Name of Sub-Project : PROVISION AND INSTALLATION OF CUSTOMIZED CONTAINER VAN AS TEMPORARY ISOLATION FACILITIES WITH AMENITIES
Physical Target : 1 - UNIT
Barangay : POBLACION 1
Municipality/Province : LEBAK, SULTAN KUDARAT
Project Monitoring and Sustainability KC NCDDP AF/ MLGU/ BLGU not required not required
6 months after date of turn-over
B. FINANCIAL AND OTHER SUPPORTS
B. PHYSICAL/TECHNICAL ASPECT
RESOURCES NEEDED
WORK ITEM PHYSICAL ACTIVITIES TO Source Of Fund EXPECTED
FREQUENCY LABOR MATERIALS REMARKS
DESCRIPTION SCOPE BEUNDERTAKEN Total OUTPUT
No. Rate Cost Qty, Price Cost Barangay Municipal Provincial
1. Structure
a. Roofing 18 sq.m Repainting/ Sealing As need arises 1 350 350.00 1.00 700.00 700.00 1,050.00 1,050.00 Aesthetic/Safety
b. Ceiling 18 sq.m Replacement As need arises 1 350 350.00 2.00 500.00 1,000.00 1,350.00 1,350.00 Aesthetic
c. Wall 27 sq.m. Repainting As need arises 1 350 350.00 2.00 800.00 1,600.00 1,950.00 1,950.00 Aesthetic
d. Door Accesories 1 pc Door Knobs As need arises 1 350 350.00 2.00 350.00 700.00 1,050.00 1,050.00 Safety
3 pc Hinges As need arises 1 350 350.00 6.00 100.00 600.00 950.00 950.00 Safety
e. Water Accesories 1 pc Faucet As need arises 1 350 350.00 3.00 100.00 300.00 650.00 650.00 Safety
1 length Pipeline As need arises 1.00 250.00 250.00 250.00 250.00 Safety
1 lot Water fiitings/accessories As need arises 1.00 450.00 450.00 450.00 450.00 Safety
f. Beds 1 set Repair/Retrofit As need arises 1 350 350.00 2.00 400.00 800.00 1,150.00 1,150.00 Safety
g. Tables and Chairs 1 set Repair/Retrofit As need arises 1 350 350.00 2.00 400.00 800.00 1,150.00 1,150.00 Safety
Total 10,000.00 10,000.00