0% found this document useful (0 votes)
530 views8 pages

Busbar 7SS522

This document records test results from inspecting and testing the busbar protection relay at the 10J substation. It details measurements taken at different bays and phases. Tests performed include injection tests to verify differential current thresholds and timing, as well as a slope test to verify the relay operation with varying currents. Signatures are included from Alfanar, Siemens, Marafiq and RCA representatives witnessing the tests.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
530 views8 pages

Busbar 7SS522

This document records test results from inspecting and testing the busbar protection relay at the 10J substation. It details measurements taken at different bays and phases. Tests performed include injection tests to verify differential current thresholds and timing, as well as a slope test to verify the relay operation with varying currents. Signatures are included from Alfanar, Siemens, Marafiq and RCA representatives witnessing the tests.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
  • General Information and Initial Measurements
  • Busbar Protection Functional Tests
  • Bus Zone Testing
  • Protection Differential Current Stop Test
  • Breaker Failure Protection Test
  • Circuit Breaker Failures and Special Functions
  • Time Delay Testing
  • Equipment and Alarm Testing

SITE INSPECTION AND TEST RECORD

Contract No: PIC P - 7703

Name of Substation: 10J SUBSTATION


Description: BUSBAR PROTECTION RELAY 7SS522
Panel: Location: Page 1 of 8

1. GENERAL INFORMATION

Panel
Equipment Tag
Frequency 60Hz
C.U Type
CT Ratio
Rated Current
Rated Voltage
Aux. Voltage 125V DC
B.U Type

2. MEASUREMENTS:

* Bays at Z1B&Z2B

Meas. Meas. (CZ) Reading by Digsi (%)


Phase

BAY I inj.
@ B.U @ C.U (%) Check zone Bus zone Bus Zone No.
No. (A) Ipri
(%) Idiff. IStab. Idiff. IStab. Idiff. IStab.
L1 0.5
L2 0.75
L3 1
L1 0.5
L2 0.75
L3 1
L1 0.5
L2 0.75
L3 1
L1 0.5
L2 0.75
L3 1
L1 0.5
L2 0.75
L3 1

* Bus Section AD
TESTED BY WITNESSED BY
xx/xx/20xx
ALFANAR T&C SIEMENS MARAFIQ RCA
Name Eng. Eng. Eng. Eng.
Signature
SITE INSPECTION AND TEST RECORD

Contract No: PIC P - 7703

Name of Substation: 10J SUBSTATION


Description: BUSBAR PROTECTION RELAY 7SS522
Panel: Location: Page 2 of 8

Meas. (CZ) Reading by Digsi (%)


Meas.
Phase

BAY I inj. @ C.U (%)


@ B.U Check zone Bus zone Bus Zone No.
No. (A) Ipri
(%)
Idiff. IStab. Idiff. IStab. Idiff. IStab.
L1 0.5 ---- ---- ---- ----
L2 0.75 ---- ---- ---- ----
L3 1 ---- ---- ---- ----
L1 0.5 ---- ---- ---- ----
L2 0.75 ---- ---- ---- ----
L3 1 ---- ---- ---- ----

* Injection was done from terminal block of the bay unit


* Bus zone (selective zone) depending on which isolator closed.

3. BUS BAR PROTECTION DIFF. CURRENT ALARM TEST:

Settings: Address 6306: Idiff supervision : ON


Address 6307: Idiff superv. Time delay : …. sec
Address 6308: Idiff superv. Limit value – BZ : …... A
Address 6309: Idiff superv. limit value – CZ : …... A
* Idiff. sup.CZ. / BZ alarm appears only at C. U (Config. Led on address CZ. / 10410, BZ/ 10415)
* Stop contact (M15, 10410) for CZ. /CU and (M16, 10415) for BZ. /CU

Check Zone Bus Zone


Relay
Bay Phase Remarks
Time LED
P/U (A) D/O (A) P/U(A) D/O(A) Time (Sec)
(Sec)
L1-N

Z 1B L2-N

L3-N

L1-N

Z 2B L2-N

L3-N
4. BUS BAR DIFF. PROTECTION CURRENT:

TESTED BY WITNESSED BY
xx/xx/20xx
ALFANAR T&C SIEMENS MARAFIQ RCA
Name Eng. Eng. Eng. Eng.
Signature
SITE INSPECTION AND TEST RECORD

Contract No: PIC P - 7703

Name of Substation: 10J SUBSTATION


Description: BUSBAR PROTECTION RELAY 7SS522
Panel: Location: Page 3 of 8

*4-1 Pickup Test:


(Check zone or Bus zone), the function which will be tested the other should be
Set at low value.

Settings: Address 6306: Idiff superv : OFF


Address 6101: Stabilizing factor (BZ) : …...
Address 6102: Idiff threshold (BZ) : …... A
Address 6103: Stabilizing factor (CZ) : …...
Address 6104: Idiff threshold (CZ) : …...A

* Bays at Z 1B & Z 2B

Bus Zone
Check Zone Relay
BAY No. Phase Q1 (Z 1A) Q2 ON (Z 2A) Remarks
Leds
PICK UP (A) PICK UP (A) PICK UP (A)
L1-N
L2-N
L3-N
L1-N
L2-N
L3-N
L1-N
L2-N
L3-N
L1-N
L2-N
L3-N
L1-N
L2-N
L3-N
L1-N
L2-N
L3-N

*4-2 Time Test:

TESTED BY WITNESSED BY
xx/xx/20xx
ALFANAR T&C SIEMENS MARAFIQ RCA
Name Eng. Eng. Eng. Eng.
Signature
SITE INSPECTION AND TEST RECORD

Contract No: PIC P - 7703

Name of Substation: 10J SUBSTATION


Description: BUSBAR PROTECTION RELAY 7SS522
Panel: Location: Page 4 of 8

* Stop contact. BB Trip 3 pole

Any Bay Phase Z 1B Z 2B Relay Leds Remarks


L1-N * Relay tripping time
Check Zone L2-N at 4 I set= 15msec
L3-N * Relay Calculs. time
L1-N ( ½ cycle ) = 8 m sec
Bus Zone L2-N * Total time= 23 msec.
L3-N

4-Bus bar Protection Diff. Current Slop Test:

* 4-1 BUS ZONE (SELECTIVE ZONE)

Settings, Address 6306: Idiff superv. : OFF


Address 6101: Stabilizing factor (BZ) : ….
Address 6102: Idiff threshold (BZ) : …. A
Address 6103: Stabilizing factor (CZ) : ….
Address 6104: Idiff threshold (CZ) : …. A

* Stop contact. BB Trip 3 pole

K- Factor Injected current Bus Zone K- factor


phase ( slop) ( slop)=Id/Is Remarks
setting I1 I2 Id Is measured

L1

L2

L3

Id= | I1 - I2 | IS = | I1| + | I2 | K= Id/Is

** Verify this connection.


Inject I1∟0 & I2∟180 equals; decrease any one up to trip,
Calculate slop = Id/Is

* 4-2 CHECK ZONE.

TESTED BY WITNESSED BY
xx/xx/20xx
ALFANAR T&C SIEMENS MARAFIQ RCA
Name Eng. Eng. Eng. Eng.
Signature
SITE INSPECTION AND TEST RECORD

Contract No: PIC P - 7703

Name of Substation: 10J SUBSTATION


Description: BUSBAR PROTECTION RELAY 7SS522
Panel: Location: Page 5 of 8

Settings, Address 6306: Idiff superv. : OFF


Address 6101: Stabilizing factor (BZ) : ….
Address 6102: Idiff threshold (BZ) : …. A
Address 6103: Stabilizing factor (CZ) : ….
Address 6104: Idiff threshold (CZ) : ….. A

* Stop contact. BB Trip L1, L2, L3/ CZ

K- Factor Injected current K- factor


phase ( slop) ( slop)=I2/I1 Remarks
setting I1 I2 measured

L1

L2

L3

** Verify this connection


Inject I1∟0 ≥ Idiff threshold (CZ), Increase I2 up to trip,
Calculate slop = I2/I1

5. BREAKER FAILURE PROTECTION TEST:

TESTED BY WITNESSED BY
xx/xx/20xx
ALFANAR T&C SIEMENS MARAFIQ RCA
Name Eng. Eng. Eng. Eng.
Signature
SITE INSPECTION AND TEST RECORD

Contract No: PIC P - 7703

Name of Substation: 10J SUBSTATION


Description: BUSBAR PROTECTION RELAY 7SS522
Panel: Location: Page 6 of 8

Settings, Address 0114: BI mode / superv. : Initiation w/o supervision


Address 0115: BF OP. mode (stg.-1) / (stg.-2): Trip repeat unbalance
Address 0118: Current threshold for BF : …. A
Address 0121: Time delay T-BF-3P (stag. -1 ): …. m sec
Address 0125: Time delay Trip rep. (Stag. -2 ): …. m sec
Test procedure: Config. , B/I CBF start, Led CBF trip, B/O-1 CBF trip 3P (stg.-2)
B/O-2 CBF rep. trip 3P (stg.-1)
Increase current up to P/U and decrease up to D/O
For timing Stg – 1 use B/O-1, for timing Stg – 2 use B/O-2

Circuit Breaker Failure


Bay Relay
Phase P/U D/O Remarks
No. Stg – 1 (m sec) Stg – 2 (m sec) Leds
(A) (A)
L1-N
BU… L2-N
L3-N
L1-N
BU… L2-N
L3-N
L1-N
BU… L2-N
L3-N

6. Breaker Failure Protection Special function Test :

1- C.B. Faulty:
Config. (B/I C.B. not ready).if this B/I is activated in the same time with (B/I CBF start)
The trip will issued after time T-BF CB fault (0124 usually set at low value m sec.)

2- Low Current mode:


If this function: ON and C.B closed , only make CBF start without current
The trip will issue after time T-BF low current (0122)

3- End fault protection:


Config. ( B/O End Flt Trip ) , make this function : ON and if the ( B/I C.B open ) is activated with
injected current.The End fault trip will issue immediately to trip the remote End.

Settings,
Address 0116: Low Current mode BF : ON
Address 0122: Time delay T-BF I< : ….. m sec
TESTED BY WITNESSED BY
xx/xx/20xx
ALFANAR T&C SIEMENS MARAFIQ RCA
Name Eng. Eng. Eng. Eng.
Signature
SITE INSPECTION AND TEST RECORD

Contract No: PIC P - 7703

Name of Substation: 10J SUBSTATION


Description: BUSBAR PROTECTION RELAY 7SS522
Panel: Location: Page 7 of 8

Address 0124: Time delay T-BF CB fault : …. m sec


Address 0129: End fault protection : ON

I<
Bay I inj. C.B faulty End fault Relay
Phase mode Remarks
No. = In ( m sec ) ( m sec ) Leds
( m sec )
L1-N
BU… L2-N 1.0 A
L3-N
L1-N
BU… L2-N 1.0 A
L3-N
L1-N
BU… L2-N 1.0 A
L3-N

** Breaker Failure Protection Slop Test:


Settings, Address 0114: BI mode / supervision : Initiation w/o supervision
Address 0115: BF OP. mode : BZ unbalances
Address 0118: Current threshold for BF : …. A

* Stop contact. CBF Trip 3 pole

K- Factor Injected current Calculate K- factor


Phase ( slop) ( slop)=Id/Is Remarks
setting I1 I2 Id Is measured
L1
L2 …..
L3

Id= | I1 - I2 | IS = | I1| + | I2 | K= Id/Is

** Verify the connection as shown before with Bus zone slop test.
Inject I1∟0 & I2∟180, fixed I1; increase I2 up to trip,
Calculate slop = Id/Is

7. Diff. Current Supervision fun. Checked:

a) Blocking during fault. : ……….

TESTED BY WITNESSED BY
xx/xx/20xx
ALFANAR T&C SIEMENS MARAFIQ RCA
Name Eng. Eng. Eng. Eng.
Signature
SITE INSPECTION AND TEST RECORD

Contract No: PIC P - 7703

Name of Substation: 10J SUBSTATION


Description: BUSBAR PROTECTION RELAY 7SS522
Panel: Location: Page 8 of 8

b) Blocking till release. : ………. ( config. >B/I, Reset Id block)


c) Alarm without blocking. : ……….
8. Isolator supervision fun. Checked:
a) Blocking during fault. : ……….
b) Blocking till release. : ………. ( config. >B/I, Reset iso mal BI)
c) Alarm without blocking. : ……….
9. All Leds checked. : ……….
10. All Binary i/p checked. : ……….
11. All Command relays checked. : ……….
12. All Signal relays checked. : ……….
13. All bay units. checked.:
a ) DC Fail ( the relay save the old status , and the bus zone concerned to this bay unit is blocked )……..
b ) Comm. Fail ( the bus zone concerned to this bay unit is blocked )………..
c ) Out Of Service ( measuring of that bay unit is stopped for that BZ but CZ still running )………
14. Communication of Relay with Laptop through Software : ……….
15. Fault Record in Relay with Laptop through Software

15. Test Equipment used:


Serial no. of Test
No. Test equipment used Calibration Due date
equipment
1 FREJA 300

TESTED BY WITNESSED BY
xx/xx/20xx
ALFANAR T&C SIEMENS MARAFIQ RCA
Name Eng. Eng. Eng. Eng.
Signature

SITE INSPECTION AND TEST RECORD
Contract No: PIC P - 7703
Name of Substation: 10J SUBSTATION
Description:  BUSBAR PROTECTION
SITE INSPECTION AND TEST RECORD
Contract No: PIC P - 7703
Name of Substation: 10J SUBSTATION
Description:  BUSBAR PROTECTION
SITE INSPECTION AND TEST RECORD
Contract No: PIC P - 7703
Name of Substation: 10J SUBSTATION
Description:  BUSBAR PROTECTION
SITE INSPECTION AND TEST RECORD
Contract No: PIC P - 7703
Name of Substation: 10J SUBSTATION
Description:  BUSBAR PROTECTION
SITE INSPECTION AND TEST RECORD
Contract No: PIC P - 7703
Name of Substation: 10J SUBSTATION
Description:  BUSBAR PROTECTION
SITE INSPECTION AND TEST RECORD
Contract No: PIC P - 7703
Name of Substation: 10J SUBSTATION
Description:  BUSBAR PROTECTION
SITE INSPECTION AND TEST RECORD
Contract No: PIC P - 7703
Name of Substation: 10J SUBSTATION
Description:  BUSBAR PROTECTION
SITE INSPECTION AND TEST RECORD
Contract No: PIC P - 7703
Name of Substation: 10J SUBSTATION
Description:  BUSBAR PROTECTION

You might also like