Schedule & Highlight Recommissioning

NR GI 150 kV SINTANG
Mai Juni
No. Activity Designation Location Status (%)
25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25
Recommisioning Individual Test HV
Equipment 4 bay. Commisioning 2 Bay
A
OHLSintang to Skadau, 1 Bay Trafo, 1 Bay
Coupler
Swyard 150 kV
1 12 Unit Substation
Surger Arrester Estimated 0%

2 Earthing Swicth Test 1 Unit 150 kV Substation Estimated 0%

3 Grounding Resistive 150 kV 1 Set 150 kV Substation Estimated 0%

4 Disconnecting Swicth Busbar 8 Set 150 kV Substation Estimated 0%

5 Disconnectiong Swicth + Earthing 2 Set 150 kV Substation Estimated 0%

6 Circuit Breaker 4 Set 150 kV Substation Estimated 0%

7 Current Transformer 12 Unit 150 kV Substation Estimated 0%

8 Capasitior Voltage Transformer 9 Unit 150 kV Substation Estimated 0%

9 Netral Grounding Resistor 1 Set 150 kV Substation Estimated 0%

10 Primary Current Injector 1 Set 150 kV Substation Estimated 0%


Recommisioning Individual Test HV
B Equipment 20 Swicthgear 1 Lineup &
Protection
11 Current Transformer Test 1 Lineup Estimated 0%

12 Voltage Transformer Test 1 Lineup Estimated 0%

13 VCB Test 1 Lineup Estimated 0%

14 LBS Test 1 Lineup Estimated 0%

15 Control Function Panel 20 KV 1 Lineup Estimated 0%

16 Relay Protection test panel 20 kV 1 Lineup Estimated 0%

17 HIPOT Cable & BUSBAR 20 kV 1 lineup Estimated 0%

Recommisioning Control Protection & (


C SAS ) 2 Bay OHL to Sintang, 1 Bay Trafo, 1
Bay Coupler
18 Control Function And Interlocing CRP/ SAS 150 kV
4 Bay Substation Estimated 0%

19 Relay Protection, Function Test trip & SAS 4 Bay CRP/ SAS 150 kV
Substation Estimated 0%

20 Commisioning 4 line bay with Pusertif 4 Bay CRP/ SAS 150 kV


Substation Estimated 0%

4 Bay CRP 150 kV / 20 kV


21 Stability Bay Trafo Substation Estimated 0%
CRP/ 150 kV
4 Bay
22 Stability Buspro Substation Estimated 0%

4 Bay CRP/ SAS 150 kV


23 Poin to Poin 2 line Bay to Sintang Substation Estimated 0%
CRP/ SAS 150 kV
2 Bay
24 Intertrip Sintang 1 to Skadau 1 Substation Estimated 0%
CRP/ SAS 150 kV
2 Bay
25 Intertrip Sintang 1 to Skadau 1 Substation Estimated 0%

25

Start Activity : 27 Mei 2022 Noted :


Estimated time Schedule Finish : 25 Juni 2022
Today : 26 Mei 2022
Estimated Duration : 29
Remaining Working Day : 29

Highlights :
Planning : - Individual test HV Equipment 150 kV
On Progress
Estimated
Finish
Not Yet
CV.MAGFLOW PERSADA PT. DISTRACO