Professional Documents
Culture Documents
Rate Analysis
Prices of Bitumen
Applicable from December 16, 2018
Bitumen Grades
BITUMEN (BULKED)
KOCHI 32390
BITUMEN (PACKED)
KOCHI 35690
Note:
(1) The above prices are in Rs. Per MT
(2) The above prices are exclusive of GST.
PREVIOUS PRICES
RA - 1
Prices of Emulsion
Applicable from December 16, 2018
Cities Prices
EMULSION (BULK)
HALDIA 26200
EMULSION (PACKED)
Note:
(1) The above prices are in Rs. Per MT
(2)The above prices are exclusive of GST.
PREVIOUS PRICES
RA - 2
Prices of CRMB/MT
Applicable from December 16, 2018
Cities Prices
CRMB (BULK)
CRMB-55 CRMB-60
CRMB (PACKED)
CHENNAI 36320
Note:
(1) The above prices are in Rs. Per MT
(2) The above prices are exclusive of GST.
PREVIOUS PRICES
RA - 3
RA - 4
RA - 5
RA - 6
RA - 7
RA - 8
CHAPTER-2
SITE CLEARANCE
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
2.1 201 Cutting of Trees, including cutting of Trunks, Branches
and Removal
Cutting of trees, including cutting of trunks, branches and
removal of stumps, roots, stacking of serviceable material
with all lifts and up to a lead of 1000 metres and earth filling
in the depression/pit.
Unit = Each
(i) Girth from 300 mm to 600 mm
a) Labour
Mate day 0.020 451.00 9.02
Mazdoors for cutting trees including cutting, refilling, day 0.600 400.00 240.00
compaction of backfilling and stacking of serviceable
materials within 1000 metres lead by manual means.
b) Machinery
Tractor-trolley hour 0.100 413.60 41.36
c) Overhead charges @ 2.615% on (a+b) 7.59
d) Contractor's profit @ 10% on (a+b+c) 29.80
Rate for each tree = a+b+c+d 327.77
say 328.00
2.1 (ii) Girth from 600 mm to 900 mm
a) Labour
Mate day 0.040 451.00 18.04
Mazdoors for cutting trees including cutting, refilling, day 0.900 400.00 360.00
compaction of backfilling, and stacking of serviceable
materials within 1000 metres lead by manual means
b) Machinery
Tractor-trolley hour 0.300 413.60 124.08
c) Overhead charges @ 2.615% on (a+b) 13.13
d) Contractor's profit @ 10% on (a+b+c) 51.53
Rate for each tree = a+b+c+d 566.78
say 567.00
2.1 (iii) Girth from 900 mm to 1800 mm
a) Labour
Mate day 0.080 451.00 36.08
Mazdoors for cutting trees including cutting, refilling, day 2.000 400.00 800.00
compaction of backfilling and stacking of serviceable
materials within 1000 metres
b) Machinery
Tractor-trolley hour 0.400 413.60 165.44
c) Overhead charges @ 2.615% on (a+b) 26.19
d) Contractor's profit @ 10% on (a+b+c) 102.77
Rate for each tree = a+b+c+d 1130.48
say 1130.00
2.1 (iv) Girth above 1800 mm
a) Labour
Mate day 0.160 451.00 72.16
Mazdoors for cutting trees including cutting, refilling, day 4.000 400.00 1600.00
compaction of backfilling and stacking of serviceable
materials within 1000 metres
b) Machinery
Tractor-trolley hour 0.600 413.60 248.16
c) Overhead charges @ 2.615% on (a+b) 50.22
d) Contractor's profit @ 10% on (a+b+c) 197.05
Rate for each tree = a+b+c+d 2167.59
say 2168.00
2.3 201 Clearing and Grubbing Road Land .
RA - 9
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Clearing and grubbing road land including uprooting rank
vegetation, grass, bushes, shrubs, saplings and trees girth
up to 300 mm, removal of stumps of trees cut earlier and
disposal of unserviceable materials and stacking of
serviceable material to be used or auctioned, up to a lead of
1000 metres including removal and disposal of top organic
soil not exceeding 150 mm in thickness.
Unit = Hectare
Taking output = 1 Hectare
2.3 (ii) By Mechanical Means
A In area of light jungle
a) Labour
Mate day 0.160 451.00 72.16
Mazdoor day 4.000 400.00 1600.00
b) Machinery
Dozer 80 HP with attachment for removal of trees & hour 10.000 2454.60 24546.00
stumps
Tractor-trolley hour 1.000 413.60 413.60
c) Overhead charges @ 2.615% on (a+b) 696.42
d) Contractor's profit @ 10% on (a+b+c) 2732.82
Rate per Hectare = a+b+c+d 30061.00
say 30061.00
2.3 (ii) B In area of thorny jungle
a) Labour
Mate day 0.240 451.00 108.24
Mazdoor day 6.000 400.00 2400.00
b) Machinery
Dozer 80 HP with attachment for removal of trees & hour 12.000 2454.60 29455.20
stumps
Tractor-trolley hour 1.500 413.60 620.40
c) Overhead charges @ 2.615% on (a+b) 852.07
d) Contractor's profit @ 10% on (a+b+c) 3343.59
Rate per Hectare = a+b+c+d 36779.50
say 36779.00
2.4 202 Dismantling of Structures
Dismantling of existing structures like culverts, bridges,
retaining walls and other structure comprising of masonry,
cement concrete, wood work, steel work, including T&P and
scaffolding wherever necessary, sorting the dismantled
material, disposal of unserviceable material and stacking the
serviceable material with all lifts and lead of 1000 metres
Unit = cum
Taking output = 1.25 cum
(i) Lime /Cement Concrete
2.4 II By Mechanical Means for items No. 202( b)& ( c)
A Cement Concrete Grade M-15 & M-20
a) Labour
Mate day 0.020 451.00 9.02
Mazdoor for loading and unloading day 0.250 400.00 100.00
Mazdoor with Pneumatic breaker day 0.250 440.00 110.00
b) Machinery
Air Compressor 250 cfm with 2 leads of pneumatic hour 0.670 556.50 372.86
breaker @ 1.5 cum per hour
Tractor-trolley hour 0.270 413.60 111.67
c) Overhead charges @ 2.615% on (a+b) 18.40
d) Contractor's profit @ 10% on (a+b+c) 72.19
Cost for 1.25 cum = a+b+c+d 794.14
Rate per cum = (a+b+c+d)/ 1.25 635.31
say 635.00
2.5 202 Dismantling of Flexible Pavements
RA - 10
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Dismantling of flexible pavements and disposal of dismantled
materials up to a lead of 1000 metres, stacking serviceable
and unserviceable materials separately
Unit = cum
Taking output = 1 cum
I By Manual Means
A Bituminous courses
a) Labour
Mate day 0.060 451.00 27.06
Mazdoor for dismantling, loading and unloading day 1.500 400.00 600.00
b) Machinery
Tractor-trolley hour 0.380 413.60 157.17
c) Overhead charges @ 2.615% on (a+b) 20.51
d) Contractor's profit @ 10% on (a+b+c) 80.47
Rate per cum = a+b+c+d 885.21
say 885.00
2.5 I B Granular courses
a) Labour
Mate day 0.040 451.00 18.04
Mazdoor for dismantling, loading and unloading. day 1.000 400.00 400.00
b) Machinery
Tractor-trolley hour 0.330 413.60 136.49
c) Overhead charges @ 2.615% on (a+b) 14.50
d) Contractor's profit @ 10% on (a+b+c) 56.90
Rate per cum = a+b+c+d 625.93
say 626.00
2.5 II By Mechanical Means
A Bituminous course
a) Labour
Mate day 0.010 451.00 4.51
Mazdoor day 0.300 400.00 120.00
b) Machinery
Tractor-trolley hour 0.380 413.60 157.17
Farm tractor with ripper @ 60 cum per hour hour 0.017 423.60 7.20
c) Overhead charges @ 2.615% on (a+b) 7.55
d) Contractor's profit @ 10% on (a+b+c) 29.64
Rate per cum = a+b+c+d 326.08
say 326.00
2.10 202 Dismantling of Kilometre Stone
Dismantling of kilometre stone including cutting of earth,
foundation and disposal of dismantled material with all lifts
and lead upto 1000 m and back filling of pit.
Unit = Each
Taking output = one KM stone
A 5th KM stone
Quantity of cement concrete = 0.392 cum
a) Labour
Mate day 0.130 451.00 58.63
Mazdoor day 0.750 400.00 300.00
b) Machinery
Tractor-trolley hour 0.150 413.60 62.04
c) Overhead charges @ 2.615% on (a+b) 11.00
d) Contractor's profit @ 10% on (a+b+c) 43.17
Rate for one 5th KM stone = a+b+c+d 474.84
say 475.00
B Ordinary KM Stone
Quantity of cement concrete = 0.269 cum
a) Labour
Mate day 0.020 451.00 9.02
Mazdoor day 0.500 400.00 200.00
b) Machinery
RA - 11
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Tractor-trolley hour 0.300 413.60 124.08
c) Overhead charges @ 2.615% on (a+b) 8.71
d) Contractor's profit @ 10% on (a+b+c) 34.18
Rate for one ordinary KM stone = a+b+c+d 375.99
say 376.00
C Hectometre Stone
Quantity of cement concrete = 0.048 cum
a) Labour
Mate day 0.004 451.00 1.80
Mazdoor day 0.100 400.00 40.00
b) Machinery
Tractor-trolley hour 0.020 413.60 8.27
c) Overhead charges @ 2.615% on (a+b) 1.31
d) Contractor's profit @ 10% on (a+b+c) 5.14
Rate for one Hectometre stone = a+b+c+d 56.52
say 57.00
RA - 12
CHAPTER - 3
EARTH WORK, EROSION CONTROL AND DRAINAGE
Ref. to
MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
3.3 301 Excavation in Soil with Dozer with lead up to 100 metres
RA - 13
Ref. to
MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Hydraulic excavator 0.9 cum bucket capacity @ 60 cum hour 6.000 2791.60 16749.60
per hour
Tipper 5.5 cum capacity, 4 trips per hour. hour 0.000 950.30 0.00
c) Overhead charges @ 2.615% on (a+b) 459.87
d) Contractor's profit @ 10% on (a+b+c) 1804.55
add Seigniorage charges cum 0.000 30.00 0.00
Add District Mineral Fund (DMF) 30% on Seinorage 0.300 0.00 0.00
charges
Cost for 360 cum = a+b+c+d 19850.10
Rate per cum = (a+b+c+d)/360 55.14
say 55.00
3.7 301 Excavation in Ordinary Rock using Hydraulic Excavator
CK-90 and Tippers with Disposal upto 1000 metres.
RA - 14
Ref. to
MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Rate per cum = (a+b+c+d)/36 740.44
say 740.00
Note 1. The quality and availability of rock shall be checked before
affording credit.
2. In case some rock is issued to the contractor at site,
the item of carriage shall be restricted/reduced to that
extent.
3.Being small quantity, manual loading will be economical in
this case and has been provided accordingly.
Tipper 5.5 cum capacity, 4 trips per hour. hour 16.360 950.30 15546.91
c) Overhead charges @ 2.615% on (a+b) 866.42
d) Contractor's profit @ 10% on (a+b+c) 3399.90
add Seigniorage charges cum 0.000 30.00 0.00
Add District Mineral Fund (DMF) 30% on Seinorage 0.300 0.00 0.00
charges
Cost for 360 cum = a+b+c+d 37398.91
Rate per cum = (a+b+c+d)/360 103.89
say 104.00
RA - 15
Ref. to
MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Note This item does not include replacement of unsuitable soil by
suitable soil. Replacement, where required, is to be provided
and paid separately under clause 305.
3.15 305.4.3 Scarifying Existing Bituminous Surface to a depth of 50
mm by Mechanical Means
Scarifying the existing bituminous road surface to a depth of
50 mm and disposal of scarified material with in all lifts and
lead upto 1000 metres.
Unit = sqm
Taking output = 100 sqm
a) Labour
Mate day 0.010 451.00 4.51
Mazdoor day 0.250 400.00 100.00
b) Machinery
Tractor with ripper attachment @ 60 cum per hour hour 0.080 423.60 33.89
Front end loader 1 cum bucket capacity @ 25 cum per hour 0.200 1594.70 318.94
hour
Tipper 5.5 cum capacity, 4 trips per hour. hour 0.230 950.30 218.57
c) Overhead charges @ 2.615% on (a+b) 17.67
d) Contractor's profit @ 10% on (a+b+c) 69.36
Cost for 100 sqm = a+b+c+d 762.94
Rate per sqm = (a+b+c+d)/100 7.63
say 8.00
3.16 305 Construction of Embankment with Material obtained
from Borrowpits
Construction of embankment with approved material
obtained from borrow pits with all lifts and leads, transporting
to site, spreading, grading to required slope and compacting
to meet requirement of table 300-2.
Unit = cum
Taking output = 100 cum
a) Labour
Mate day 0.040 451.00 18.04
Mazdoor day 1.000 400.00 400.00
b) Machinery
Hydraulic Excavator1 cum bucket capacity @ 60 cum hour 1.670 2791.60 4661.97
per hour
Tipper 10 tonne capacity tonne.km 160 x L 6.56 5245.66
RA - 16
Ref. to
MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
3.17 305 Construction of Embankment with Material Deposited
from Roadway Cutting
Construction of embankment with approved materials
deposited at site from roadway cutting and excavation from
drain and foundation of other structures graded and
compacted to meet requirement of table 300-2.
Unit = cum
Taking output = 100 cum
a) Labour
Mate day 0.020 451.00 9.02
Mazdoor day 0.500 400.00 200.00
b) Machinery
Dozer 80 HP for spreading @ 200 cum per hour hour 0.500 2454.60 1227.30
Motor grader for grading @ 100 cum per hour hour 1.000 3020.40 3020.40
Water tanker6 KL capacity hour 4.000 655.20 2620.80
Vibratory roller 8-10 tonnes @ 100 cum per hour hour 1.000 2736.20 2736.20
c) Material
Cost of water KL 24.000 77.00 1848.00
d) Overhead charges @ 2.615% on (a+b+c) 304.95
e) Contractor's profit @ 10% on (a+b+c+d) 1196.67
Rate for 100 cum = a+b+c+d+e 13163.34
Rate per cum = (a+b+c+d+e)/100 131.63
say 132.00
Note In case the earth cutting is done by dozer and pushed for
filling in the embankment, the input of dozer in the cost of
embankment shall be deleted as the same is already
provided in the cost of excavation. However, if the earth is
dumped by tippers from roadway cutting, the input of dozer
for spreading is required to be provided.
3.18 305 Construction of Subgrade and Earthen Shoulders
Construction of sub-grade and earthen shoulders with
approved material obtained from borrow pits with all lifts &
leads, transporting to site, spreading, grading to required
slope and compacted to meet requirement of table No. 300-2
Unit = cum
Taking output = 100 cum
a) Labour
Mate day 0.040 451.00 18.04
Mazdoor day 1.000 400.00 400.00
b) Machinery
Hydraulic excavator1 cum bucket capacity @ 60 cum hour 1.670 2791.60 4661.97
per hour
Tipper 10 tonne capacity tonne.km 175xL 6.56 5737.44
RA - 17
Ref. to
MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
3.22 307 Turfing with Sods
Furnishing and laying of the live sods of perennial turf
forming grass on embankment slope, verges or other
locations shown on the drawing or as directed by the
engineer including preparation of ground, fetching of sods
and watering.
Unit = sqm
Taking output = 100 sqm
a) Labour
Mate day 0.120 451.00 54.12
Mazdoor for preparation of ground and fetching of sods 400.00
day 3.000 1200.00
b) Machinery
Water tanker including watering for 3 months hour 2.000 655.20 1310.40
Tractor-trolley hour 1.000 413.60 413.60
c) Material
Farm yard manure @ 0.18 cum per 100 sqm at site of
cum 0.180 150.00 27.00
work
Cost of water KL 12.000 77.00 924.00
d) Overhead charges @ 2.615% on (a+b+c) 102.75
e) Contractor's profit @ 10% on (a+b+c+d) 403.19
Cost for 100 sqm = a+b+c+d+e 4435.05
Rate per 100 sqm = (a+b+c+d+e)/100 44.35
say 44.00
3.24 309 Surface Drains in Soil
Construction of unlined surface drains of average cross
sectional area 0.63 sqm in soil to specified lines, grades,
levels and dimensions to the requirement of clause 301 and
309. Excavated material to be used in embankment within a
lead of 50 metres (average lead 25 metres)
(Area - 0.625 sqm, Base - 0.5m, Ht - 0.5m, Slopes - 1 V :
1.5H)
Unit = metre
Taking output = 10 metres
A Mechanical means
a) Labour
Mate day 0.016 451.00 7.22
Mazdoor for dressing of bed and side of drain day 0.394 400.00 157.60
b) Machinery
Hydraulic Excavator 0.3 cum bucket capacity @ 30
hour 0.520 2791.60 1451.63
metres per hour
c) Overhead charges @ 2.615% on (a+b) 42.27
d) Contractor's profit @ 10% on (a+b+c) 165.87
Cost for 10 metres = a+b+c+d 1824.59
Rate per metre = (a+b+c+d)/10 182.46
say 182.00
RA - 18
Ref. to
MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
3.36 Suggesti Embankment Construction with Flyash/Pond ash
ve available from coal or lignite burning Thermal Plants as
waste material.
Construction of embankment with Flyash conforming to table
1 of IRC: SP: 58 - 2001 obtained from coal or lignite burning
thermal power stations as waste material, spread and
compacted in layer of 200mm thickness each at OMC, all as
specified in IRC: SP: 58-2001 and as per approved plans.
Unit = cum
Taking output = 360 cum
a) Labour
Mate day 0.160 451.00 72.16
Mazdoor day 4.000 400.00 1600.00
b) Machinery
Hydraulic Excavator 0.9 cum bucket capacity @ 60 hour 6.000 2791.60 16749.60
cum/hour
Tipper 10Tcapacity flyash 360 x 1.2 = 432 tonnes tonne.km 432 x L 6.56 76481.66
RA - 19
CHAPTER - 4
SUB-BASES, BASES ( NON- BITUMINOUS) AND SHOULDERS
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
4.1 401 Granular Sub-Base with Close Graded Material (Table:-
400-1)
4.1 B By Mix in Place Method
Construction of granular sub-base by providing close graded
material, spreading in uniform layers with motor grader on
prepared surface, mixing by mix in place method with rotavator
at OMC, and compacting with vibratory roller to achieve the
desired density, complete as per clause 401
Unit = cum
Taking output = 300 cum
a) Labour
Mate day 0.480 451.00 216.48
Mazdoor skilled day 2.000 515.00 1030.00
Mazdoor unskilled day 10.000 400.00 4000.00
b) Machinery
Motor Grader 110 HP @ 50 cum hour 6.000 3020.40 18122.40
Vibratory roller 8 -10 tonne hour 6.000 2736.20 16417.20
Tractor - Rotavator hour 12.000 423.60 5083.20
Water tanker 6 KL capacity hour 3.000 655.20 1965.60
c) Material
Close graded Granular sub-base Material as per table 400-1
RA - 20
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
d) Overhead charges @ 2.615% on (a+b+c) 6237.35
e) Contractor's profit @ 10% on (a+b+c+d) 24475.93
add seignorage charges cum 384.000 75.00 28800.00
Add District Mineral Fund (DMF) 30% on Seinorage 0.300 28800.00 8640.00
charges
Cost for 300 cum = a+b+c+d+e 306675.25
Rate per cum = (a+b+c+d+e)/300 1022.25
Add lead charges of metal 25.00 Km 575.36
say 1598.00
Note Any one of the grading for material may be adopted as per
design
4.6 403 Cement Treated Crushed Rock or combination as per
clause 403.2 and table 400.4in Sub base/ Base
Providing, laying and spreading Material on a prepared sub
grade, adding the designed quantity of cement to the spread
Material, mixing in place with rotavator, grading with the motor
grader and compacting with the road roller at OMC to achieve
the desired unconfined compressive strength and to form a
layer of sub-base/base.
Unit = cum
Taking output = 300 cum (600 tonnes)
Quantity of cement assumed as 4 per cent of quantity of
crushed rock by weight.
a) Labour
Mate day 0.480 451.00 216.48
Mazdoor skilled day 2.000 515.00 1030.00
Mazdoor day 10.000 400.00 4000.00
b) Machinery
Motor Grader 110 HP @ 50 cum per hour hour 6.000 3020.40 18122.40
Vibratory roller 8 - 10 tonne hour 6.000 2736.20 16417.20
Tractor with Rotavator and blade @ 25 cum per hour hour 12.000 423.60 5083.20
Water tanker 6 KL capacity hour 10.000 655.20 6552.00
c) Material
Cement at site @ 4 per cent by weight of crushed
tonne 24.000 3900.00 93600.00
aggregate (600 tonne)
Grading of material for sub-base course
37.5 mm to 9.5 mm @ 55 per cent cum 211.200 811.80 171452.16
9.5 mm to 4.75 mm @ 20 per cent cum 76.800 760.47 58404.10
4.75 mm to 75 micron @ 25 per cent cum 96.000 384.84 36944.64
Cost of water KL 60.000 77.00 4620.00
or
Grading of material for Base course
37.5 mm to 9.5 mm @ 32.5 per cent cum 124.800 811.80 101312.64
9.5 mm to 4.75 mm @ 5 per cent cum 19.200 760.47 14601.02
4.75 mm to 75 micron @ 62.5 per cent cum 240.000 384.84 92361.60
Cost of water KL 60.000 77.00 4620.00
4.6 (i) For Sub-Base course
d) Overhead charges @ 2.615% on (a+b+c) 10889.96
e) Contractor's profit @ 10% on (a+b+c+d) 42733.21
Cost for 300 cum = a+b+c+d+e 470065.35
RA - 21
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
add seignorage charges cum 384.000 75.00 28800.00
Add District Mineral Fund (DMF) 30% on Seinorage 0.300 28800.00 8640.00
charges
Add lead charges of metal 25.00 Km 575.36
Rate per cum = (a+b+c+d+e)/300 2046.84
say 2047.00
Note Quantities of aggregates provided under 'c' above are
uncompacted quantities.
4.12 406 Providing, laying, spreading and compacting graded stone
aggregate to wet mix macadam specification including
premixing the Material with water at OMC in mechanical mix
plant carriage of mixed Material by tipper to site, laying in
uniform layers with paver in sub- base / base course on well
prepared surface and compacting with vibratory roller to
achieve the desired density.
Unit = cum
Taking output = 225 cum (495 tonnes)
a) Labour
Mate day 0.480 451.00 216.48
Mazdoor skilled day 2.000 515.00 1030.00
Mazdoor day 10.000 400.00 4000.00
b) Machinery
Wet mix plant of 75 tonne hourly capacity hour 6.600 1679.70 11086.02
Electric generator 125 KVA hour 6.000 1543.10 9258.60
Front end loader 1 cum capacity hour 6.000 1594.70 9568.20
Paver finisher hour 6.000 2290.60 13743.60
Vibratory roller 8 - 10 tonne hour 6x0.65 2736.20 10671.18
or
Smooth 3 wheeled steel roller @ 8-10 tonnes. hour 12.000
Water tanker 6 KL capacity hour 3.000 655.20 1965.60
Tipper tonne.km 495 x L 6.56 25966.00
RA - 22
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
c) Material ( Table 400-11)
45 mm to 22.4 mm@ 30 per cent cum 89.100 1068.42 95196.22
22.4 mm to 2.36 mm @ 40 per cent cum 118.800 839.53 99736.16
2.36 mm to 75 micron@ 30 per cent cum 89.100 333.00 29670.30
Cost of water KL 18.000 77.00 1386.00
d) Overhead charges @ 2.615% on (a+b+c) 8265.78
e) Contractor's profit @ 10% on (a+b+c+d) 32435.67
Add seignorage charges cum 297.000 75.00 22275.00
Add District Mineral Fund (DMF) 30% on Seinorage 0.300 22275.00 6682.50
charges
Cost for 225 cum = a+b+c+d+e 385749.92
Rate per cum = (a+b+c+d+e)/225 1714.44
say 1714.00
a) Add Lead charges for metal 25.00 Km 593.34
2307.78
say 2308.00
Note 1. Though vibratory roller is required only for 3 hours as per
norms, the same is required to be available at site for 6 hours
to match with other machines. The usage rates of vibratory
roller may be multiplied with a factor of 0.65
2. As three wheeled smooth steel rollers are commonly in use,
the same has been provided as an alternative which can be
used if the thickness of individual layer does not exceed 100
mm..
4.13 407 Construction of Median and Island with Soil Taken from
Roadway Cutting
Construction of Median and Island above road level with
approved material deposited at site from roadway cutting and
excavation for drain and foundation of other structures, spread,
graded and compacted as per clause 407
Unit = cum
Taking output =21 cum
a) Labour
Mate day 0.240 451.00 108.24
Mazdoor day 6.000 400.00 2400.00
b) Machinery
Water tanker 6 KL with 5 km lead and 1 trip per hour hour 1.000 655.20 655.20
Plate compactor @ 3.5 cum per hour hour 6.000 59.10 354.60
c) Material
Cost of water KL 6.000 77.00 462.00
d) Overhead charges @ 2.615% on (a+b+c) 104.08
e) Contractor's profit @ 10% on (a+b+c+d) 408.41
Cost for 21 cum = a+b+c+d+e 4492.53
Rate per cum = (a+b+c+d+e)/21 213.93
say 214.00
Note This analysis provides for median and island with earthen top.
In case the surface is required to be turfed or planted with
shrubs, the same is required to be provided separately as per
analysis given in the chapter on horticulture. In case granular
fill is required to be paved, quantities of paving are required to
be calculated as per approved design and paid separately.
4.14 407 Construction of Median and Island with Soil Taken from
Borrow Areas
Construction of median and Island above road level with
approved material brought from borrow pits, spread, sloped
and compacted as per clause 407
Unit = cum
Taking output = 21 cum
a) Labour
Mate day 0.160 451.00 72.16
RA - 23
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Mazdoor day 4.000 400.00 1600.00
b) Machinery
Water tanker with 5 km lead hour 1.000 655.20 655.20
Plate Compactor @ 3.5 cum per hour hour 6.000 59.10 354.60
Hydraulic Excavator1.0 cum bucket capacity @60 cum hour 0.500 2791.60 1395.80
per hour
Tipper 10 tonne capacity tonne.km 52.5 x L 6.56 1721.23
Unit = sqm
Taking output = 300 sqm
a) Labour
Mate day 1.360 451.00 613.36
Mason day 4.000 455.00 1820.00
Mazdoor day 30.000 400.00 12000.00
b) Machinery
Vibratory road roller 8 -10 tonnes @60 cum per hour hour 0.750 2736.20 2052.15
Water tanker 6 KL capacity @ 1 trip per hour hour 2.000 655.20 1310.40
Concrete mixer 0.4/0.28 cum per hour hour 6.000 525.50 3153.00
c) Material
i) For Granular sub base material
53 mm to 26.5 mm @ 35 per cent cum 20.790 858.90 17856.53
26.5 mm to 4.75 mm @ 45 per cent cum 26.730 990.95 26488.09
2.36 mm below @ 20 per cent cum 11.880 333.00 3956.04
ii) For cement concrete grade M157.5 cum
Aggregate 12 mm crushed @ 0.9 cum of concrete cum 6.750 998.56 6740.30
Sand @ 0.45 cum/cum of concrete cum 3.380 182.00 615.16
Cement tonne 1.880 3900.00 7332.00
RA - 24
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
iii) For cement plaster 1:3
Sand cum 3.840 182.00 698.88
Cement tonne 1.830 3900.00 7137.00
iv) Pre-cast cement concrete tiles
Tiles size 300 x 300 mm and 25 mm thick each 3300.000 23.49 77524.75
v) RCC pipes
Pipes 200 mm dia,2.5 m long for drainage metre 22.500 263.00 5917.50
vi) Cost of water KL 12.000 77.00 924.00
d) Overhead charges @ 2.615% on (a+b+c) 4606.04
e) Contractor's profit @ 10% on (a+b+c+d) 18074.52
Add Seigniorage Fee on Sand Cum 7.220 50.00 361.00
Add Seigniorage Fee on Road Metal Cum 66.150 75.00 4961.25
Add District Mineral Fund (DMF) 30% on Seinorage 0.300 5322.25 1596.68
charges
Cost for 300 sqm = a+b+c+d+e 205738.65
Rate per sqm = (a+b+c+d+e)/300 685.80
say 686.00
Add lead charges of metal 25.00 Km 0.221 449.50 99.11
Add lead charges of sand 41.00 Km 0.012 718.12 8.64
Add lead charges of Manufactured Sand 25.00 Km 0.012 505.00 6.08
say 799.83
say 800.00
RA - 25
CHAPTER - 5
BASES AND SURFACE COURSES (BITUMINOUS)
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
5.1 502 Prime Coat
Providing and applying primer coat with bitumen
emulsion on prepared surface of granular Base
including clearing of road surface and spraying primer
at the rate of 0.70 kg/sqm using mechanical means.
Unit = sqm
Taking output = 3500 sqm
a) Labour
Mate day 0.080 451.00 36.08
Mazdoor day 2.000 400.00 800.00
b) Machinery
Mechanical broom @ 1250 sqm per hour hour 2.800 381.80 1069.04
Air compressor 250 cfm hour 2.800 556.50 1558.20
Emulsion pressure distributor @ 1750 sqm per hour hour 2.000 875.60 1751.20
Water tanker 6 KL capacity @ 1 trip per hour hour 1.000 655.20 655.20
c) Material
Bitumen emulsion @ 0.6 kg per sqm (SS1) tonne 2.100 44730.00 93933.00
Cost of water KL 6.000 77.00 462.00
d) Overhead charges @ 2.615% on (a+b+c) 2621.92
e) Contractor's profit @ 10% on (a+b+c+d) 10288.66
Cost for 3500 sqm = a+b+c+d+e 113175.31
Rate per sqm = (a+b+c+d+e)/3500 32.34
say 32.30
add lead charges of bitumen 250.00 Km 0.28
total rate per sqm 32.62
say 32.60
Note Bitumen primer has been provided @ 0.60 kg per sqm as per
clause 502.8. Payment shall be made with adjustment, plus
or minus, for the variation between this quantity and the
actual quantity approved by the Engineer after the
preliminary trials referred to in clause No. 502.4.3.
5.2 503 Tack Coat
Providing and applying tack coat with bitumen emulsion
using emulsion pressure distributor at the rate of 0.25
kg per sqm on the prepared bituminous/granular
surface cleaned with mechanical broom.
Unit = sqm
Taking output = 3500 sqm
a) Labour
Mate day 0.080 451.00 36.08
Mazdoor day 2.000 400.00 800.00
b) Machinery
Mechanical broom @ 1250 sqm per hour hour 2.800 381.80 1069.04
Air compressor 250 cfm hour 2.800 556.50 1558.20
Emulsion pressure distributor @ 1750 sqm per hour hour 2.000 875.60 1751.20
c) Material
Bitumen emulsion @ 0.25kg per sqm (RS) tonne 0.875 35790.00 31316.25
d) Overhead charges @ 2.615% on (a+b+c) 955.28
e) Contractor's profit @ 10% on (a+b+c+d) 3748.60
Cost for 3500 sqm = a+b+c+d+e 41234.65
Rate per sqm = (a+b+c+d+e)/3500 11.78
say 11.80
add lead charges of bitumen 250.00 Km 0.12
total rate per sqm 11.90
say 11.90
RA - 26
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Note 1. Bitumen emulsion has been provided @ 0.20 kg per sqm
as per clause 503.8. Payment shall be made with
adjustment, plus or minus, for the variation between this
quantity and actual quantity approved by the Engineer after
preliminary trials referred to in clause No. 503.4.3
2. An output of 3500 sqm has been considered in case of
prime coat and tack coat which can be covered by
bituminous courses on the same day.
5.6 507 Dense Graded Bituminous Macadam
Providing and laying dense graded bituminous
macadam with 100-120 TPH batch type HMP producing
an average output of 75 tonnes per hour using crushed
aggregates of specified grading, premixed with
bituminous binder @ 4.0 to 4.5 per cent by weight of
total mix and filler, transporting the hot mix to work site,
laying with a hydrostatic paver finisher with sensor
control to the required grade, level and alignment,
rolling with smooth wheeled, vibratory and tandem
rollers to achieve the desired compaction as per MoRTH
specification clause No. 507 complete in all respects.
Unit = cum
Taking output = 195 cum (450 tonnes)
a) Labour
Mate day 0.840 451.00 378.84
Mazdoor working with HMP, mechanical broom, paver, day 14.000 400.00 5600.00
roller, asphalt cutter and assistance for setting out lines,
levels and layout of construction
Skilled mazdoor for checking line & levels day 5.000 515.00 2575.00
b) Machinery
Batch mix HMP @ 75 tonne per hour hour 6.000 24636.00 147816.00
Paver finisher hydrostatic with sensor control @ 75 cum hour 6.000 3115.20 18691.20
per hour
Generator 250 KVA hour 6.000 2162.60 12975.60
Front end loader 1 cum bucket capacity hour 6.000 1594.70 9568.20
Tipper 10 tonne capacity tonne.km 450 x L 6.56 23605.45
RA - 27
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Add seignorage charges for metal cum 282.240 75.00 21168.00
Add seignorage charges for filler tonne 8.640 88.00 760.32
Add District Mineral Fund (DMF) 30% on Seinorage 0.300 21928.32 6578.50
charges
Cost for 195 cum = a+b+c+d+e 1234671.49
Rate per cum = (a+b+c+d+e)/195 (For Grading I) 6331.65
say 6332.00
a) Add Lead charges for metal 25.00 Km 650.60
b) Add lead charges for Bitumen 250.00 Km 42.98
7025.23
Say 7025.00
c) Materials for Grade II
Bitumen @ 4.5 per cent of weight of mix tonne 20.250 33760.00 683640.00
Aggregate
Total weight of mix = 450 tonnes
Weight of bitumen = 20.25 tonnes
Weight of aggregate = 450 -20.25 = 429.75 tonnes
Taking density of aggregate = 1.5 ton/cum
Volume of aggregate = 286.5 cum
Grading - II19 mm (Nominal Size)
25 - 10 mm 30 per cent cum 85.950 1071.19 92068.78
10 - 5 mm 28 per cent cum 80.220 760.47 61004.90
5 mm and below 40 per cent cum 114.600 384.84 44102.66
Filler @ 2 per cent of weight of aggregates. tonne 8.595 2491.00 21410.15
* Any one of the alternative may be adopted as per approved
design
(ii) For GradingII(19 mm nominal size)
d) Overhead charges @ 2.615% on (a+b+c) 30043.62
e) Contractor's profit @ 10% on (a+b+c+d) 117893.91
Add seignorage charges for metal cum 280.770 75.00 21057.75
Add seignorage charges for filler tonne 8.595 88.00 756.36
Add District Mineral Fund (DMF) 30% on Seinorage 0.300 21814.11 6544.23
charges
Cost for195 cum = a+b+c+d+e 1325191.34
Rate per cum = (a+b+c+d+e)/195 (For Grading-II) 6795.85
say 6796.00
a) Add Lead charges for metal 25.00 Km 647.21
b) Add lead charges for Bitumen 250.00 Km 48.35
7491.42
Say 7491.00
Note *1. Although the roller are required only for 3 hours as per
norms of output, but the same have to be available at site for
six hours as the hot mix plant and paver will take six hours
for mixing and paving the output of 450 tonnes considered in
this analysis. To cater for the idle period of these rollers, their
usage rates have been multiplied by a factor of 0.65.
RA - 28
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
5. The individual density for each size of aggregates to be
used for construction I.e. 37.5-25 mm, 25-10 mm etc. should
be found in the laboratory and accordingly the quantities
should be ammended for use in field. The average density of
1.5 tonne/cum is only a reference density in this Data Book.
RA - 29
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Add seignorage charges for metal cum 278.712 75.00 20903.40
Add seignorage charges for filler tonne 8.532 88.00 750.82
Add District Mineral Fund (DMF) 30% on Seinorage 0.300 21654.22 6496.26
charges
Cost for 191 cum = a+b+c+d+e 1441229.38
Rate per cum = (a+b+c+d+e)/191 7545.70
say 7546.00
a) Add Lead charges for metal 25.00 Km 655.92
b) Add lead charges for Bitumen 250.00 Km 57.04
8258.67
Say 8259.00
c) Material for Grade II
i) Bitumen@ 5.4 per cent of weight of mix tonne 24.300 33670.00 818181.00
ii) Aggregate
Total weight of mix = 450 tonnes
Weight of bitumen = 24.3 tonnes
Weight of aggregate = 450 -24.30 = 425.70 tonnes
Taking density of aggregate = 1.5 ton/cum
Volume of aggregate = 284.4 cum
Grading - II-13 mm (Nominal Size)
13.2 - 10 mm30 per cent cum 85.140 924.75 78733.22
10 - 5 mm 25 per cent cum 70.950 760.47 53955.35
5 mm and below43 per cent cum 122.034 384.84 46963.56
Filler @ 2 per cent of weight of aggregates. tonne 8.514 2491.00 21208.37
*Any one of the alternative may be adopted as per
approved design
5.8 (ii) for Grading-II(13 mm nominal size)
d) Overhead charges @ 2.615% on (a+b+c) 33098.33
e) Contractor's profit @ 10% on (a+b+c+d) 129880.88
Add seignorage charges for metal cum 278.124 75.00 20859.30
Add seignorage charges for filler tonne 8.514 88.00 749.23
Add District Mineral Fund (DMF) 30% on Seinorage 0.300 21608.53 6482.56
charges
Cost for 191 cum = a+b+c+d+e 1456780.78
Rate per cum = (a+b+c+d+e)/191 (For Grading-II) 7627.12
say 7627.00
a) Add Lead charges for metal 25.00 Km 654.54
b) Add lead charges for Bitumen 250.00 Km 59.24
8340.90
Say 8341.00
Note *1. Although the rollers are required only for 3 hours as per
norms of output, but the same have to be available at site for
six hours as the hot mix plant and paver will take six hours
for mixing and paving the output of 450 tonnes considered in
this analysis. To cater for the idle period of these rollers, their
usage rates have been multiplied by a factor of 0.65
RA - 30
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
5. The individual density for each size of aggregates to be
used for construction i.e. 37.5-25 mm, 25-10 mm etc. should
be found in the laboratory and accordingly the quantities
should be ammended for use in field. The average density of
1.5 tonne/cum is only a reference density in this Data Book.
Unit = sqm
Taking output = 35.00 sqm (0.87 cum ) assuming a
density of 2.3 tonnes/cum.-2 tonnes
a) Labour
Mate day 0.440 451.00 198.44
Mazdoor day 10.000 400.00 4000.00
Mazdoor skilled day 1.000 515.00 515.00
b) Machinery
Mechanical broom @ 1250 sqm per hour hour 0.060 381.80 22.91
Air compressor 250 cfm hour 0.060 556.50 33.39
Mastic cooker 1 tonne capacity hour 6.000 79.50 477.00
Bitumen boiler 1500 litres capacity hour 6.000 223.00 1338.00
Tractor for towing and positioning of mastic cooker and hour 1.000 413.60 413.60
bitumen boiler
c) Material
Base mastic (without coarse aggregates) = 60 per cent
Coarse aggregate (6.3mm to 13.2 mm) = 40 per cent .
Proportion of material required for mastic asphalt with coarse
aggregates (based on mix design done by CRRI for a
specific case)
I) Bitumen 85/25 or 30/40 @ 10.2 per cent by weight of tonne 0.204 33760.00 6887.04
mix. 2 x 10.2/100 = 0.204
ii) Fine aggregate passing 2.36mm and retained on cum 0.390 333.00 129.87
0.075mm sieve @ 31.9 per cent by weight of mix = 2 x
31.9/100 = 0.638 tonnes = 0.638/1.625 = 0.39
iii) Lime stone dust filler with calcium content not less tonne 0.360 2491.00 896.76
than 80 per cent by weight @ 17.92 per cent by weight
of mix = 2 x 17.92/100 = 0.36
iv) Coarse aggregates 6.3 mm to 13.2 mm @ 40 per cum 0.550 839.83 461.91
cent by weight of mix = 2 x 40/100 = 0.8 MT =
0.8/1.456 = 0.55
v) Pre-coated stone chips of 13.2 mm nominal size for cum 0.018 333.00 5.99
skid resistance = 35 x 0.005/10 = 0.018
vi) Bitumen for coating of chips @ 2 per cent by weight kg 0.500 33.76 16.88
= 0.018 x 1.456 x 2/100 = 0.0005 MT = 0.5kg
RA - 31
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
e) Contractor's profit @ 10% on (a+b+c+d) 1579.94
Add seignorage charges for metal cum 0.958 75.00 71.85
Add seignorage charges for filler tonne 0.360 88.00 31.68
Add District Mineral Fund (DMF) 30% on Seinorage 0.300 103.53 31.06
charges
Cost for 35.00 sqm = a+b+c+d+e 17513.94
Rate per sqm = (a+b+c+d+e)/35 500.40
say 500.00
a) Add Lead charges for metal 25.00 Km 12.30
b) Add lead charges for Bitumen 250.00 Km 2.71
515.02
say 515.00
RA - 32
CHAPTER - 5
BASES AND SURFACE COURSES (BITUMINOUS)
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
5.12 513 Stress Absorbing Membrane Interlayer (SAMI)
Providing and laying of Stress Absorbing Membrane
Interlayer (SAMI) on a WMM surface laid to the specified
levels, grade and cross fall using Type A and B
Unit = sqm
Taking output = 10250 sqm (92.25 cum)
(i) Case - I : Type A
a) Labour
Mate day 0.240 451.00 108.24
Mazdoor day 6.000 400.00 2400.00
b) Machinery
Hydraulic self propelled chip spreader hour 6.000 2743.70 16462.20
Tipper 5.5 cum capacity hour 6.000 950.30 5701.80
Front end loader 1 cum bucket capacity hour 6.000 1594.70 9568.20
Bitumen pressure distributor @ 1750 sqm per hour hour 6.000 1527.10 9162.60
Smooth wheeled roller 8 -10 tonne weight hour 6.000 1329.90 7979.40
c) Material
Modified Bitumen @ 11.00 kg per 10 sqm (IRC 37-
tonne 11.275 33670.00 379629.25
2018, Cl. 8.3)
Crushed stone chipping of 6.7 mm size defined as 100
per cent passing 11.2 mm sieve and retained on 2.36
cum 102.500 850.94 87221.09
mm sieve applied @ 0.1 cum per 10 sqm (IRC 37-
2018, Cl. 8.3)
d) Overhead charges @ 2.615% on (a+b+c) 13551.79
e) Contractor's profit @ 10% on (a+b+c+d) 53178.46
Add Seigniorage Fee cum 102.500 75.00 7687.50
Add District Mineral Fund (DMF) 30% on Seinorage 0.300 7687.50 2306.25
charges
Cost for 10250 sqm = a+b+c+d+e 594956.78
Rate per sqm = (a+b+c+d+e)/10250 58.04
a) Add Lead charges for metal 25.00 Km 4.50
b) Add lead charges for Bitumen 250.00 Km 0.51
say 63.00
Note Since seal coat is provided immediately over the bituminous
layers, mechanical broom for clearing has not been catered.
RA - 33
CEMENT CONCRETE PAVEMENTS
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
6.1 601 Dry Lean Cement Concrete Sub- base
Construction of dry lean cement concrete Sub- base over a
prepared sub-grade with coarse and fine aggregate
conforming to IS: 383, the size of coarse aggregate not
exceeding 25 mm, aggregate cement ratio not to exceed
15:1, aggregate gradation after blending to be as per table
600-1, cement content not to be less than 150 kg/ cum,
optimum moisture content to be determined during trial
length construction, concrete strength not to be less than 10
Mpa at 7 days, mixed in a batching plant, transported to site,
laid with a paver with electronic sensor, compacting with 8-
10 tonnes vibratory roller, finishing and curing.
Unit = cum
Taking output = 450 cum (990 tonne)
a) Labour
Mate day 1.120 451.00 505.12
Mazdoor skilled day 6.000 515.00 3090.00
Mazdoor day 22.000 400.00 8800.00
b) Machinery
Front end loader 1 cum bucket capacity hour 6.000 1594.70 9568.20
Cement concrete batch mix plant @ 75 cum per hour hour 6.000 1310.90 7865.40
Coarse Sand as per IS: 383 @ 0.45 cum/cum of cum 203.000 182.00 36946.00
concrete
Cement @ 150 kg/cum of concrete tonne 67.500 3900.00 263250.00
Cost of water KL 48.000 77.00 3696.00
d) Overhead charges @ 2.615% on (a+b+c) 23232.87
e) Contractor's profit @ 10% on (a+b+c+d) 91167.90
Add seignorage charges for metal cum 405.000 75.00 30375.00
Add seignorage charges for sand cum 203.000 50.00 10150.00
Add District Mineral Fund (DMF) 30% on Seinorage 0.300 40525.00 12157.50
charges
Cost for 205 cum = a+b+c+d+e 1055529.38
Rate per cum = (a+b+c+d+e)/450 2345.62
say 2346.00
Add lead charges of metal 25.00 Km 0.900 449.50 404.55
Add lead charges of sand 41.00 Km 0.451 718.12 323.95
Add lead charges of Manufactured Sand 25.00 Km 0.000 505.00 0.00
3074.50
Say 3075.00
Note Quantity provided for aggregate is for estimating purpose.
Exact quantity shall be as per mix design.
RA - 34
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
6.2 602 Cement Concrete Pavement
Construction of un-reinforced, dowel jointed, plain cement
concrete pavement over a prepared sub base with 43 grade
cement @ 400 kg per cum, coarse and fine aggregate
conforming to IS 383, maximum size of coarse aggregate
not exceeding 25 mm, mixed in a batching and mixing plant
as per approved mix design, transported to site, laid with a
fixed form or slip form paver, spread, compacted and
finished in a continuous operation including provision of
contraction, expansion, construction and longitudinal joints,
joint filler, separation membrane, sealant primer, joint
sealant, debonding strip, dowel bar, tie rod, admixtures as
approved, curing compound, finishing to lines and grades as
per drawing
Unit = cum
Taking output = 1050 cum (2415 tonne)
a) Labour
Mate day 2.000 451.00 902.00
Mazdoor skilled day 15.000 515.00 7725.00
Mazdoor day 35.000 400.00 14000.00
b) Machinery
Road Sweeper @ 1250 sqm per hour hour 2.800 381.80 1069.04
Front end loader 1 cum bucket capacity hour 18.000 1594.70 28704.60
Cement concrete batch mix plant @ 175 cum per hour hour 6.000 1310.90 7865.40
(effective output)
Electric generator 250 KVA hour 6.000 2162.60 12975.60
Slip form paver with electronic sensor hour 6.000 3247.20 19483.20
Water tanker6 KL capacity hour 36.000 655.20 23587.20
Transit truck agitator 5 cum capacity. tonne.km 2415xL 6.56 126682.59
RA - 35
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Add 1 per cent of material for cost of miscellaneous 36190.35
materials like tarpauline, Hessian cloth, metal cap, cotton /
compressible sponge and cradle for dowel bars, work
bridges for men to approach concrete surface without
walking over it, cutting blades and bites, minor equipments
like scabbling machine, threads, ropes, guide wires and any
other unforeseen items.
d) Overhead charges @ 2.615% on (a+b+c) 102515.13
e) Contractor's profit @ 10% on (a+b+c+d) 402278.78
Add seignorage charges for metal cum 945.000 75.00 70875.00
Add seignorage charges for sand cum 473.000 50.00 23650.00
Add District Mineral Fund (DMF) 30% on Seinorage 0.300 94525.00 28357.50
charges
Cost for 1050cum = a+b+c+d+e 4547949.08
Rate per cum = (a+b+c+d+e)/1050 4331.38
say 4331.00
Add lead charges of metal 25.00 Km 0.900 449.50 404.55
Add lead charges of sand 41.00 Km 0.450 718.12 323.50
Add lead charges of Manufactured Sand 25.00 Km 0.000 505.00 0.00
728.05
Say 5059.00
Note The quantities for cement, coarse aggregate and fine
aggregates are for estimating only .The exact quantities will
be as per mix design.
RA - 36
CHAPTER-7
GEOSYNTHETICS AND REINFORCED EARTH
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
7.5 3100 Reinforced Earth Structures
Reinforced earth Structures have four main components as
under:
a) Excavation for foundation, foundation concrete and
cement concrete grooved seating in the foundation for facing
elements (facia material).
b) Facia material and its placement.
c) Assembling, joining with facing elements and laying of
the reinforcing elements.
d) Earth fill with granular material which is to be retained
by the wall.
Each component is analysed separately as under:
considering Average height of wall = 8 m.
7.5(i) B With reinforcing elements of synthetic geogrids
Unit = sqm
Taking output = 300 sqm
a) Labour
Mate day 0.360 451.00 162.36
Mazdoor day 6.000 400.00 2400.00
Mazdoor skilled day 3.000 515.00 1545.00
b) Material
Synthetic Geogrids as per clause 3102.8 and approved
sqm 300.000 500.00 150000.00
design and specifications.
Add 10 per cent of the cost of reinforcing elements
(synthetic geogrids) for accessories like tie-strips, nuts
and bolts and loops/lugs for joining reinforcing elements 15000.00
with the facia panels, overlaps and other protective
elements for synthetic geogrids.
c) Overhead charges @ 2.615% on (a+b) 4422.16
d) Contractor's profit @ 10% on (a+b+c) 17352.95
Cost of 300 sqm of Synthetic geogrids = a+b+c+d 190882.47
Rate per sqm = (a+b+c+d)/ 300 636.27
say 636.00
7.5 3104 (ii) Facing elements of RCC
Unit = sqm
Taking output = 75 sqm
a) Labour
Mate day 0.180 451.00 81.18
Mazdoor day 3.000 400.00 1200.00
Mazdoor skilled day 1.500 515.00 772.50
b) Machinery
Light crane with lifting capacity up to 3 tonne hour 6.000 429.60 2577.60
c) Material
Pre-cast RCC M-35 facing elements of size as per
design and 18 cm thick for 75 sqm. (Refer Item 12.8 (H)) cum 13.500 4796.00 64746.00
HYSD steel @ 5 kg / sqm (Refer Item 13.6) tonnes 0.380 54927.00 20872.26
Add 2 per cent of cost of facia panels, for all necessary
temporary form work, scaffolding and provision of loops/lugs
1712.37
for lifting of panels and joining the reinforcing elements.
Unit = sqm
Taking output = 1 sqm
c) Material
Facing elements of RCC Sq.m 1.000 1234.00 1234.00
Synthetic Geogrids as per clause 3102.8 and approved Sq.m 5.517 636.00 3508.81
design and specifications.
d) Overhead charges @ 3% on (a+b) 124.02
e) Contractor's profit @ 10% on (a+b+d) 486.68
Cost for 1 sqm = c+d+e 5353.52
Rate per sqm = (c+d+e)/1Sqm say 5354.00
Unit = cum
Taking output = 100 cum
a) Labour
Mate day 0.040 451.00 18.04
Mazdoor day 1.000 400.00 400.00
b) Machinery
Hydraulic excavator1 cum bucket capacity @ 60 cum hour 1.670 2791.60 4661.97
per hour
Tipper 10 tonne capacity tonne.km 175xL 6.56 5737.44
RA - 40
Rate Analysis as per approved SOR 2018-19
RA - 41
CHAPTER-8
TRAFFIC SIGNS, MARKINGS & OTHER ROAD APPURTENANCES
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
8.1 408 Cast in Situ Cement Concrete M20 Kerb
Construction of cement concrete kerb with top and bottom
width 115 and 165 mm respectively, 250 mm high in M 20
grade PCC on M-10 grade foundation 150 mm thick,
foundation having 50 mm projection beyond kerb stone, kerb
stone laid with kerb laying machine, foundation concrete laid
manually, all complete as per clause 408
Unit = Running metre
Taking output = 360 metre
A. Using Concrete Mixer
Cement Concrete
Cement concrete of grade M20 = 12.60 cum
Cement concrete of grade M10 for base= 11.61 cum
Total Concrete = 24.21 cu.m
a) Labour
Mate day 0.720 451.00 324.72
Mason day 2.000 455.00 910.00
Mazdoor day 16.000 400.00 6400.00
b) Machinery
Kerb casting machine @ 60 metres/hour hour 6.000 671.90 4031.40
Concrete mixer 0.48/0.28 cum capacity hour 12.000 525.50 6306.00
Water tanker6 KL capacity hour 5.000 655.20 3276.00
c) Material
Crushed stone aggregate 20 mm nominal size 59 per 1303.00 28392.37
cum 21.790
cent
Coarse sand 30 per cent cum 10.900 182.00 1983.80
Cement 11 per cent tonne 5.700 3900.00 22230.00
Cost of water KL 30.000 77.00 2310.00
d) Overhead charges @ 2.615% on (a+b+c) 1991.70
e) Contractor's profit @ 10% on (a+b+c+d) 7815.60
Add seignorage charges for metal cum 21.790 75.00 1634.25
Add seignorage charges for sand cum 10.900 50.00 545.00
Add District Mineral Fund (DMF) 30% on Seinorage 0.300 2179.25 653.78
charges
Cost for 360 meter = a+b+c+d+e 88804.61
Rate per metre = (a+b+c+d+e)/360 246.68
Add lead charges of metal 25.00 Km 0.061 449.50 27.21
Add lead charges of sand 41.00 Km 0.030 718.12 21.74
Add lead charges of Manufactured Sand 25.00 Km 0.000 505.00 0.00
295.63
say 296.00
B Using Concrete Batching and Mixing Plant
Cement Concrete
Cement concrete of grade M20 = 12.60 cum
Cement concrete of grade M10 for base = 11.61 cum
Total Concrete = 24.21 cu.m
a) Labour
Mate day 0.120 451.00 54.12
Mason day 1.000 455.00 455.00
Mazdoor day 2.000 400.00 800.00
b) Machinery
Kerb casting machine @ 60 metres/hour hour 6.000 671.90 4031.40
Concrete batching and mixing plant @ 15 cum/hr. hour 1.600 1083.10 1732.96
Water tanker6 KL capacity hour 5.000 655.20 3276.00
Tipper 5.5 cum capacity hour 6.000 950.30 5701.80
c) Material
Crushed stone aggregate 20 mm nominal size 59 per 1303.00 28392.37
cum 21.790
cent
Coarse sand 30 per cent cum 10.900 182.00 1983.80
Cement 11 per cent tonne 5.700 3900.00 22230.00
RA - 42
CHAPTER-8
TRAFFIC SIGNS, MARKINGS & OTHER ROAD APPURTENANCES
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Cost of water KL 30.000 77.00 2310.00
d) Overhead charges @ 2.615% on (a+b+c) 1855.80
e) Contractor's profit @ 10% on (a+b+c+d) 7282.32
Add seignorage charges for metal cum 21.790 75.00 1634.25
Add seignorage charges for sand cum 10.900 50.00 545.00
Add District Mineral Fund (DMF) 30% on Seinorage 0.300 2179.25 653.78
charges
Cost for 360 meter = a+b+c+d+e 82938.60
Rate per metre = (a+b+c+d+e)/360 230.38
say 230.00
Add lead charges of metal 25.00 Km 0.061 449.50 27.21
Add lead charges of sand 41.00 Km 0.030 718.12 21.74
Add lead charges of Manufactured Sand 25.00 Km 0.000 505.00 0.00
278.95
say 279.00
8.4 801 Retro-Reflectorised Traffic Signs
Unit = Each
Taking output = one traffic sign
416.00 89.86
i) Excavation for foundation cum 0.216
4729.00 567.48
ii) Cement concrete M15 grade cum 0.120
iii) Painting angle iron post two coats sqm 0.430 68.00 29.24
a) Labour (For fixing at site)
Mate day 0.010 451.00 4.51
Mazdoor day 0.250 400.00 100.00
b) Material
42.00 798.00
Mild steel angle iron 75 x 75 x 6 mm kg 19.000
Aluminium sheeting fixed with encapsulated lens type
reflective sheeting of size including lettering and signs as
applicable
Add 2 per cent of cost of angle iron towards cost of drilling
holes, nuts, bolts etc.
(i) 90 cm equilateral triangle sqm 0.350 819.00 286.65
or
( ii ) 60 cm equilateral triangle sqm 0.156 819.00 127.76
or
( iii ) 60 cm circular sqm 0.283 819.00 231.78
or
( iv ) 80 mm x 60 mm rectangular sqm 0.480 819.00 393.12
or
(v) 60 cm x 45 cm rectangular sqm 0.270 819.00 221.13
or
(vi ) 60 cm x 60 cm square sqm 0.360 819.00 294.84
or
( vii ) 90 cm high octagon sqm 0.672 819.00 550.37
c) Machinery
Tractor-trolley hour 0.010 413.60 4.14
(i) 90 cm equilateral triangle
d) Overhead charges @ 2.615% on (a+b+c) 31.20
RA - 43
CHAPTER-8
TRAFFIC SIGNS, MARKINGS & OTHER ROAD APPURTENANCES
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
e) Contractor's profit @ 10% on (a+b+c+d) 122.45
Rate per traffic sign = ( i+ii+iii+a+b+c+d+e) 2033.53
say 2034.00
( ii ) 60 cm equilateral triangle
d) Overhead charges @ 2.615% on (a+b+c) 27.05
e) Contractor's profit @ 10% on (a+b+c+d) 106.15
Rate per traffic sign = ( i+ii+iii+a+b+c+d+e) 1854.18
say 1854.00
( iii ) 60 cm circular
d) Overhead charges @ 2.615% on (a+b+c) 29.77
e) Contractor's profit @ 10% on (a+b+c+d) 116.82
Rate per traffic sign = ( i+ii+iii+a+b+c+d+e) 1971.59
say 1972.00
( iv ) 80 mm x 60 mm rectangular
d) Overhead charges @ 2.615% on (a+b+c) 33.99
e) Contractor's profit @ 10% on (a+b+c+d) 133.38
Rate per traffic sign = ( i+ii+iii+a+b+c+d+e) 2153.71
say 2154.00
(v) 60 cm x 45 cm rectangular
d) Overhead charges @ 2.615% on (a+b+c) 29.49
e) Contractor's profit @ 10% on (a+b+c+d) 115.73
Rate per traffic sign = ( i+ii+iii+a+b+c+d+e) 1959.57
say 1960.00
(vi ) 60 cm x 60 cm square
d) Overhead charges @ 2.615% on (a+b+c) 31.42
e) Contractor's profit @ 10% on (a+b+c+d) 123.29
Rate per traffic sign = ( i+ii+iii+a+b+c+d+e) 2042.77
say 2043.00
( vii ) 90 cm high octagon
d) Overhead charges @ 2.615% on (a+b+c) 38.10
e) Contractor's profit @ 10% on (a+b+c+d) 149.51
Rate per traffic sign = ( i+ii+iii+a+b+c+d+e) 2331.20
say 2331.00
1.Any one area of aluminium sheeting given at (i) to (vii) may
Note be adopted as per site requirement and in accordance with
IRC : 67
2.Rate for excavation, cement concrete M-15 and painting
may be taken from respective chapters
3. The depth of foundation and quantity of cement concrete
in the foundation are indicative. These may be increased for
areas having higher wind velocities like in coastal areas. This
is applicable to all road signs and directions boards.
Direction and Place Identification Signs upto 0.9 sqm
8.5 801
Size Board.
RA - 44
CHAPTER-8
TRAFFIC SIGNS, MARKINGS & OTHER ROAD APPURTENANCES
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
iii) Painting angle iron post two coats sqm 0.430 68.00 29.24
a) Labour (For fixing at site)
Mate day 0.010 451.00 4.51
Mazdoor day 0.200 400.00 80.00
b) Material
Mild steel angle iron 75 mm x 75 mm x 6 mm,2.85 42.00 798.00
kg 19.000
metres long
Aluminium sheeting fixed with encapsulated lens type 819.00 737.10
sqm 0.900
reflective sheeting of size 0.9 sqm
Add 2 per cent of cost of materials for drilling holes, nuts,
bolts, fabrication etc.
c) Machinery
Tractor-trolley hour 0.020 413.60 8.27
d) Overhead charges @ 2.615% on (a+b+c) 42.57
e) Contractor's profit @ 10% on (a+b+c+d) 167.05
Cost for 0.9 sqm =I+ii+ii+ a+b+c+d+e 2524.07
Rate per sqm (for sign having area upto 0.9 sqm) =
2804.52
(I+ii+iii+a+b+c+d+e)/0.90
say 2805.00
I) Lettering and arrow marks on sign board to be provided
Note separately as per actual requirement. Rates for these items
have been analysed separately
ii) Rate for excavation, cement concrete M-15 and painting
may be taken from respective chapters
Direction and Place Identification Signs with size more
8.6 801
than 0.9 sqm size Board.
Unit = sqm
Taking output = 1.50 sqm
416.00 178.88
i) Excavation for foundation cum 0.430
4729.00 1134.96
ii) Cement concrete M15 grade cum 0.240
iii) Painting angle iron post 2 coats sqm 0.860 68.00 58.48
a) Labour (For fixing at site)
Mate day 0.010 451.00 4.51
Mazdoor day 0.300 400.00 120.00
b) Material
Mild steel angle iron 75 mm x 75 mm x 6 mm, 2.85 42.00 1596.00
kg 38.000
metres long, 2 nos
Aluminium sheeting fixed with encapsulated lens type 819.00 1228.50
sqm 1.500
reflective sheeting
Add 2 per cent of cost of materials for drilling holes, nuts,
bolts, fabrication etc.
c) Machinery
Tractor-trolley hour 0.020 413.60 8.27
d) Overhead charges @ 2.615% on (a+b+c) 74.08
e) Contractor's profit @ 10% on (a+b+c+d) 303.14
Cost for 1.5 sqm =I+ii+ii+ a+b+c+d+e 4706.81
Rate per sqm ( for sign having area more than 0.9 sqm)
5229.79
= ( i+ii+iii+a+b+c+d+e)/1.50
say 5230.00
RA - 45
CHAPTER-8
TRAFFIC SIGNS, MARKINGS & OTHER ROAD APPURTENANCES
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
i) Lettering and arrow marks on sign board to be provided
Note separately as per actual requirement. Rates for these items
have been analysed separately
ii) Rate for excavation, cement concrete M-15 and painting
may be taken from respective chapters
8.7 802 Overhead Signs
RA - 46
CHAPTER-8
TRAFFIC SIGNS, MARKINGS & OTHER ROAD APPURTENANCES
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
RA - 47
CHAPTER-8
TRAFFIC SIGNS, MARKINGS & OTHER ROAD APPURTENANCES
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
a) Labour
Mate day 0.030 451.00 13.53
Mazdoor day 0.750 400.00 300.00
b) Machinery
Road marking machine @ 60 sqm per hour hour 10.000 135.50 1355.00
Tractor-trolley hour 0.500 413.60 206.80
c) Material
Hot applied thermoplastic compound Litre 1500.000 229.64 344460.00
Reflectorising glass beads kg 150.000 80.30 12045.00
d) Overhead charges @ 2.615% on (a+b+c) 9371.65
e) Contractor's profit @ 10% on (a+b+c+d) 36775.20
Cost for 600 sqm = a+b+c+d+e 404527.17
Rate per sqm = a+b+c+d+e)/600 674.21
say 674.00
1. A sealing primer may be applied in advance on cement
concrete pavement to ensure proper bonding. Any laitance
Note
and/or curing compound to be removed where paint is
required to be applied on concrete surface.
2.Cost of painter is already included in hire charges of road
marking machine.
8.14 804 Kilometre Stone
Reinforced cement concrete M15grade kilometre stone of
standard design as per IRC:8-1980, fixing in position
including painting and printing etc
(i) 5th kilometre stone (precast)
Unit = Nos.
Taking output = 6 Nos.
4729.00 11113.15
a) M-15 grade of concrete cum 2.350
54.93 1212.79
b) Steel reinforcement @ 5 kg per sqm kg 22.080
416.00 698.88
c) Excavation in soil for foundation cum 1.680
d) Painting two coats on concrete surface sqm 9.850 76.00 748.60
e) Lettering on km post (average 30 letters of 10 per cm per 0.70 1260.00
1800.000
cm height each) letter
Transportation and fixing
f) Labour
Mate day 0.260 451.00 117.26
Mason day 0.600 455.00 273.00
Mazdoor including loading/unloading day 6.000 400.00 2400.00
g) Machinery
Tractor-trolley hour 6.000 413.60 2481.60
h) Overhead charges @ 2.615% on (f+g) 137.86
i) Contractor's profit @ 10% on (f+g+h) 540.97
Cost for 6 Nos. 5th km stone = a+b+c+ d+e +f+g+h +i 20984.11
Rate for each 5th km stone = (a+b+c+ d+e +f+g+h +i )
3497.35
/6
say 3497.00
8.14 (ii) Ordinary kilometer stone (precast)
Unit = Nos.
Taking output = 14 Nos.
4729.00 17828.33
a) M-15 grade of concrete cum 3.770
54.93 1445.68
b) Steel reinforcement @ 5 kg per sqm kg 26.320
416.00 1152.32
c) Excavation in soil for foundation cum 2.770
d) Painting two coats on concrete surface sqm 11.410 76.00 867.16
RA - 48
CHAPTER-8
TRAFFIC SIGNS, MARKINGS & OTHER ROAD APPURTENANCES
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
e) Lettering on km post ( average 12 letters of 10 per cm per 0.70 1176.00
1680.000
cm height each) letter
Transportation and fixing
f) Labour
Mate day 0.320 451.00 144.32
Mason day 1.000 455.00 455.00
Mazdoor day 7.000 400.00 2800.00
g) Machinery
Tractor-trolley hour 6.000 413.60 2481.60
h) Overhead charges @ 2.615% on (f+g) 153.79
i) Contractor's profit @ 10% on (f+g+h) 603.47
Cost for 14 Nos. ordinary km stone = (a+b+ c +d+e+f+g+h+i) 29107.67
Rate for each ordinary km stone = (a+b+ c
2079.12
+d+e+f+g+h+j) /14
say 2079.00
8.14 (iii) Hectometer stone (precast)
Unit = Nos.
Taking output = 33 Nos.
4729.00 7471.82
a) M-15 grade of concrete cum 1.580
54.93 3625.18
b) Steel reinforcement @ 5 kg per sqm kg 66.000
416.00 578.24
c) Excavation in soil for foundation cum 1.390
d) Painting two coats on concrete surface sqm 6.270 76.00 476.52
e) Lettering on km post (average 1 letter of 10 cm per cm per 0.70 231.00
330.000
height each) letter
Transportation and fixing
f) Labour
Mate day 0.340 451.00 153.34
Mason day 1.500 455.00 682.50
Mazdoor day 7.000 400.00 2800.00
g) Machinery
Tractor-trolley hour 6.000 413.60 2481.60
h) Overhead charges @ 2.615% on (f+g) 159.97
i) Contractor's profit @ 10% on (f+g+h) 627.74
Cost for 33 Nos. Hectometer stone = (a+b +c +d+e+f+ g+h+i) 19287.91
Rate for each Hectometer stone = (a+b +c +d+e+f+
584.48
g+h+i) 33
say 584.00
The rate for excavation, cement concrete, steel
Note reinforcement, painting and lettering may be taken from
respective chapters.
8.15 805 Road Delineators
Supplying and installation of delineators (road way indicators,
hazard markers, object markers), 80-100 cm high above
ground level, painted black and white in 15 cm wide strips,
fitted with 80 x 100 mm rectangular or 75 mm dia circular
reflectorised panels at the top, buried or pressed into the
ground and conforming toIRC-79 and the drawings.
Unit = Each
Taking output= 30 Nos.
a) Labour
Mate day 0.040 451.00 18.04
Mazdoor for fixing day 1.000 400.00 400.00
b) Material
RA - 49
CHAPTER-8
TRAFFIC SIGNS, MARKINGS & OTHER ROAD APPURTENANCES
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
750.00 22500.00
Cost of approved type of delineators from ISI certified
each 30.000
firm as per the standard drawing given in IRC - 79
Add 10 per cent cost of material for installation 2250.00
c) Overhead charges @ 2.615% on (a+b) 658.14
d) Contractor's profit @ 10% on (a+b+c) 2582.62
Cost for 30 Nos. delineators = (a+b+ c+d) 28408.80
Rate per delineators = (a+b+c+d) /30 946.96
say 947.00
In case of soft ground, a proper foundation may be provided
as per approved design. In case foundation is required to be
Note
provided, the items of excavation and foundation concrete
are required to be measured and paid separately.
Tubular Steel Railing on Medium Weight Steel Channel (
8.20 808
ISMC series) 100 mm x 50 mm
Providing, fixing and erecting 50 mm dia steel pipe railing in
3 rows duly painted on medium weight steel channels (ISMC
series) 100 mm x 50 mm, 1.2 metres high above ground, 2 m
centre to centre, complete as per approved drawings
Unit = Running metre
Taking output = 10metres
i) Excavation for foundation (6 Nos)6 x 0.6 x 0.6 x 416.00 539.14
cum 1.296
0.6
ii) Foundation concrete M-15 grade PCC 6 x 0.6 x 4729.00 3064.39
cum 0.648
0.6 x 0.3
iii) Painting of pipe sqm 4.710 68.00 320.28
iv) Painting of channel section 6 nos,1.8 metres 68.00 146.88
sqm 2.160
each 0.2 x 1.8 x 6 = 2.16
a) Labour (For fixing at site)
Mate day 0.010 451.00 4.51
Mazdoor day 0.250 400.00 100.00
Plumber day 0.010 482.20 4.82
b) Material
Steel pipe 50 mm external dia as per IS:1239 metre 30.000 475.00 14250.00
42.00 4173.12
Medium weight steel channel (ISMC series) 100 mm x
kg 99.360
50 mm,10.8 metres length @ 9.2 kg per metre
Add for drilling holes @ 2 per cent of cost of channels 83.46
c) Machinery
Tractor-trolley hour 0.040 413.60 16.54
d) Overhead charges @ 2.615% on (a+b+c) 593.25
e) Contractor's profit @ 10% on (a+b+c+d) 2327.99
Cost for 10 metre =i+ii+iii+iv+ a+b+c+d+e 25624.39
Rate per metre = (i+ii+iii+iv+a+b+c+d+e)/10 2562.44
say 2562.00
Tubular Steel Railing on Precast RCC Posts, 1.2 m High
8.21 808
Above Ground Level
Providing, fencing and erecting 50 mm dia painted steel pipe
railing in 3 rows on precast M20 grade RCC vertical posts1.8
metres high (1.2 m above GL) with 3 holes 50 mm dia for
pipe, fixed 2 metres centre to, complete as per approved
drawing
Unit = Running metre
Taking output = 10metres
i) Excavation for foundation (6 Nos)6 x 0.6 x 0.6 x 416.00 539.14
cum 1.296
0.6
ii) Foundation concrete M - 15 grade PCC 6 x 0.6 x 4729.00 3064.39
cum 0.648
0.6 x 0.3
RA - 50
CHAPTER-8
TRAFFIC SIGNS, MARKINGS & OTHER ROAD APPURTENANCES
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
iii) RCC M - 20 for pre cast posts 6 nos of 1.8 4922.00 1575.04
cum 0.320
metres each
iv) Painting of pipe sqm 4.710 68.00 320.28
a) Labour
Mate day 0.014 451.00 6.31
Mazdoor day 0.350 400.00 140.00
Plumber day 0.010 482.20 4.82
b) Material
Steel pipe 50 mm dia as per IS:1239 metre 30.000 475.00 14250.00
c) Machinery
Tractor-trolley hour 0.250 413.60 103.40
d) Overhead charges @ 2.615% on (a+b+c) 379.29
e) Contractor's profit @ 10% on (a+b+c+d) 1488.38
Cost for 10 metre =i+ii+iii+iv+ a+b+c+d+e 21871.06
Rate per metre = (i+ii+iii+iv+a+b+c+d+e)/10 2187.11
say 2187.00
8.22 809 Reinforced Cement Concrete Crash Barrier
RA - 51
CHAPTER-8
TRAFFIC SIGNS, MARKINGS & OTHER ROAD APPURTENANCES
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Unit = Running metre
Taking output = 4.5 metre length
a) Labour
Mate day 0.060 451.00 27.06
Blacksmith day 0.500 482.20 241.10
Mazdoor day 1.000 400.00 400.00
b) Machinery
Tractor-trolley hour 0.100 413.60 41.36
c) Material
Corrugated sheet,3 mm thick, "W" beam section 61.00 2513.81
kg 41.210
railing,4.5 m in length
Channel post 150 x 75 x 5 mm,1.8 m long,3 Nos @ 42.00 3719.52
kg 88.560
16.4 kg per metre
Spacer 150 x 75 x 5 mm channel 0.33 m long,3 Nos @ 42.00 682.08
kg 16.240
16.4 kg per metre
Nuts and bolts kg 20.000 85.00 1700.00
Add 25 per cent of the cost of material for fabrication, nuts,
2153.85
bolts and washers etc.)
d) Overhead charges @ 2.615% on (a+b+c) 300.17
e) Contractor's profit @ 10% on (a+b+c+d) 1177.90
Cost for 4.5 metre = a+b+c+d+e 12956.85
Rate per metre = (a+b+c+d+e)/4.5 2879.30
say 2879.00
Suggesti
8.27 Street Lighting
ve
Providing and erecting street light mounted on a steel circular
hollow pole of standard specifications for street lighting, 9 m
high spaced 40 m apart, 1.8 m overhang on both sides if
fixed in the median and on one side if fixed on the footpath,
fitted with sodium vapour lamp and fixed firmly in concrete
foundation.
Unit = Each
Taking output = one light
a) Labour
Mate day 0.030 451.00 13.53
Mazdoor day 0.500 400.00 200.00
Electrician day 0.250 482.20 120.55
b) Material
i) Steel circular hollow pole of standard specification for 16876.00 16876.00
street lighting to mount light at 9 m height above road each 1.000
level
ii) Sodium vapour lamp each 1.000 3500.00 3500.00
Add 5 per cent of cost of material for holder, electric cable,
1018.80
insulation, ladder, scaffolding etc
c) Painting
For Fixing in Median
Providing two coats of alluminium paint over steel 68.00 391.00
sqm 5.750
circular hollow pipe with overhang on both sides
For fixing in Footpath
Providing two coats of alluminium paint over steel 68.00 314.84
sqm 4.630
circular hollow pipe with overhang on one side
(i) For Fixing in Median
d) Overhead charges @ 2.615% on (a+b) 568.21
e) Contractor's profit @ 10% on (a+b+d) 2229.71
Rate per light for fixing in Median= a+b+c+d+e 24917.80
say 24918.00
(ii) For fixing in Footpath
Rate per light for Fixing in Footpath = a+b+c+d+e 24841.64
say 24842.00
RA - 52
CHAPTER-8
TRAFFIC SIGNS, MARKINGS & OTHER ROAD APPURTENANCES
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
The items of excavation and cement concrete foundation will
be measured and included separately in the estimate as per
Note
approved design and drawing. The rate for painting has been
analysed in this chapter.
Suggesti
8.28 Lighting on Bridges
ve
Providing and fixing lighting on bridges, mounted on steel
hollow circular poles of standard specifications, 5 m high
fixed on parapets with cement concrete, 20 m apart and fitted
with sodium vapour lamp
Unit = Each
Taking output = one light
a) Labour
Mate day 0.020 451.00 9.02
Mazdoor day 0.400 400.00 160.00
Electrician day 0.200 482.20 96.44
b) Material
7619.33 7619.33
i) Steel circular hollow pole of standard specification for
each 1.000
street lighting to mount light at 5 m above deck level
ii) Sodium vapour lamp 70 watt each 1.000 3500.00 3500.00
Add 1 per cent of cost of material for holder, electric cable,
111.19
insulation, ladder, scaffolding etc
c) Painting
Providing two coats of alluminium paint over steel 68.00 187.68
sqm 2.760
circular hollow pipe
d) Overhead charges @ 2.615% on (a+b) 300.62
e) Contractor's profit @ 10% on (a+b+d) 1179.66
Rate per light = a+b+c+d+e 13163.95
say 13164.00
The items of cement concrete to be measured and paid
Note separately as per approved design. The rate for painting has
already been analysed in this chapter.
Suggesti
8.35 Road Markers/Road Stud with Lense Reflector
ve
Providing and fixing of road stud 100x 100 mm, die-cast in
aluminium, resistant to corrosive effect of salt and grit, fitted
with lense reflectors, installed in concrete or asphaltic surface
by drilling hole 30 mm upto a depth of 60 mm and bedded in
a suitable bituminous grout or epoxy mortar, all as per BS
873 part 4:1973
Unit = Nos
Taking output = 50Nos
a) Labour
Mate day 0.040 451.00 18.04
Mazdoor day 1.000 400.00 400.00
b) Material
Aluminium studs 100 x 100 mm fitted with lense 200.00 10000.00
each 50.000
reflectors
Add 10 per cent of cost of material for fixing and installation 1000.00
c) Overhead charges @ 2.615% on (a+b) 298.58
d) Contractor's profit @ 10% on (a+b+c) 1171.66
Cost for 50 studs = a+b+c+d 12888.28
Rate per studs = (a+b+c+d)/50 257.77
say 258.00
Suggesti
8.38 Rumble Strips
ve
RA - 53
CHAPTER-8
TRAFFIC SIGNS, MARKINGS & OTHER ROAD APPURTENANCES
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
RA - 54
CHAPTER-11
HORTICULTURE
Ref. to Remarks
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs / Input
H Spec. ref.
11.08 307 Planting and Maintaining of Flowering Plants
and Shrubs
(a) Planting flowering plants and shrubs in
central verge
Unit = Running metres 200 plants and 800
shrubs in two rows in one km length of road
where width of verge is 3m and above.
Taking output = 1000 metres
a) Labour
Mate day 1.200 451.00 541.20 L-12
Mazdoor day 12.000 400.00 4800.00 L-13
b) Machinery
Water tanker6 KL capacity hour 6.000 655.20 3931.20 P&M-060
c) Material
Plants each 200.000 40.00 8000.00 M-100
Shrubs each 800.000 15.00 12000.00 M-166
Manure sludge/Farm yard manure cum 63.640 150.00 9546.00 M-167
Pesticide kg 0.500 150.00 75.00 M-136
Cost of water KL 36.000 77.00 2772.00 M-189
d) Overhead charges @ 2.615% on (a+b+c)
1089.55
e) Contractor's profit @ 10% on (a+b+c+d)
4275.50
Rate per Km = (a+b+c+d+e) 47030.45
say 47030.00 km
11.08 (b) Maintenance of flowering plants and shrubs in
central verge for one year
Unit = km
Taking output = one km
a) Labour
Mate day 36.000 451.00 16236.00 L-12
Mazdoor day 365.000 400.00 146000.00 L-13
b) Machinery
Water tanker6 KL capacity hour 90.000 655.20 58968.00 P&M-060
c) Material
Manure Sludge / farm yard manure at site cum 10.000 150.00 1500.00 M-167
Cost of water KL 180.000 77.00 13860.00 M-189
Replacement of casualties @ 10 per cent
Plants each 20.000 40.00 800.00 M-100
Shrubs each 80.000 15.00 1200.00 M-166
Pesticides kg 1.500 150.00 225.00 M-136
d) Overhead charges @ 2.615% on (a+b+c) 6244.33
e) Contractor's profit @ 10% on (a+b+c+d)
24503.33
Rate per Km for one year = (a+b+c+d+e) 269536.67
say 269537.00 km
11.09 307 Planting of Trees and their Maintenance for
one Year
Planting of trees by the road side (Avenue trees)
in 0.60 m dia holes, 1 m deep dug in the ground,
mixing the soil with decayed farm yard/sludge
manure, planting the saplings, backfilling the
trench, watering, fixing the tree guard and
maintaining the plants for one year
Unit = Each
Taking output = 10 trees
a) Labour
Mate day 1.700 451.00 766.70 L-12
SOR 2018-19 Roads-Horticulture
RA - 55
CHAPTER-11
HORTICULTURE
Ref. to Remarks
Sr No MoRT Description Unit Quantity Rate Rs Cost Rs / Input
H Spec. ref.
Mazdoor for planting day 2.000 400.00 800.00 L-13
Mazdoor for maintenance for one year day 15.000 400.00 6000.00 L-13
b) Machinery
Water tanker6 KL capacity hour 2.000 655.20 1310.40 P&M-060
c) Material
Sapling 2 m high 25 mm dia each 10.000 25.00 250.00 M-160
Farm yard manure cum 0.940 150.00 141.00 M-167
Pesticide kg 0.500 150.00 75.00 M-136
Cost of water KL 12.000 77.00 924.00 M-189
d) Overhead charges @ 2.615% on (a+b+c) 268.48
e) Contractor's profit @ 10% on (a+b+c+d) 1053.56
Cost for 10 trees = a+b+c+d+e 11589.14
Rate per trees = (a+b+c+d+e)/10 1158.91
say 1159.00 each
11.19 New Tree Guard with MS Iron
Providing and fixing MS iron tree guard 60 cm
dia and 2 metre high above ground level formed
of 4 Nos (25 x 6 mm) and 8 Nos (25 x 3 mm)
vertical MS riveted to 3 Nos (25 x 6 mm) iron
rings in two halves, bolted together with 8 mm
dia and 30 mm long bolts including painting two
coats with paint of approved brand over a coat of
priming, complete in all respects.
Unit = Each
Taking output = one tree guard
a) Labour
Mate day 0.050 451.00 22.55 L-12
Blacksmith day 0.250 440.00 110.00 L-01
Mazdoor day 0.250 400.00 100.00 L-13
b) Material
MS iron 25 x 6 mm M-179
kg 19.200 42.00 806.40
/1000
MS iron 25 x 3 mm M-179
kg 9.600 42.00 403.20
/1000
Add 5 per cent of cost of material for
riveting, bolting and welding accessories
c) Machinery
Tractor-trolley P&M-
hour 0.040 413.60 16.54
053
d) Painting
Painting two coats including priming sqm 1.770 68.00 120.36 Item 8.9
e) Overhead charges @ 2.615% on
41.29
(a+b+c+d)
f) Contractor's profit @ 10% on 162.03
(a+b+c+d+e)
Rate per tree guard =a+b+c+d+e+f 1782.38
say 1782.00 each
Note 1 The items of excavation and concreting to be
measured and paid separately as per design .
2 . Rate of painting may be adopted from the
chapter as Traffic signs.
RA - 56
(A) Usage Rates of Plant and Machinery
Output of
Sl. No. Description of Machine Activity Output Unit Rate
Machine
P&M-001 Air Compressor General Purpose capacity in cfm 170/250 hour 556.50
P&M-002 Batching and Mixing Plant (a) 30 cum capacity Concrete Mixing cum/hour 20 hour 1343.30
P&M-003 Batching and Mixing Plant (b) 15 - 20 cum capacity Concrete Mixing cum/hour 13 hour 1083.10
P&M-004 Bitumen Pressure Distributor Applying bitumen tack coat sqm/hour 1750 hour 1527.10
P&M-005 Bitumen Boiler oil fired Bitumen Spraying capacity in litre 1500 hour 223.00
P&M-006 Concrete Paver Finisher with 40 HP Motor Paving of concrete surface cum / hour 20 hour 3247.20
P&M-007 Concrete Pump of 45 & 30 cum capacity Pumping of concrete cum / hour 33 / 22 hour 1508.80
P&M-008 Concrete Bucket For Pouring concrete capacity in cum 1 hour 12.90
P&M-009 Concrete Mixer (a) 0.4/0.28 cum Concrete Mixing cum/hour 2.5 hour 525.50
P&M-010 Concrete Mixer (b) 1 cum Concrete Mixing cum/hour 7.5 hour 661.50
P&M-011 Crane (a) 80 tonnes Lifting Purpose hour 1311.20
P&M-012 Cranes b) 35 tonnes Lifting Purpose hour 885.70
P&M-013 Cranes c) 3 tonnes Lifting Purpose hour 429.60
P&M-014 Dozer D - 80 - A 12 ( as per MORTH data ) Spreading /Cutting / Clearing cum/hour 300/ 150/250 hour 2454.60
P&M-015 Dozer D - 50 - A 15( as per MORTH data ) Spreading /Cutting / Clearing cum/hour 200/ 100/150 hour 1546.80
P&M-016 Emulsion Pressure Distributor Applying emulsion tack coat sqm/hour 1750 hour 875.60
P&M-017 Front End loader 1 cum bucket capacity Soil loading / Aggregate loading cum/hour 60 /25 hour 1594.70
P&M-018 Generator (a) 125 KVA Genration of electric Energy KVA 100 hour 1543.10
P&M-019 Generator( b) 63 KVA Genration of electric Energy KVA 50 hour 1,174.15
P&M-020 GSB Plant 50 cum Producing GSB cum/hour 40 hour 1279.70
P&M-021 Hotmix Plant - 120 TPH capacity DBM/BM/SDC/ Premix cum/hour 40 hour 28708.00
P&M-022 Hotmix Plant - 100 TPH capacity DBM/BM/SDC/ Premix cum/hour 30 hour 24636.00
P&M-023 Hotmix Plant - 60 to 90 TPH capacity DBM/BM/SDC/ Premix cum/hour 25 hour 22092.00
P&M-024 Hotmix Plant - 40 to 60 TPH capacity DBM/BM/SDC/ Premix cum/hour 17 hour 19546.00
P&M-025 Hydraulic Chip Spreader Surface Dressing sqm/hour 1500 hour 2743.70
P&M-026 Hydraulic Excavator of 1 cum bucket Soil Ordinary/Soil Marshy / Soil Unsuitable cum/hour 60 /60 /60 hour 2791.60
P&M-027 Integrated Stone Crusher 100TPH Crushing of Spalls TPH 100 hour 9755.20
P&M-028 Integrated Stone Crusher 200 TPH Crushing of Spalls TPH 200 hour 20570.00
P&M-029 Kerb Casting Machine Kerb Making Rm/hour 80 hour 671.90
P&M-030 Mastic Cooker Mastic Wearing coat capacity in tonne 1 hour 79.50
P&M-031 Mechanical Broom Hydraulic Surface Cleaning sqm/hour 1250 hour 381.80
P&M-032 Motor Grader 3.35 mtr blade Clearing /Spreading /GSB /WBM cum/hour 200/200/50/50 hour 3020.40
P&M-033 Mobile slurry seal equipment Mixing and laying slurry seal sqm/hour 2700 hour 1261.40
Paver Finisher Hydrostatic with sensor control 100
P&M-034 Paving of DBM/ BM/SDC/ Premix cum/hour 40 hour 3115.20
TPH
P&M-035 Paver Finisher Mechanical 100 TPH Paving of WMM /Paving of DLC cum/hour 40/30 hour 2290.60
P&M-036 Piling Rig with Bantonite Pump 0.75 m dia to 1.2 m dia Boring attachment Rm/hour 2 to 3 hour 6131.70
P&M-037 Pneumatic Road Roller Rolling of Asphalt Surface cum/hour 25 hour 1515.60
P&M-038 Pneumatic Sinking Plant Pneumatic Sinking of wells cum/hour 1.5 to 2.00 hour 5701.00
P&M-039 Pot Hole Repair Machine Repair of potholes cum/hour 4 hour 903.00
P&M-040 Prestressing Jack with Pump & access Stressing of steel wires/stands hour 157.80
P&M-041 Ripper Scarifying cum/hour 60 hour 423.60
P&M-042 Rotavator Scarifying cum/hour 25 hour 423.60
P&M-043 Road marking machine Road marking Sqm/hour 100 hour 135.50
P&M-044 Smooth Wheeled Roller 8 tonne(Adopted 10T) Soil Compaction /BM Compaction cum/hour 70/25 hour 1329.90
P&M-045 Tandem Road Roller Rolling of Aspalt Surface cum/hour 30 hour 1856.50
Transportation of soil, GSB, WMM, Hotmix
P&M-046 Tipper - 5 cum Capacity in cum 5.5 km input
etc.
RA - 57
Transportation of soil, GSB, WMM, Hotmix
P&M-047 Tipper - 5 cum Capacity in cum 5.5 tonne.km 6.56
etc.
Transportation of soil, GSB, WMM, Hotmix
P&M-048 Tipper - 5 cum Capacity in cum 5.5 hour 950.30
etc.
P&M-049 Transit Mixer 4.0/4.5 cum Transportation of Concrete Mix to site cum/hour 4.5 hour 2071.70
P&M-050 Transit Mixer 4/4.5 cum Transportation of Concrete Mix to site cum/hour 4.5 tonne.km 13.18
P&M-051 Transit Mixer 3.0 cum (adopted 2cum) Transportation of Concrete Mix to site cum/hour 3 hour 2071.70
P&M-052 Transit Mixer 3.0 cum Transportation of Concrete Mix to site cum/hour 3 tonne.km input
P&M-057 Truck 5.5 cum per 10 tonnes Material Transport capacity/cum 4.5 hour 950.30
P&M-058 Truck 5.5 cum per 10 tonnes Material Transport capacity/cum 4.5 tonne.km 6.56
P&M-059 Vibratory Roller 8 tonne Earth or soil / GSB / WBM cum/hour 100/60/60 hour 2736.20
P&M-082 Induction, deinduction and erection of plant and equipment including all components and accessories for pneumatic method of well sinking. hour input
P&M-083 Joint Cutting Machine with 2-3 blades (for rigid pavement)… hour 332.00
RA - 58
(B) Labour
L-19 Para medical personnel(assumed as work inspector with I.T.I qualification) day 560.00
(C) Materials
M-001 Stone Boulder of size 150 mm and below at Cruser Plant cum 160.50
M-002 Supply of quarried stone 150 - 200 mm size for Hand Broken at site cum 238.55
M-003 Boulder with minimum size of 300 mm for Pitching at Site cum 163.80
M-009 Granular Material or hard murrum for GSB works at Site Cum 110.00
M-010 Granular Material or hard murrum for GSB works at Mixing Plant Cum 110.00
M-011 Fly ash conforming to IS: 3812 ( Part II & I) at HMP Plant / Batching Plant / Crushing Plant Cum 61.00
M-012 Filter media/Filter Material as per Table 300-3 (MoRT&H Specification) (Assumed Average rate of 150mm and 40) Cum 390.30
RA - 59
Rate at Plant
Description Unit (HMP/Batching Rate at Site
)
M-013 Close graded Granular sub-base Material 53 mm to 9.5 mm cum 944.60 944.60
M-014 Close graded Granular sub-base Material 37.5 mm to 9.5 mm cum 811.80 811.80
M-015 Close graded Granular sub-base Material 26.5 mm to 9.5 mm cum 1071.19 1071.19
M-016 Close graded Granular sub-base Material 9.5 mm to 4.75 mm cum 760.47 760.47
M-017 Close graded Granular sub-base Material 9.5 mm to 2.36 mm cum 652.54 652.54
M-018 Close graded Granular sub-base Material 4.75mm to 2.36 mm cum 436.69 436.69
M-019 Close graded Granular sub-base Material 4.75mm to 75 micron mm cum 384.84 384.84
M-020 Close graded Granular sub-base Material 2.36 mm cum 333.00 333.00
M-021 Stone crusher dust finer than 3mm with not more than 10% passing 0.075 sieve. cum 333.00 333.00
M-022 Coarse graded Granular sub-base Material 2.36 mm & below cum 333.00 333.00
M-023 Coarse graded Granular sub-base Material 4.75mm to 75 micron mm cum 384.84 384.84
M-024 Coarse graded Granular sub-base Material 4.75 mm to 2.36 mm cum 436.69 436.69
M-025 Coarse graded Granular sub-base Material 9.5 mm to 4.75 mm cum 760.47 760.47
M-026 Coarse graded Granular sub-base Material 26.5 mm to 4.75 mm cum 990.95 990.95
M-027 Coarse graded Granular sub-base Material 26.5 mm to 9.5 mm cum 1071.19 1071.19
M-028 Coarse graded Granular sub-base Material 37.5 mm to 9.5 mm cum 811.80 811.80
M-029 Coarse graded Granular sub-base Material 53 mm to 26 .5mm cum 858.90 858.90
RA - 60
M-064 Bearing (Cost of parts) nos 483.00
M-065 Bearing (Cast steel rocker bearing assembly of 250 tonne ) nos 665.00
Bearing (Elastomeric bearing assembly consisting of 7 internal layers of elastomer bonded to 6 nos. internal reinforcing steel laminates by the
M-066 nos 15310.00
process of vulcanisation,)
M-067 Bearing (Forged steel roller bearing of 250 tonne nos 125475.00
Bearing (Pot type bearing assembly consisting of a metal piston supported by a disc, PTFE pads providing sliding surfaces against stainless
M-068 nos 47355.00
steel mating together with cast steel assemblies/fabricated structural steel assemblies duly painted with all components
M-069 Bearing (PTFE sliding plate bearing assembly of 80 tonnes ) nos 15430.00
M-070 Bearing (Supply of sliding plate bearing of 80 tonne) nos 16201.50
M-071 Bentonite kg 7.00
M-072 Binding wire kg 53.00
M-073 Bitumen ( Cationic Emulsion ) tonne
M-074 Bitumen (30-40 grade) VG-40 as on 16.12.2018 tonne 33760.00
M-075 Bitumen (80-100 grade) VG-10 as on 16.12.2018 tonne 31690.00
M-076 Bitumen (Cutback ) tonne 45000.00
M-077 Bitumen (emulsion) RS as on 16.12.2018 tonne 35790.00
M-078 Bitumen (modified graded) (CRMB 55) as on 16.12.2018 tonne 33670.00
M-079 Brick (as SSR 2018-19 building materials S. No -1 (1) each 5.70
M-080 C.I.shoes for the pile kg 46.00
M-081 Cement tonne 3900.00
M-082 Cold twisted bars (HYSD Bars) FE 500 for the month of October 2018 tonne 42500.00
M-083 Coller for joints 300 mm dia nos 128.00
M-084 Compressible Fibre Board (20mm thick) sqm 473.00
M-085 Connectors/ Staples each 64.00
M-086 Copper Plate(12m long x 250mmwide) kg 254.00
M-087 Corrosion resistant Structural steel tonne 50138.00
M-088 Corrugated sheet, 3 mm thick, "Thrie" beam section railing kg 174.00
M-089 Credit for excavated rock found suitable for use cum 194.00
M-090 Curing compound . liter 101.00
M-091 Delineators from ISI certified firm as per the standard drawing given in IRC - 79 each 750.00
M-092 Earth Cost or compensation for earth taken from private land cum 55.00
Elastomeric slab seal expansion joint assembly manufactured by using chloroprene, elastomer for elastomeric slab unit conforming to clause
M-093 metre input
915.1 of IRC: 83 (part II),
M-094 Electric Detonators @ 1 detonator for 1/2 gelatin stick of 125 gms each 100 nos 900.00
M-095 Epoxy compound with accessories for preparing epoxy mortar kg 280.00
M-096 Epoxy mortar kg 92.00
M-097 Epoxy primer kg 476.00
M-098 Epoxy resin-hardner mix for prime coat kg 491.00
M-099 Flag of red color cloth 600 x 600 mm each 24.00
M-100 Flowering Plants each 40.00
M-101 Galvanised MS flat clamp nos 165.00
M-102 Galvanised steel wire crates of mesh size 100 mm x 100 mm woven with 4mm dia. GI wire in rolls of required size. sqm 152.00
M-103 Galvanised structural steel plate 200 mm wide, 6 mm thick, 24 m long kg 789.00
M-104 Gelatin 80% old rare kg 57.00
M-105 Geo grids sqm 825.00
M-106 Geomembrane - 750 micron sqm 114.00
M-107 Geonets sqm 58.00
M-108 Geotextile sqm 116.00
M-109 Geotextile filter fabric (250 gsm) sqm 116.00
M-110 GI bolt 10 mm Dia nos 19.00
M-111 Grouting pump with agitator hour 353.00
M-112 Grass (Doob) kg 6.00
M-113 Grass (Fine) kg 8.00
M-114 HDPE pipes 75mm dia metre 104.00
M-115 HDPE pipes 90mm dia metre 150.00
M-116 Hedge plants each 150.00
M-117 Helical pipes 600mm diameter metre input
M-118 Hot applied thermoplastic compound litre 229.64
RA - 61
M-119 HTS strand tonne 35556.00
M-120 Joint Sealant Compound kg 58.00
M-121 Jute netting, open weave, 2.5 cm square opening for seeding and Mulching sqm 76.00
M-122 LDO for steam curing litre 57.00
M-123 M.S. Clamps nos 0.00
M-124 M.S. Clamps (structural steel rate adopted ) kg 50.14
M-125 M.S.shoes @ 35 Kg per pile of 15 m (structural steel rate adopted ) kg 50.14
M-126 Mild Steel bars tonne 39674.00
Modular strip/box seal expansion joint including anchorage catering to a horizontal movement beyond 70 mm and upto 140mm assembly
M-127 comprising of edge beams, central beam,2 modules chloroprene seal, anchorage elements, support and control system, all steel sections metre input
protected against corrosion and installed by the manufacturer or his authorised representative
Modular strip/box seal expansion joint catering to a horizontal movement beyond 140mm and upto 210mm box/box seal joint assembly
M-128 containing 3 modules/cells and comprising of edge beams, two central beams, chloroprene seal, anchorage elements, support and control metre input
system, all steel sections protected against corrosion and installed by the manufacturer or his authorised representative
M-141 Pre moulded Joint filler,25 mm thick for expansion joint. sqm 262.00
M-155 Reinforcement strips 60 mm wide 5 mm thick as per clause 3102. (Glass reinforced polymer/fibre reinforced polymer/polymeric strips) metre 500.00
M-156 Reinforcement strips 60 mm wide 5 mm thick as per clause 3102. (Stainless steel strips) metre 500.00
M-157 Reinforcement strips 60 mm wide 5 mm thick as per clause 3102. Aluminium strips) metre 500.00
M-158 Rivets each 6.00
M-159 Sand bags (Cost of sand and Empty cement bag) nos 8.50
M-160 Sapling 2 m high 25 mm dia each 25.00
M-161 Scrap tyres of size 900 x 20 nos 68.00
M-162 Seeds (Assumed L.S rate) kg 18.00
M-163 Selected earth excluding seignorage cum 55.00
M-164 Separation Membrane of impermeable plastic sheeting 125 micron thick sqm 14.35
M-165 Sheathing duct metre 79.29
M-166 Shrubs(As per Old SSR)) each 15.00
M-167 Sludge / Farm yard manure @ 0.18 cum per 100 sqm at site of work for turfing (Assuming L.S rate of Rs 150/- per Cum) cum 150.00
M-168 Sodium vapour lamp of 250W (Market rate) each 3500.00
M-169 Square Rubble Coursed Stone cum 2130.00
M-170 Steel circular hollow pole of standard specification for street lighting to mount light at 5 m height above deck level each 7619.33
M-171 Steel circular hollow pole of standard specification for street lighting to mount light at 9 m height above road level each 16876.00
RA - 62
M-172 Steel drum 300 mm dia 1.2 m high/empty bitumen drum nos 114.17
M-173 Steel helmet and cushion block on top of pile head during driving. kg 36.58
M-174 Steel pipe 25 mm external dia as per IS:1239 metre 244.00
M-175 Steel pipe 50 mm external dia as per IS:1239 metre 475.00
M-176 Steel wire rope 20 mm kg 157.00
M-177 Steel wire rope 40 mm kg 179.00
M-178 Strip seal expansion joint metre 4200
M-179 Structural Steel for the month of October 2018 tonne 42000.00
M-180 Super plastisizer admixture IS marked as per 9103-1999 kg 43.00
M-181 Synthetic Geogrids as per clause 3102.8 and approved design and specifications. sqm 500.00
M-182 Through and bond stone (25 x 25x 40 cm) each 37.00
M-183 Tie rods 20mm diameter nos 46.00
M-184 Tiles size 300 x 300 mm and 25 mm thick (As per SSR buildings meterial S.No 87) each 261.00
M-185 Timber cum 59715.00
M-186 Traffic cones with 150 mm reflective sleeve nos 200.00
M-187 Tube anchorage set complete with bearing plate, permanent wedges etc nos 43.24
M-188 Unstaked lime ( as per I&C ) tonne 2491.00
M-189 Water (Rural) KL 77.00
M-190 Water based cement paint ( Buildng SOR) litre 51.00
M-191 Welded steel wire fabric kg 131.00
M-192 Wire mesh 50mm x 50mm size of 3mm wire kg 213.00
M-193 Wooden ballies 2" Dia for bracing each 21.21
M-194 Wooden ballies 8" Dia and 9 m long each 513.12
M-195 Wooden packing ( as per AP-2018-19 - M-195) cum 1071.00
M-196 Wooden staff for fastening of flag 25 mm dia, one m long ( as per AP-2018-19 - M-196) each 67.00
Overheads for Bridge Works 2.615% for input of Overheads or Contractors profit please type in collum C as like below
Type symble of apostrope(') then input value then one space then symble of
Overheads for Bridge Works (Rehabilitation) 10 %
percentage (%) for example '08 %
Items No. Summary of Rates calculated and used for analysis of rates of other items Unit Rate
per cm height
Item 8.3 Printing new letter and figures of any shade (ii) English Roman 0.70
per letter
Item 8.8 Painting Two Coats on New Concrete Surfaces sqm 76.00
Item 8.9 Painting angle iron post two coats sqm 68.00
Item 12.6 (B) Cement mortor 1:2 (Excluding OH & CP) cum 3900.00
Item 12.6 (A) Cement mortor 1:3 (Excluding OH & CP) cum 2558.00
Item 12.6 (D) Cement mortor 1:6 (Excluding OH & CP) cum 1720.00
Item 12.7 (A ) Course Rubble masonary in cement mortor 1:3 (including OH & CP) cum 5454.00
Item 12.7 (Addl) B) Random Rubble masonary in cement mortor 1:6 (including OH & CP) cum 4226.00
Item 12.8 (A) PCC Grade M15 including OH & CP for Open Foundation by Mixer cum 4729.00
Item 12.8 (A) PCC Grade M15 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by Mixer cum 3309.00
Item 12.8 (B) PCC PCC Grade M20 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by Mixer cum 3573.00
Item 12.8 (C) RCC Grade M20 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by Mixer cum 3690.00
Item 12.8 (C) RCC RCC Grade M20 including OH & CP for Open Foundation by Batching Plant cum 4407.00
Item 12.8 (C) RCC Grade M20 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by Batching Plant cum 3035.00
Item 12.8 (D) PCC Grade M25 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by Mixer cum 3788.00
Item 12.8 (D) PCC Grade M25 including OH & CP for Open Foundation by Batching Plant cum 4494.00
RA - 63
Item 12.8 (D) PCC Grade M25 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by Batching Plant cum 3140.00
Item 12.8 (E) RCC Grade M25 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by Mixer cum 3909.00
Item 12.8 (E) RCC Grade M25 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by Batching Plant cum 3322.00
Item 12.8 (F) PCC Grade M30 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by Mixer cum 3812.00
Item 12.8 (F) PCC Grade M30 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by Batching Plant cum 3161.00
Item 12.8 (G) RCC Grade M30 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by Mixer cum 3922.00
Item 12.8 (G) RCC Grade M30 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by Batching Plant cum 3267.00
Item 12.8 (H) RCC Grade M35 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by Mixer cum 3981.00
Item 12.8 (H) RCC Grade M35 including OH & CP for Open Foundation by Batching Plant cum 4796.00
Item 12.8 (H) RCC Grade M35 excluding OH & CP for Open Foundation by Batching Plant cum 3501.00
Item 12.8 (H) RCC Grade M35 for Open Foundation Per Cum Basic Cost of Labour, Material & Mechinery by Batching Plant cum 3399.00
Item 12.11 (C) i PCC Grade M20 for Open Foundation (Bottom Plug) Per Cum Basic Cost of Labour, Material & Mechinery by Mixer cum 3900.00
PCC Grade M20 for Open Foundation (Bottom Plug) Per Cum Basic Cost of Labour, Material & Mechinery by
Item 12.11 (C) i cum 3177.00
Batching Plant
Item 12.11 (C) ii PCC Grade M25 for Open Foundation (Bottom Plug) Per Cum Basic Cost of Labour, Material & Mechinery by Mixer cum 4023.00
PCC Grade M25 for Open Foundation (Bottom Plug) Per Cum Basic Cost of Labour, Material & Mechinery by
Item 12.11 (C) ii cum 3299.00
Batching Plant
Item 12.11 (C) iii PCC Grade M30 for Open Foundation (Bottom Plug) Per Cum Basic Cost of Labour, Material & Mechinery by Mixer cum 4047.00
PCC Grade M30 for Open Foundation (Bottom Plug) Per Cum Basic Cost of Labour, Material & Mechinery by
Item 12.11 (C) iii cum 3324.00
Batching Plant
Item 12.11 (C) iv PCC Grade M35 for Open Foundation (Bottom Plug) Per Cum Basic Cost of Labour, Material & Mechinery by Mixer cum 4101.00
Item 12.11 (C) iv PCC Grade M35 including OH & CP for Well Foundation (Bottom Plug) by Batching Plant cum 4789.00
PCC Grade M35 for Open Foundation (Bottom Plug) Per Cum Basic Cost of Labour, Material & Mechinery by
Item 12.11 (C) iv cum 3518.00
Batching Plant
Item 12.11 (F) iv PCC Grade M35 including OH & CP for Well Foundation (Well Cap) by Batching Plant cum 3867.00
Item No. 3.13 Excavation for Structures (Manual Means) cum 416.00
Item No. 3.13 Excavation for Structures (Mechenical Meanse) cum 115.00
Item 14.1(A) RCC Grade M20 for super-structure including OH & CP by Batching Plant cum 4922.00
Item 14.1(B) RCC Grade M20 for super-structure including OH & CP by Batching Plant cum 5205.00
Item 14.1(E) RCC Grade M20 for super-structure including OH & CP by Batching Plant cum 5427.00
Item 14.1(C) RCC Grade M30 for super-structure including formwork and excluding OH & CP by Batching Plant cum 3924.00
Item 14.1(C) RCC Grade M30 for super-structure excluding formwork and excluding OH & CP by Batching Plant cum 3270.00
Item 14.2 A Supplying ,fitting and placing HYSD bar reinforcement in super-structure exncluding OH & CP tonne 49895.00
Item 13.6 Supplying, fitting and placing HYSD including OH & CP for sub-structure tonne 54927.00
Item 5.17 Fog Seal sqm 36.00
Item 5.21 Case-I Crack Prevention courses. Case-I Stress Absorbing Membrane (SAM) crack width less than 6 mm sqm 46.00
Item 5.21 Case-II Crack Prevention courses. Case-II Stress Absorbing Membrane (SAM) with crack width 6 mm to 9 mm sqm 56.00
Crack Prevention courses. Case-III Stress Absorbing Membrane (SAM) crack width above 9 mm and cracked area
Item 5.21 Case-IV sqm 73.00
above 50 %
Item 5.21 Case-IV Crack Prevention courses. Case-IV Bitumen Impregnated Geotextile sqm 186.00
Item 5.15 Case-I Slurry Seal Case-I 5 mm thickness sqm 54.00
Item 5.15 Case-II Slurry Seal Case-II 3 mm thickness sqm 38.00
Item 5.15 Case-III Slurry Seal Case III 1.5 mm thickness sqm 24.00
Item 5.9 Case-I Surface Dressing Case-I 19 mm nominal chipping size sqm 74.00
Item 5.9 Case-II Surface Dressing Case-II 13 mm nominal size chipping sqm 58.00
Rate at Plant
Description (HAND BROKEN) Unit Rate at Site
(HMP/Batching
M-197 Aggregates 60 mm to 63 mm CUM 459.15 459.15
Crushed metal
M-205 Aggregates 53 mm to 26.5 mm CUM 858.90 858.90
RA - 64
M-210 Aggrgates 26.5 to 9.5 mm CUM 1071.19 1071.19
M-217 Stone dust (2.36 mm to 75 microns ) for WMM cum 333.00 333.00
M-218 bitumen grade 30/40 (Bulk) ( 60/70 grade adopted) tonne 33760.00 33760.00
RA - 65
Rates for carraiage of meterials including loading & unloading on surface and
unsurfaced roads( FOR RCC ITEMS with 3% O.H charges) - CC Pavement
RA - 66
Rates for carraiage of meterials including loading & unloading on surface roads
Seal Coat (Case-I, Type A) 513 Sqm 0.0090 1.65 0.0999 0.00098 0.00183
Seal Coat (Case-II, Type B) 513 Sqm 0.0060 1.10 0.0666 0.00068 0.00127
13 Mastic asphalt 516 Sqm 0.0274 5.01 0.3038 0.00583 0.01086 --- --- ---
14 GSB with closely graded
401 Cum 1.2773 233.88 14.1784 --- --- 1.2773 236.72 17.0141
material Grade I
15 GSB with closely graded
401 Cum 1.2800 234.37 14.2080 --- --- 1.2800 237.21 17.0496
material Grade II and III
16 GSB with coarse graded
401 Cum 1.2800 234.37 14.2080 --- --- 1.2800 237.21 17.0496
material ( Grade I ,II, III )
RA - 67
Rates for carraiage of meterials including loading & unloading on surface roads
RA - 68
Rates of Material for the Year 2018-19
Machine
Initial rate after Total Rate as per
crushing Blasting
S.NO Description of Material Unit deducting stcaking SSR 2018-19
charges @ charges
charges excluding taxes
25%
1 75mm metal (IS 383,1970) Cum 289.50 ---- 0.00 289.50
2 65mm metal (IS 383,1970) Cum 360.95 ---- 70.00 430.95
3 60 - 63 mm metal (IRC-MORTH)
Cum 399.05 99.76 70.00 568.81
4 60 - 63 mm metal (Hand broken) Cum 389.15 70.00 459.15
5 50 - 55 mm metal (IRC-MORTH)
Cum 434.30 108.58 70.00 612.88
6 50 - 55 mm metal (Hand broken) Cum 424.40 70.00 494.40
7 40 - 45 mm metal (IRC-MORTH)Cum 560.00 140.00 70.00 770.00
8 40 -45 mm metal (Hand broken) Cum 550.10 70.00 620.10
9 25 - 27 mm metal (IRC-MORTH)Cum 899.05 224.76 70.00 1193.81
10 25 - 27 mm metal (Hand Broken) Cum 889.15 70.00 959.15
11 20 - 22 mm metal (IRC-MORTH)Cum 937.15 234.29 70.00 1241.44
12 20 - 22 mm metal (Hand broken) Cum 927.25 70.00 997.25
13 12 - 14 mm metal (IRC-MORTH)Cum 742.85 185.71 70.00 998.56
14 10 - 11.2 mm metal (IRC-MORTH)
Cum 624.75 156.19 70.00 850.94
15 5mm to 7mm metal (IRC-MORTH)
Cum 480.00 120.00 70.00 670.00
16 2.36mm to 5mm metal (IRC-MORTH)
Cum 293.35 73.34 70.00 436.69
17 Stone dust(HBG stone chips
Cum 333.00 ---- ----
2.36 mm and below ) 333.00
18 Stone boulders of size 150mm Cum 90.50 ---- 70.00 160.50
Supply of stone 150 -200 mm
Cum 168.55 ---- 70.00
19 size 238.55
Boulder with minimum size of
Cum 163.80 ----
20 300 mm for Pitching at Site 163.80
21 Lime Cum 940.00 ---- 940.00
22 Gravel Cum 110.00 ---- ---- 110.00
23 Sand for mortar (Concrete) Cum 182.00 ---- ---- 182.00
24 Sand for filling, blindage Cum 100.00 ---- ---- 100.00
25 Bulk Bitumen Grade 30/40 MT 33760.00 ---- ---- 33760.00
26 Bulk Bitumen Grade 80/100 MT 31690.00 ---- ---- 31690.00
27 Modified Bitumen CRMB55 MT 33670.00 ---- ---- 33670.00
28 Bitumen emulsion (Bulk) MT 35790.00 ---- ---- 35790.00
29 Cement MT 3900.00 ---- ---- 3900.00
30 20 mm metal SS 5 (IS383,1970) Cum 986.40 246.60 70.00 1303.00
31 40 mm metal ss5 (IS383,1970) Cum 590.40 147.60 70.00 808.00
32 10 mm metal ss5 (IS383,1970) Cum 659.20 164.80 70.00 894.00
33 RR masonary (Granite) Cum 240.00 70.00 310.00
34 CR masonary Cum 274.30 70.00 344.30
35 Bond stone each 47.60 ---- ---- 47.60
36 Fe 500 steel MT 42500.00 42500.00
37 Mild steel rods MT 39674.00 39674.00
38 Structural steel MT 42000.00 42000.00
39 HT wire 4mm MT 35556.00 35556.00
40 Murrum Cum 185.00 185.00
RA - 69
SOR 2018- 19 RMR
Average rates of material
S.No Description Unit Average Rate
1 Aggregates below 5.6mm Cum 384.84
2 Aggregates 22.4 mm to 2.36 mm Cum 839.53
3 Aggregates 22.4 mm to 5.6 mm Cum 940.23
4 Aggregates 45 mm to 2.8 mm Cum 880.21
5 Aggregates 45 mm to 22.4 mm Cum 1068.42
6 Aggregates 53 mm to 2.8 mm Cum 846.79
7 Aggregates 53 mm to 22.4 mm Cum 954.53
8 Aggregates 63 mm to 2.8 mm Cum 815.90
9 Aggregates 63 mm to 45 mm Cum 650.56
10 Aggregates 10 mm to 5 mm Cum 760.47
11 Aggregates 11.2 mm to 0.99 mm Cum 572.66
12 Aggregates 13.2 mm to 0.99 mm Cum 657.84
13 Aggregates 13.2mm to 5.60 mm Cum 839.83
14 Aggregates 13.2 mm to 10 mm Cum 924.75
15 Aggregates 20 mm to 10 mm Cum 1030.31
16 Aggregates 25 mm to 10 mm Cum 1071.19
17 Aggregates 19 mm to 6 mm Cum 940.23
18 Aggregates 37.5 mm to 19 mm Cum 1068.42
19 Aggregates 37.5 mm to 25 mm Cum 981.91
20 Aggregates 6mm nominal size Cum 670.00
21 Aggregates 10 mm nominal size Cum 850.94
22 Aggregates 13.2/12.5 mm nominal size Cum 998.56
23 Aggregates 20 mm nominal size Cum 1241.44
24 Aggregates 25 mm nominal size Cum 1193.81
25 Aggregates 40 mm nominal size Cum 770.00
26 Filter media avg of 150mm & 40mm) (Hand broken) Cum 390.30
27 Aggregates 45 mm to 22.4 mm (Hand Broken) Cum 858.83
28 Aggregates 53 mm to 22.4 mm (Hand Broken) Cum 767.73
29 Aggregates 90 mm to 45 mm (Hand Broken) Cum 458.82
30 Aggregates 63 mm to 45 mm (Hand Broken) Cum 524.55
31 Aggregates 4.75 mm to 75 microns Cum 384.84
32 Aggregates 37.5 mm to 9.5 microns Cum 811.80
33 Aggregates 9.5 mm to 75 microns Cum 572.66
34 Aggregates 53 to 26.5 Cum 858.90
35 Aggregates 26.5 to 4.75 Cum 990.95
36 Aggergates 9.5 mm to 4.75 mm Cum 760.47
37 Aggregates 2.36 mm and below (stone dust) Cum 333.00
38 Aggregates 53mm to 9.5 mm Cum 944.60
39 Aggregates 26.5mm to 9.5 mm Cum 1071.19
40 Aggregates 9.5 mm to 2.36 mm Cum 652.54
41 Aggregates 4.75mm to 2.36 mm Cum 436.69
42 Aggregates 20mm SS 5 Cum 1303.00
RA - 71
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Cost for 12.5 metres = a+b+c+d 109869.94
Rate per metre = (a+b+c+d)/12.5 8789.60
say 8790.00
e) seigniorage charges per cum
Coarse Sand cum 0.01 50.00 0.28
Granular material cum 0.36 30.00 10.80
Add District Mineral Fund (DMF) 30% on Seinorage 0.300 11.08 3.32
charges
Rate per cum say 14.40
a) Add lead charges for NP-4 class 1000mm dia pipes in 41.00 Km 691.92
single row.
b) Add lead charges for Granular Material 25.00 Km 0.36 181.80 65.45
c) Add lead charges for Sand 41.00 Km 0.01 4.02 0.02
d) Add lead charges of Manufactured Sand 25.00 Km 0.000 2.83 0.00
say 757.39
Total rate 9561.79
Say 9562.00
Note 1. In case of cement craddle bedding, quantity of PCC M15
is to be calculated as per design and priced separately and
added .
2. The rate analysis does not include excavation, cement
/masonry works in head walls, backfilling, protection works
and parapet walls. The same are to be calculated as per
approved design and drawings and priced separately on
rates available under respective sections
RA - 72
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
2. The rate analysis does not include excavation, cement
/masonry works in head walls, backfilling, protection works
and parapet walls. The same are to be calculated as per
approved design and drawings and priced separately on
rates available under respective sections
9.3 2900 Laying Reinforced Cement Concrete Pipe NP4 /
Prestressed Concrete Pipe on First Class Bedding in
Double Row .
Laying Reinforced cement concrete pipe NP4 / prestressed
concrete pipe for culverts on first class bedding of granular
material in double row including fixing collar with cement
mortar 1:2 but excluding excavation, protection works,
backfilling, concrete
Unit = metre
Taking output = 12.5 metres ( 10 pipes of 2.5 m length
each in two rows.)
A 1000 mm dia
a) Labour
Mate day 0.360 451.00 162.36
Mason day 1.000 455.00 455.00
Mazdoor day 8.000 400.00 3200.00
b) Material
Sand at site cum 0.140 182.00 25.48
Cement at site tonne 0.100 3900.00 390.00
RCC pipe NP-4/prestressed concrete pipe including metre 25.000 7578.00 189450.00
collar at site
Granular material passing 5.6 mm sieve for bedding cum 12.500 110.00 1375.00
RA - 73
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
RCC pipe NP-4 /prestressed concrete pipe including metre 25.000 10340.00 258500.00
collar at site
Granular material passing 5-6 mm sieve for class cum 13.750 110.00 1512.50
bedding
c) Overhead charges @ 2.615% on (a+b) 6970.38
d) Contractor's profit @ 10% on (a+b+c) 27352.42
Cost for 12.5 metres = a+b+c+d 300876.62
Rate per metre= (a+b+c+d)/12.5 24070.13
Note 1. In case of cement craddle bedding, quantity of PCC M15 say 24070.00
is to be calculated as per design and priced separately and
added .
e) seigniorage charges per cum
Coarse Sand cum 0.01 50.00 0.72
Granular material cum 1.10 30.00 33.00
Add District Mineral Fund (DMF) 30% on Seinorage 0.300 33.72 10.12
charges
Rate per cum say 43.84
a) Add lead charges for NP-4 class 1200mm dia pipes in 41.00 Km 1507.16
double row.
b) Add lead charges for Granular Material 25.00 Km 1.10 555.50 611.05
c) Add lead charges for Sand 41.00 Km 0.01 10.34 0.15
d) Add lead charges of Manufactured Sand 25.00 Km 0.00 7.27 0.00
say 2118.36
Total rate 26232.32
Say 26232.00
Note 1. In case of cement craddle bedding, quantity of PCC M15
is to be calculated as per design and priced separately and
added .
2. The rate analysis does not include excavation, cement
/masonry works in head walls, backfilling, protection works
and parapet walls. The same are to be calculated as per
approved design and drawings and priced separately on
rates available under respective sections
9.2 a 2900 Laying Reinforced Cement Concrete Pipe NP4 /
Prestressed Concrete Pipe on First Class Bedding in
Single Row .
Laying Reinforced cement concrete pipe NP4/prestressed
concrete pipe for culverts on first class bedding of granular
material in single row including fixing collar with cement
mortar 1:2 but excluding excavation, protection works,
backfilling, concrete an
Unit = metre
Taking output = 12.5 metres ( 5 pipes of 2.5 m length
each )
A 600 mm dia
a) Labour
Mate day 0.180 451.00 81.18
Mason day 0.500 455.00 227.50
Mazdoor day 4.000 400.00 1600.00
b) Material
Sand at site cum 0.070 182.00 12.74
Cement at site tonne 0.050 3900.00 195.00
RCC pipe NP-4 /prestressed concrete pipe including metre 12.500 2545.00 31812.50
collar at site
Granular material passing 5.6 mm sieve for bedding cum 4.500 110.00 495.00
RA - 74
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Granular material cum 0.36 30.00 10.80
Add District Mineral Fund (DMF) 30% on Seinorage 0.300 11.08 3.32
charges
Rate per cum say 14.40
a) Add lead charges for NP-4 class 600mm dia pipes in 41.00 Km 352.39
single row.
b) Add lead charges for Granular Material 25.00 Km 0.36 181.80 65.45
c) Add lead charges for Sand 41.00 Km 0.01 4.02 0.02
d) Add lead charges of Manufactured Sand 25.00 Km 0.00 2.83 0.00
say 417.86
Total rate 3540.79
Say 3541.00
RA - 75
Rates for conveyance of R.C.C. NP-4 plain ended pipes
RA - 77
Rates for carriage of materials including loading and unloading on surfaces and un-
surface roads
2 Laying reinforced cement 2900 Mtr 0.36 67.69 5.77 0.0056 1.053 0.090
concrete pipe NP4/Pre
stressed concrete pipe on
first class bedding in single
row 1000 mm dia (Un-
Surface roads)
3 Laying reinforced cement 2900 Mtr 0.40 74.13 5.33 0.0072 1.334 0.096
concrete pipe NP4/Pre
stressed concrete pipe on
first class bedding in single
row 1200 mm dia (Surface
roads)
4 Laying reinforced cement 2900 Mtr 0.40 75.21 6.41 0.0072 1.354 0.115
concrete pipe NP4/Pre
stressed concrete pipe on
first class bedding in single
row 1200 mm dia (Un-
Surface roads)
5 Laying reinforced cement 2900 Mtr 1.00 185.32 13.32 0.0112 2.076 0.149
concrete pipe NP4/Pre
stressed concrete pipe on
first class bedding in double
row 1000 mm dia (Surface
roads)
7 Laying reinforced cement 2900 Mtr 1.10 203.85 14.65 0.0144 2.669 0.192
concrete pipe NP4/Pre
stressed concrete pipe on
first class bedding in double
row 1200 mm dia (Surface
roads)
8 Laying reinforced cement 2900 Mtr 1.10 206.82 17.62 0.0144 2.707 0.231
concrete pipe NP4/Pre
stressed concrete pipe on
first class bedding in double
row 1200 mm dia (Un-
Surface roads)
1 PCC (1:3:6) 408 cum 0.92 x 1.5 or 1.380 MT 168.452 10.212 Metal on surface roads
2 PCC (1:3:6) 408 cum 0.92 x 1.5 or 1.380 MT 170.522 12.282 Metal on un-surface roads
0.46 x 1.80 or 0.83
3 PCC (1:3:6) 408 cum 85.262 6.142 Sand on surface roads
cum
0.46 x 1.80 or 0.83
4 PCC (1:3:6) 408 cum 86.507 7.387 Sand on un-surface roads
cum
(WC2)c = 3.14/4*(1.638*1.638-1.45*1.45)*0.2*360
32.812 kg/collar
For pipe of 1000mmØ (Ws1)p=6.04 kg/m
(WC1)p = 3.14/4*(1.23*1.23-1*1)*360
144.95 kg/m
For pipe of 1200mmØ (Ws2)p=6.04 kg/m
(WC2)p = 3.14/4*(1.45*1.45-1.2*1.2)*360
187.22 kg/m
6 MM R1=[(44000-41500)/1000*6.04 = Rs 15.1
RODS Rs- 15.1
6 MM R1=[(44000-41500)/1000*6.04 = Rs 15.1
RODS
R2=[(3900-3882)/1000*187.22 = Rs 3.370005
cement
6 MM R1=[(44000-41500)/1000*0.33 = Rs 0.825
RODS per collar 0.825
RA - 81
b Revised Cost=947+R1+R2 = Rs 948.2458249
per collar 948.2458249
6 MM R1=[(44000-41500)/1000*0.50 = Rs 1.25
RODS
R2=[(3900-3882)/1000*32.812 = Rs 0.590622244
cement
Revised Cost=1505+R1+R2 = Rs 1506.840622
per collar 1506.840622
RA - 82
For Pipes of 300, 600 & 900 mm dia
The weight of cement and steel for pipe
and collar are calculated as per
IS.458/2003. Table 22 & 8
6 MM R1=[(44000-41500)/1000*0.78 = Rs 1.95
RODS Rs- 1.95
6 MM R1=[(44000-41500)/1000*2.34 = Rs 5.85
RODS Rs- 5.85
RA - 83
For pipe of 900mmØ
R1=[(44000-41500)/1000*3.44 = Rs 8.6
R2=[(3900-3882)/1000*113.040 = Rs 58.55
R1=[(44000-41500)/1000*0.11 = Rs 0.28
per collar
R2=[(3900-3882)/1000*3.479 = Rs 1.80
per collar
R1=[(44000-41500)/1000*0.23 = Rs 0.58
per collar
R2=[(3900-3882)/1000*10.791 = Rs 0.19
per collar
R1=[(44000-41500)/1000*0.33 = Rs 0.825
R2=[(3900-3882)/1000*19.641 = Rs 0.35
RA - 84
CHAPTER-12
FOUNDATIONS
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
12.1 304 Excavation for Structures
Earth work in excavation of foundation of structures as per
drawing and technical specification, including setting out,
construction of shoring and bracing, removal of stumps and
other deleterious matter, dressing of sides and bottom and
backfilling with
I Ordinary soil
Unit = cum
Taking output = 10 cum
A Manual Means
(i) Depth upto 3 m
a) Labour
Mate day 0.14 451.00 63.14
Mazdoor day 3.50 400.00 1400.00
b) Overhead charges @ 2.615% on (a) 38.26
c) Contractor's profit @ 10% on (a+b) 150.14
Cost for 10 cum = a+b+c 1651.54
Rate per cum = (a+b+c)/10 165.15
Total 165.00
Note 1. Cost of dewatering may be added where required upto, 10
per cent of labour cost Assessment for dewatering shall be
made as per site conditions.
2.The excavated earth can be used partially for backfilling of
foundation pit and partly for road work except for marshy soil.
Hence cost of disposal has not been added except for
marshy soil. This remark is common to all cases of item 12.1
excluding mars
3.The cost of shoring and shuttering, where needed, may be
added @ 1 per cent on cost of excavation for open
foundation.
12.1 (I) (ii) Depth 3 m to 6 m
A
a) Labour
Mate/Supervisor day 0.18 451.00 81.18
Mazdoor day 4.50 400.00 1800.00
b) Overhead charges @ 2.615% on (a) 49.19
c) Contractor's profit @ 10% on (a+b) 193.04
Cost for 10 cum = a+b+c 2123.41
Rate per cum = (a+b+c)/10 212.34
Total 212.00
Note Cost of dewatering may be added where required upto 15
per cent of labour cost. Assessment for dewatering shall be
done as per actual ground conditions.
12.1 (I) (iii) Depth above 6 m
A
a) Labour
Mate/Supervisor day 0.24 451.00 108.24
Mazdoor day 6.00 400.00 2400.00
b) Overhead charges @ 2.615% on (a) 65.59
c) Contractor's profit @ 10% on (a+b) 257.38
Cost for 10 cum = a+b+c 2831.21
Rate per cum = (a+b+c)/10 283.12
Total 283.00
Note 1. Cost of dewatering may be added where required upto 20
per cent of labour cost. Assessment for dewatering shall be
made as per site conditions..
12.1 (I) B Mechanical Means
(i) Depth upto 3 m
Unit = cum
Taking output = 240 cum
a) Labour
Unit : cum
Taking Output = 120 cum
a) Material
Cement tonne 41.66 3900.00 162474.00
Coarse Sand cum 54.00 182.00 9828.00
20 mm Aggregate cum 64.80 1303.00 84434.40
10 mm Aggregate cum 43.20 894.00 38620.80
b) Labour
Mate day 0.84 451.00 378.84
Mason day 3.00 455.00 1365.00
Mazdoor day 18.00 400.00 7200.00
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1343.30 8059.80
Generator 100 KVA hour 6.00 1316.30 7897.80
Loader 1 cum capacity hour 6.00 1594.70 9568.20
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 2071.70 31075.50
Lead beyond 1 km, L-lead in km tonne.km 300L 13.18 31634.26
Unit = Nos.
Taking output = 30 Nos.
a) Material
AC pipe 100 mm dia. (including wastage @ 5 per cent ) metre 31.50 253.00 7969.50
b) Labour
Mate day 0.03 451.00 13.53
Mason day 0.50 455.00 227.50
Mazdoor day 0.25 400.00 100.00
c) Overhead charges @ 2.615% on (a+b) 228.36
d) Contractor's profit @ 10% on (a+b+c) 896.09
Cost for 30 m = a+b+c+d 9856.97
Rate per m (a+b+c+d)/30 328.57
Total 329
Note 1. In case of stone masonry, the size of the weep hole shall be
150 mm x 80 mm or circular with 150 mm diameter.
Unit = cum
Taking output = 10 cum.
a) Labour
Mate day 0.32 451.00 144.32
Mazdoor for filling, watering, ramming etc. day 7.00 400.00 2800.00
Mazdoor (Skilled) day 1.00 515.00 515.00
b) Material
Filter media of stone aggregate conforming to clause cum 12.00 597.90 7174.80
2504.2.2. of MoRTH specifications.
c) Machinery
Water Tanker of 6 KL capacity hour 0.06 655.20 39.31
d) Overhead charges @ 2.615% on (a+b+c) 279.11
e) Contractor's profit @ 10% on (a+b+c+d) 1095.25
cost for 10 cum of Fiter Media = a+b+c+d+e 12047.80
Rate per cum = (a+b+c+d+e)/10 1204.78
say 1205
Add seignorage charges of metal cum 1.20 75.00 90.00
Add District Mineral Fund (DMF) 30% on Seinorage 0.300 90.00 27.00
charges
Add lead charges of metal 25.00 Km 1.20 449.50 539.40
TOTAL Rate Total 1861.00
13.14 2000 & Supplying, fitting and fixing in position true to line and
2200 level elastomeric bearing conforming to IRC: 83 (Part-II)
section IX and clause 2005 of MoRTH specifications
complete including all accessories as per drawing and
Technical Specifications.
Unit: one cubic centimetre
Considering an elastomeric bearing of size 500 x 400 x 96 mm
for this analysis.
Overall volume - 19200 cu.cm
Volume of 6 nos. 488 x 388 x 4 mm size reinforcing steel
plates = 4545 cu.cm.
Hence volume of elastometer = 14655 cu.cm.
a) Labour
Mate day 0.06 451.00 27.06
Mazdoor day 1.00 400.00 400.00
Mazdoor (Skilled) day 0.50 515.00 257.50
b) Material
Total 1
Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 51.60 3900.00 201240.00
Coarse sand cum 54.00 182.00 9828.00
20 mm Aggregate cum 64.80 1303.00 84434.40
10 mm Aggregate cum 43.20 894.00 38620.80
Admixture @ 0.4 per cent of cement kg 206.40 43.00 8875.20
b) Labour
Mate day 0.94 451.00 423.94
Mason day 3.50 455.00 1592.50
Mazdoor day 20.00 400.00 8000.00
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1343.30 8059.80
Generator 100 KVA hour 6.00 1316.30 7897.80
Loader hour 6.00 1594.70 9568.20
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity lead upto1 Km hour 15.00 2071.70 31075.50
Lead beyond 1 Km, L - lead in Kilometer tonne.km 300L 13.18 31634.26
Unit = sqm
Taking output = 10 sqm
a) Labour
Mate day 0.01 451.00 4.51
Painter day 0.25 473.00 118.25
Mazdoor (Skilled) day 0.25 515.00 128.75
b) Material
Water based paint of approved quality for cement Litres 5.00 51.00 255.00
concrete surface
c) Overhead charges @ 2.615% on (a+b) 13.25
d) Contractor's profit @ 10% on (a+b+c) 51.98
Cost for 10 sqm (a+b+c+d) 571.73
Rate per sqm (a+b+c+d)/10 57.17
Total 57.00
DEDUC
INITIAL RATE T MACHINE SEIGNO Total Rate as
S. excluding STACK CRUSHING BLASTING RAGE per SSR 2018-
DESCRIPTION OF THE MATERIAL UNIT
NO stacking ING CHARGES CHARGES CHARGE 19 excluding
charges CHARG @ 25% S Taxes
ES
1 40 mm SS 5 metal (IS383,1970) Cum 590.4 147.60 70.00 808.00
2 20 mm SS 5 metal (IS383,1970) Cum 986.40 246.60 70.00 1303.00
3 25 mm SS 5 metal (IS383,1970) Cum 947.2 236.80 70.00 1254.00
4 10 mm SS 5 metal (IS383,1970) Cum 659.20 164.80 70.00 894.00
5 6 mm SS 5 metal (IS383,1970) Cum 506.4 126.60 70.00 703.00
6 Gravel Cum 110.00 110.00
7 Sand for mortar Cum 182 182.00
8 Sand for filling, blindage Cum 100 100.00
9 12 mm SS 5 metal (IS383,1970) Cum 782.4 195.60 70.00 1048.00
10 RR masonary (Granite) Cum 240 70.00 310.00
11 CR masonary (Granite) Cum 274.3 70.00 344.30
Stone boulder of size 150 mm size
90.50
12 Cum 70.00 160.50
Stone boulder of size 150-200mm
168.55
13 size Cum 70.00 238.55
163.80
14 Stone boulder of size 300 mm size Cum 70.00 233.80
Stone dust (HBG stone chips 2.36
333.00
15 mm and below) Cum 333.00
16 Sand for mortar Cum 182 182.00
17 Bulk Bitumen Grade 30/40 mt 33760.00 33760.00
18 Bulk Bitumen Grade 80/100 mt 31690.00 31690.00
19 Modified Bitumen CRMB55 mt 33670.00 33670.00
20 Bitumen emulsion (Bulk) mt 35790.00 35790.00
21 Cement mt 3900.00 3900.00
22 Fe 500 steel mt 42500.00 42500.00
23 Mild steel rods mt 39674.00 39674.00
24 Structural steel mt 42000.00 42000.00
25 HT wire 4mm mt 35556.00 35556.00
26 40 mm metal (hand broken) Cum 580.50 70.00 650.50
27 Moorum at Site Cum 185.00 185.00
28 2.36mm to 5mm metal (IRC-MORTH) Cum 293.35 73.3375 70.00 436.69
1 METAL / STONE / RUBBLE STONE 183.10 11.10 185.35 13.35 198.85 26.85
RA - 115
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Hydraulic excavator 1.0 cum bucket capacity hour 6.00 2791.60 16749.60
c) Overhead charges @ 14.615% on (a+b) 2936.73
d) Contractor's profit @ 10% on (a+b+c) 2303.06
Cost for 240 cum = a+b+c+d 25333.71
Rate per cum = (a+b+c+d)/240 105.56
Total 106.00
Note Cost of dewatering upto 5 per cent of (a+b) may be added,
where required. Assessment for dewatering shall be made
as per site conditions..
12.1 (I) (ii) Depth 3 m to 6 m
B
Unit = cum
Taking output = 210 cum
a) Labour
Mate day 0.32 451.00 144.32
Mazdoor day 8.00 400.00 3200.00
b) Machinery
Hydraulic excavator 1.0 cum bucket capacity hour 6.00 2791.60 16749.60
c) Overhead charges @ 14.615% on (a+b) 2936.73
d) Contractor's profit @ 10% on (a+b+c) 2303.06
Cost for 210 cum = a+b+c+d 25333.71
Rate per cum = (a+b+c+d)/210 120.64
Total 121.00
Note Cost of dewatering upto 7.5 per cent of (a+b) may be
added, where required. Assessment for dewatering shall be
made as per site conditions..
12.1 (I) (iii) Depth above 6m
B
Unit = cum
Taking output = 180 cum
a) Labour
Mate day 0.40 451.00 180.40
Mazdoor day 10.00 400.00 4000.00
b) Machinery
Hydraulic excavator 1.0 cum bucket capacity hour 6.00 2791.60 16749.60
c) Overhead charges @ 14.615% on (a+b) 3058.92
d) Contractor's profit @ 10% on (a+b+c) 2398.89
Cost for 180 cum = a+b+c+d 26387.81
Rate per cum = (a+b+c+d)/180 146.60
Total 147.00
Note 1. Cost of dewatering upto 10 per cent of (a+b) may be
added, where required. Assessment for dewatering shall be
made as per site conditions..
2.Labour provided for excavation by mechanical means
includes that required for trimming of bottom and side
slopes.
12.1 II Ordinary Rock (not requiring blasting)
A Manual Means
(i) Depth upto 3 m
Unit = cum
Taking output = 10 cum
a) Labour
Mate day 0.20 451.00 90.20
Mazdoor day 5.00 400.00 2000.00
b) Overhead charges @ 14.615% on (a) 305.48
c) Contractor's profit @ 10% on (a+b) 239.57
Cost for 10 cum = a+b+c 2635.25
Rate per cum = (a+b+c)/10 263.53
Total 264.00
Note Cost of dewatering upto 10 per cent of labour cost may be
added, where required. Assessment for dewatering shall be
made as per site conditions..
12.1(II) B Mechanical Means
RA - 116
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Unit = cum
Taking output = 180 cum
a) Labour
Mate day 0.24 451.00 108.24
Mazdoor day 6.00 400.00 2400.00
b) Machinery
Hydraulic excavator 1.0 cum bucket capacity hour 6.00 2791.60 16749.60
c) Overhead charges @ 14.615% on (a+b) 2814.53
d) Contractor's profit @ 10% on (a+b+c) 2207.24
Cost for 180 cum = a+b+c+d 24279.61
Rate per cum = (a+b+c+d)/180 134.89
Total 135.00
Note 1.Cost of dewatering upto 10 per cent of (a+b), may be
added, where required Assessment for dewatering shall be
made as per site conditions.
2.In case of rock, foundation beyond3 m is not dug and
hence not included.
12.1 III Hard Rock ( requiring blasting )
A Manual Means
Unit = cum
Taking output = 10 cum
a) Labour
Mate day 0.35 451.00 157.85
Driller day 0.50 550.00 275.00
Blaster day 0.25 550.00 137.50
Mazdoor day 8.00 400.00 3200.00
b) Machinery
Air Compressor 250 cfm with 2 jack hammer for hour 1.00 556.50 556.50
drilling.
c) Material
Blasting Material kg 3.50 57.00 199.50
Detonator electric each 14.00 9.00 126.00
d) Overhead charges @ 14.615% on (a+b+c) 679.94
e) Contractor's profit @ 10% on (a+b+c+d) 533.23
Cost for 10 cum = a+b+c+d+e 5865.52
Rate per cum = (a+b+c+d+e)/10 586.55
Total 587.00
Note Cost of dewatering @ 10 per cent of (a+b) may be
added, where required Assessment for dewatering shall be
made as per site conditions.
12.8 1500, 1700 Plain/Reinforced Cement Concrete in Open Foundation
& 2100 complete as per Drawing and Technical Specifications.
RA - 117
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
d) Formwork @ 4 per cent on cost of concrete i.e. cost 1985.30
of material, labour and machinery
RA - 118
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
12.8 G Case II Using Batching Plant, Transit Mixer and Concrete Pump
Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 48.80 3900.00 190320.00
Coarse sand cum 54.00 182.00 9828.00
20 mm Aggregate cum 64.80 1303.00 84434.40
10 mm Aggregate cum 43.20 894.00 38620.80
Admixture Kg 195.20 43.00 8393.60
b) Labour
Mate day 0.84 451.00 378.84
Mason day 3.00 455.00 1365.00
Mazdoor day 18.00 400.00 7200.00
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1343.30 8059.80
Generator 100 KVA hour 6.00 1316.30 7897.80
Loader 1 cum capacity hour 6.00 1594.70 9568.20
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 2071.70 31075.50
Transit Mixer 4 cum capacity lead beyond 1 Km, L - tonne.km 300L 13.18 31634.26
lead in Kilometer
Concrete Pump hour 6.00 1508.80 9052.80
Per Cum Basic Cost of Labour, Material & Machinery 3649.00
(a+b+c)
d) Formwork @ 3.5 per cent of cost of concrete i.e. cost 15324.01
of material, labour and machinery
e) Overhead charges @ 14.615% on (a+b+c+d) 66228.31
f) Contractor's profit @ 10% on (a+b+c+d+e) 51938.13
cost of 120 cum = a+b+c+d+e+f 571319.46
Rate per cum (a+b+c+d+e+f )/120 4761.00
say 4761.00
g) seigniorage charges per cum
Coarse Sand 0.45 50.00 22.50
Aggregate 0.90 75.00 67.50
Add District Mineral Fund (DMF) 30% on Seinorage 0.300 90.00 27.00
charges
Rate per cum say 117.00
Add lead charges of metal 25.00 Km 0.90 504.25 453.83
Add lead charges of sand 41.00 Km 0.45 805.54 362.49
Add lead charges of Manufactured Sand 25.00 Km 0.00 566.50 0.00
816.32
TOTAL Rate Total 5694.00
12.8 H RCC Grade M35
12.8 H Case II Using Batching Plant, Transit Mixer and Concrete Pump
Unit ; cum
Taking Output = 120 cum
a) Material
Cement tonne 50.64 3900.00 197496.00
Coarse sand cum 54.00 182.00 9828.00
20 mm Aggregate cum 64.80 1303.00 84434.40
10 mm Aggregate cum 43.20 894.00 38620.80
Admixture Kg 202.56 43.00 8710.08
b) Labour
Mate day 0.84 451.00 378.84
Mason day 3.00 455.00 1365.00
Mazdoor day 18.00 400.00 7200.00
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1343.30 8059.80
Generator 100 KVA hour 6.00 1316.30 7897.80
Loader1 cum capacity hour 6.00 1594.70 9568.20
RA - 119
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Transit Mixer 4 cum capacity for lead upto 1 km. hour 15.00 2071.70 31075.50
Transit Mixer 4 cum capacity lead beyond 1 Km, L - tonne.km 300L 13.18 31634.26
lead in Kilometer
Concrete Pump hour 6.00 1508.80 9052.80
Per Cum Basic Cost of Labour, Material & Machinery 3712.00
(a+b+c)
d) Formwork @ 3 per cent on cost of concrete i.e. cost 13359.64
of material, labour and machinery
e) Overhead charges @ 14.615% on (a+b+c+d) 67036.25
f) Contractor's profit @ 10% on (a+b+c+d+e) 52571.74
cost of 120 cum = a+b+c+d+e+f 578289.10
Rate per cum = (a+b+c+d+e+f)/120 4819.08
say 4819.00
g) seigniorage charges per cum
Coarse Sand 0.45 50.00 22.50
Aggregate 0.90 75.00 67.50
Add District Mineral Fund (DMF) 30% on Seinorage 0.300 90.00 27.00
charges
Rate per cum say 117.00
Add lead charges of metal 25.00 Km 0.90 504.25 453.83
Add lead charges of sand 41.00 Km 0.45 805.54 362.49
Add lead charges of Manufactured Sand 25.00 Km 0.00 566.50 0.00
816.32
TOTAL Rate Total 5752.00
Note: Where ever concrete is carried out using batching plant,
transit mixer, concrete pump, Admixtures @ 0.4 per cent of
weight of cement may be added for achieving desired slump
of concrete.
12.22 1200 & Providing Steel Liner 10 mm thick for Curbs and 6 mm
1900 thick for Steining of Wells including Fabricating and
Setting out as per Detailed Drawing.
Unit = 1 MT
Taking output = 1 MT
a) Material
i) Structural steel including 5 per cent wastage tonne 1.05 42000 44100.00
b) Labour
Mate day 1.24 451.00 559.24
Fitter day 6.00 520.00 3120.00
Blacksmith day 5.00 440.00 2200.00
Welder day 5.00 482.20 2411.00
Mazdoor day 10.00 400.00 4000.00
Electrodes, cutting gas and other consumables @ 5 2205.00
per cent on cost a (a) above.
c) Overhead charges @ 14.615% on (a+b) 8563.69
d) Contractor's profit @ 10% on (a+b+c) 6715.89
Rate for per MT (a+b+c+d) 73874.83
Total 73875.00
12.25 1100 & Bored cast-in-situ M35 grade R.C.C. Pile excluding
1700 Reinforcement complete as per Drawing and Technical
Specifications and removal of excavated earth with all
lifts and lead upto 1000 m.
Pile diameter-1200 mm
Unit = meter
Taking output = 9 m
a) Materials
PCC Grade M35 cum 10.17 5738.00 58355.46
RA - 120
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Hire and running charges of hydraulic piling rig with hour 6.00 6131.70 36790.20
power unit and complete accessories including shifting
from one bore location to another.
Hire and running charges of light crane for lowering hour 0.50 429.60 214.80
reinforcement cage
Hire and running charges of Bentonite pump hour 6.00 Rate included
in piling rig
Loader I cum bucket capacity. hour 0.50 1594.70 797.35
Tipper 5.5 cum capacity for disposal of muck from pile hour 0.50 950.30 475.15
bore hole
Bentonite kg 385.00 7.00 2695.00
c) Labour
Mate/Supervisor day 0.18 451.00 81.18
Mazdoor day 4.50 400.00 1800.00
d) Overhead charges @ 14.615% on (b+c) 6263.07
e) Contractor's profit @ 10% on (b+c+d) 4911.67
Cost for 9 m = a+b+c+d+d+e 112383.88
Rate per metre (a+b+c+d+e)/9 12487.10
Total 12487.00
12.40 1600 Supplying, Fitting and Placing un-coated HYSD bar
Reinforcement in Foundation complete as per Drawing
and Technical Specifications.
Unit = 1 MT
Taking output = 1 MT
a) Material
HYSD bars including5 per cent overlaps and wastage tonne 1.05 42500 44625.00
RA - 121
CHAPTER-13
SUB-STRUCTURE
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
13.5 1500, Plain/Reinforced cement concrete in sub-structure
1700 & complete as per drawing and Technical Specifications
2200
Unit = cum
Taking output = 1 cum
13.5 E RCC Grade M20
(p) Height upto 5m
Same as Item 12.8 (C) upto 5 m height, except for formwork
which shall be 10 per cent instead of 4 per cent of cost of
material, labour and machinery.
Case Using concrete Mixer
I
Per Cum Basic Cost of Labour, Material & Machinery 3690.00
(a+b+c) of Item 12.8 (C) Case I
d) formwork
Add 10 per cent of cost of material, labour and 10.00 369.00
machinery (a+b+c) for Formwork
e) Overhead charges @ 14.615% on (a+b+c+d) 593.22
f) Contractor's profit @ 10% on (a+b+c+d+e) 465.22
Rate perm (a+b+c+d+e+f) 5117.45
say 5117
g) seinarage charges per cum
Coarse Sand 0.45 50.00 22.50
Aggregate 0.90 75.00 67.50
Add District Mineral Fund (DMF) 30% on Seinorage 0.300 90.00 27.00
charges
Rate per cum say 117.00
Add lead charges of metal 25.00 Km 0.90 504.25 453.83
Add lead charges of sand 41.00 Km 0.45 805.54 362.49
Add lead charges of Manufactured Sand 25.00 Km 0.00 566.50 0.00
TOTAL Rate Total 6051.00
13.5 E (p) Case With Batching Plant, Transit Mixer and Concrete Pump
II
Per Cum Basic Cost of Labour, Material & Machinery 3347.00
(a+b+c) of Item 12.8 (C) Case II
d) formwork
Add 10 per cent of cost of material, labour and 10.00 334.70
machinery (a+b+c) for Formwork
e) Overhead charges @ 14.615% on (a+b+c+d) 538.08
f) Contractor's profit @ 10% on (a+b+c+d+e) 421.98
Rate perm (a+b+c+d+e+f) 4641.76
say 4642
g) seinarage charges per cum
Coarse Sand 0.45 50.00 22.50
Aggregate 0.90 75.00 67.50
Add District Mineral Fund (DMF) 30% on Seinorage 0.300 90.00 27.00
charges
Rate per cum say 117.00
Add lead charges of metal 25.00 Km 0.90 504.25 453.83
Add lead charges of sand 41.00 Km 0.45 805.54 362.49
Add lead charges of Manufactured Sand 25.00 Km 0.00 566.50 0.00
TOTAL Rate Total 5575.00
13.5 E (q) Height 5m to 10m
For height, upto 10m, add 2 per cent of cost as above
excluding formwork. For cost of formwork add 12 per cent of
cost of material, labour and machinery instead of 4 per cent .
RA - 122
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
d) formwork
Add 12 per cent of cost of material, labour and 12.00 442.80
machinery (a+b+c) for Formwork
Add 2 per cent of cost of material, Labour and 2.00 73.80
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 14.615% on (a+b+c+d) 614.79
f) Contractor's profit @ 10% on (a+b+c+d+e) 482.14
Rate perm (a+b+c+d+e+f) 5303.53
say 5304
g) seinarage charges per cum
Coarse Sand 0.45 50.00 22.50
Aggregate 0.90 75.00 67.50
Add District Mineral Fund (DMF) 30% on Seinorage 0.300 90.00 27.00
charges
Rate per cum say 117.00
Add lead charges of metal 25.00 Km 0.90 504.25 453.83
Add lead charges of sand 41.00 Km 0.45 805.54 362.49
Add lead charges of Manufactured Sand 25.00 Km 0.00 566.50 0.00
TOTAL Rate Total 6237.00
13.5 E (q) Case With Batching Plant, Transit Mixer and Concrete Pump
II
Per Cum Basic Cost of Labour, Material & Machinery 3347.00
(a+b+c) of Item 12.8 (C) Case II
d) formwork
Add 12 per cent of cost of material, labour and 12.00 401.64
machinery (a+b+c) for Formwork
Add 2 per cent of cost of material, Labour and 2.00 66.94
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 14.615% on (a+b+c+d) 557.65
f) Contractor's profit @ 10% on (a+b+c+d+e) 437.32
Rate perm (a+b+c+d+e+f) 4810.55
say 4811
g) seinarage charges per cum
Coarse Sand 0.45 50.00 22.50
Aggregate 0.90 75.00 67.50
Add District Mineral Fund (DMF) 30% on Seinorage 0.300 90.00 27.00
charges
Rate per cum say 117.00
Add lead charges of metal 25.00 Km 0.90 504.25 453.83
Add lead charges of sand 41.00 Km 0.45 805.54 362.49
Add lead charges of Manufactured Sand 25.00 Km 0.00 566.50 0.00
TOTAL Rate Total 5744.00
13.5 E (r) Height above 10m
Same as Item 12.8 (C) with the following changes: (i) Add 4
per cent of cost of material, labour and machinery excluding
form work to cater for extra lift. (ii) The provision of form work
shall be 15 per cent instead of 4 per cent of cost of material,
RA - 123
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Aggregate 0.90 75.00 67.50
Add District Mineral Fund (DMF) 30% on Seinorage 0.300 90.00 27.00
charges
Rate per cum say 117.00
Add lead charges of metal 25.00 Km 0.90 504.25 453.83
Add lead charges of sand 41.00 Km 0.45 805.54 362.49
Add lead charges of Manufactured Sand 25.00 Km 0.00 566.50 0.00
TOTAL Rate Total 6469.00
13.5 E (r) Case With Batching Plant, Transit Mixer and Concrete Pump
II
Per Cum Basic Cost of Labour, Material & Machinery 3347.00
(a+b+c) of Item 12.8 (C) Case II
d) formwork
Add 15 per cent of cost of material, labour and 15.00 502.05
machinery (a+b+c) for Formwork
Add 4 per cent of cost of material, Labour and 4.00 133.88
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 14.615% on (a+b+c+d) 582.11
f) Contractor's profit @ 10% on (a+b+c+d+e) 456.50
Rate perm (a+b+c+d+e+f) 5021.54
say 5022
g) seinarage charges per cum
Coarse Sand 0.45 50.00 22.50
Aggregate 0.90 75.00 67.50
Add District Mineral Fund (DMF) 30% on Seinorage 0.300 90.00 27.00
charges
Rate per cum say 117.00
Add lead charges of metal 25.00 Km 0.90 504.25 453.83
Add lead charges of sand 41.00 Km 0.45 805.54 362.49
Add lead charges of Manufactured Sand 25.00 Km 0.00 566.50 0.00
TOTAL Rate Total 5955.00
13.5 G RCC Grade M30
(p) Height upto 5m
Same as Item 12.8 (G) upto 5m height, excluding formwork.
For cost of formwork, add 10 per cent of cost of material,
labour and machinery instead of 3.5 per cent .
RA - 124
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Add 10 per cent of cost of material, labour and 10.00 364.90
machinery (a+b+c) for Formwork
e) Overhead charges @ 14.615% on (a+b+c+d) 586.63
f) Contractor's profit @ 10% on (a+b+c+d+e) 460.05
Rate perm (a+b+c+d+e+f) 5060.58
say 5061
g) seinarage charges per cum
Coarse Sand 0.45 50.00 22.50
Aggregate 0.90 75.00 67.50
Add District Mineral Fund (DMF) 30% on Seinorage 0.300 90.00 27.00
charges
Rate per cum say 117.00
Add lead charges of metal 25.00 Km 0.90 504.25 453.83
Add lead charges of sand 41.00 Km 0.45 805.54 362.49
Add lead charges of Manufactured Sand 25.00 Km 0.00 566.50 0.00
TOTAL Rate Total 5994.00
13.5 G (q) Height 5m to 10m
For height, upto 10m, add 1.6 per cent of cost as above
excluding formwork. For cost of formwork add 11.5 per cent
of cost of material, labour and machinery
Case Using concrete Mixer
I
Per Cum Basic Cost of Labour, Material & Machinery 3922.00
(a+b+c) of Item 12.8 (G) Case I
d) formwork
Add 11.5 per cent of cost of material, labour and 11.50 451.03
machinery (a+b+c) for Formwork
Add 1.6 per cent of cost of material, Labour and 1.60 62.75
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 14.615% on (a+b+c+d) 648.29
f) Contractor's profit @ 10% on (a+b+c+d+e) 508.41
Rate perm (a+b+c+d+e+f) 5592.48
say 5592
g) seinarage charges per cum
Coarse Sand 0.45 50.00 22.50
Aggregate 0.90 75.00 67.50
Add District Mineral Fund (DMF) 30% on Seinorage 0.300 90.00 27.00
charges
Rate per cum say 117.00
Add lead charges of metal 25.00 Km 0.90 504.25 453.83
Add lead charges of sand 41.00 Km 0.45 805.54 362.49
Add lead charges of Manufactured Sand 25.00 Km 0.00 566.50 0.00
TOTAL Rate Total 6526.00
13.5 G (q) Case With Batching Plant, Transit Mixer and Concrete Pump
II
Per Cum Basic Cost of Labour, Material & Machinery 3649.00
(a+b+c) of Item 12.8 (G) Case II
d) formwork
Add 11.5 per cent of cost of material, labour and 11.50 419.64
machinery (a+b+c) for Formwork
Add 1.6 per cent of cost of material, Labour and 1.60 58.38
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 14.615% on (a+b+c+d) 603.16
f) Contractor's profit @ 10% on (a+b+c+d+e) 473.02
Rate perm (a+b+c+d+e+f) 5203.20
say 5203
g) seinarage charges per cum
Coarse Sand 0.45 50.00 22.50
Aggregate 0.90 75.00 67.50
Add District Mineral Fund (DMF) 30% on Seinorage 0.300 90.00 27.00
charges
Rate per cum say 117.00
Add lead charges of metal 25.00 Km 0.90 504.25 453.83
RA - 125
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Add lead charges of sand 41.00 Km 0.45 805.54 362.49
Add lead charges of Manufactured Sand 25.00 Km 0.00 566.50 0.00
TOTAL Rate Total 6137.00
13.5 G (r) Height above 10m
For height, above 10m, add 3.5 per cent of cost as above
excluding formwork. For cost of formwork add 14 per cent of
cost of material, labour and machinery
Case Using concrete Mixer
I
Per Cum Basic Cost of Labour, Material & Machinery 3922.00
(a+b+c) of Item 12.8 (G) Case I
d) formwork
Add 14 per cent of cost of material, labour and 14.00 549.08
machinery (a+b+c) for Formwork
Add 3.5 per cent of cost of material, Labour and 3.50 137.27
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 14.615% on (a+b+c+d) 673.51
f) Contractor's profit @ 10% on (a+b+c+d+e) 528.19
Rate perm (a+b+c+d+e+f) 5810.05
say 5810
g) seinarage charges per cum
Coarse Sand 0.45 50.00 22.50
Aggregate 0.90 75.00 67.50
Add District Mineral Fund (DMF) 30% on Seinorage 0.300 90.00 27.00
charges
Rate per cum say 117.00
Add lead charges of metal 25.00 Km 0.90 504.25 453.83
Add lead charges of sand 41.00 Km 0.45 805.54 362.49
Add lead charges of Manufactured Sand 25.00 Km 0.00 566.50 0.00
TOTAL Rate Total 6743.00
13.5 G (r) Case With Batching Plant, Transit Mixer and Concrete Pump
II
Per Cum Basic Cost of Labour, Material & Machinery 3649.00
(a+b+c) of Item 12.8 (G) Case II
d) formwork
Add 14 per cent of cost of material, labour and 14.00 510.86
machinery (a+b+c) for Formwork
Add 3.5 per cent of cost of material, Labour and 3.50 127.72
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 14.615% on (a+b+c+d) 626.63
f) Contractor's profit @ 10% on (a+b+c+d+e) 491.42
Rate perm (a+b+c+d+e+f) 5405.62
say 5406
g) seinarage charges per cum
Coarse Sand 0.45 50.00 22.50
Aggregate 0.90 75.00 67.50
Add District Mineral Fund (DMF) 30% on Seinorage 0.300 90.00 27.00
charges
Rate per cum say 117.00
Add lead charges of metal 25.00 Km 0.90 504.25 453.83
Add lead charges of sand 41.00 Km 0.45 805.54 362.49
Add lead charges of Manufactured Sand 25.00 Km 0.00 566.50 0.00
TOTAL Rate Total 6339.00
13.5 H RCC Grade M35
(p) Height upto 5m
Same as Item 12.8 (H) upto 5m height, excluding formwork.
For cost of formwork, add 10 per cent of cost of material,
labour and machinery instead of 3 per cent .
Case Using concrete Mixer
I
Per Cum Basic Cost of Labour, Material & Machinery 3981.00
(a+b+c) of Item 12.8 (H) Case I
d) formwork
RA - 126
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Add 10 per cent of cost of material, labour and 10.00 398.10
machinery (a+b+c) for Formwork
e) Overhead charges @ 14.615% on (a+b+c+d) 640.01
f) Contractor's profit @ 10% on (a+b+c+d+e) 501.91
Rate perm (a+b+c+d+e+f) 5521.02
say 5521
g) seinarage charges per cum
Coarse Sand 0.45 50.00 22.50
Aggregate 0.90 75.00 67.50
Add District Mineral Fund (DMF) 30% on Seinorage 0.300 90.00 27.00
charges
Rate per cum say 117.00
Add lead charges of metal 25.00 Km 0.90 504.25 453.83
Add lead charges of sand 41.00 Km 0.45 805.54 362.49
Add lead charges of Manufactured Sand 25.00 Km 0.00 566.50 0.00
TOTAL Rate Total 6454.00
13.5 H (p) Case With Batching Plant, Transit Mixer and Concrete Pump
II
Per Cum Basic Cost of Labour, Material & Machinery 3712.00
(a+b+c) of Item 12.8 (H) Case II
d) formwork
Add 10 per cent of cost of material, labour and 10.00 371.20
machinery (a+b+c) for Formwork
e) Overhead charges @ 14.615% on (a+b+c+d) 596.76
f) Contractor's profit @ 10% on (a+b+c+d+e) 468.00
Rate perm (a+b+c+d+e+f) 5147.96
say 5148
g) seinarage charges per cum
Coarse Sand 0.45 50.00 22.50
Aggregate 0.90 75.00 67.50
Add District Mineral Fund (DMF) 30% on Seinorage 0.300 90.00 27.00
charges
Rate per cum say 117.00
Add lead charges of metal 25.00 Km 0.90 504.25 453.83
Add lead charges of sand 41.00 Km 0.45 805.54 362.49
Add lead charges of Manufactured Sand 25.00 Km 0.00 566.50 0.00
TOTAL Rate Total 6081.00
13.5 H (q) Height 5m to 10m
For height, upto 10m, add 1.4 per cent of cost as above
excluding formwork. For cost of formwork add 11 per cent of
cost of material, labour and machinery .
Case Using concrete Mixer
I
Per Cum Basic Cost of Labour, Material & Machinery 3981.00
(a+b+c) of Item 12.8 (H) Case I
d) formwork
Add 11 per cent of cost of material, labour and 11.00 437.91
machinery (a+b+c) for Formwork
Add 1.4 per cent of cost of material, Labour and 1.40 55.73
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 14.615% on (a+b+c+d) 653.97
f) Contractor's profit @ 10% on (a+b+c+d+e) 512.86
Rate perm (a+b+c+d+e+f) 5641.47
say 5641
g) seinarage charges per cum
Coarse Sand 0.45 50.00 22.50
Aggregate 0.90 75.00 67.50
Add District Mineral Fund (DMF) 30% on Seinorage 0.300 90.00 27.00
charges
Rate per cum say 117.00
Add lead charges of metal 25.00 Km 0.90 504.25 453.83
Add lead charges of sand 41.00 Km 0.45 805.54 362.49
Add lead charges of Manufactured Sand 25.00 Km 0.00 566.50 0.00
RA - 127
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
TOTAL Rate Total 6575.00
13.5 H (q) Case With Batching Plant, Transit Mixer and Concrete Pump
II
Per Cum Basic Cost of Labour, Material & Machinery 3712.00
(a+b+c) of Item 12.8 (H) Case II
d) formwork
Add 11 per cent of cost of material, labour and 11.00 408.32
machinery (a+b+c) for Formwork
Add 1.4 per cent of cost of material, Labour and 1.40 51.97
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 14.615% on (a+b+c+d) 609.78
f) Contractor's profit @ 10% on (a+b+c+d+e) 478.21
Rate perm (a+b+c+d+e+f) 5260.27
say 5260
g) seinarage charges per cum
Coarse Sand 0.45 50.00 22.50
Aggregate 0.90 75.00 67.50
Add District Mineral Fund (DMF) 30% on Seinorage 0.300 90.00 27.00
charges
Rate per cum say 117.00
Add lead charges of metal 25.00 Km 0.90 504.25 453.83
Add lead charges of sand 41.00 Km 0.45 805.54 362.49
Add lead charges of Manufactured Sand 25.00 Km 0.00 566.50 0.00
TOTAL Rate Total 6194.00
13.5 H (r) Height above 10m
For height, above 10m, add 3 per cent of cost as above
excluding formwork. For cost of formwork add 13 per cent of
cost of material, labour and machinery
Case Using concrete Mixer
I
Per Cum Basic Cost of Labour, Material & Machinery 3981.00
(a+b+c) of Item 12.8 (H) Case I
d) formwork
Add 13 per cent of cost of material, labour and 13.00 517.53
machinery (a+b+c) for Formwork
Add 3 per cent of cost of material, Labour and 3.00 119.43
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 14.615% on (a+b+c+d) 674.91
f) Contractor's profit @ 10% on (a+b+c+d+e) 529.29
Rate perm (a+b+c+d+e+f) 5822.16
say 5822
g) seinarage charges per cum
Coarse Sand 0.45 50.00 22.50
Aggregate 0.90 75.00 67.50
Add District Mineral Fund (DMF) 30% on Seinorage 0.300 90.00 27.00
charges
Rate per cum say 117.00
Add lead charges of metal 25.00 Km 0.90 504.25 453.83
Add lead charges of sand 41.00 Km 0.45 805.54 362.49
Add lead charges of Manufactured Sand 25.00 Km 0.00 566.50 0.00
TOTAL Rate Total 6755.00
13.5 H (r) Case With Batching Plant, Transit Mixer and Concrete Pump
II
Per Cum Basic Cost of Labour, Material & Machinery 3712.00
(a+b+c) of Item 12.8 (H) Case II
d) formwork
Add 13 per cent of cost of material, labour and 13.00 482.56
machinery (a+b+c) for Formwork
Add 3 per cent of cost of material, Labour and 3.00 111.36
machinery excluding formwork to cater for extra lift
e) Overhead charges @ 14.615% on (a+b+c+d) 629.31
f) Contractor's profit @ 10% on (a+b+c+d+e) 493.52
Rate perm (a+b+c+d+e+f) 5428.75
RA - 128
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
say 5429
g) seinarage charges per cum
Coarse Sand 0.45 50.00 22.50
Aggregate 0.90 75.00 67.50
Add District Mineral Fund (DMF) 30% on Seinorage 0.300 90.00 27.00
charges
Rate per cum say 117.00
Add lead charges of metal 25.00 Km 0.90 504.25 453.83
Add lead charges of sand 41.00 Km 0.45 805.54 362.49
Add lead charges of Manufactured Sand 25.00 Km 0.00 566.50 0.00
TOTAL Rate Total 6362.00
Note The basic components of this analysis are the same as those
of items 13.8 (A to H). The only changes are as under:
RA - 129
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
13.8 2706 & Providing weep holes in Brick masonry/Plain/ Reinforced
2200 concrete abutment, wing wall/ return wall with 100 mm
dia AC pipe, extending through the full width of the
structure with slope of 1V :20H towards drawing foce.
Complete as per drawing and Technical
Unit = Nos.
Taking output = 30 Nos.
a) Material
AC pipe 100 mm dia. (including wastage @ 5 per cent ) metre 31.50 253.00 7969.50
b) Labour
Mate day 0.03 451.00 13.53
Mason day 0.50 455.00 227.50
Mazdoor day 0.25 400.00 100.00
c) Overhead charges @ 14.615% on (a+b) 1276.93
d) Contractor's profit @ 10% on (a+b+c) 1001.41
Cost for 30 m = a+b+c+d 11015.47
Rate per m (a+b+c+d)/30 367.18
Total 367
Note 1. In case of stone masonry, the size of the weep hole shall be
150 mm x 80 mm or circular with 150 mm diameter.
RA - 130
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
13.10 710.1.4.of Providing and laying of Filter media with granular
IRC:78 materials/stone crushed aggregates satisfying the
and 2200 requirements laid down in clause 2504.2.2. of MoRTH
specifications to a thickness of not less than 600 mm with
smaller size towards the soil and bigger si
Unit = cum
Taking output = 10 cum.
a) Labour
Mate day 0.32 451.00 144.32
Mazdoor for filling, watering, ramming etc. day 7.00 400.00 2800.00
Mazdoor (Skilled) day 1.00 515.00 515.00
b) Material
Filter media of stone aggregate conforming to clause cum 12.00 597.90 7174.80
2504.2.2. of MoRTH specifications.
c) Machinery
Water Tanker of 6 KL capacity hour 0.06 655.20 39.31
d) Overhead charges @ 14.615% on (a+b+c) 1559.92
e) Contractor's profit @ 10% on (a+b+c+d) 1223.34
cost for 10 cum of Fiter Media = a+b+c+d+e 13456.69
Rate per cum = (a+b+c+d+e)/10 1345.67
say 1346
Add seignorage charges of metal cum 1.20 75.00 90.00
Add District Mineral Fund (DMF) 30% on Seinorage 0.300 90.00 27.00
charges
Add lead charges of metal 25.00 Km 1.20 504.25 605.10
TOTAL Rate Total 2068.00
13.13 2000 & Supplying, fitting and fixing in position true to line and
2200 level sliding plate bearing with PTFE surface sliding on
stainless steel complete including all accessories as per
drawing and Technical Specifications and BS: 5400,
section 9.1 & 9.2 (for PTFE) and clause 2004 of MoRTH
Specifications.
Unit: one tonne capacity
Considering a 80 tonne capacity bearing for this analysis
a) Labour
Mate day 0.06 451.00 27.06
Mazdoor day 1.00 400.00 400.00
Mazdoor (Skilled) day 0.50 515.00 257.50
b) Material
PTFE sliding plate bearing assembly of 80 tonnes design
load capacity duly painted complete with all its
each. 1.00 15430.00 15430.00
components as per drawing and Technical Specifications
RA - 131
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Hence volume of elastometer = 14655 cu.cm.
a) Labour
Mate day 0.06 451.00 27.06
Mazdoor day 1.00 400.00 400.00
Mazdoor (Skilled) day 0.50 515.00 257.50
b) Material
Elastomeric bearing assembly consisting of 7 layers of each. 1.00 15310.00 15310.00
elastomer bonded to 6 nos. internal reinforcing steel
laminates by the process of vulcanisation, complete with
all components as per drawing and Technical
Specifications.
Add 1 per cent of cost of bearing assembly for 153.10
foundation anchorage bolts and consumables.
c) Overhead charges @ 14.615% on (a+b) 2359.98
d) Contractor's profit @ 10% on (a+b+c) 1850.76
cost for 19200cc of elastomeric bearing = a+b+c+d 20358.40
Rate per cc of elastomeric bearing = (a+b+c+d)/19200 1.06
Total 1
RA - 132
CHAPTER-14
SUPER-STRUCTURE
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
14.1 1500 Furnishing and Placing Reinforced/ Prestressed cement
&1600 concrete in super-structure as per drawing and
1700 Technical Specification
14.1 C RCC Grade M 30
14.1C Case II Using Batching Plant, Transit Mixer and Concrete
Pump.
Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 48.79 3900.00 190281.00
Coarse sand cum 54.60 182.00 9937.20
20 mm Aggregate cum 64.80 1303.00 84434.40
10 mm Aggregate cum 43.20 894.00 38620.80
b) Labour
Mate day 0.88 451.00 396.88
Mason day 3.00 455.00 1365.00
Mazdoor day 19.00 400.00 7600.00
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1343.30 8059.80
Generator 100 KVA hour 6.00 1316.30 7897.80
Loader hour 6.00 1594.70 9568.20
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity lead upto1 Km hour 15.00 2071.70 31075.50
Lead beyond 1 Km, L - lead in Kilometer tonne.km 300L 13.18 31634.26
RA - 133
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
e) Overhead charges @ 14.615% on (a+b+c+d) 78541.74
f) Contractor's profit @ 10% on (a+b+c+d+e) 61594.67
Cost for 120 cum = a+b+c+d+e+f 677541.41
Rate per cum = (a+b+c+d+e+f)/120 5646.18
say 5646.00
g) seiniorage charges per cum 111.15
Rate per cum say 111.15
RA - 134
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Cost for 120 cum = a+b+c+d+e+f 704643.07
Rate per cum = (a+b+c+d+e+f)/120 5872.03
say 5872.00
g) seiniorage charges per cum 111.15
Rate per cum say 111.15
RA - 135
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
say 5964.00
g) seiniorage charges per cum
Coarse Sand cum 0.45 50.00 18.00
Aggregate cum 0.90 75.00 67.50
Add District Mineral Fund (DMF) 30% on Seinorage 0.300 85.50 25.65
charges
Rate per cum say 111.15
Add lead charges of metal 25.00 Km 0.90 504.25 453.83
Add lead charges of sand 41.00 Km 0.45 805.54 362.49
Add lead charges of Manufactured Sand 25.00 Km 0.00 566.50 0.00
816.32
Total 6891.00
14.1D (q) Height 5m to 10m
Case I (i)
RA - 136
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Rate per cum = (a+b+c+d+e+f)/15 6216.51
say 6217.00
g) seiniorage charges per cum 111.15
Rate per cum say 111.15
RA - 137
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
g) seiniorage charges per cum 111.15
Rate per cum say 111.15
Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 50.64 3900.00 197496.00
Coarse sand cum 54.00 182.00 9828.00
20 mm Aggregate cum 64.80 1303.00 84434.40
10 mm Aggregate cum 43.20 894.00 38620.80
b) Labour
Mate day 0.88 451.00 396.88
Mason day 3.00 455.00 1365.00
Mazdoor day 19.00 400.00 7600.00
c) Machinery
RA - 138
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Batching Plant @ 20 cum/hour hour 6.00 1343.30 8059.80
Generator 100 KVA hour 6.00 1316.30 7897.80
Loader hour 6.00 1594.70 9568.20
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity lead upto1 Km hour 15.00 2071.70 31075.50
Lead beyond 1 Km, L - lead in Kilometer tonne.km 300L 13.18 31634.26
RA - 139
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Rate per cum = (a+b+c+d+e+f)/120 5877.25
say 5877.00
g) seiniorage charges per cum 111.15
Rate per cum say 111.15
RA - 140
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
14.1D (iii) For box girder and balanced cantilever, 38-58 per cent
Case II of cost of concrete.
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) for 437030.00
120 cum
d) Formwork and staging 38 per cent of (a+b+c) 38.00 166071.40
RA - 141
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
10 mm Aggregate cum 5.40 894.00 4827.60
Admixture @ 0.4 per cent of cement kg 25.80 43.00 1109.40
b) Labour
Mate day 0.96 451.00 432.96
Mason day 2.00 455.00 910.00
Mazdoor day 22.00 400.00 8800.00
c) Machinery
Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 525.50 3153.00
Generator 33 KVA hour 6.00 1032.00 6192.00
Basic Cost of Labour, Material & Machinery (a+b+c) 62363.00
for 15 cum
For formwork and staging add the following:
14.1E (i) For solid slab super-structure, 20-30 per cent of
Case I (a+b+c)
(p) Height upto 5m
Basic Cost of Labour, Material & Machinery (a+b+c) for 62363.00
15 cum
d) Formwork and staging 20 per cent of (a+b+c) 20.00 12472.60
RA - 142
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Cost for 15 cum = a+b+c+d+e+f 102212.61
Rate per cum = (a+b+c+d+e+f)/15 6814.17
say 6814.00
g) seiniorage charges per cum 111.15
Rate per cum say 111.15
RA - 143
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Total 8004.00
14.1E Case II Using Batching Plant, Transit Mixer and Concrete Pump
Unit = cum
Taking output = 120 cum
a) Material
Cement tonne 51.60 3900.00 201240.00
Coarse sand cum 54.00 182.00 9828.00
20 mm Aggregate cum 64.80 1303.00 84434.40
10 mm Aggregate cum 43.20 894.00 38620.80
Admixture @ 0.4 per cent of cement kg 206.40 43.00 8875.20
b) Labour
Mate day 0.94 451.00 423.94
Mason day 3.50 455.00 1592.50
Mazdoor day 20.00 400.00 8000.00
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1343.30 8059.80
Generator 100 KVA hour 6.00 1316.30 7897.80
Loader hour 6.00 1594.70 9568.20
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity lead upto1 Km hour 15.00 2071.70 31075.50
Lead beyond 1 Km, L - lead in Kilometer tonne.km 300L 13.18 31634.26
RA - 144
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
say 5819.00
g) seiniorage charges per cum 111.15
Rate per cum say 111.15
RA - 145
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
14.1E (r) Height above 10m
Case II
(ii)
Basic Cost of Labour, Material & Machinery (a+b+c) for 450304.00
120 cum
d) Formwork and staging 33 per cent of (a+b+c) 33.00 148600.32
RA - 146
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Cost for 120 cum = a+b+c+d+e+f 897009.49
Rate per cum = (a+b+c+d+e+f)/120 7475.08
say 7475.00
g) seiniorage charges per cum 111.15
Rate per cum say 111.15
f) Lead charges for Material say 816.32
TOTAL Rate 8402.55
Total 8403.00
14.1F F PSC Grade M-45
Unit = 1 cum
Taking output = 120 cum
a) Material
Cement tonne 55.80 3900.00 217620.00
Coarse sand cum 54.00 182.00 9828.00
20 mm Aggregate cum 64.80 1303.00 84434.40
10 mm Aggregate cum 43.20 894.00 38620.80
Admixture @ 0.4 per cent of cement kg 223.20 43.00 9597.60
b) Labour
Mate day 0.94 451.00 423.94
Mason day 3.50 455.00 1592.50
Mazdoor day 20.00 400.00 8000.00
c) Machinery
Batching Plant @ 20 cum/hour hour 6.00 1343.30 8059.80
Generator 100 KVA hour 6.00 1316.30 7897.80
Loader hour 6.00 1594.70 9568.20
Transit Mixer ( capacity 4.0 cu.m )
Transit Mixer 4 cum capacity lead upto1 Km hour 15.00 2071.70 31075.50
Lead beyond 1 Km, L - lead in Kilometer tonne.km 300L 13.18 31634.26
RA - 147
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
d) Formwork and staging 21 per cent of (a+b+c) 21.00 98155.26
RA - 148
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
f) Lead charges for Material say 816.32
TOTAL Rate 7115.00
Total 7115.00
14.1F (r) Height above 10m
(ii)
Basic Cost of Labour, Material & Machinery (a+b+c) for 467406.00
120 cum
d) Formwork and staging 31 per cent of (a+b+c) 31.00 144895.86
RA - 149
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
f) Contractor's profit @ 10% on (a+b+c+d+e) 83571.91
Cost for 120 cum = a+b+c+d+e+f 919291.04
Rate per cum = (a+b+c+d+e+f)/120 7660.76
say 7661.00
g) seiniorage charges per cum 111.15
Rate per cum say 111.15
RA - 150
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
14.1G (q) Height 5m to 10m
(i)
Basic Cost of Labour, Material & Machinery (a+b+c) for 479622.00
120 cum
d) Formwork and staging 45 per cent of (a+b+c) 45.00 215829.90
RA - 151
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
H.T. Strand @ 9.42 kg/m including 2 per cent for tonne 0.39 35556.00 13689.06
wastage and extra length for jacking
Sheathing duct ID 66 mm along with 5 per cent extra metre 42.00 79.29 3330.18
length 40 x 1.05 = 42 m.
Tube anchorage set complete with bearing plate, each 2.00 43.24 86.48
permanent wedges etc
Cement for grouting including 3 per cent wastage @ tonne 0.125 3900.00 487.50
3.00 kg/m = 3 x 1.03 x 40 = 123.60 kg (say, = 125 kg)
RA - 152
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Providing and laying 12 mm thick mastic asphalt
wearing course on top of deck slab excluding prime
coat with paving grade bitumen meeting the
requirements given in table 500-29, prepared by using
mastic cooker and laid to required level and slope after
cleaning the surface, including providing antiskid
surface with bitumen precoated fine grained hard stone
chipping of 9.5 mm nominal size at the rate of 0.005cum
per 10 sqm and at an approximate spacing of 10 cm
center to center in both directions, pressed into surface
when the temperature of surfaces not less than 100
deg. C, protruding 1 mm to 4 mm over mastic surface,
all complete as per clause 515.
Unit = sqm
Taking output = 72.46 sqm (2 tonnes)(0.869 cum)
assuming a density of 2.3 tonnes/cum.
a) Labour
Mate day 0.49 451.00 220.99
Mazdoor day 11.00 400.00 4400.00
Mazdoor (Skilled) day 1.25 515.00 643.75
b) Machinery
Mechanical broom @ 1250 sqm per hour hour 0.06 381.80 22.91
Air compressor 250 cfm hour 0.06 556.50 33.39
Mastic cooker 1 tonne capacity hour 6.00 79.50 477.00
Bitumen boiler 1500 litres capacity hour 6.00 223.00 1338.00
Tractor for towing and positioning of mastic cooker and hour 1.00 413.60 413.60
bitumen boiler
c) Material
Base mastic (without coarse aggregates) = 60 per cent
Coarse aggregate(3.35mm to 9.5 mm size) = 40 per cent .
iv) Coarse aggregates 9.5 mm to 3.35 mm size @ 40 cum 0.55 894.00 491.70
per cent by weight of mix = 2 x 40/100 = 0.8 MT =
0.8/1.456 = 0.55
v) Pre-coated stone chips of 13.5 mm nominal size for cum 0.036 4580.00 164.88
skid resistance = 72.46x0.005/10 = 0.036
vi) Bitumen for coating of chips @ 2 per cent by kg 1.05 33.76 35.45
weight = 0.036 x 1.456 x 2/100 = 0.001048MT =
1.05kg
d) Overhead charges @ 14.615% on (a+b+c) 2361.10
e) Contractor's profit @ 10% on (a+b+c+d) 1851.64
Cost for 72.46 sqm = a+b+c+d+e 20368.08
f) seigniorage charges for metal cum 0.98 75.00 73.20
Add District Mineral Fund (DMF) 30% on Seinorage 0.300 73.20 21.96
charges
95.16
g) Lead charges for metal 25.00 Km 0.98 504.25 492.15
g) Lead charges for Bitumen 250.00 Km 0.57 520.07 293.86
Rate per sqm = (a+b+c+d+e)/72.46 293.25
Total 293.00
RA - 153
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Note 1.The rates for 6 mm or any other thickness may be worked
out on pro-rata basis.
2. Where tack coat is required to be provided before laying
mastic asphalt, the same is required to be measured and
paid separately.
3.The quantities of binder, filler and aggregates are for
estimating purpose. Exact quantities shall be as per mix
design.
4.This rate analysis is based on design made by CRRI for a
specific case and is meant for estimating purposes only.
Actual design is required to be done for each case.
Unit = 1 RM
Taking output = 2 x 24 m span = 48 m
a) Material
Cement concreteM30 Grade Refer relevant item of cum 4.09 3583.00 14661.64
concrete in Item 14.1(C) by using batching plant,
excluding formwork i.e. per cum basic cost (a+b+c)
No. of vertical posts = (12 + 2)2 = 28 Nos., External
area of vertical post 0.25x0.275 = 0.069sqm, Concrete
in Vertical posts = 0.069 x 28 = 1.932 cum, Hand rail in
3 tiers = 3 x 24 = 72 m, External area = 0.170 x 0.175
= 0.03 sqm, Concrete in hand rails = 0.03 x 72 = 2.16
cum, Total Concrete = 1.932 + 2.16 = 4.092 cum.
(Refer MoRTH SD / 202).
Add 5 per cent of above cost for form work for casting 733.08
in casting yard.
HYSD bar reinforcement Rate as per item No tonne 0.865 49895.00 43159.18
14.2(Excluding OH & CP)
Refer MoRTH SD / 202.
Add 5 per cent of (a) for handling and fixing of 2927.69
precast panels in position
b) Overhead charges @ 14.615% on (a) 8985.53
c) Contractor's profit @ 10% on (a+b) 7046.71
Rate for 48 m (a+b+c) 77513.83
Rate per metre (a+b+c)/48 1614.87
say 1615.00
g) seiniorage charges per cum 117.33
Rate per cum say 117.33
RA - 154
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
14.7 2703, Construction of RCC railing of M30 Grade in-situ with 20
1500, mm nominal size aggregate, true to line and grade,
1600 & tolerance of vertical RCC post not to exceed 1 in 500,
1700 centre to centre spacing between vertical post not to
exceed 2000 mm, leaving adequate space between
vertical post for expansion, complete as per approved
drawings and technical specifications.
Unit = 1 RM
Taking output = 2 x 24 m span = 48 m.
a) Material
Cement concreteM30 Grade Refer relevant item of cum 4.092 3583.00 14661.64
concrete in Item 14.1(C) by using batching plant,
excluding formwork i.e. per cum basic cost (a+b+c)
No. of vertical posts = (12 + 2)2 = 28 Nos., External
area of vertical post 0.25x0.275 = 0.069sqm, Concrete
in vehicle posts = 0.069 x 28 = 1.932 cum, Hand rail in
3 tiers = 3 x 24 = 72 m, External area = 0.170 x 0.175
= 0.03 sqm, Concrete in hand rails = 0.03 x 72 = 2.16
cum, Total Concrete = 1.932 + 2.16 = 4.092 cum.
(Refer MoRTH SD / 202).
Unit = 1 RM
Taking output = 2 x 50 m span = 100 m
a) Material:
1) ISMC 100 = 2.806 x 1.05 = 2.946 MT tonne 2.95 42000.00 123732.00
2) MS Flat = 0.964 x 1.05 = 1.012 MT tonne 1.01 42000.00 42504.00
3) MS bars = 0.17 x 1.05 = 0.180 MT tonne 0.18 42000.00 7560.00
4) MS bolts, nuts and washers tonne 0.15 85000 12750.00
RA - 155
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Mate day 2.80 451.00 1262.80
Mazdoor (Skilled) day 30.00 515.00 15450.00
Mazdoor day 40.00 400.00 16000.00
c) Overhead charges @ 14.615% on (a+b) 33953.13
d) Contractor's profit @ 10% on (a+b+c) 26627.02
Cost for 100 m steel railing = a+b+c+d 292897.17
Rate per metre (a+b+c+d)/100 2928.97
Total 2929.00
14.9 2705 Drainage Spouts complete as per drawing and
Technical specification
Unit = 1 No.
Taking output = 1 No.
a) Material
Corrosion resistant Structural steel including 5 per cent Kg 4.00 50.14 200.55
wastage
GI pipe 100mm dia metre 2.00 253.00 506.00
GI bolt 10 mm Dia each 6.00 19.00 114.00
Galvanised MS flat clamp each 2.00 165.00 330.00
b) Labour
For fabrication
Mate day 0.02 451.00 9.02
Skilled (Blacksmith, welder etc.) day 0.02 482.20 9.64
Mazdoor day 0.02 400.00 8.00
For fixing in position
Mate day 0.01 451.00 4.51
Mason day 0.01 455.00 4.55
Mazdoor day 0.20 400.00 80.00
Add @ 5 per cent of cost of material and labour for 63.31
electrodes, cutting gas, sealant, anti-corrosive
bituminous paint, mild steel grating etc.
c) Overhead charges @ 14.615% on (a+b) 194.32
d) Contractor's profit @ 10% on (a+b+c) 152.39
Rate per metre (a+b+c+d) 1676.30
Total 1676.00
Note 1. In case of viaducts in urban areas, the drainage spouts
should be connected with suitably located pipelines to
discharge the surface run-off to drains provided at ground
level.
2. In case of bridges, sufficient length of G.I Pipe shall be
provided to ensure that there is no splashing of water from
the drainage spout on the structure.
14.10 2700 PCC M15 Grade leveling course below approach slab
complete as per drawing and Technical specification
Unit = 1 cum
Taking output = 1 cum
Material
Concrete, Rate as per item No. 12.8 (A) excluding cum 1.00 3309.00 3309.00
formworks
c) Overhead charges @ 14.615% on (a+b) 483.61
d) Contractor's profit @ 10% on (a+b+c) 379.26
Rate per cum say 4171.87
e) seiniorage charges as per item 12.8 (A) 117.00
Rate per cum say 117.00
RA - 156
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Taking output = 1 cum
a) Material
Cement concreteM30 Grade Refer relevant item of cum 1.00 3649.00 3649.00
concrete in item 12.8(G)by using batching plant,
excluding formwork i.e. per cum basic cost (a+b+c)
(Excluding OH & CP)
( Refer relevant item of concrete in item No. 13.8 (G) 72.98
except that form work may be added at the rate of 2
per cent of cost against 3.5 per cent provided in the
foundation concrete.
HYSD bar reinforcement Rate as per item No tonne 0.05 49895.00 2494.75
14.2(Excluding OH & CP)
b) Overhead charges @ 14.615% on (a) 908.58
c) Contractor's profit @ 10% on(a+b) 712.53
Rate per cum (a+b+c) 7837.84
say 7838.00
d) seiniorage charges as per item 12.8 (G) 117.00
Rate per cum say 117.00
Unit = sqm
Taking output = 10 sqm
a) Labour
Mate day 0.01 451.00 4.51
Painter day 0.25 473.00 118.25
Mazdoor (Skilled) day 0.25 515.00 128.75
b) Material
Water based paint of approved quality for cement Litres 5.00 51.00 255.00
concrete surface
c) Overhead charges @ 14.615% on (a+b) 74.03
d) Contractor's profit @ 10% on (a+b+c) 58.05
Cost for 10 sqm (a+b+c+d) 638.59
Rate per sqm (a+b+c+d)/10 63.86
Total 64.00
14.22 2607 Strip Seal Expansion Joint
Providing and laying of a strip seal expansion joint
catering to maximum horizontal movement upto 70 mm,
complete as per approved drawings and standard
specifications to be installed by the
manufacturer/supplier or their authorised
representative ensuring compliance to the
manufacturer's instructions for installation.
Unit = Running meter
Taking output = 12 m
a) Labour
Mate day 0.05 451.00 22.55
Mazdoor day 1.00 400.00 400.00
Mazdoor (Skilled) day 0.25 515.00 128.75
b) Material
RA - 157
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Supply of complete assembly of strip seal expansion metre 12.00 4200.00 50400.00
joint comprising of edge beams, anchorage, strip seal
element and complete accessories as per approved
specifications and drawings.
RA - 158
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
Taking output = 12 m
a) Labour
Mate day 0.07 451.00 31.57
Mazdoor day 1.25 400.00 500.00
Mazdoor (Skilled) day 0.50 515.00 257.50
b) Material
Supply of a modular box/box seal joint assembly metre 12.00 input #VALUE!
containing 3 modules/cells and comprising of edge
beams, two central beams, chloroprene seal,
anchorage elements, support and control system, all
steel sections protected against corrosion and installed
by the manufacturer or his authorised representative.
RA - 159
CHAPTER - 15
RIVER TRAINING AND PROTECTION WORKS
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
15.1 2503 Providing and laying boulders apron on river bed for
protection against scour with stone boulders weighing
not less than 40 kg each complete as per drawing and
Technical specification.
A Boulder Laid Dry Without Wire Crates.
Unit = cum
Taking output = 1 cum
a) Material
Stone cum 1.00 233.80 233.80
Stone Spalls cum 0.20 110.00 22.00
b) Labour
Mate day 0.04 451.00 18.04
Mason day 0.35 455.00 159.25
Mazdoor * day 0.75 400.00 300.00
c) Overhead charges @ 14.615% on (a+b) 107.14
d) Contractor's profit @ 10% on (a+b+c) 84.02
Rate per cum = (a+b+c+d) 924.25
say 924.00
e) seiniorage charges per cum
Stone cum 1.00 75.00 75.00
Stone Spalls cum 0.20 75.00 15.00
Add District Mineral Fund (DMF) 30% on Seinorage 0.300 90.00 27.00
charges
Add lead charges of metal 25.00 Km 1.20 504.25 605.10
Total rate 1646.35
Rate per cum Total 1646.00
* Including excavation for trimming for preparation of bed.
Note Nominal excavation required for preparation of bed has
been taken into account while making provision for labour.
Unit = cum
Taking out put = 1 cum
Concrete Grade M15 Rate as per item No. 12.8 (A) cum 1.00 5272.00 5272.00
including OH & CP
Add 2 per cent of cost to account for excavation for 105.44
preparation of bed, nominal surface reinforcement and
filling of granular material in recesses between blocks.
RA - 160
Ref. to
Sr No MoRTH Description Unit Quantity Rate Rs Cost Rs
Spec.
e) seiniorage charges per cum
Stone cum 1.00 75.00 75.00
Stone Spalls cum 0.20 75.00 15.00
Add District Mineral Fund (DMF) 30% on Seinorage 0.300 90.00 27.00
charges
say 117.00
Add lead charges of metal 25.00 Km 1.20 504.25 605.10
Total rate 1646.35
Rate per cum Total 1646.00
RA - 161
RATES OF CONVEYANCE OF MATERIALS INCLUDING LOADING AND UNLOADING -- BRIDGE WORKS
1 METAL / STONE / RUBBLE STONE 205.45 12.45 207.85 14.85 223.00 30.00
RA - 162
Rates of Material for the Year 2018-19
DEDUC
INITIAL RATE T MACHINE SEIGNO Total Rate as
S. excluding STACKI CRUSHING BLASTING RAGE per SSR 2018-
DESCRIPTION OF THE MATERIAL UNIT
NO stacking NG CHARGES CHARGES CHARGE 19 excluding
charges CHARG @ 25% S Taxes
ES
1 40 mm SS 5 metal (IS383,1970) Cum 590.4 147.60 70.00 808.00
2 20 mm SS 5 metal (IS383,1970) Cum 986.40 246.60 70.00 1303.00
3 25 mm SS 5 metal (IS383,1970) Cum 947.2 236.80 70.00 1254.00
4 10 mm SS 5 metal (IS383,1970) Cum 659.20 164.80 70.00 894.00
5 6 mm SS 5 metal (IS383,1970) Cum 506.4 126.60 70.00 703.00
6 Gravel Cum 110.00 110.00
7 Sand for mortar (Concrete) Cum 182 182.00
8 Sand for filling, blindage Cum 100 100.00
9 12 mm SS 5 metal (IS383,1970) Cum 782.4 195.60 70.00 1048.00
10 RR masonary (Granite) Cum 240 70.00 310.00
11 CR masonary (Granite) Cum 274.3 70.00 344.30
Stone boulder of size 150 mm size
90.50
12 Cum 70.00 160.50
Stone boulder of size 150-200mm size
168.55
13 Cum 70.00 238.55
163.80
14 Stone boulder of size 300 mm size Cum 70.00 233.80
Stone dust (HBG stone chips 2.36 mm
333.00
15 and below) Cum 333.00
16 Sand for mortar Cum 182 182.00
17 Bulk Bitumen Grade 30/40 mt 33760.00 33760.00
18 Bulk Bitumen Grade 80/100 mt 31690.00 31690.00
19 Modified Bitumen CRMB55 mt 33670.00 33670.00
20 Bitumen emulsion (Bulk) mt 35790.00 35790.00
21 Cement mt 3900.00 3900.00
22 Fe 500 steel mt 42500.00 42500.00
23 Mild steel rods mt 39674.00 39674.00
24 Structural steel mt 42000.00 42000.00
25 HT wire 4mm mt 35556.00 35556.00
26 40 mm metal (hand broken) Cum 580.50 70.00 650.50
27 Moorum at Site Cum 185.00 185.00
28 2.36mm to 5mm metal (IRC-MORTH) Cum 293.35 73.3375 70.00 436.69
RA - 163
RA - 164
Khammam - Devarapalli (NH-365BB)
LEAD CALCULATION FOR PACKAGE V (KM 132+664 to KM 162+126, LENGTH = 29.462 KM )
RA - 165
RA - 166
KHAMMAM- DEVARAPALLI PROJECT
Pathipaka
Crusher 11.00 Km Bhadrachalam
Sand
6.0 Km
8.00 Km
NH-30
6.0 Km Mallampally
WARANGAL Palwancha
Km
Crusher
NH-365
Kothagudem
Power Plant
3 0.5
10 5
36 Km
4 Km
5.50 Km
NH
m Kuravi 3.5Km
2 0K
65
Pipes
Balaji
Maripeda H3 1.
10.00
N Garloddu Km 00
Km
Crusher
13.00 Km
6.00
Mulakalapally Kothagudem Km
Km
Crusher Chidipi Sand
.00
SH-3
1.00
64
D.Ch: 89+874
17.50 Km
55.30 Km
Km
SH-12
Km 30
NH-30
9.00 Km
3.
PROJECT PROJECT
.40
7.00
D.Ch: 33+240 D.Ch: 0.50 Km 0.50 Km 9.00 Km Km
6+240 38+040 15.00
2.00
0.50 Km D.Ch: 0.50
Km
0.50 Km D.Ch: D.Ch:
Devarapalli
0.50 Km
RAJAHMUNDRY
22.00
SURYAPET Km Km
Km
ANDHRA PRADESH
Km
Kapavaram
00 VIZAG
NH-365A
28.800 Km
Bonakalu .
P-1 CMP 22
Duddukuru
P-2 CMP P-3 CMP BITUMEN
Kovvuru
9.00
Km
16+800
TELANGANA
Crusher
48+350 84+200 (235 Km)
Pipes
61.00 Km
NH-30
Lingala Nallajarla
0 Sand
5.00 Km 1.0 m
KODAD K
NH-65 1.50 G. Kodudru
Km Km
Crusher 0 6
.0 -1
64
6.00 NH
Dorakunta Km
Crusher
15.00
NH-30
Km Hanuman
K
0
33.0
m
Vijayawada
-16 Junction
Power Plant 29.00 K
m NH QUARRY CHART
2.5 Vijayawada
Km NH-65
RA - 167