You are on page 1of 1

Ref. No.

FFCII-L-MMSP-051
October 26, 2022
Shimizu-Takenaka-Fujita-EEI JV
SFTE JV Project Main Office Building
Mindanao Avenue, Gate 2
VMMC-VGC Clubhouse Complex
Veterans Memorial Medical Center
Project 6, District I, Quezon City 1100, Philippines

To : Kiyoshi Mimura
Project Manager

Thru : Yasui Mitsuru


DPM-Tunnel

Reynaldo Lamson
Asst. Project Manager – Quality

Furumura Takao
Tunnel Manager

Project : Metro Manila Project CP-101 Phase 1

Subject : Segment Performance Test after 1,500 Rings Casted

Dear Sirs,

This is to inform SFTE-JV of the schedule of the Segment Performance Test after
1,500 rings casted which was agreed by FFC and SFTE-JV QC and Tunnel team
representative to be conducted on January 11 and 13, 2023.

Please note that the 1,500 rings casted will be achieved on November 12, 2022.

Very Truly Yours,

Harold F. Festijo Danny S. Aguilar


Production Manager VP-Operation
Frey-Fil Corporation Frey-Fil Corporation

83 West Bldg, No. 83 West Avenue, Brgy. Paltok Quezon City Tel: (632) 373-9345 Fax: (632) 373-9345 loc. 1000

Plant Facility: Km. 52, Brgy. Pungo, CalumpitBulacan Plant Facility: SitioRizza, Brgy. Pinugay, Baras Rizal