43.00 8710.08
b) Labour
Mate day 0.84 451.00 378.84
Mason day 3.00 455.00 1365.00
Mazdoor day 18.00 400.00 7200.00
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1343.30 8059.80
Generator 100 KVA hour 6.00 1316.30 7897.80
Loader1 cum capacity hour 6.00 1594.70 9568.20

SOR 2018-19 (15% OH) BRIDGES - FOUNDATIONS

RA - 119
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 2071.70 31075.50
Transit Mixer 4 cum capacity lead beyond 1 Km, L - tonne.km 300L 13.18 31634.26
lead in Kilometer
Concrete Pump hour 6.00 1508.80 9052.80
Per Cum Basic Cost of Labour, Material & Machinery 3712.00
(a+b+c)
d) Formwork @ 3 per cent on cost of concrete i.e. cost 13359.64
of material, labour and machinery
e) Overhead charges @ 14.615% on (a+b+c+d) 67036.25
f) Contractor's profit @ 10% on (a+b+c+d+e) 52571.74
cost of 120 cum = a+b+c+d+e+f 578289.10
Rate per cum = (a+b+c+d+e+f)/120 4819.08
say 4819.00
g) seigniorage charges per cum
Coarse Sand 0.45 50.00 22.50
Aggregate 0.90 75.00 67.50
Add District Mineral Fund (DMF) 30% on Seinorage 0.300 90.00 27.00
charges
Rate per cum say 117.00
Add lead charges of metal 25.00 Km 0.90 504.25 453.83
Add lead charges of sand 41.00 Km 0.45 805.54 362.49
Add lead charges of Manufactured Sand 25.00 Km 0.00 566.50 0.00
816.32
TOTAL Rate Total 5752.00
Note: Where ever concrete is carried out using batching plant,
transit mixer, concrete pump, Admixtures @ 0.4 per cent of
weight of cement may be added for achieving desired slump
of concrete.
12.22 1200 & Providing Steel Liner 10 mm thick for Curbs and 6 mm
1900 thick for Steining of Wells including Fabricating and
Setting out as per Detailed Drawing.

Unit = 1 MT
Taking output = 1 MT
a) Material
i) Structural steel including 5 per cent wastage tonne 1.05 42000 44100.00
b) Labour
Mate day 1.24 451.00 559.24
Fitter day 6.00 520.00 3120.00
Blacksmith day 5.00 440.00 2200.00
Welder day 5.00 482.20 2411.00
Mazdoor day 10.00 400.00 4000.00
Electrodes, cutting gas and other consumables @ 5 2205.00
per cent on cost a (a) above.
c) Overhead charges @ 14.615% on (a+b) 8563.69
d) Contractor's profit @ 10% on (a+b+c) 6715.89
Rate for per MT (a+b+c+d) 73874.83
Total 73875.00
12.25 1100 & Bored cast-in-situ M35 grade R.C.C. Pile excluding
1700 Reinforcement complete as per Drawing and Technical
Specifications and removal of excavated earth with all
lifts and lead upto 1000 m.
Pile diameter-1200 mm
Unit = meter
Taking output = 9 m
a) Materials
PCC Grade M35 cum 10.17 5738.00 58355.46

Rate for concrete may be adopted same as for bottom plug


vide item no. 12.11( C ) (IV)
Concrete to be cast with a tremie pipe 200mm dia.
b) Machinery( for boring and construction )

SOR 2018-19 (15% OH) BRIDGES - FOUNDATIONS

RA - 120
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Hire and running charges of hydraulic piling rig with hour 6.00 6131.70 36790.20
power unit and complete accessories including shifting
from one bore location to another.
Hire and running charges of light crane for lowering hour 0.50 429.60 214.80
reinforcement cage
Hire and running charges of Bentonite pump hour 6.00 Rate included
in piling rig
Loader I cum bucket capacity. hour 0.50 1594.70 797.35
Tipper 5.5 cum capacity for disposal of muck from pile hour 0.50 950.30 475.15
bore hole
Bentonite kg 385.00 7.00 2695.00
c) Labour
Mate/Supervisor day 0.18 451.00 81.18
Mazdoor day 4.50 400.00 1800.00
d) Overhead charges @ 14.615% on (b+c) 6263.07
e) Contractor's profit @ 10% on (b+c+d) 4911.67
Cost for 9 m = a+b+c+d+d+e 112383.88
Rate per metre (a+b+c+d+e)/9 12487.10
Total 12487.00
12.40 1600 Supplying, Fitting and Placing un-coated HYSD bar
Reinforcement in Foundation complete as per Drawing
and Technical Specifications.
Unit = 1 MT
Taking output = 1 MT
a) Material
HYSD bars including5 per cent overlaps and wastage tonne 1.05 42500 44625.00

Binding wire Kg 6.00 53.00 318.00


b) Labour for cutting, bending, shifting to site, tying
and placing in position
Mate day 0.40 451.00 180.40
Blacksmith day 2.00 482.20 964.40
Mazdoor day 6.00 400.00 2400.00
c) Overhead charges @ 14.615% on (a+b) 7086.49
d) Contractor's profit @ 10% on (a+b+c) 5557.43
Rate for per MT (a+b+c+d) 61131.72
Total 61132.00
12.41 1600 Supplying, fitting and placing un-coated Mild steel
reinforcement complete in foundation as per drawing
and technical specification
Unit = 1 MT
Taking output = 1 MT
a) Material
MS bars including 5 per cent overlaps and wastage tonne 1.05 39674.00 41657.70

Binding wire Kg 6.00 53.00 318.00


b) Labour for straightening, cutting, bending, shifting
to site, tying and placing in position
Mate day 0.43 451.00 193.93
Blacksmith day 2.25 482.20 1084.95
Mazdoor day 6.50 400.00 2600.00
c) Overhead charges @ 14.615% on (a+b) 6701.65
d) Contractor's profit @ 10% on (a+b+c) 5255.62
Rate for per MT (a+b+c+d) 57811.85
Total 57812.00

SOR 2018-19 (15% OH) BRIDGES - FOUNDATIONS

RA - 121
CHAPTER-13
SUB-STRUCTURE
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
13.5 1500, Plain/Reinforced cement concrete in sub-structure
1700 & complete as per drawing and Technical Specifications
2200
Unit = cum
Taking output = 1 cum
13.5 E RCC Grade M20
(p) Height upto 5m
Same as Item 12.8 (C) upto 5 m height, except for formwork
which shall be 10 per cent instead of 4 per cent of cost of
material, labour and machinery.
Case Using concrete Mixer
I
Per Cum Basic Cost of Labour, Material & Machinery 3690.00
(a+b+c) of Item 12.8 (C) Case I
d) formwork
Add 10 per cent of cost of material, labour and 10.00 369.00
machinery (a+b+c) for Formwork
e) Overhead charges @ 14.615% on (a+b+c+d) 593.22
f) Contractor's profit @ 10% on (a+b+c+d+e) 465.22
Rate perm (a+b+c+d+e+f) 5117.45
say 5117
g) seinarage charges per cum
Coarse Sand 0.45 50.00 22.50
Aggregate 0.90 75.00 67.50
Add District Mineral Fund (DMF) 30% on Seinorage 0.300 90.00 27.00
charges
Rate per cum say 117.00
Add lead charges of metal 25.00 Km 0.90 504.25 453.83
Add lead charges of sand 41.00 Km 0.45 805.54 362.49
Add lead charges of Manufactured Sand 25.00 Km 0.00 566.50 0.00
TOTAL Rate Total 6051.00
13.5 E (p) Case With Batching Plant, Transit Mixer and Concrete Pump
II
Per Cum Basic Cost of Labour, Material & Machinery 3347.00
(a+b+c) of Item 12.8 (C) Case II
d) formwork
Add 10 per cent of cost of material, labour and 10.00 334.70
machinery (a+b+c) for Formwork
e) Overhead charges @ 14.615% on (a+b+c+d) 538.08
f) Contractor's profit @ 10% on (a+b+c+d+e) 421.98
Rate perm (a+b+c+d+e+f) 4641.76
say 4642
g) seinarage charges per cum
Coarse Sand 0.45 50.00 22.50
Aggregate 0.90 75.00 67.50
Add District Mineral Fund (DMF) 30% on Seinorage 0.300 90.00 27.00
charges
Rate per cum say 117.00
Add lead charges of metal 25.00 Km 0.90 504.25 453.83
Add lead charges of sand 41.00 Km 0.45 805.54 362.49
Add lead charges of Manufactured Sand 25.00 Km 0.00 566.50 0.00
TOTAL Rate Total 5575.00
13.5 E (q) Height 5m to 10m
For height, upto 10m, add 2 per cent of cost as above
excluding formwork. For cost of formwork add 12 per cent of
cost of material, labour and machinery instead of 4 per cent .

Case Using concrete Mixer


I
Per Cum Basic Cost of Labour, Material & Machinery 3690.00
(a+b+c) of Item 12.8 (C) Case I

SOR 2018-19 (15% OH) BRIDGES - SUB STRUCTURE

RA - 122
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
d) formwork
Add 12 per cent of cost of material, labour and 12.00 442.80
machinery (a+b+c) for Formwork
Add 2 per cent of cost of material, Labour and 2.00 73.80
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 14.615% on (a+b+c+d) 614.79
f) Contractor's profit @ 10% on (a+b+c+d+e) 482.14
Rate perm (a+b+c+d+e+f) 5303.53
say 5304
g) seinarage charges per cum
Coarse Sand 0.45 50.00 22.50
Aggregate 0.90 75.00 67.50
Add District Mineral Fund (DMF) 30% on Seinorage 0.300 90.00 27.00
charges
Rate per cum say 117.00
Add lead charges of metal 25.00 Km 0.90 504.25 453.83
Add lead charges of sand 41.00 Km 0.45 805.54 362.49
Add lead charges of Manufactured Sand 25.00 Km 0.00 566.50 0.00
TOTAL Rate Total 6237.00
13.5 E (q) Case With Batching Plant, Transit Mixer and Concrete Pump
II
Per Cum Basic Cost of Labour, Material & Machinery 3347.00
(a+b+c) of Item 12.8 (C) Case II
d) formwork
Add 12 per cent of cost of material, labour and 12.00 401.64
machinery (a+b+c) for Formwork
Add 2 per cent of cost of material, Labour and 2.00 66.94
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 14.615% on (a+b+c+d) 557.65
f) Contractor's profit @ 10% on (a+b+c+d+e) 437.32
Rate perm (a+b+c+d+e+f) 4810.55
say 4811
g) seinarage charges per cum
Coarse Sand 0.45 50.00 22.50
Aggregate 0.90 75.00 67.50
Add District Mineral Fund (DMF) 30% on Seinorage 0.300 90.00 27.00
charges
Rate per cum say 117.00
Add lead charges of metal 25.00 Km 0.90 504.25 453.83
Add lead charges of sand 41.00 Km 0.45 805.54 362.49
Add lead charges of Manufactured Sand 25.00 Km 0.00 566.50 0.00
TOTAL Rate Total 5744.00
13.5 E (r) Height above 10m
Same as Item 12.8 (C) with the following changes: (i) Add 4
per cent of cost of material, labour and machinery excluding
form work to cater for extra lift. (ii) The provision of form work
shall be 15 per cent instead of 4 per cent of cost of material,

Case Using concrete Mixer


I
Per Cum Basic Cost of Labour, Material & Machinery 3690.00
(a+b+c) of Item 12.8 (C) Case I
d) formwork
Add 15 per cent of cost of material, labour and 15.00 553.50
machinery (a+b+c) for Formwork
Add 4 per cent of cost of material, Labour and 4.00 147.60
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 14.615% on (a+b+c+d) 641.76
f) Contractor's profit @ 10% on (a+b+c+d+e) 503.29
Rate perm (a+b+c+d+e+f) 5536.15
say 5536
g) seinarage charges per cum
Coarse Sand 0.45 50.00 22.50

SOR 2018-19 (15% OH) BRIDGES - SUB STRUCTURE

RA - 123
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Aggregate 0.90 75.00 67.50
Add District Mineral Fund (DMF) 30% on Seinorage 0.300 90.00 27.00
charges
Rate per cum say 117.00
Add lead charges of metal 25.00 Km 0.90 504.25 453.83
Add lead charges of sand 41.00 Km 0.45 805.54 362.49
Add lead charges of Manufactured Sand 25.00 Km 0.00 566.50 0.00
TOTAL Rate Total 6469.00
13.5 E (r) Case With Batching Plant, Transit Mixer and Concrete Pump
II
Per Cum Basic Cost of Labour, Material & Machinery 3347.00
(a+b+c) of Item 12.8 (C) Case II
d) formwork
Add 15 per cent of cost of material, labour and 15.00 502.05
machinery (a+b+c) for Formwork
Add 4 per cent of cost of material, Labour and 4.00 133.88
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 14.615% on (a+b+c+d) 582.11
f) Contractor's profit @ 10% on (a+b+c+d+e) 456.50
Rate perm (a+b+c+d+e+f) 5021.54
say 5022
g) seinarage charges per cum
Coarse Sand 0.45 50.00 22.50
Aggregate 0.90 75.00 67.50
Add District Mineral Fund (DMF) 30% on Seinorage 0.300 90.00 27.00
charges
Rate per cum say 117.00
Add lead charges of metal 25.00 Km 0.90 504.25 453.83
Add lead charges of sand 41.00 Km 0.45 805.54 362.49
Add lead charges of Manufactured Sand 25.00 Km 0.00 566.50 0.00
TOTAL Rate Total 5955.00
13.5 G RCC Grade M30
(p) Height upto 5m
Same as Item 12.8 (G) upto 5m height, excluding formwork.
For cost of formwork, add 10 per cent of cost of material,
labour and machinery instead of 3.5 per cent .

Case Using concrete Mixer


I
Per Cum Basic Cost of Labour, Material & Machinery 3922.00
(a+b+c) of Item 12.8 (G) Case I
d) formwork
Add 10 per cent of cost of material, labour and 10.00 392.20
machinery (a+b+c) for Formwork
e) Overhead charges @ 14.615% on (a+b+c+d) 630.52
f) Contractor's profit @ 10% on (a+b+c+d+e) 494.47
Rate perm (a+b+c+d+e+f) 5439.19
say 5439
g) seinarage charges per cum
Coarse Sand 0.45 50.00 22.50
Aggregate 0.90 75.00 67.50
Add District Mineral Fund (DMF) 30% on Seinorage 0.300 90.00 27.00
charges
Rate per cum say 117.00
Add lead charges of metal 25.00 Km 0.90 504.25 453.83
Add lead charges of sand 41.00 Km 0.45 805.54 362.49
Add lead charges of Manufactured Sand 25.00 Km 0.00 566.50 0.00
TOTAL Rate Total 6373.00
13.5 G (p) Case With Batching Plant, Transit Mixer and Concrete Pump
II
Per Cum Basic Cost of Labour, Material & Machinery 3649.00
(a+b+c) of Item 12.8 (G) Case II
d) formwork

SOR 2018-19 (15% OH) BRIDGES - SUB STRUCTURE

RA - 124
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Add 10 per cent of cost of material, labour and 10.00 364.90
machinery (a+b+c) for Formwork
e) Overhead charges @ 14.615% on (a+b+c+d) 586.63
f) Contractor's profit @ 10% on (a+b+c+d+e) 460.05
Rate perm (a+b+c+d+e+f) 5060.58
say 5061
g) seinarage charges per cum
Coarse Sand 0.45 50.00 22.50
Aggregate 0.90 75.00 67.50
Add District Mineral Fund (DMF) 30% on Seinorage 0.300 90.00 27.00
charges
Rate per cum say 117.00
Add lead charges of metal 25.00 Km 0.90 504.25 453.83
Add lead charges of sand 41.00 Km 0.45 805.54 362.49
Add lead charges of Manufactured Sand 25.00 Km 0.00 566.50 0.00
TOTAL Rate Total 5994.00
13.5 G (q) Height 5m to 10m
For height, upto 10m, add 1.6 per cent of cost as above
excluding formwork. For cost of formwork add 11.5 per cent
of cost of material, labour and machinery
Case Using concrete Mixer
I
Per Cum Basic Cost of Labour, Material & Machinery 3922.00
(a+b+c) of Item 12.8 (G) Case I
d) formwork
Add 11.5 per cent of cost of material, labour and 11.50 451.03
machinery (a+b+c) for Formwork
Add 1.6 per cent of cost of material, Labour and 1.60 62.75
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 14.615% on (a+b+c+d) 648.29
f) Contractor's profit @ 10% on (a+b+c+d+e) 508.41
Rate perm (a+b+c+d+e+f) 5592.48
say 5592
g) seinarage charges per cum
Coarse Sand 0.45 50.00 22.50
Aggregate 0.90 75.00 67.50
Add District Mineral Fund (DMF) 30% on Seinorage 0.300 90.00 27.00
charges
Rate per cum say 117.00
Add lead charges of metal 25.00 Km 0.90 504.25 453.83
Add lead charges of sand 41.00 Km 0.45 805.54 362.49
Add lead charges of Manufactured Sand 25.00 Km 0.00 566.50 0.00
TOTAL Rate Total 6526.00
13.5 G (q) Case With Batching Plant, Transit Mixer and Concrete Pump
II
Per Cum Basic Cost of Labour, Material & Machinery 3649.00
(a+b+c) of Item 12.8 (G) Case II
d) formwork
Add 11.5 per cent of cost of material, labour and 11.50 419.64
machinery (a+b+c) for Formwork
Add 1.6 per cent of cost of material, Labour and 1.60 58.38
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 14.615% on (a+b+c+d) 603.16
f) Contractor's profit @ 10% on (a+b+c+d+e) 473.02
Rate perm (a+b+c+d+e+f) 5203.20
say 5203
g) seinarage charges per cum
Coarse Sand 0.45 50.00 22.50
Aggregate 0.90 75.00 67.50
Add District Mineral Fund (DMF) 30% on Seinorage 0.300 90.00 27.00
charges
Rate per cum say 117.00
Add lead charges of metal 25.00 Km 0.90 504.25 453.83

SOR 2018-19 (15% OH) BRIDGES - SUB STRUCTURE

RA - 125
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Add lead charges of sand 41.00 Km 0.45 805.54 362.49
Add lead charges of Manufactured Sand 25.00 Km 0.00 566.50 0.00
TOTAL Rate Total 6137.00
13.5 G (r) Height above 10m
For height, above 10m, add 3.5 per cent of cost as above
excluding formwork. For cost of formwork add 14 per cent of
cost of material, labour and machinery
Case Using concrete Mixer
I
Per Cum Basic Cost of Labour, Material & Machinery 3922.00
(a+b+c) of Item 12.8 (G) Case I
d) formwork
Add 14 per cent of cost of material, labour and 14.00 549.08
machinery (a+b+c) for Formwork
Add 3.5 per cent of cost of material, Labour and 3.50 137.27
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 14.615% on (a+b+c+d) 673.51
f) Contractor's profit @ 10% on (a+b+c+d+e) 528.19
Rate perm (a+b+c+d+e+f) 5810.05
say 5810
g) seinarage charges per cum
Coarse Sand 0.45 50.00 22.50
Aggregate 0.90 75.00 67.50
Add District Mineral Fund (DMF) 30% on Seinorage 0.300 90.00 27.00
charges
Rate per cum say 117.00
Add lead charges of metal 25.00 Km 0.90 504.25 453.83
Add lead charges of sand 41.00 Km 0.45 805.54 362.49
Add lead charges of Manufactured Sand 25.00 Km 0.00 566.50 0.00
TOTAL Rate Total 6743.00
13.5 G (r) Case With Batching Plant, Transit Mixer and Concrete Pump
II
Per Cum Basic Cost of Labour, Material & Machinery 3649.00
(a+b+c) of Item 12.8 (G) Case II
d) formwork
Add 14 per cent of cost of material, labour and 14.00 510.86
machinery (a+b+c) for Formwork
Add 3.5 per cent of cost of material, Labour and 3.50 127.72
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 14.615% on (a+b+c+d) 626.63
f) Contractor's profit @ 10% on (a+b+c+d+e) 491.42
Rate perm (a+b+c+d+e+f) 5405.62
say 5406
g) seinarage charges per cum
Coarse Sand 0.45 50.00 22.50
Aggregate 0.90 75.00 67.50
Add District Mineral Fund (DMF) 30% on Seinorage 0.300 90.00 27.00
charges
Rate per cum say 117.00
Add lead charges of metal 25.00 Km 0.90 504.25 453.83
Add lead charges of sand 41.00 Km 0.45 805.54 362.49
Add lead charges of Manufactured Sand 25.00 Km 0.00 566.50 0.00
TOTAL Rate Total 6339.00
13.5 H RCC Grade M35
(p) Height upto 5m
Same as Item 12.8 (H) upto 5m height, excluding formwork.
For cost of formwork, add 10 per cent of cost of material,
labour and machinery instead of 3 per cent .
Case Using concrete Mixer
I
Per Cum Basic Cost of Labour, Material & Machinery 3981.00
(a+b+c) of Item 12.8 (H) Case I
d) formwork

SOR 2018-19 (15% OH) BRIDGES - SUB STRUCTURE

RA - 126
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Add 10 per cent of cost of material, labour and 10.00 398.10
machinery (a+b+c) for Formwork
e) Overhead charges @ 14.615% on (a+b+c+d) 640.01
f) Contractor's profit @ 10% on (a+b+c+d+e) 501.91
Rate perm (a+b+c+d+e+f) 5521.02
say 5521
g) seinarage charges per cum
Coarse Sand 0.45 50.00 22.50
Aggregate 0.90 75.00 67.50
Add District Mineral Fund (DMF) 30% on Seinorage 0.300 90.00 27.00
charges
Rate per cum say 117.00
Add lead charges of metal 25.00 Km 0.90 504.25 453.83
Add lead charges of sand 41.00 Km 0.45 805.54 362.49
Add lead charges of Manufactured Sand 25.00 Km 0.00 566.50 0.00
TOTAL Rate Total 6454.00
13.5 H (p) Case With Batching Plant, Transit Mixer and Concrete Pump
II
Per Cum Basic Cost of Labour, Material & Machinery 3712.00
(a+b+c) of Item 12.8 (H) Case II
d) formwork
Add 10 per cent of cost of material, labour and 10.00 371.20
machinery (a+b+c) for Formwork
e) Overhead charges @ 14.615% on (a+b+c+d) 596.76
f) Contractor's profit @ 10% on (a+b+c+d+e) 468.00
Rate perm (a+b+c+d+e+f) 5147.96
say 5148
g) seinarage charges per cum
Coarse Sand 0.45 50.00 22.50
Aggregate 0.90 75.00 67.50
Add District Mineral Fund (DMF) 30% on Seinorage 0.300 90.00 27.00
charges
Rate per cum say 117.00
Add lead charges of metal 25.00 Km 0.90 504.25 453.83
Add lead charges of sand 41.00 Km 0.45 805.54 362.49
Add lead charges of Manufactured Sand 25.00 Km 0.00 566.50 0.00
TOTAL Rate Total 6081.00
13.5 H (q) Height 5m to 10m
For height, upto 10m, add 1.4 per cent of cost as above
excluding formwork. For cost of formwork add 11 per cent of
cost of material, labour and machinery .
Case Using concrete Mixer
I
Per Cum Basic Cost of Labour, Material & Machinery 3981.00
(a+b+c) of Item 12.8 (H) Case I
d) formwork
Add 11 per cent of cost of material, labour and 11.00 437.91
machinery (a+b+c) for Formwork
Add 1.4 per cent of cost of material, Labour and 1.40 55.73
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 14.615% on (a+b+c+d) 653.97
f) Contractor's profit @ 10% on (a+b+c+d+e) 512.86
Rate perm (a+b+c+d+e+f) 5641.47
say 5641
g) seinarage charges per cum
Coarse Sand 0.45 50.00 22.50
Aggregate 0.90 75.00 67.50
Add District Mineral Fund (DMF) 30% on Seinorage 0.300 90.00 27.00
charges
Rate per cum say 117.00
Add lead charges of metal 25.00 Km 0.90 504.25 453.83
Add lead charges of sand 41.00 Km 0.45 805.54 362.49
Add lead charges of Manufactured Sand 25.00 Km 0.00 566.50 0.00

SOR 2018-19 (15% OH) BRIDGES - SUB STRUCTURE

RA - 127
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
TOTAL Rate Total 6575.00
13.5 H (q) Case With Batching Plant, Transit Mixer and Concrete Pump
II
Per Cum Basic Cost of Labour, Material & Machinery 3712.00
(a+b+c) of Item 12.8 (H) Case II
d) formwork
Add 11 per cent of cost of material, labour and 11.00 408.32
machinery (a+b+c) for Formwork
Add 1.4 per cent of cost of material, Labour and 1.40 51.97
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 14.615% on (a+b+c+d) 609.78
f) Contractor's profit @ 10% on (a+b+c+d+e) 478.21
Rate perm (a+b+c+d+e+f) 5260.27
say 5260
g) seinarage charges per cum
Coarse Sand 0.45 50.00 22.50
Aggregate 0.90 75.00 67.50
Add District Mineral Fund (DMF) 30% on Seinorage 0.300 90.00 27.00
charges
Rate per cum say 117.00
Add lead charges of metal 25.00 Km 0.90 504.25 453.83
Add lead charges of sand 41.00 Km 0.45 805.54 362.49
Add lead charges of Manufactured Sand 25.00 Km 0.00 566.50 0.00
TOTAL Rate Total 6194.00
13.5 H (r) Height above 10m
For height, above 10m, add 3 per cent of cost as above
excluding formwork. For cost of formwork add 13 per cent of
cost of material, labour and machinery
Case Using concrete Mixer
I
Per Cum Basic Cost of Labour, Material & Machinery 3981.00
(a+b+c) of Item 12.8 (H) Case I
d) formwork
Add 13 per cent of cost of material, labour and 13.00 517.53
machinery (a+b+c) for Formwork
Add 3 per cent of cost of material, Labour and 3.00 119.43
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 14.615% on (a+b+c+d) 674.91
f) Contractor's profit @ 10% on (a+b+c+d+e) 529.29
Rate perm (a+b+c+d+e+f) 5822.16
say 5822
g) seinarage charges per cum
Coarse Sand 0.45 50.00 22.50
Aggregate 0.90 75.00 67.50
Add District Mineral Fund (DMF) 30% on Seinorage 0.300 90.00 27.00
charges
Rate per cum say 117.00
Add lead charges of metal 25.00 Km 0.90 504.25 453.83
Add lead charges of sand 41.00 Km 0.45 805.54 362.49
Add lead charges of Manufactured Sand 25.00 Km 0.00 566.50 0.00
TOTAL Rate Total 6755.00
13.5 H (r) Case With Batching Plant, Transit Mixer and Concrete Pump
II
Per Cum Basic Cost of Labour, Material & Machinery 3712.00
(a+b+c) of Item 12.8 (H) Case II
d) formwork
Add 13 per cent of cost of material, labour and 13.00 482.56
machinery (a+b+c) for Formwork
Add 3 per cent of cost of material, Labour and 3.00 111.36
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 14.615% on (a+b+c+d) 629.31
f) Contractor's profit @ 10% on (a+b+c+d+e) 493.52
Rate perm (a+b+c+d+e+f) 5428.75

SOR 2018-19 (15% OH) BRIDGES - SUB STRUCTURE

RA - 128
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
say 5429
g) seinarage charges per cum
Coarse Sand 0.45 50.00 22.50
Aggregate 0.90 75.00 67.50
Add District Mineral Fund (DMF) 30% on Seinorage 0.300 90.00 27.00
charges
Rate per cum say 117.00
Add lead charges of metal 25.00 Km 0.90 504.25 453.83
Add lead charges of sand 41.00 Km 0.45 805.54 362.49
Add lead charges of Manufactured Sand 25.00 Km 0.00 566.50 0.00
TOTAL Rate Total 6362.00
Note The basic components of this analysis are the same as those
of items 13.8 (A to H). The only changes are as under:

a) Ramps/Stairs: Extra expenditure on structures which are


more than 5 m high @ 2 per cent of cost for height upto 10 m
and 4 per cent for heights above 10 m will be involved for
approaching the work spot by providing higher ramp/stair case
for use
b) The above mentioned percentages have been suitably
modified for different categories as cost for various categories
varies, whereas effort for access for same height will be
similar. As the cost of richer concrete is comparatively more,
the percent
13.6 1600 & Supplying, fitting and placing HYSD bar reinforcement in
2200 sub-structure complete as per drawing and Technical
Specifications
Output: MT
Taking output = 1 MT
a) Material
HYSD bars including 5 per cent overlaps and wastage tonne 1.05 42500 44625

Binding wire kg 6.00 53.00 318.00


b) Labour for cutting, bending, shifting to site, tying
and placing in position
Mate day 0.34 451.00 153.34
Blacksmith day 2.00 482.20 964.40
Mazdoor day 6.50 400.00 2600.00
c) Overhead charges @ 14.615% on (a+b) 7111.77
d) Contractor's profit @ 10% on (a+b+c) 5577.25
Rate for per MT (a+b+c+d) 61349.76
Total 61350
13.7 1600 & Supplying, fitting and placing Mild steel reinforcement
2200 complete in sub-structure as per drawing and Technical
Specification
Unit = MT
Taking output = 1 MT
a) Material
MS bars including 5 per cent overlaps and wastage tonne 1.05 39674 41657.70
Binding wire kg 6.00 53.00 318.00
b) Labour for straightening, cutting, bending, shifting
to site, tying and placing in position
Mate day 0.28 451.00 126.28
Blacksmith day 1.50 482.20 723.30
Mazdoor day 5.50 400.00 2200.00
c) Overhead charges @ 14.615% on (a+b) 6580.44
d) Contractor's profit @ 10% on (a+b+c) 5160.57
Rate for per MT (a+b+c+d) 56766.30
Total 56766

SOR 2018-19 (15% OH) BRIDGES - SUB STRUCTURE

RA - 129
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
13.8 2706 & Providing weep holes in Brick masonry/Plain/ Reinforced
2200 concrete abutment, wing wall/ return wall with 100 mm
dia AC pipe, extending through the full width of the
structure with slope of 1V :20H towards drawing foce.
Complete as per drawing and Technical

Unit = Nos.
Taking output = 30 Nos.
a) Material
AC pipe 100 mm dia. (including wastage @ 5 per cent ) metre 31.50 253.00 7969.50

Average length of weep hole is taken as one metre for the


purpose of estimating.
MS clamp each. 30.00 0.00 0.00
collar for AC pipe (average) taking 10% of above pipe each. 10.00 25.30 253.00
rate
Cement mortar 1:3 (Rate as in Item 12.6) cum 0.05 3472.00 173.60

b) Labour
Mate day 0.03 451.00 13.53
Mason day 0.50 455.00 227.50
Mazdoor day 0.25 400.00 100.00
c) Overhead charges @ 14.615% on (a+b) 1276.93
d) Contractor's profit @ 10% on (a+b+c) 1001.41
Cost for 30 m = a+b+c+d 11015.47
Rate per m (a+b+c+d)/30 367.18
Total 367
Note 1. In case of stone masonry, the size of the weep hole shall be
150 mm x 80 mm or circular with 150 mm diameter.

2. For structure in stone masonry, the weep holes shall be


deemed to be included in the item of stone masonry work and
shall not be paid separately.
13.9 710.1.4.of Back filling behind abutment, wing wall and return wall
IRC:78 & complete as per drawing and Technical Specification
2200
Unit = cum
Taking output = 10 cum
A Granular material
a) Labour
Mate day 0.28 451.00 126.28
Mazdoor day 7.00 400.00 2800.00
b) Material
Granular material cum 12.00 110.00 1320.00
c) Machinery
Plate compactor/power rammer hour 2.50 59.10 147.75
Water Tanker hour 0.05 655.20 32.76
d) Overhead charges @ 14.615% on (a+b+c) 646.98
e) Contractor's profit @ 10% on (a+b+c+d) 507.38
Cost for 10 cum of granular backfill = a+b+c+d+e 5581.14
Rate per cum = (a+b+c+d+e)/10 558.11
say 558
g) seinarage charges per cum
Granular material cum 1.20 30.00 36.00
Add District Mineral Fund (DMF) 30% on Seinorage 0.300 36.00 10.80
charges
Rate per cum say 46.80
Add Lead charges of gravel 5.00 Km 1.20 267.70 321.24
TOTAL Rate Total 915.00

SOR 2018-19 (15% OH) BRIDGES - SUB STRUCTURE

RA - 130
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
13.10 710.1.4.of Providing and laying of Filter media with granular
IRC:78 materials/stone crushed aggregates satisfying the
and 2200 requirements laid down in clause 2504.2.2. of MoRTH
specifications to a thickness of not less than 600 mm with
smaller size towards the soil and bigger si

Unit = cum
Taking output = 10 cum.
a) Labour
Mate day 0.32 451.00 144.32
Mazdoor for filling, watering, ramming etc. day 7.00 400.00 2800.00
Mazdoor (Skilled) day 1.00 515.00 515.00
b) Material
Filter media of stone aggregate conforming to clause cum 12.00 597.90 7174.80
2504.2.2. of MoRTH specifications.
c) Machinery
Water Tanker of 6 KL capacity hour 0.06 655.20 39.31
d) Overhead charges @ 14.615% on (a+b+c) 1559.92
e) Contractor's profit @ 10% on (a+b+c+d) 1223.34
cost for 10 cum of Fiter Media = a+b+c+d+e 13456.69
Rate per cum = (a+b+c+d+e)/10 1345.67
say 1346
Add seignorage charges of metal cum 1.20 75.00 90.00
Add District Mineral Fund (DMF) 30% on Seinorage 0.300 90.00 27.00
charges
Add lead charges of metal 25.00 Km 1.20 504.25 605.10
TOTAL Rate Total 2068.00
13.13 2000 & Supplying, fitting and fixing in position true to line and
2200 level sliding plate bearing with PTFE surface sliding on
stainless steel complete including all accessories as per
drawing and Technical Specifications and BS: 5400,
section 9.1 & 9.2 (for PTFE) and clause 2004 of MoRTH
Specifications.
Unit: one tonne capacity
Considering a 80 tonne capacity bearing for this analysis
a) Labour
Mate day 0.06 451.00 27.06
Mazdoor day 1.00 400.00 400.00
Mazdoor (Skilled) day 0.50 515.00 257.50
b) Material
PTFE sliding plate bearing assembly of 80 tonnes design
load capacity duly painted complete with all its
each. 1.00 15430.00 15430.00
components as per drawing and Technical Specifications

Add 1 per cent for foundation anchorage bolts and


154.30
consumables.
c) Overhead charges @ 14.615% on (a+b) 2377.69
d) Contractor's profit @ 10% on (a+b+c) 1864.66
cost for 80 tonnes capacity bearing = a+b+c+d 20511.21
Rate per tonne capacity = (a+b+c+d)/80 256.39
say 256.00
13.14 2000 & Supplying, fitting and fixing in position true to line and
2200 level elastomeric bearing conforming to IRC: 83 (Part-II)
section IX and clause 2005 of MoRTH specifications
complete including all accessories as per drawing and
Technical Specifications.
Unit: one cubic centimetre
Considering an elastomeric bearing of size 500 x 400 x 96 mm
for this analysis.
Overall volume - 19200 cu.cm
Volume of 6 nos. 488 x 388 x 4 mm size reinforcing steel
plates = 4545 cu.cm.

SOR 2018-19 (15% OH) BRIDGES - SUB STRUCTURE

RA - 131
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Hence volume of elastometer = 14655 cu.cm.
a) Labour
Mate day 0.06 451.00 27.06
Mazdoor day 1.00 400.00 400.00
Mazdoor (Skilled) day 0.50 515.00 257.50
b) Material
Elastomeric bearing assembly consisting of 7 layers of each. 1.00 15310.00 15310.00
elastomer bonded to 6 nos. internal reinforcing steel
laminates by the process of vulcanisation, complete with
all components as per drawing and Technical
Specifications.
Add 1 per cent of cost of bearing assembly for 153.10
foundation anchorage bolts and consumables.
c) Overhead charges @ 14.615% on (a+b) 2359.98
d) Contractor's profit @ 10% on (a+b+c) 1850.76
cost for 19200cc of elastomeric bearing = a+b+c+d 20358.40
Rate per cc of elastomeric bearing = (a+b+c+d)/19200 1.06

Total 1

SOR 2018-19 (15% OH) BRIDGES - SUB STRUCTURE

RA - 132
CHAPTER-14
SUPER-STRUCTURE
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
14.1 1500 Furnishing and Placing Reinforced/ Prestressed cement
&1600 concrete in super-structure as per drawing and
1700 Technical Specification
14.1 C RCC Grade M 30
14.1C Case II Using Batching Plant, Transit Mixer and Concrete
Pump.
Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 48.79 3900.00 190281.00
Coarse sand cum 54.60 182.00 9937.20
20 mm Aggregate cum 64.80 1303.00 84434.40
10 mm Aggregate cum 43.20 894.00 38620.80
b) Labour
Mate day 0.88 451.00 396.88
Mason day 3.00 455.00 1365.00
Mazdoor day 19.00 400.00 7600.00
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1343.30 8059.80
Generator 100 KVA hour 6.00 1316.30 7897.80
Loader hour 6.00 1594.70 9568.20
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity lead upto1 Km hour 15.00 2071.70 31075.50
Lead beyond 1 Km, L - lead in Kilometer tonne.km 300L 13.18 31634.26

Concrete Pump hour 6.00 1508.80 9052.80


Basic Cost of Labour, Material & Machinery (a+b+c) 429924.00
for 120 cum
For formwork and staging add the following:
14.1C (i) For solid slab super-structure, 20-30 per cent of
Case II (a+b+c)
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) for 429924.00
120 cum
d) Formwork and staging 20 per cent of (a+b+c) 20.00 85984.80

e) Overhead charges @ 14.615% on (a+b+c+d) 75400.07


f) Contractor's profit @ 10% on (a+b+c+d+e) 59130.89
Cost for 120 cum = a+b+c+d+e+f 650439.76
Rate per cum = (a+b+c+d+e+f)/120 5420.33
say 5420.00
g) seiniorage charges per cum
Coarse Sand cum 0.46 50.00 18.00
Aggregate cum 0.90 75.00 67.50
Add District Mineral Fund (DMF) 30% on Seinorage 0.300 85.50 25.65
charges
Rate per cum say 111.15
Add lead charges of metal 25.00 Km 0.90 504.25 453.83
Add lead charges of sand 41.00 Km 0.46 805.54 366.52
Add lead charges of Manufactured Sand 25.00 Km 0.00 566.50 0.00
820.35
Total 6352.00
14.1C (q) Height 5m to 10m
Case II
(i)
Basic Cost of Labour, Material & Machinery (a+b+c) for 429924.00
120 cum
d) Formwork and staging 25 per cent of (a+b+c) 25.00 107481.00

SOR 2018-19 (15% OH) BRIDGES - SUPER STRUCTURE

RA - 133
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
e) Overhead charges @ 14.615% on (a+b+c+d) 78541.74
f) Contractor's profit @ 10% on (a+b+c+d+e) 61594.67
Cost for 120 cum = a+b+c+d+e+f 677541.41
Rate per cum = (a+b+c+d+e+f)/120 5646.18
say 5646.00
g) seiniorage charges per cum 111.15
Rate per cum say 111.15

Add lead charges of metal 25.00 Km 0.90 504.25 453.83


Add lead charges of sand 41.00 Km 0.46 805.54 366.52
Add lead charges of Manufactured Sand 25.00 Km 0.00 566.50 0.00
820.35
Total 6578.00
14.1C (r) Height above 10m
Case II
(i)
Basic Cost of Labour, Material & Machinery (a+b+c) for 429924.00
120 cum
d) Formwork and staging 30 per cent of (a+b+c) 30.00 128977.20

e) Overhead charges @ 14.615% on (a+b+c+d) 81683.41


f) Contractor's profit @ 10% on (a+b+c+d+e) 64058.46
Cost for 120 cum = a+b+c+d+e+f 704643.07
Rate per cum = (a+b+c+d+e+f)/120 5872.03
say 5872.00
g) seiniorage charges per cum 111.15
Rate per cum say 111.15

Add lead charges of metal 25.00 Km 0.90 504.25 453.83


Add lead charges of sand 41.00 Km 0.46 805.54 366.52
Add lead charges of Manufactured Sand 25.00 Km 0.00 566.50 0.00
820.35
Total 6804.00
14.1C (ii) For T-beam & slab, 25-35 per cent of (a+b+c)
Case II
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) for 429924.00
120 cum
d) Formwork and staging 25 per cent of (a+b+c) 25.00 107481.00

e) Overhead charges @ 14.615% on (a+b+c+d) 78541.74


f) Contractor's profit @ 10% on (a+b+c+d+e) 61594.67
Cost for 120 cum = a+b+c+d+e+f 677541.41
Rate per cum = (a+b+c+d+e+f)/120 5646.18
say 5646.00
g) seiniorage charges per cum 111.15
Rate per cum say 111.15

Add lead charges of metal 25.00 Km 0.90 504.25 453.83


Add lead charges of sand 41.00 Km 0.46 805.54 366.52
Add lead charges of Manufactured Sand 25.00 Km 0.00 566.50 0.00
820.35
Total 6578.00
14.1C (q) Height 5m to 10m
Case II
(ii)
Basic Cost of Labour, Material & Machinery (a+b+c) for 429924.00
120 cum
d) Formwork and staging 30 per cent of (a+b+c) 30.00 128977.20

e) Overhead charges @ 14.615% on (a+b+c+d) 81683.41


f) Contractor's profit @ 10% on (a+b+c+d+e) 64058.46

SOR 2018-19 (15% OH) BRIDGES - SUPER STRUCTURE

RA - 134
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Cost for 120 cum = a+b+c+d+e+f 704643.07
Rate per cum = (a+b+c+d+e+f)/120 5872.03
say 5872.00
g) seiniorage charges per cum 111.15
Rate per cum say 111.15

Add lead charges of metal 25.00 Km 0.90 504.25 453.83


Add lead charges of sand 41.00 Km 0.46 805.54 366.52
Add lead charges of Manufactured Sand 25.00 Km 0.00 566.50 0.00
820.35
Total 6804.00
14.1C (r) Height above 10m
Case II
(ii)
Basic Cost of Labour, Material & Machinery (a+b+c) for 429924.00
120 cum
d) Formwork and staging 35 per cent of (a+b+c) 35.00 150473.40

e) Overhead charges @ 14.615% on (a+b+c+d) 84825.08


f) Contractor's profit @ 10% on (a+b+c+d+e) 66522.25
Cost for 120 cum = a+b+c+d+e+f 731744.73
Rate per cum = (a+b+c+d+e+f)/120 6097.87
say 6098.00
g) seiniorage charges per cum 111.15
Rate per cum say 111.15

Add lead charges of metal 25.00 Km 0.90 504.25 453.83


Add lead charges of sand 41.00 Km 0.46 805.54 366.52
Add lead charges of Manufactured Sand 25.00 Km 0.00 566.50 0.00
820.35
Total 7029.00
14.1 D RCC/PSC Grade M35
Case I Using Concrete Mixer.
Unit = 1 cum
Taking output = 15 cum
a) Material
Cement tonne 6.33 3900.00 24687.00
Coarse sand cum 6.75 182.00 1228.50
20 mm Aggregate cum 8.10 1303.00 10554.30
10 mm Aggregate cum 5.40 894.00 4827.60
b) Labour
Mate day 0.90 451.00 405.90
Mason day 1.50 455.00 682.50
Mazdoor day 21.00 400.00 8400.00
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 525.50 3153.00
Generator 33 KVA hour 6.00 1032.00 6192.00
Basic Cost of Labour, Material & Machinery (a+b+c) 60131.00
for 15 cum
For formwork and staging add the following:
14.1D (i) For solid slab super-structure, 18-28 per cent of
Case I (a+b+c)
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) for 60131.00
15 cum
d) Formwork and staging 18 per cent of (a+b+c) 18.00 10823.58

e) Overhead charges @ 14.615% on (a+b+c+d) 10370.01


f) Contractor's profit @ 10% on (a+b+c+d+e) 8132.46
Cost for 15 cum = a+b+c+d+e+f 89457.05
Rate per cum = (a+b+c+d+e+f)/15 5963.80

SOR 2018-19 (15% OH) BRIDGES - SUPER STRUCTURE

RA - 135
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
say 5964.00
g) seiniorage charges per cum
Coarse Sand cum 0.45 50.00 18.00
Aggregate cum 0.90 75.00 67.50
Add District Mineral Fund (DMF) 30% on Seinorage 0.300 85.50 25.65
charges
Rate per cum say 111.15
Add lead charges of metal 25.00 Km 0.90 504.25 453.83
Add lead charges of sand 41.00 Km 0.45 805.54 362.49
Add lead charges of Manufactured Sand 25.00 Km 0.00 566.50 0.00
816.32
Total 6891.00
14.1D (q) Height 5m to 10m
Case I (i)

Basic Cost of Labour, Material & Machinery (a+b+c) for 60131.00


15 cum
d) Formwork and staging 23 per cent of (a+b+c) 23.00 13830.13

e) Overhead charges @ 14.615% on (a+b+c+d) 10809.42


f) Contractor's profit @ 10% on (a+b+c+d+e) 8477.05
Cost for 15 cum = a+b+c+d+e+f 93247.60
Rate per cum = (a+b+c+d+e+f)/15 6216.51
say 6217.00
g) seiniorage charges per cum 111.15
Rate per cum say 111.15

Add lead charges of metal 25.00 Km 0.90 504.25 453.83


Add lead charges of sand 41.00 Km 0.45 805.54 362.49
Add lead charges of Manufactured Sand 25.00 Km 0.00 566.50 0.00
816.32
Total 7144.00
14.1D (r) Height above 10m
Case I (i)

Basic Cost of Labour, Material & Machinery (a+b+c) for 60131.00


15 cum
d) Formwork and staging 28 per cent of (a+b+c) 28.00 16836.68

e) Overhead charges @ 14.615% on (a+b+c+d) 11248.83


f) Contractor's profit @ 10% on (a+b+c+d+e) 8821.65
Cost for 15 cum = a+b+c+d+e+f 97038.16
Rate per cum = (a+b+c+d+e+f)/15 6469.21
say 6469.00
g) seiniorage charges per cum 111.15
Rate per cum say 111.15

Add lead charges of metal 25.00 Km 0.90 504.25 453.83


Add lead charges of sand 41.00 Km 0.45 805.54 362.49
Add lead charges of Manufactured Sand 25.00 Km 0.00 566.50 0.00
816.32
Total 7397.00
14.1D (ii) For T-beam & slab, 23-33 per cent of (a+b+c)
Case I
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) for 60131.00
15 cum
d) Formwork and staging 23 per cent of (a+b+c) 23.00 13830.13

e) Overhead charges @ 14.615% on (a+b+c+d) 10809.42


f) Contractor's profit @ 10% on (a+b+c+d+e) 8477.05
Cost for 15 cum = a+b+c+d+e+f 93247.60

SOR 2018-19 (15% OH) BRIDGES - SUPER STRUCTURE

RA - 136
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Rate per cum = (a+b+c+d+e+f)/15 6216.51
say 6217.00
g) seiniorage charges per cum 111.15
Rate per cum say 111.15

Add lead charges of metal 25.00 Km 0.90 504.25 453.83


Add lead charges of sand 41.00 Km 0.45 805.54 362.49
Add lead charges of Manufactured Sand 25.00 Km 0.00 566.50 0.00
816.32
Total 7144.00
14.1D (q) Height 5m to 10m
Case I
(ii)
Basic Cost of Labour, Material & Machinery (a+b+c) for 60131.00
15 cum
d) Formwork and staging 28 per cent of (a+b+c) 28.00 16836.68

e) Overhead charges @ 14.615% on (a+b+c+d) 11248.83


f) Contractor's profit @ 10% on (a+b+c+d+e) 8821.65
Cost for 15 cum = a+b+c+d+e+f 97038.16
Rate per cum = (a+b+c+d+e+f)/15 6469.21
say 6469.00
g) seiniorage charges per cum 111.15
Rate per cum say 111.15

Add lead charges of metal 25.00 Km 0.90 504.25 453.83


Add lead charges of sand 41.00 Km 0.45 805.54 362.49
Add lead charges of Manufactured Sand 25.00 Km 0.00 566.50 0.00
816.32
Total 7397.00
14.1D (r) Height above 10m
Case I
(ii)
Basic Cost of Labour, Material & Machinery (a+b+c) for 60131.00
15 cum
d) Formwork and staging 33 per cent of (a+b+c) 33.00 19843.23

e) Overhead charges @ 14.615% on (a+b+c+d) 11688.23


f) Contractor's profit @ 10% on (a+b+c+d+e) 9166.25
Cost for 15 cum = a+b+c+d+e+f 100828.71
Rate per cum = (a+b+c+d+e+f)/15 6721.91
say 6722.00
g) seiniorage charges per cum 111.15
Rate per cum say 111.15

Add lead charges of metal 25.00 Km 0.90 504.25 453.83


Add lead charges of sand 41.00 Km 0.45 805.54 362.49
Add lead charges of Manufactured Sand 25.00 Km 0.00 566.50 0.00
816.32
Total 7649.00
14.1D (iii) For box girder and balanced cantilever, 38-58 per cent
Case I of cost of concrete.
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) for 60131.00
15 cum
d) Formwork and staging 38 per cent of (a+b+c) 38.00 22849.78

e) Overhead charges @ 14.615% on (a+b+c+d) 12127.64


f) Contractor's profit @ 10% on (a+b+c+d+e) 9510.84
Cost for 15 cum = a+b+c+d+e+f 104619.26
Rate per cum = (a+b+c+d+e+f)/15 6974.62
say 6975.00

SOR 2018-19 (15% OH) BRIDGES - SUPER STRUCTURE

RA - 137
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
g) seiniorage charges per cum 111.15
Rate per cum say 111.15

Add lead charges of metal 25.00 Km 0.90 504.25 453.83


Add lead charges of sand 41.00 Km 0.45 805.54 362.49
Add lead charges of Manufactured Sand 25.00 Km 0.00 566.50 0.00
816.32
Total 7902.00
14.1D (q) Height 5m to 10m
Case I
(iii)
Basic Cost of Labour, Material & Machinery (a+b+c) for 60131.00
15 cum
d) Formwork and staging 48 per cent of (a+b+c) 48.00 28862.88

e) Overhead charges @ 14.615% on (a+b+c+d) 13006.46


f) Contractor's profit @ 10% on (a+b+c+d+e) 10200.03
Cost for 15 cum = a+b+c+d+e+f 112200.37
Rate per cum = (a+b+c+d+e+f)/15 7480.02
say 7480.00
g) seiniorage charges per cum 111.15
Rate per cum say 111.15

Add lead charges of metal 25.00 Km 0.90 504.25 453.83


Add lead charges of sand 41.00 Km 0.45 805.54 362.49
Add lead charges of Manufactured Sand 25.00 Km 0.00 566.50 0.00
816.32
Total 8407.00
14.1D (r) Height above 10m
Case I
(iii)
Basic Cost of Labour, Material & Machinery (a+b+c) for 60131.00
15 cum
d) Formwork and staging 58 per cent of (a+b+c) 58.00 34875.98

e) Overhead charges @ 14.615% on (a+b+c+d) 13885.27


f) Contractor's profit @ 10% on (a+b+c+d+e) 10889.23
Cost for 15 cum = a+b+c+d+e+f 119781.48
Rate per cum = (a+b+c+d+e+f)/15 7985.43
say 7985.00
g) seiniorage charges per cum 111.15
Rate per cum say 111.15

Add lead charges of metal 25.00 Km 0.90 504.25 453.83


Add lead charges of sand 41.00 Km 0.45 805.54 362.49
Add lead charges of Manufactured Sand 25.00 Km 0.00 566.50 0.00
816.32
Total 8913.00
Case II Using Batching Plant, Transit Mixer and Concrete Pump

Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 50.64 3900.00 197496.00
Coarse sand cum 54.00 182.00 9828.00
20 mm Aggregate cum 64.80 1303.00 84434.40
10 mm Aggregate cum 43.20 894.00 38620.80
b) Labour
Mate day 0.88 451.00 396.88
Mason day 3.00 455.00 1365.00
Mazdoor day 19.00 400.00 7600.00
c) Machinery

SOR 2018-19 (15% OH) BRIDGES - SUPER STRUCTURE

RA - 138
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Batching Plant @ 20 cum/hour hour 6.00 1343.30 8059.80
Generator 100 KVA hour 6.00 1316.30 7897.80
Loader hour 6.00 1594.70 9568.20
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity lead upto1 Km hour 15.00 2071.70 31075.50
Lead beyond 1 Km, L - lead in Kilometer tonne.km 300L 13.18 31634.26

Concrete Pump hour 6.00 1508.80 9052.80


Basic Cost of Labour, Material & Machinery (a+b+c) 437030.00
for 120 cum
For formwork and staging add the following:
14.1D (i) For solid slab super-structure, 18-28 per cent of
Case II (a+b+c)
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) for 437030.00
120 cum
d) Formwork and staging 18 per cent of (a+b+c) 18.00 78665.40

e) Overhead charges @ 14.615% on (a+b+c+d) 75368.88


f) Contractor's profit @ 10% on (a+b+c+d+e) 59106.43
Cost for 120 cum = a+b+c+d+e+f 650170.71
Rate per cum = (a+b+c+d+e+f)/120 5418.09
say 5418.00
g) seiniorage charges per cum
Coarse Sand cum 0.45 50.00 18.00
Aggregate cum 0.90 75.00 67.50
Add District Mineral Fund (DMF) 30% on Seinorage 0.300 85.50 25.65
charges
Rate per cum say 111.15
Add lead charges of metal 25.00 Km 0.90 504.25 453.83
Add lead charges of sand 41.00 Km 0.45 805.54 362.49
Add lead charges of Manufactured Sand 25.00 Km 0.00 566.50 0.00
say 816.32
Total 6346.00
14.1D (q) Height 5m to 10m
Case II
(i)
Basic Cost of Labour, Material & Machinery (a+b+c) for 437030.00
120 cum
d) Formwork and staging 23 per cent of (a+b+c) 23.00 100516.90

e) Overhead charges @ 14.615% on (a+b+c+d) 78562.48


f) Contractor's profit @ 10% on (a+b+c+d+e) 61610.94
Cost for 120 cum = a+b+c+d+e+f 677720.32
Rate per cum = (a+b+c+d+e+f)/120 5647.67
say 5648.00
g) seiniorage charges per cum 111.15
Rate per cum say 111.15

f) Lead charges for Material say 816.32


TOTAL Rate 6575.14
Total 6575.00
14.1D (r) Height above 10m
Case II
(i)
Basic Cost of Labour, Material & Machinery (a+b+c) for 437030.00
120 cum
d) Formwork and staging 28 per cent of (a+b+c) 28.00 122368.40

e) Overhead charges @ 14.615% on (a+b+c+d) 81756.08


f) Contractor's profit @ 10% on (a+b+c+d+e) 64115.45
Cost for 120 cum = a+b+c+d+e+f 705269.92

SOR 2018-19 (15% OH) BRIDGES - SUPER STRUCTURE

RA - 139
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Rate per cum = (a+b+c+d+e+f)/120 5877.25
say 5877.00
g) seiniorage charges per cum 111.15
Rate per cum say 111.15

f) Lead charges for Material say 816.32


TOTAL Rate 6804.72
Total 6805.00
14.1D (ii) For T-beam & slab, 23-33 per cent of (a+b+c)
Case II
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) for 437030.00
120 cum
d) Formwork and staging 23 per cent of (a+b+c) 23.00 100516.90

e) Overhead charges @ 14.615% on (a+b+c+d) 78562.48


f) Contractor's profit @ 10% on (a+b+c+d+e) 61610.94
Cost for 120 cum = a+b+c+d+e+f 677720.32
Rate per cum = (a+b+c+d+e+f)/120 5647.67
say 5648.00
g) seiniorage charges per cum 111.15
Rate per cum say 111.15

f) Lead charges for Material say 816.32


TOTAL Rate 6575.14
Total 6575.00
14.1D (q) Height 5m to 10m
Case II
(ii)
Basic Cost of Labour, Material & Machinery (a+b+c) for 437030.00
120 cum
d) Formwork and staging 28 per cent of (a+b+c) 28.00 122368.40

e) Overhead charges @ 14.615% on (a+b+c+d) 81756.08


f) Contractor's profit @ 10% on (a+b+c+d+e) 64115.45
Cost for 120 cum = a+b+c+d+e+f 705269.92
Rate per cum = (a+b+c+d+e+f)/120 5877.25
say 5877.00
g) seiniorage charges per cum 111.15
Rate per cum say 111.15

f) Lead charges for Material say 816.32


TOTAL Rate 6804.72
Total 6805.00
14.1D (r) Height above 10m
Case II
(ii)
Basic Cost of Labour, Material & Machinery (a+b+c) for 437030.00
120 cum
d) Formwork and staging 33 per cent of (a+b+c) 33.00 144219.90

e) Overhead charges @ 14.615% on (a+b+c+d) 84949.67


f) Contractor's profit @ 10% on (a+b+c+d+e) 66619.96
Cost for 120 cum = a+b+c+d+e+f 732819.53
Rate per cum = (a+b+c+d+e+f)/120 6106.83
say 6107.00
g) seiniorage charges per cum 111.15
Rate per cum say 111.15

f) Lead charges for Material say 816.32


TOTAL Rate 7034.30
Total 7034.00

SOR 2018-19 (15% OH) BRIDGES - SUPER STRUCTURE

RA - 140
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
14.1D (iii) For box girder and balanced cantilever, 38-58 per cent
Case II of cost of concrete.
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) for 437030.00
120 cum
d) Formwork and staging 38 per cent of (a+b+c) 38.00 166071.40

e) Overhead charges @ 14.615% on (a+b+c+d) 88143.27


f) Contractor's profit @ 10% on (a+b+c+d+e) 69124.47
Cost for 120 cum = a+b+c+d+e+f 760369.14
Rate per cum = (a+b+c+d+e+f)/120 6336.41
say 6336.00
g) seiniorage charges per cum 111.15
Rate per cum say 111.15

f) Lead charges for Material say 816.32


TOTAL Rate 7263.88
Total 7264.00
14.1D (q) Height 5m to 10m
Case II
(iii)
Basic Cost of Labour, Material & Machinery (a+b+c) for 437030.00
120 cum
d) Formwork and staging 48 per cent of (a+b+c) 48.00 209774.40

e) Overhead charges @ 14.615% on (a+b+c+d) 94530.46


f) Contractor's profit @ 10% on (a+b+c+d+e) 74133.49
Cost for 120 cum = a+b+c+d+e+f 815468.35
Rate per cum = (a+b+c+d+e+f)/120 6795.57
say 6796.00
g) seiniorage charges per cum 111.15
Rate per cum say 111.15

f) Lead charges for Material say 816.32


TOTAL Rate 7723.04
Total 7723.00
14.1D (r) Height above 10m
Case II
(iii)
Basic Cost of Labour, Material & Machinery (a+b+c) for 437030.00
120 cum
d) Formwork and staging 58 per cent of (a+b+c) 58.00 253477.40

e) Overhead charges @ 14.615% on (a+b+c+d) 100917.66


f) Contractor's profit @ 10% on (a+b+c+d+e) 79142.51
Cost for 120 cum = a+b+c+d+e+f 870567.56
Rate per cum = (a+b+c+d+e+f)/120 7254.73
say 7255.00
g) seiniorage charges per cum 111.15
Rate per cum say 111.15

f) Lead charges for Material say 816.32


TOTAL Rate 8182.20
Total 8182.00
14.1 E PSC Grade M-40
Case 1 Using concrete mixer.
Unit = 1 cum
Taking output = 15 cum
a) Material
Cement tonne 6.45 3900.00 25155.00
Coarse sand cum 6.75 182.00 1228.50
20 mm Aggregate cum 8.10 1303.00 10554.30

SOR 2018-19 (15% OH) BRIDGES - SUPER STRUCTURE

RA - 141
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
10 mm Aggregate cum 5.40 894.00 4827.60
Admixture @ 0.4 per cent of cement kg 25.80 43.00 1109.40
b) Labour
Mate day 0.96 451.00 432.96
Mason day 2.00 455.00 910.00
Mazdoor day 22.00 400.00 8800.00
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 525.50 3153.00
Generator 33 KVA hour 6.00 1032.00 6192.00
Basic Cost of Labour, Material & Machinery (a+b+c) 62363.00
for 15 cum
For formwork and staging add the following:
14.1E (i) For solid slab super-structure, 20-30 per cent of
Case I (a+b+c)
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) for 62363.00
15 cum
d) Formwork and staging 20 per cent of (a+b+c) 20.00 12472.60

e) Overhead charges @ 14.615% on (a+b+c+d) 10937.22


f) Contractor's profit @ 10% on (a+b+c+d+e) 8577.28
Cost for 15 cum = a+b+c+d+e+f 94350.11
Rate per cum = (a+b+c+d+e+f)/15 6290.01
say 6290.00
g) seiniorage charges per cum
Coarse Sand cum 0.45 50.00 18.00
Aggregate cum 0.90 75.00 67.50
Add District Mineral Fund (DMF) 30% on Seinorage 0.300 85.50 25.65
charges
Rate per cum say 111.15
Add lead charges of metal 25.00 Km 0.90 504.25 453.83
Add lead charges of sand 41.00 Km 0.45 805.54 362.49
Add lead charges of Manufactured Sand 25.00 Km 0.00 566.50 0.00
say 816.32
Total 7217.00
14.1E (q) Height 5m to 10m
Case I (i)

Basic Cost of Labour, Material & Machinery (a+b+c) for 62363.00


15 cum
d) Formwork and staging 25 per cent of (a+b+c) 25.00 15590.75

e) Overhead charges @ 14.615% on (a+b+c+d) 11392.94


f) Contractor's profit @ 10% on (a+b+c+d+e) 8934.67
Cost for 15 cum = a+b+c+d+e+f 98281.36
Rate per cum = (a+b+c+d+e+f)/15 6552.09
say 6552.00
g) seiniorage charges per cum 111.15
Rate per cum say 111.15

f) Lead charges for Material say 816.32


TOTAL Rate 7479.56
Total 7480.00
14.1E (r) Height above 10m
Case I (i)

Basic Cost of Labour, Material & Machinery (a+b+c) for 62363.00


15 cum
d) Formwork and staging 30 per cent of (a+b+c) 30.00 18708.90

e) Overhead charges @ 14.615% on (a+b+c+d) 11848.66


f) Contractor's profit @ 10% on (a+b+c+d+e) 9292.06

SOR 2018-19 (15% OH) BRIDGES - SUPER STRUCTURE

RA - 142
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Cost for 15 cum = a+b+c+d+e+f 102212.61
Rate per cum = (a+b+c+d+e+f)/15 6814.17
say 6814.00
g) seiniorage charges per cum 111.15
Rate per cum say 111.15

f) Lead charges for Material say 816.32


TOTAL Rate 7741.64
Total 7742.00
14.1E (ii) For T-beam & slab, 25-35 per cent of (a+b+c)
Case I
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) for 62363.00
15 cum
d) Formwork and staging 25 per cent of (a+b+c) 25.00 15590.75

e) Overhead charges @ 14.615% on (a+b+c+d) 11392.94


f) Contractor's profit @ 10% on (a+b+c+d+e) 8934.67
Cost for 15 cum = a+b+c+d+e+f 98281.36
Rate per cum = (a+b+c+d+e+f)/15 6552.09
say 6552.00
g) seiniorage charges per cum 111.15
Rate per cum say 111.15

f) Lead charges for Material say 816.32


TOTAL Rate 7479.56
Total 7480.00
14.1E (q) Height 5m to 10m
Case I
(ii)
Basic Cost of Labour, Material & Machinery (a+b+c) for 62363.00
15 cum
d) Formwork and staging 30 per cent of (a+b+c) 30.00 18708.90

e) Overhead charges @ 14.615% on (a+b+c+d) 11848.66


f) Contractor's profit @ 10% on (a+b+c+d+e) 9292.06
Cost for 15 cum = a+b+c+d+e+f 102212.61
Rate per cum = (a+b+c+d+e+f)/15 6814.17
say 6814.00
g) seiniorage charges per cum 111.15
Rate per cum say 111.15

f) Lead charges for Material say 816.32


TOTAL Rate 7741.64
Total 7742.00
14.1E (r) Height above 10m
Case I
(ii)
Basic Cost of Labour, Material & Machinery (a+b+c) for 62363.00
15 cum
d) Formwork and staging 35 per cent of (a+b+c) 35.00 21827.05

e) Overhead charges @ 14.615% on (a+b+c+d) 12304.38


f) Contractor's profit @ 10% on (a+b+c+d+e) 9649.44
Cost for 15 cum = a+b+c+d+e+f 106143.87
Rate per cum = (a+b+c+d+e+f)/15 7076.26
say 7076.00
g) seiniorage charges per cum 111.15
Rate per cum say 111.15

f) Lead charges for Material say 816.32


TOTAL Rate 8003.73

SOR 2018-19 (15% OH) BRIDGES - SUPER STRUCTURE

RA - 143
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Total 8004.00
14.1E Case II Using Batching Plant, Transit Mixer and Concrete Pump

Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 51.60 3900.00 201240.00
Coarse sand cum 54.00 182.00 9828.00
20 mm Aggregate cum 64.80 1303.00 84434.40
10 mm Aggregate cum 43.20 894.00 38620.80
Admixture @ 0.4 per cent of cement kg 206.40 43.00 8875.20
b) Labour
Mate day 0.94 451.00 423.94
Mason day 3.50 455.00 1592.50
Mazdoor day 20.00 400.00 8000.00
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1343.30 8059.80
Generator 100 KVA hour 6.00 1316.30 7897.80
Loader hour 6.00 1594.70 9568.20
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity lead upto1 Km hour 15.00 2071.70 31075.50
Lead beyond 1 Km, L - lead in Kilometer tonne.km 300L 13.18 31634.26

Concrete Pump hour 6.00 1508.80 9052.80


Basic Cost of Labour, Material & Machinery (a+b+c) for 450304.00
120 cum
For formwork and staging add the following:
14.1E (i) For solid/voided slab super-structure, 18-28 per cent of
Case II (a+b+c)
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) for 120 450304.00
cum
d) Formwork and staging 18 per cent of (a+b+c) 18.00 81054.72

e) Overhead charges @ 14.615% on (a+b+c+d) 77658.08


f) Contractor's profit @ 10% on (a+b+c+d+e) 60901.68
Cost for 15 cum = a+b+c+d+e+f 669918.48
Rate per cum = (a+b+c+d+e+f)/120 5582.65
say 5583.00
g) seiniorage charges per cum
Coarse Sand cum 0.45 50.00 18.00
Aggregate cum 0.90 75.00 67.50
Add District Mineral Fund (DMF) 30% on Seinorage 0.300 85.50 25.65
charges
Rate per cum say 111.15
Add lead charges of metal 25.00 Km 0.90 504.25 453.83
Add lead charges of sand 41.00 Km 0.45 805.54 362.49
Add lead charges of Manufactured Sand 25.00 Km 0.00 566.50 0.00
say 816.32
Total 6510.00
14.1E (q) Height 5m to 10m
Case II
(i)
Basic Cost of Labour, Material & Machinery (a+b+c) for 450304.00
120 cum
d) Formwork and staging 23 per cent of (a+b+c) 23.00 103569.92

e) Overhead charges @ 14.615% on (a+b+c+d) 80948.67


f) Contractor's profit @ 10% on (a+b+c+d+e) 63482.26
Cost for 120 cum = a+b+c+d+e+f 698304.85
Rate per cum = (a+b+c+d+e+f)/120 5819.21

SOR 2018-19 (15% OH) BRIDGES - SUPER STRUCTURE

RA - 144
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
say 5819.00
g) seiniorage charges per cum 111.15
Rate per cum say 111.15

f) Lead charges for Material say 816.32


TOTAL Rate 6746.68
Total 6747.00
14.1E (r) Height above 10m
Case II
(i)
Basic Cost of Labour, Material & Machinery (a+b+c) for 450304.00
120 cum
d) Formwork and staging 28 per cent of (a+b+c) 28.00 126085.12

e) Overhead charges @ 14.615% on (a+b+c+d) 84239.27


f) Contractor's profit @ 10% on (a+b+c+d+e) 66062.84
Cost for 120 cum = a+b+c+d+e+f 726691.23
Rate per cum = (a+b+c+d+e+f)/120 6055.76
say 6056.00
g) seiniorage charges per cum 111.15
Rate per cum say 111.15

f) Lead charges for Material say 816.32


TOTAL Rate 6983.23
Total 6983.00
14.1E (ii) For T-beam & slab, 23-33 per cent of (a+b+c)
Case II
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) for 450304.00
120 cum
d) Formwork and staging 23 per cent of (a+b+c) 23.00 103569.92

e) Overhead charges @ 14.615% on (a+b+c+d) 80948.67


f) Contractor's profit @ 10% on (a+b+c+d+e) 63482.26
Cost for 120 cum = a+b+c+d+e+f 698304.85
Rate per cum = (a+b+c+d+e+f)/120 5819.21
say 5819.00
g) seiniorage charges per cum 111.15
Rate per cum say 111.15

f) Lead charges for Material say 816.32


TOTAL Rate 6746.68
Total 6747.00
14.1E (q) Height 5m to 10m
Case II
(ii)
Basic Cost of Labour, Material & Machinery (a+b+c) for 450304.00
120 cum
d) Formwork and staging 28 per cent of (a+b+c) 28.00 126085.12

e) Overhead charges @ 14.615% on (a+b+c+d) 84239.27


f) Contractor's profit @ 10% on (a+b+c+d+e) 66062.84
Cost for 120 cum = a+b+c+d+e+f 726691.23
Rate per cum = (a+b+c+d+e+f)/120 6055.76
say 6056.00
g) seiniorage charges per cum 111.15
Rate per cum say 111.15

f) Lead charges for Material say 816.32


TOTAL Rate 6983.23
Total 6983.00

SOR 2018-19 (15% OH) BRIDGES - SUPER STRUCTURE

RA - 145
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
14.1E (r) Height above 10m
Case II
(ii)
Basic Cost of Labour, Material & Machinery (a+b+c) for 450304.00
120 cum
d) Formwork and staging 33 per cent of (a+b+c) 33.00 148600.32

e) Overhead charges @ 14.615% on (a+b+c+d) 87529.87


f) Contractor's profit @ 10% on (a+b+c+d+e) 68643.42
Cost for 120 cum = a+b+c+d+e+f 755077.61
Rate per cum = (a+b+c+d+e+f)/120 6292.31
say 6292.00
g) seiniorage charges per cum 111.15
Rate per cum say 111.15

f) Lead charges for Material say 816.32


TOTAL Rate 7219.78
Total 7220.00
14.1E (iii) For cast-in-situ box girder, segment construction and
Case II balanced cantilever, 38-58 per cent of cost of concrete.

(p) Height upto 5m


Basic Cost of Labour, Material & Machinery (a+b+c) for 450304.00
120 cum
d) Formwork and staging 38 per cent of (a+b+c) 38.00 171115.52

e) Overhead charges @ 14.615% on (a+b+c+d) 90820.46


f) Contractor's profit @ 10% on (a+b+c+d+e) 71224.00
Cost for 120 cum = a+b+c+d+e+f 783463.98
Rate per cum = (a+b+c+d+e+f)/120 6528.87
say 6529.00
g) seiniorage charges per cum 111.15
Rate per cum say 111.15
f) Lead charges for Material say 816.32
TOTAL Rate 7456.33
Total 7456.00
14.1E (q) Height 5m to 10m
Case II
(iii)
Basic Cost of Labour, Material & Machinery (a+b+c) for 450304.00
120 cum
d) Formwork and staging 48 per cent of (a+b+c) 48.00 216145.92

e) Overhead charges @ 14.615% on (a+b+c+d) 97401.66


f) Contractor's profit @ 10% on (a+b+c+d+e) 76385.16
Cost for 120 cum = a+b+c+d+e+f 840236.73
Rate per cum = (a+b+c+d+e+f)/120 7001.97
say 7002.00
g) seiniorage charges per cum 111.15
Rate per cum say 111.15
f) Lead charges for Material say 816.32
TOTAL Rate 7929.44
Total 7929.00
14.1E (r) Height above 10m
Case II
(iii)
Basic Cost of Labour, Material & Machinery (a+b+c) for 450304.00
120 cum
d) Formwork and staging 58 per cent of (a+b+c) 58.00 261176.32

e) Overhead charges @ 14.615% on (a+b+c+d) 103982.85


f) Contractor's profit @ 10% on (a+b+c+d+e) 81546.32

SOR 2018-19 (15% OH) BRIDGES - SUPER STRUCTURE

RA - 146
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Cost for 120 cum = a+b+c+d+e+f 897009.49
Rate per cum = (a+b+c+d+e+f)/120 7475.08
say 7475.00
g) seiniorage charges per cum 111.15
Rate per cum say 111.15
f) Lead charges for Material say 816.32
TOTAL Rate 8402.55
Total 8403.00
14.1F F PSC Grade M-45
Unit = 1 cum
Taking output = 120 cum
a) Material
Cement tonne 55.80 3900.00 217620.00
Coarse sand cum 54.00 182.00 9828.00
20 mm Aggregate cum 64.80 1303.00 84434.40
10 mm Aggregate cum 43.20 894.00 38620.80
Admixture @ 0.4 per cent of cement kg 223.20 43.00 9597.60
b) Labour
Mate day 0.94 451.00 423.94
Mason day 3.50 455.00 1592.50
Mazdoor day 20.00 400.00 8000.00
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1343.30 8059.80
Generator 100 KVA hour 6.00 1316.30 7897.80
Loader hour 6.00 1594.70 9568.20
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity lead upto1 Km hour 15.00 2071.70 31075.50
Lead beyond 1 Km, L - lead in Kilometer tonne.km 300L 13.18 31634.26

Concrete Pump hour 6.00 1508.80 9052.80


Basic Cost of Labour, Material & Machinery (a+b+c) 467406.00
for 120 cum
For formwork and staging add the following:
14.1F (i) For solid slab/voided slab super-structure, 16-26 per
cent of cost of concrete (a+b+c)
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) for 467406.00
120 cum
d) Formwork and staging 16 per cent of (a+b+c) 16.00 74784.96

e) Overhead charges @ 14.615% on (a+b+c+d) 79241.21


f) Contractor's profit @ 10% on (a+b+c+d+e) 62143.22
Cost for 120 cum = a+b+c+d+e+f 683575.39
Rate per cum = (a+b+c+d+e+f)/120 5696.46
say 5696.00
g) seiniorage charges per cum
Coarse Sand cum 0.45 50.00 18.00
Aggregate cum 0.90 75.00 67.50
Add District Mineral Fund (DMF) 30% on Seinorage 0.300 85.50 25.65
charges
Rate per cum say 111.15
Add lead charges of metal 25.00 Km 0.90 504.25 453.83
Add lead charges of sand 41.00 Km 0.45 805.54 362.49
Add lead charges of Manufactured Sand 25.00 Km 0.00 566.50 0.00
say 816.32
Total 6624.00
14.1F (q) Height 5m to 10m
(i)
Basic Cost of Labour, Material & Machinery (a+b+c) for 467406.00
120 cum

SOR 2018-19 (15% OH) BRIDGES - SUPER STRUCTURE

RA - 147
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
d) Formwork and staging 21 per cent of (a+b+c) 21.00 98155.26

e) Overhead charges @ 14.615% on (a+b+c+d) 82656.78


f) Contractor's profit @ 10% on (a+b+c+d+e) 64821.80
Cost for 120 cum = a+b+c+d+e+f 713039.84
Rate per cum = (a+b+c+d+e+f)/120 5942.00
say 5942.00
g) seiniorage charges per cum 111.15
Rate per cum say 111.15

f) Lead charges for Material say 816.32


TOTAL Rate 6869.47
Total 6869.00
14.1F (r) Height above 10m
(i)
Basic Cost of Labour, Material & Machinery (a+b+c) for 467406.00
120 cum
d) Formwork and staging 26 per cent of (a+b+c) 26.00 121525.56

e) Overhead charges @ 14.615% on (a+b+c+d) 86072.35


f) Contractor's profit @ 10% on (a+b+c+d+e) 67500.39
Cost for 120 cum = a+b+c+d+e+f 742504.30
Rate per cum = (a+b+c+d+e+f)/120 6187.54
say 6188.00
g) seiniorage charges per cum 111.15
Rate per cum say 111.15

f) Lead charges for Material say 816.32


TOTAL Rate 7115.00
Total 7115.00
14.1F (ii) For T-beam & slab including launching of precast
girders by launching truss upto 40 m span, 21-31 per
cent of cost of concrete.
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) for 467406.00
120 cum
d) Formwork and staging 21 per cent of (a+b+c) 21.00 98155.26

e) Overhead charges @ 14.615% on (a+b+c+d) 82656.78


f) Contractor's profit @ 10% on (a+b+c+d+e) 64821.80
Cost for 120 cum = a+b+c+d+e+f 713039.84
Rate per cum = (a+b+c+d+e+f)/120 5942.00
say 5942.00
g) seiniorage charges per cum 111.15
Rate per cum say 111.15

f) Lead charges for Material say 816.32


TOTAL Rate 6869.47
Total 6869.00
14.1F (q) Height 5m to 10m
(ii)
Basic Cost of Labour, Material & Machinery (a+b+c) for 467406.00
120 cum
d) Formwork and staging 26 per cent of (a+b+c) 26.00 121525.56

e) Overhead charges @ 14.615% on (a+b+c+d) 86072.35


f) Contractor's profit @ 10% on (a+b+c+d+e) 67500.39
Cost for 120 cum = a+b+c+d+e+f 742504.30
Rate per cum = (a+b+c+d+e+f)/120 6187.54
say 6188.00
g) seiniorage charges per cum 111.15
Rate per cum say 111.15

SOR 2018-19 (15% OH) BRIDGES - SUPER STRUCTURE

RA - 148
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
f) Lead charges for Material say 816.32
TOTAL Rate 7115.00
Total 7115.00
14.1F (r) Height above 10m
(ii)
Basic Cost of Labour, Material & Machinery (a+b+c) for 467406.00
120 cum
d) Formwork and staging 31 per cent of (a+b+c) 31.00 144895.86

e) Overhead charges @ 14.615% on (a+b+c+d) 89487.92


f) Contractor's profit @ 10% on (a+b+c+d+e) 70178.98
Cost for 120 cum = a+b+c+d+e+f 771968.75
Rate per cum = (a+b+c+d+e+f)/120 6433.07
say 6433.00
g) seiniorage charges per cum 111.15
Rate per cum say 111.15

f) Lead charges for Material say 816.32


TOTAL Rate 7360.54
Total 7361.00
14.1F (iii) For cast-in-situ box girder, segmental construction and
balanced cantilever, 36-56 per cent of cost of concrete.

(p) Height upto 5m


Basic Cost of Labour, Material & Machinery (a+b+c) for 467406.00
120 cum
d) Formwork and staging 36 per cent of (a+b+c) 36.00 168266.16

e) Overhead charges @ 14.615% on (a+b+c+d) 92903.49


f) Contractor's profit @ 10% on (a+b+c+d+e) 72857.56
Cost for 120 cum = a+b+c+d+e+f 801433.21
Rate per cum = (a+b+c+d+e+f)/120 6678.61
say 6679.00
g) seiniorage charges per cum 111.15
Rate per cum say 111.15

f) Lead charges for Material say 816.32


TOTAL Rate 7606.08
Total 7606.00
14.1F (q) Height 5m to 10m
(iii)
Basic Cost of Labour, Material & Machinery (a+b+c) for 467406.00
120 cum
d) Formwork and staging 46 per cent of (a+b+c) 46.00 215006.76

e) Overhead charges @ 14.615% on (a+b+c+d) 99734.62


f) Contractor's profit @ 10% on (a+b+c+d+e) 78214.74
Cost for 120 cum = a+b+c+d+e+f 860362.12
Rate per cum = (a+b+c+d+e+f)/120 7169.68
say 7170.00
g) seiniorage charges per cum 111.15
Rate per cum say 111.15

f) Lead charges for Material say 816.32


TOTAL Rate 8097.15
Total 8097.00
14.1F (r) Height above 10m
(iii)
Basic Cost of Labour, Material & Machinery (a+b+c) for 467406.00
120 cum
d) Formwork and staging 56 per cent of (a+b+c) 56.00 261747.36

e) Overhead charges @ 14.615% on (a+b+c+d) 106565.76

SOR 2018-19 (15% OH) BRIDGES - SUPER STRUCTURE

RA - 149
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
f) Contractor's profit @ 10% on (a+b+c+d+e) 83571.91
Cost for 120 cum = a+b+c+d+e+f 919291.04
Rate per cum = (a+b+c+d+e+f)/120 7660.76
say 7661.00
g) seiniorage charges per cum 111.15
Rate per cum say 111.15

f) Lead charges for Material say 816.32


TOTAL Rate 8588.23
Total 8588.00
14.1 G PSC Grade M-50
Unit = 1 cum
Taking output = 120 cum
a) Material
Cement tonne 58.80 3900.00 229320.00
Coarse sand cum 54.00 182.00 9828.00
20 mm Aggregate cum 64.80 1303.00 84434.40
10 mm Aggregate cum 43.20 894.00 38620.80
Admixture @ 0.4 per cent of cement kg 235.20 43.00 10113.60
b) Labour
Mate day 0.94 451.00 423.94
Mason day 3.50 455.00 1592.50
Mazdoor day 20.00 400.00 8000.00
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1343.30 8059.80
Generator 100 KVA hour 6.00 1316.30 7897.80
Loader hour 6.00 1594.70 9568.20
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity lead upto1 Km hour 15.00 2071.70 31075.50
Lead beyond 1 Km, L - lead in Kilometer tonne.km 300L 13.18 31634.26

Concrete Pump hour 6.00 1508.80 9052.80


Basic Cost of Labour, Material & Machinery (a+b+c) 479622.00
for 120 cum
For formwork and staging add the following:
14.1G (i) For cast-in-situ box girder, segmental construction and
balanced cantilever, 35-55 per cent of cost of concrete

(p) Height upto 5m


Basic Cost of Labour, Material & Machinery (a+b+c) for 479622.00
120 cum
d) Formwork and staging 35 per cent of (a+b+c) 35.00 167867.70

e) Overhead charges @ 14.615% on (a+b+c+d) 94630.62


f) Contractor's profit @ 10% on (a+b+c+d+e) 74212.03
Cost for 120 cum = a+b+c+d+e+f 816332.35
Rate per cum = (a+b+c+d+e+f)/120 6802.77
say 6803.00
g) seiniorage charges per cum
Coarse Sand cum 0.45 50.00 18.00
Aggregate cum 0.90 75.00 67.50
Add District Mineral Fund (DMF) 30% on Seinorage 0.300 85.50 25.65
charges
Rate per cum say 111.15
Add lead charges of metal 25.00 Km 0.90 504.25 453.83
Add lead charges of sand 41.00 Km 0.45 805.54 362.49
Add lead charges of Manufactured Sand 25.00 Km 0.00 566.50 0.00
say 816.32
Total 7730.00

SOR 2018-19 (15% OH) BRIDGES - SUPER STRUCTURE

RA - 150
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
14.1G (q) Height 5m to 10m
(i)
Basic Cost of Labour, Material & Machinery (a+b+c) for 479622.00
120 cum
d) Formwork and staging 45 per cent of (a+b+c) 45.00 215829.90

e) Overhead charges @ 14.615% on (a+b+c+d) 101640.30


f) Contractor's profit @ 10% on (a+b+c+d+e) 79709.22
Cost for 120 cum = a+b+c+d+e+f 876801.41
Rate per cum = (a+b+c+d+e+f)/120 7306.68
say 7307.00
g) seiniorage charges per cum 111.15
Rate per cum say 111.15

f) Lead charges for Material say 816.32


TOTAL Rate 8234.15
Total 8234.00
14.1G (r) Height above 10m
(i)
Basic Cost of Labour, Material & Machinery (a+b+c) for 479622.00
120 cum
d) Formwork and staging 55 per cent of (a+b+c) 55.00 263792.10

e) Overhead charges @ 14.615% on (a+b+c+d) 108649.97


f) Contractor's profit @ 10% on (a+b+c+d+e) 85206.41
Cost for 120 cum = a+b+c+d+e+f 937270.48
Rate per cum = (a+b+c+d+e+f)/120 7810.59
say 7811.00
g) seiniorage charges per cum 111.15
Rate per cum say 111.15

f) Lead charges for Material say 816.32


TOTAL Rate 8738.06
Total 8738.00
14.2 1600 Supplying, fitting and placing HYSD Fe 500 bar
reinforcement in super-structure complete as per
drawing and technical specifications
Unit = 1 MT
Taking output = 1 MT
a) Material
HYSD bars including 5 per cent for laps and wastage tonne 1.05 42500.00 44625.00

Binding wire Kg 8.00 53.00 424.00


b) Labour for cutting, bending, tying and placing in
position
Mate day 0.44 451.00 198.44
Blacksmith day 3.00 482.20 1446.60
Mazdoor day 8.00 400.00 3200.00
Basic Cost of Labour & Material (a+b) 49895.00
c) Overhead charges @ 14.615% on (a+b) 7292.01
d) Contractor's profit @ 10% on (a+b+c) 5718.61
Rate per MT = a+b+c+d 62904.66
Total 62905.00
14.3 1800 High tensile steel wires/strands including all
accessories for stressing, stressing operations and
grouting complete as per drawing and Technical
Specifications
Unit = 1 MT
Taking output = 0.377 MT
Details of cost for 12T13 strand 40 m long cable (weight =
0.377 MT)
a) Material

SOR 2018-19 (15% OH) BRIDGES - SUPER STRUCTURE

RA - 151
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
H.T. Strand @ 9.42 kg/m including 2 per cent for tonne 0.39 35556.00 13689.06
wastage and extra length for jacking
Sheathing duct ID 66 mm along with 5 per cent extra metre 42.00 79.29 3330.18
length 40 x 1.05 = 42 m.
Tube anchorage set complete with bearing plate, each 2.00 43.24 86.48
permanent wedges etc
Cement for grouting including 3 per cent wastage @ tonne 0.125 3900.00 487.50
3.00 kg/m = 3 x 1.03 x 40 = 123.60 kg (say, = 125 kg)

Add 0.50 per cent cost of material for Spacers, 879.66


Insulation tape and miscellaneous items
b) Labour
i) For making and fixing cables, anchorages
Mate day 0.16 451.00 72.16
Blacksmith day 1.00 482.20 482.20
Mazdoor day 3.00 400.00 1200.00
ii) For prestressing
Mate/Supervisor day 0.05 451.00 22.55
Prestressing operator / Fitter day 0.25 520.00 130.00
Mazdoor day 1.00 400.00 400.00
iii) For grouting
Mate/Supervisor day 0.05 451.00 22.55
Mason day 0.25 455.00 113.75
Mazdoor day 1.00 400.00 400.00
c) Machinery
Stressing jack with pump hour 2.50 157.80 394.50
Grouting pump with agitator hour 1.00 353.00 353.00
Generator 33 KVA. hour 3.50 1032.00 3612.00
d) Overhead charges @ 14.615% on (a+b+c) 3752.49
e) Contractor's profit @ 10% on (a+b+c+d) 2942.81
Cost for 0.377 MT (a+b+c+d+e) 32370.89
Rate per MT = (a+b+c+d+e)/0.377 85864.42
Total 85864.00
Note Cost of HT steel has been taken for delivery at site. Hence
carriage has not been considered.
14.4 2702 Providing and laying Cement concrete wearing coat M-
30 grade including reinforcement complete as per
drawing and Technical Specifications
Unit = 1 cum
Taking output = 1 cum
a) Material
Cement concrete M30 Grade Refer relevant item of cum 1.00 3583.00 3583.00
concrete in Item 14.1 excluding formwork
HYSD bar reinforcement Rate as per item No tonne 0.075 49895.00 3742.13
14.2(Excluding OH & CP)
b) Labour
Mazdoor for cleaning deck slab concrete surface. day 0.15 400.00 60.00
c) Overhead charges @ 14.615% on (a+b) 1079.34
d) Contractor's profit @ 10% on (a+b+c) 846.45
Rate per cum (a+b+c+d) 9310.91
say 9311.00
e) seigniorage charges per cum 117.33
f) Lead charges for Material per cum 820.35
Total 10249.00
14.5 515 & Mastic Asphalt
2702

SOR 2018-19 (15% OH) BRIDGES - SUPER STRUCTURE

RA - 152
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Providing and laying 12 mm thick mastic asphalt
wearing course on top of deck slab excluding prime
coat with paving grade bitumen meeting the
requirements given in table 500-29, prepared by using
mastic cooker and laid to required level and slope after
cleaning the surface, including providing antiskid
surface with bitumen precoated fine grained hard stone
chipping of 9.5 mm nominal size at the rate of 0.005cum
per 10 sqm and at an approximate spacing of 10 cm
center to center in both directions, pressed into surface
when the temperature of surfaces not less than 100
deg. C, protruding 1 mm to 4 mm over mastic surface,
all complete as per clause 515.

Unit = sqm
Taking output = 72.46 sqm (2 tonnes)(0.869 cum)
assuming a density of 2.3 tonnes/cum.
a) Labour
Mate day 0.49 451.00 220.99
Mazdoor day 11.00 400.00 4400.00
Mazdoor (Skilled) day 1.25 515.00 643.75
b) Machinery
Mechanical broom @ 1250 sqm per hour hour 0.06 381.80 22.91
Air compressor 250 cfm hour 0.06 556.50 33.39
Mastic cooker 1 tonne capacity hour 6.00 79.50 477.00
Bitumen boiler 1500 litres capacity hour 6.00 223.00 1338.00
Tractor for towing and positioning of mastic cooker and hour 1.00 413.60 413.60
bitumen boiler
c) Material
Base mastic (without coarse aggregates) = 60 per cent
Coarse aggregate(3.35mm to 9.5 mm size) = 40 per cent .

Proportion of material required for mastic asphalt with


coarse aggregates (based on mix design done by CRRI for
a specific case)
i) Bitumen 80/100 or 60/70 or 30/40 @ 10.2 per cent tonne 0.204 33760.00 6887.04
by weight of mix. 2 x 10.2/100 = 0.204
ii) Crusher stone dust @ 31.9 per cent by weight of cum 0.39 333.00 129.87
mix = 2 x 31.9/100 = 0.638 tonnes = 0.638/1.625 =
0.39
iii) Lime stone dust filler with calcium carbonate tonne 0.36 2491.00 896.76
content not less than 80 per cent by weight @ 17.92
per cent by weight of mix = 2 x 17.92/100 = 0.36

iv) Coarse aggregates 9.5 mm to 3.35 mm size @ 40 cum 0.55 894.00 491.70
per cent by weight of mix = 2 x 40/100 = 0.8 MT =
0.8/1.456 = 0.55
v) Pre-coated stone chips of 13.5 mm nominal size for cum 0.036 4580.00 164.88
skid resistance = 72.46x0.005/10 = 0.036
vi) Bitumen for coating of chips @ 2 per cent by kg 1.05 33.76 35.45
weight = 0.036 x 1.456 x 2/100 = 0.001048MT =
1.05kg
d) Overhead charges @ 14.615% on (a+b+c) 2361.10
e) Contractor's profit @ 10% on (a+b+c+d) 1851.64
Cost for 72.46 sqm = a+b+c+d+e 20368.08
f) seigniorage charges for metal cum 0.98 75.00 73.20
Add District Mineral Fund (DMF) 30% on Seinorage 0.300 73.20 21.96
charges
95.16
g) Lead charges for metal 25.00 Km 0.98 504.25 492.15
g) Lead charges for Bitumen 250.00 Km 0.57 520.07 293.86
Rate per sqm = (a+b+c+d+e)/72.46 293.25
Total 293.00

SOR 2018-19 (15% OH) BRIDGES - SUPER STRUCTURE

RA - 153
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Note 1.The rates for 6 mm or any other thickness may be worked
out on pro-rata basis.
2. Where tack coat is required to be provided before laying
mastic asphalt, the same is required to be measured and
paid separately.
3.The quantities of binder, filler and aggregates are for
estimating purpose. Exact quantities shall be as per mix
design.
4.This rate analysis is based on design made by CRRI for a
specific case and is meant for estimating purposes only.
Actual design is required to be done for each case.

5.The quantity of bitumen works out 17 per cent of the


mastic asphalt blocks without aggregates and falls within the
standards laid down by MoRTH Specifications.
14.6 2703, Construction of precast RCC railing of M30 Grade,
1500, aggregate size not exceeding 12 mm, true to line and
1600 & grade, tolerance of vertical RCC post not to exceed 1 in
1700 500, centre to centre spacing between vertical post not
to exceed 2000 mm, leaving adequate space between
vertical post for expansion, complete as per approved
drawings and technical specifications.

Unit = 1 RM
Taking output = 2 x 24 m span = 48 m
a) Material
Cement concreteM30 Grade Refer relevant item of cum 4.09 3583.00 14661.64
concrete in Item 14.1(C) by using batching plant,
excluding formwork i.e. per cum basic cost (a+b+c)
No. of vertical posts = (12 + 2)2 = 28 Nos., External
area of vertical post 0.25x0.275 = 0.069sqm, Concrete
in Vertical posts = 0.069 x 28 = 1.932 cum, Hand rail in
3 tiers = 3 x 24 = 72 m, External area = 0.170 x 0.175
= 0.03 sqm, Concrete in hand rails = 0.03 x 72 = 2.16
cum, Total Concrete = 1.932 + 2.16 = 4.092 cum.
(Refer MoRTH SD / 202).

Add 5 per cent of above cost for form work for casting 733.08
in casting yard.
HYSD bar reinforcement Rate as per item No tonne 0.865 49895.00 43159.18
14.2(Excluding OH & CP)
Refer MoRTH SD / 202.
Add 5 per cent of (a) for handling and fixing of 2927.69
precast panels in position
b) Overhead charges @ 14.615% on (a) 8985.53
c) Contractor's profit @ 10% on (a+b) 7046.71
Rate for 48 m (a+b+c) 77513.83
Rate per metre (a+b+c)/48 1614.87
say 1615.00
g) seiniorage charges per cum 117.33
Rate per cum say 117.33

f) Lead charges for material 820.35


TOTAL Rate 2552.54
Total 2553.00
Note 1.Quantities of material have been adopted from standard
plans of MoRTH vide drawing no. SD/202.
2.48 m length is the total linear length adding both sides of
24 m span.

SOR 2018-19 (15% OH) BRIDGES - SUPER STRUCTURE

RA - 154
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
14.7 2703, Construction of RCC railing of M30 Grade in-situ with 20
1500, mm nominal size aggregate, true to line and grade,
1600 & tolerance of vertical RCC post not to exceed 1 in 500,
1700 centre to centre spacing between vertical post not to
exceed 2000 mm, leaving adequate space between
vertical post for expansion, complete as per approved
drawings and technical specifications.

Unit = 1 RM
Taking output = 2 x 24 m span = 48 m.
a) Material
Cement concreteM30 Grade Refer relevant item of cum 4.092 3583.00 14661.64
concrete in Item 14.1(C) by using batching plant,
excluding formwork i.e. per cum basic cost (a+b+c)
No. of vertical posts = (12 + 2)2 = 28 Nos., External
area of vertical post 0.25x0.275 = 0.069sqm, Concrete
in vehicle posts = 0.069 x 28 = 1.932 cum, Hand rail in
3 tiers = 3 x 24 = 72 m, External area = 0.170 x 0.175
= 0.03 sqm, Concrete in hand rails = 0.03 x 72 = 2.16
cum, Total Concrete = 1.932 + 2.16 = 4.092 cum.
(Refer MoRTH SD / 202).

Add 12 per cent of above cost for form work. 1759.40


HYSD bar reinforcement Rate as per item No tonne 0.87 49895.00 43159.18
14.2(Excluding OH & CP)
refer MoRTH SD / 202.
b) Overhead charges @ 14.615% on (a) 8707.65
c) Contractor's profit @ 10% on (a+b) 6828.79
Rate for 48 m (a+b+c) 75116.64
Rate per metre (a+b+c)/48 1564.93
say 1565.00
g) seiniorage charges per cum 117.33
Rate per cum say 117.33

f) Lead charges for material 820.35


TOTAL Rate 2502.60
Total 2503.00

Note 1. Quantities of material have been adopted from standard


plans of MoRTH vide drawing no. SD/202.
2. 48 m length is the total linear length adding both sides of
24 m span.
14.8 2703.2 & Providing, fitting and fixing mild steel railing complete
1900 as per drawing and Technical Specification

Unit = 1 RM
Taking output = 2 x 50 m span = 100 m
a) Material:
1) ISMC 100 = 2.806 x 1.05 = 2.946 MT tonne 2.95 42000.00 123732.00
2) MS Flat = 0.964 x 1.05 = 1.012 MT tonne 1.01 42000.00 42504.00
3) MS bars = 0.17 x 1.05 = 0.180 MT tonne 0.18 42000.00 7560.00
4) MS bolts, nuts and washers tonne 0.15 85000 12750.00

Add @ 5 per cent of cost of material for painting one 9327.30


shop coat with red oxide primer and three coats of
synthetic enamel paint and consumables to safeguard
against weathering and corrosion.
Add for cost of concrete for fixing vertical posts in the 1865.46
performed recess @ 1 per cent of cost of material.

Add for electricity charges, welding and drilling 1865.46


equipment, electrodes and other consumables @ 1
per cent of cost of material.
b) Labour

SOR 2018-19 (15% OH) BRIDGES - SUPER STRUCTURE

RA - 155
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Mate day 2.80 451.00 1262.80
Mazdoor (Skilled) day 30.00 515.00 15450.00
Mazdoor day 40.00 400.00 16000.00
c) Overhead charges @ 14.615% on (a+b) 33953.13
d) Contractor's profit @ 10% on (a+b+c) 26627.02
Cost for 100 m steel railing = a+b+c+d 292897.17
Rate per metre (a+b+c+d)/100 2928.97
Total 2929.00
14.9 2705 Drainage Spouts complete as per drawing and
Technical specification
Unit = 1 No.
Taking output = 1 No.
a) Material
Corrosion resistant Structural steel including 5 per cent Kg 4.00 50.14 200.55
wastage
GI pipe 100mm dia metre 2.00 253.00 506.00
GI bolt 10 mm Dia each 6.00 19.00 114.00
Galvanised MS flat clamp each 2.00 165.00 330.00
b) Labour
For fabrication
Mate day 0.02 451.00 9.02
Skilled (Blacksmith, welder etc.) day 0.02 482.20 9.64
Mazdoor day 0.02 400.00 8.00
For fixing in position
Mate day 0.01 451.00 4.51
Mason day 0.01 455.00 4.55
Mazdoor day 0.20 400.00 80.00
Add @ 5 per cent of cost of material and labour for 63.31
electrodes, cutting gas, sealant, anti-corrosive
bituminous paint, mild steel grating etc.
c) Overhead charges @ 14.615% on (a+b) 194.32
d) Contractor's profit @ 10% on (a+b+c) 152.39
Rate per metre (a+b+c+d) 1676.30
Total 1676.00
Note 1. In case of viaducts in urban areas, the drainage spouts
should be connected with suitably located pipelines to
discharge the surface run-off to drains provided at ground
level.
2. In case of bridges, sufficient length of G.I Pipe shall be
provided to ensure that there is no splashing of water from
the drainage spout on the structure.
14.10 2700 PCC M15 Grade leveling course below approach slab
complete as per drawing and Technical specification

Unit = 1 cum
Taking output = 1 cum
Material
Concrete, Rate as per item No. 12.8 (A) excluding cum 1.00 3309.00 3309.00
formworks
c) Overhead charges @ 14.615% on (a+b) 483.61
d) Contractor's profit @ 10% on (a+b+c) 379.26
Rate per cum say 4171.87
e) seiniorage charges as per item 12.8 (A) 117.00
Rate per cum say 117.00

f) Lead charges for Material as per item 12.8(A) 816.32


TOTAL Rate 5105.19
Total 5105.00
14.11 1500,160 Reinforced cement concrete approach slab including
0,1700 & reinforcement and formwork complete as per drawing
2704 and Technical specification
Unit = 1 cum

SOR 2018-19 (15% OH) BRIDGES - SUPER STRUCTURE

RA - 156
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Taking output = 1 cum
a) Material
Cement concreteM30 Grade Refer relevant item of cum 1.00 3649.00 3649.00
concrete in item 12.8(G)by using batching plant,
excluding formwork i.e. per cum basic cost (a+b+c)
(Excluding OH & CP)
( Refer relevant item of concrete in item No. 13.8 (G) 72.98
except that form work may be added at the rate of 2
per cent of cost against 3.5 per cent provided in the
foundation concrete.
HYSD bar reinforcement Rate as per item No tonne 0.05 49895.00 2494.75
14.2(Excluding OH & CP)
b) Overhead charges @ 14.615% on (a) 908.58
c) Contractor's profit @ 10% on(a+b) 712.53
Rate per cum (a+b+c) 7837.84
say 7838.00
d) seiniorage charges as per item 12.8 (G) 117.00
Rate per cum say 117.00

e) Lead charges for Material as per item 12.8(G) 816.32


TOTAL Rate 8771.15
Total 8771.00

Note The grade of reinforced cement concrete may be adopted


as M30 for severe conditions and M25 for moderate
conditions.
14.16 800 Painting on concrete surface
Providing and applying 2 coats of water based cement
paint to unplastered concrete surface after cleaning the
surface of dirt, dust, oil, grease, efflorescence and
applying paint @ of 1 litre for 2 sqm.

Unit = sqm
Taking output = 10 sqm
a) Labour
Mate day 0.01 451.00 4.51
Painter day 0.25 473.00 118.25
Mazdoor (Skilled) day 0.25 515.00 128.75
b) Material
Water based paint of approved quality for cement Litres 5.00 51.00 255.00
concrete surface
c) Overhead charges @ 14.615% on (a+b) 74.03
d) Contractor's profit @ 10% on (a+b+c) 58.05
Cost for 10 sqm (a+b+c+d) 638.59
Rate per sqm (a+b+c+d)/10 63.86
Total 64.00
14.22 2607 Strip Seal Expansion Joint
Providing and laying of a strip seal expansion joint
catering to maximum horizontal movement upto 70 mm,
complete as per approved drawings and standard
specifications to be installed by the
manufacturer/supplier or their authorised
representative ensuring compliance to the
manufacturer's instructions for installation.
Unit = Running meter
Taking output = 12 m
a) Labour
Mate day 0.05 451.00 22.55
Mazdoor day 1.00 400.00 400.00
Mazdoor (Skilled) day 0.25 515.00 128.75
b) Material

SOR 2018-19 (15% OH) BRIDGES - SUPER STRUCTURE

RA - 157
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Supply of complete assembly of strip seal expansion metre 12.00 4200.00 50400.00
joint comprising of edge beams, anchorage, strip seal
element and complete accessories as per approved
specifications and drawings.

Add 5 per cent of cost of material for anchorage 2547.57


reinforcement, welding and other incidentals.
c) Overhead charges @ 14.615% on (a+b) 7818.86
d) Contractor's profit @ 10% on (a+b+c) 6131.77
Cost for 12 m = (a+b+c+d) 67449.50
Rate per m = (a+b+c+d)/12 5620.79
Total 5621.00
Note 1. The installation shall be done by the manufacturer or his
authorised representative to the satisfaction of the Engineer.

2. The concreting for joining the expansion joint assembly


with the deck has not been included in this analysis as the
same is catered in the quantities of RCC deck.

14.23 2600 Modular Strip / Box Seal Joint


Providing and laying of a modular strip Box seal
expansion joint including anchorage catering to a
horizontal movement beyond 70 mm and upto 140mm,
complete as per approved drawings and standard
specifications to be installed by the
manufacturer/supplier or their authorised
representative ensuring compliance to the
manufacturer's instructions for installation.
Unit = Running meter
Taking output = 12 m
a) Labour
Mate day 0.056 451.00 25.26
Mazdoor day 1.00 400.00 400.00
Mazdoor (Skilled) day 0.40 515.00 206.00
b) Material
Supply of a modular strip/box seal joint assembly metre 12.00 input #VALUE!
comprising of edge beams, central beam,2 modules
chloroprene seal, anchorage elements, support and
control system, all steel sections protected against
corrosion and installed by the manufacturer or his
authorised representative.
c) Overhead charges @ 14.615% on (a+b) #VALUE!
d) Contractor's profit @ 10% on (a+b+c) #VALUE!
Cost for 12 m Modular strip/box seal joint = (a+b+c+d) #VALUE!
Rate per m = (a+b+c+d)/12 #VALUE!
Total #VALUE!
Note 1. The installation shall be done by the manufacturer or his
authorised representative to the satisfaction of the Engineer.

2. The concreting for joining the expansion joint assembly


with the deck has not been included in this analysis as the
same is catered in the quantities of RCC deck.

3. The anchoring bars of the expansion joint assembly shall


be welded to the main reinforcement of the deck.
14.24 2600 Modular Strip / Box Seal Joint
Providing and laying of a modular strip box seal
expansion joint catering to a horizontal movement
beyond 140mm and upto 210mm, complete as per
approved drawings and standard specifications to be
installed by the manufacturer/supplier or their
authorised representative ensuring compliance to the
manufacturer's instructions for installation.
Unit = Running meter

SOR 2018-19 (15% OH) BRIDGES - SUPER STRUCTURE

RA - 158
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Taking output = 12 m
a) Labour
Mate day 0.07 451.00 31.57
Mazdoor day 1.25 400.00 500.00
Mazdoor (Skilled) day 0.50 515.00 257.50
b) Material
Supply of a modular box/box seal joint assembly metre 12.00 input #VALUE!
containing 3 modules/cells and comprising of edge
beams, two central beams, chloroprene seal,
anchorage elements, support and control system, all
steel sections protected against corrosion and installed
by the manufacturer or his authorised representative.

c) Overhead charges @ 14.615% on (a+b) #VALUE!


d) Contractor's profit @ 10% on (a+b+c) #VALUE!
Cost for 12 m Modular strip/box seal joint = (a+b+c+d) #VALUE!
Rate per m = (a+b+c+d)/12 #VALUE!
Total #VALUE!
Note 1. The installation shall be done by the manufacturer or his
authorised representative to the satisfaction of the Engineer.

2. The concreting for joining the expansion joint assembly


with the deck has not been included in this analysis as the
same is catered in the quantities of RCC deck.

3. The anchoring bars of the expansion joint assembly shall


be welded to the main reinforcement of the deck.

SOR 2018-19 (15% OH) BRIDGES - SUPER STRUCTURE

RA - 159
CHAPTER - 15
RIVER TRAINING AND PROTECTION WORKS
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
15.1 2503 Providing and laying boulders apron on river bed for
protection against scour with stone boulders weighing
not less than 40 kg each complete as per drawing and
Technical specification.
A Boulder Laid Dry Without Wire Crates.
Unit = cum
Taking output = 1 cum
a) Material
Stone cum 1.00 233.80 233.80
Stone Spalls cum 0.20 110.00 22.00
b) Labour
Mate day 0.04 451.00 18.04
Mason day 0.35 455.00 159.25
Mazdoor * day 0.75 400.00 300.00
c) Overhead charges @ 14.615% on (a+b) 107.14
d) Contractor's profit @ 10% on (a+b+c) 84.02
Rate per cum = (a+b+c+d) 924.25
say 924.00
e) seiniorage charges per cum
Stone cum 1.00 75.00 75.00
Stone Spalls cum 0.20 75.00 15.00
Add District Mineral Fund (DMF) 30% on Seinorage 0.300 90.00 27.00
charges
Add lead charges of metal 25.00 Km 1.20 504.25 605.10
Total rate 1646.35
Rate per cum Total 1646.00
* Including excavation for trimming for preparation of bed.
Note Nominal excavation required for preparation of bed has
been taken into account while making provision for labour.

15.3 2503 Cement Concrete Blocks (size 0.5 x 0.5 x 0.5 m)


Providing and laying of apron with cement concrete blocks
of size 0.5x0.5x0.5 m cast in-situ and made with nominal
mix of M-15 grade cement concrete with a minimum cement
content of 250 kg/cum as per IRC: 21-2000.

Unit = cum
Taking out put = 1 cum
Concrete Grade M15 Rate as per item No. 12.8 (A) cum 1.00 5272.00 5272.00
including OH & CP
Add 2 per cent of cost to account for excavation for 105.44
preparation of bed, nominal surface reinforcement and
filling of granular material in recesses between blocks.

Rate per cum 5377.44


Total 5377.00
15.4 2504 Providing and laying Pitching on slopes laid over
prepared filter media including boulder apron laid dry in
front of toe of embankment complete as per drawing
and Technical specifications
A Stone/Boulder
Unit = cum
Taking output = 1 cum
a) Material
Stone weighing not less than 40kg cum 1.00 233.80 233.80
Stone spalls of minimum 25 mm size cum 0.20 110.00 22.00
b) Labour
Mate day 0.04 451.00 18.04
Mason day 0.35 455.00 159.25
Mazdoor day 0.75 400.00 300.00
c) Overhead charges @ 14.615% on (a+b) 107.14
d) Contractor's profit @ 10% on (a+b+c) 84.02
Rate per cum = (a+b+c+d) 924.25
say 924.00

SOR 2018-19 (15% OH) BRIDGES - PROTECTION WORKS

RA - 160
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
e) seiniorage charges per cum
Stone cum 1.00 75.00 75.00
Stone Spalls cum 0.20 75.00 15.00
Add District Mineral Fund (DMF) 30% on Seinorage 0.300 90.00 27.00
charges
say 117.00
Add lead charges of metal 25.00 Km 1.20 504.25 605.10
Total rate 1646.35
Rate per cum Total 1646.00

15.4 B Cement Concrete Blocks of size 0.3x0.3 x0.3 m cast in


cement concrete of Grade M15
Unit = cum
Taking output = 1 cum
Concrete Grade M15 Rate as per item No. 12.8 (A) cum 1.00 5272.00 5272.00

Add 2 per cent of cost to account for nominal surface 105.44


reinforcement and filling of granular material in
recesses between blocks.
Rate per cum 5377.44
Total 5377.00
15.5 2504 Providing and laying Filter material underneath pitching
in slopes complete as per drawing and Technical
specification
Unit = cum
Taking output = 1 cum
a) Material
Graded stone aggregate of required size cum 1.20 597.90 717.48
b) Labour
Mate day 0.05 451.00 22.55
Mazdoor (Skilled) day 0.25 515.00 128.75
Mazdoor * day 1.00 400.00 400.00
c) Overhead charges @ 14.615% on (a+b) 185.43
d) Contractor's profit @ 10% on (a+b+c) 145.42
Rate per cum = (a+b+c+d) 1599.63
say 1600.00
e) seiniorage charges per cum
Stone cum 1.20 75.00 90.00
Add District Mineral Fund (DMF) 30% on Seinorage 0.300 90.00 27.00
charges
Add lead charges of metal 25.00 Km 1.20 504.25 605.10
Total rate 2321.73
Rate per cum Total 2322.00

Includes Mazdoor required for trimming of slope to proper


profile and preparation of bed.
15.10 2507.2 Curtain wall complete as per drawing and Technical
specification
A Stone masonry in cement mortar (1:3)
Coursed rubble masonry (1st sort) cum 1.00 7099.00 7099.00

Rate same as per item No. 12.7 (A) including OH & CP

Rate per cum total 7099.00


or
15.10 B Cement concrete Grade M15
Concrete Grade M15 Rate as per item No. 12.8 (A) cum 1.00 5272.00 5272.00
including OH & CP
Rate per cum say 5272.00
Total 5272.00
Note Other items like excavation for foundation, filling behind wall,
filter media, weep holes etc. shall be added separately as
per approved design.

SOR 2018-19 (15% OH) BRIDGES - PROTECTION WORKS

RA - 161
RATES OF CONVEYANCE OF MATERIALS INCLUDING LOADING AND UNLOADING -- BRIDGE WORKS

SURFACED ROADS UNSURFACED ROADS KATCHA ROADS


BEYOND 1
UPTO 1 KM BEYOND 1 KM UPTO 1 KM BEYOND 1 KM UPTO 1 KM
KM
S.NO DESCRIPTION OF THE ITEM INCLUDING INCLUDING INCLUDING INCLUDING INCLUDING
INCLUDING
CP & OH CP & OH PER CP & OH CP & OH PER CP & OH PER
CP & OH
PER CUM CUM PER CUM CUM CUM
PER CUM

1 METAL / STONE / RUBBLE STONE 205.45 12.45 207.85 14.85 223.00 30.00

2 EARTH / GRAVEL / SAND 207.94 14.94 210.82 17.82 229.00 36.00

3 BITUMEN / LUBRICANTS 2.08 2.08 2.08 2.08 2.08 2.08

SOR 2018-19 (15% OH) BRIDGES - CONVEYANCE

RA - 162
Rates of Material for the Year 2018-19

DEDUC
INITIAL RATE T MACHINE SEIGNO Total Rate as
S. excluding STACKI CRUSHING BLASTING RAGE per SSR 2018-
DESCRIPTION OF THE MATERIAL UNIT
NO stacking NG CHARGES CHARGES CHARGE 19 excluding
charges CHARG @ 25% S Taxes
ES
1 40 mm SS 5 metal (IS383,1970) Cum 590.4 147.60 70.00 808.00
2 20 mm SS 5 metal (IS383,1970) Cum 986.40 246.60 70.00 1303.00
3 25 mm SS 5 metal (IS383,1970) Cum 947.2 236.80 70.00 1254.00
4 10 mm SS 5 metal (IS383,1970) Cum 659.20 164.80 70.00 894.00
5 6 mm SS 5 metal (IS383,1970) Cum 506.4 126.60 70.00 703.00
6 Gravel Cum 110.00 110.00
7 Sand for mortar (Concrete) Cum 182 182.00
8 Sand for filling, blindage Cum 100 100.00
9 12 mm SS 5 metal (IS383,1970) Cum 782.4 195.60 70.00 1048.00
10 RR masonary (Granite) Cum 240 70.00 310.00
11 CR masonary (Granite) Cum 274.3 70.00 344.30
Stone boulder of size 150 mm size
90.50
12 Cum 70.00 160.50
Stone boulder of size 150-200mm size
168.55
13 Cum 70.00 238.55
163.80
14 Stone boulder of size 300 mm size Cum 70.00 233.80
Stone dust (HBG stone chips 2.36 mm
333.00
15 and below) Cum 333.00
16 Sand for mortar Cum 182 182.00
17 Bulk Bitumen Grade 30/40 mt 33760.00 33760.00
18 Bulk Bitumen Grade 80/100 mt 31690.00 31690.00
19 Modified Bitumen CRMB55 mt 33670.00 33670.00
20 Bitumen emulsion (Bulk) mt 35790.00 35790.00
21 Cement mt 3900.00 3900.00
22 Fe 500 steel mt 42500.00 42500.00
23 Mild steel rods mt 39674.00 39674.00
24 Structural steel mt 42000.00 42000.00
25 HT wire 4mm mt 35556.00 35556.00
26 40 mm metal (hand broken) Cum 580.50 70.00 650.50
27 Moorum at Site Cum 185.00 185.00
28 2.36mm to 5mm metal (IRC-MORTH) Cum 293.35 73.3375 70.00 436.69

SOR 2018-19 (15% OH) BRIDGES - RMR

RA - 163
RA - 164
Khammam - Devarapalli (NH-365BB)
LEAD CALCULATION FOR PACKAGE V (KM 132+664 to KM 162+126, LENGTH = 29.462 KM )

Sand (Chidipi Sand) Metal (Doddukuru Crusher)


Cart Track 1.0 Km Cart Track to Doddukuru 1.0 Km
Chidipi to Kapavaram 9.0 Km Doddukuru to Project End at D.Ch 162+126 9.0 Km
Kapavaram to Project End 16.0 Km Project End at D.Ch 162+126 to Plant at D.Ch 147+400 14.7 Km
Project End at D.Ch 162+126 to Plant at D.Ch 147+400 14.7 Km Total 25.0 Km
Total 41.0 Km

Bitumen Flyash (Kothagudem PP)


Vizag to Project End at D.Ch 162+126 235.0 Km Cart Track 4.0 Km
Project End at D.Ch 162+126 to Plant at D.Ch 147+400 14.7 Km Kothagudem Power plant to D.Ch 62+740 on NH-30 65.3 Km
Total 250.0 Km D.Ch 62+740 to Plant at D.Ch 147+400 84.7 Km
Total 154.0 Km

Hume Pipes (Kovvuru)


Cart Track 2.5 Km Gravel / Murrum
Kovvuru to Project End at D.Ch 162+126 24.0 Km Average Lead 5.0 Km
Project End at D.Ch 162+126 to Plant at D.Ch 147+400 14.7 Km Total 5.0 Km
Total 41.0 Km

Hot Mix Plant to Site


Cart track 0.5 Km
Project Stretch 7.4 Km
Total 8.0 Km

RA - 165
RA - 166
KHAMMAM- DEVARAPALLI PROJECT

Pathipaka
Crusher 11.00 Km Bhadrachalam
Sand

6.0 Km

8.00 Km

NH-30
6.0 Km Mallampally
WARANGAL Palwancha
Km
Crusher
NH-365

Kothagudem
Power Plant
3 0.5
10 5
36 Km

4 Km
5.50 Km
NH
m Kuravi 3.5Km
2 0K
65

Pipes
Balaji
Maripeda H3 1.

10.00
N Garloddu Km 00

Km
Crusher
13.00 Km

6.00
Mulakalapally Kothagudem Km

Km
Crusher Chidipi Sand

.00
SH-3

1.00

64

D.Ch: 89+874
17.50 Km

P-4 CMP P-5 CMP

55.30 Km
Km
SH-12
Km 30

NH-30

9.00 Km
3.

D.Ch-0+000 118+950 147+400 D.Ch-162+126


Km

PROJECT PROJECT
.40

START D.Ch: END 16.00 Km


VIZAG
13

7.00
D.Ch: 33+240 D.Ch: 0.50 Km 0.50 Km 9.00 Km Km
6+240 38+040 15.00

2.00
0.50 Km D.Ch: 0.50

Km
0.50 Km D.Ch: D.Ch:

Devarapalli
0.50 Km

RAJAHMUNDRY
22.00

SURYAPET Km Km
Km

62+740 118+950 147+400

ANDHRA PRADESH
Km

Kapavaram
00 VIZAG
NH-365A
28.800 Km

Bonakalu .
P-1 CMP 22

Duddukuru
P-2 CMP P-3 CMP BITUMEN

Kovvuru
9.00
Km

16+800

TELANGANA

Crusher
48+350 84+200 (235 Km)

Pipes
61.00 Km
NH-30

Lingala Nallajarla
0 Sand
5.00 Km 1.0 m
KODAD K
NH-65 1.50 G. Kodudru
Km Km
Crusher 0 6
.0 -1
64
6.00 NH
Dorakunta Km
Crusher
15.00
NH-30

Km Hanuman
K

0
33.0
m

Vijayawada
-16 Junction
Power Plant 29.00 K
m NH QUARRY CHART
2.5 Vijayawada
Km NH-65

RA - 167

You might also like