Professional Documents
Culture Documents
Project Information
Client : Sri Lanka Institute of Advance Technological
Education (SLIATE)
Contractor : Darinton Construction (Pvt)Ltd
Consultant : Central Engineering Consultancy Bureau
Total Cost Estimate : Rs. 529 million (With Taxes-Allocation
confirmed by Client)
Contract Amount : Rs. 412,420,706.50
Date of Award : 26-11-2020
Date of Commencement : 08-02-2021
Original Contract Period : 540 Days
Scheduled Date of Completion : 02-08-2022
Extended Date of Completion(EOT) : 01-01-2023
Background
It has been noted that significant price escalation is recorded due to substantial price hike of
construction materials from April -2022.Beacause of this, a large portion of allocated money
will be spent on the price adjustments. In this circumstance, Employer requested a reduced
scope of work to be prepared in order to function the Institute at minimum requirements.
1
Two Hardware Labs (Capacity -50x2)
02 no of IT Labs (Capacity -100x2)
Auditorium (Capacity -260)
01 no of Lecture room (Capacity -80)
Overhead Tank, Fire Protection, Lightning Protection
Building No. 02
Tourism Hospitality Management (THM) Lecture room (Capacity -80)
Library
Cafeteria and Kitchen
8 no of Lecture rooms (Capacity - 80x8)
Overhead Tank, Fire Protection, Lightning Protection
Common
Service building including security hut, generator room and transformer room.
Waste Water Treatment plant
Water Sump
2
COST FORCAST-(in each case)
900
850
800
750
700 289
650 327
600
550
28
500
69 59
450 159
400 270
350 61
300
309
250
432 67 432
200
20
150 309
100
172
50
0
Initial Expectation As at 01-12-2022 to complete whole with reduced socpe
project
Therefore, following reduce scope is initiated to complete the project within the balance
amount of fund.
Reduced Scope
Building No. 01
Building structure with roof will be completed
Masonry works will be completed only at Ground floor
Due to higher cost on AC and Lift, this building cannot be completed as planned.
As limited fund (529m), Building no 01 will not be functionable. But if the Client can
spend 551 million rupees, half of the ground floor can be functioned.
3
Materials remain at site
With this scope reduction all Aluminum material which brought to site cannot be utilized.
Materials of about 9 million rupees will be remain. Additional 3 million ( rupees 590 million)
is required to utilize all remaining aluminum material (for brick work and plastering work in
first floor of Building no 01).
Building No. 02
Library - space will be used for two Air-Conditioned computer labs (capacity – 80x2)
THM room will be used as Library
Cafeteria and Kitchen-will be completed
Out of 8 Lecture rooms, 3 Lecture rooms will be used as an adequate administration
unit
Two Wash room blocks (at Ground and first floor) facilities will be provided
Sport room will be converted as server room.
Floor finishes changed to Cement rendering from Tiling.
Water tanks will be provided.
Fire extinguishers will be fixed.
Common Works
Entrance Gate with security hut, Transformer and Generator room, Essential part of landscaping,
waste water treatment plant, water and power supply will be included
Omissions
Installation of Generator
Water Sump
4
Original Scope
Building 01
Building 02
Kitchen +
Ground Floor Cafeteria Library THM Room
First Floor Lecture Lecture Lecture Lecture Lecture Lecture Lecture Lecture
Room Room Room Room Room Room Room Room
01 02 03 04 05 06 07 08
5
Reduced Scope