You are on page 1of 4

1 To ensure K1F modules tally with overall Arch construction drawings.

To reference Archi elevation drawings


2 To ensure the sequence of the module installation tally with Archi construction drawings
3 To do checking on site prior to installing of all K1F modules at the respective location
4 Setting out of all modules (height and width) to tally with construction
5 To obtain C&S comments/approval prior to fabrication

Please note that no further comments pertain only to compliance to architectural design intent. It does not release you from:
1. ensuring accurate dimensioning through thorough site measurement;
2. highlighting any deviation on shop drawings from the contract drawings if any;
3. highlighting any deviation on site from the shop drawings if any;
4. coordinating among other works and disciplines;
5. any other implied responsibility as the builder under this contract;
6. your obligations and responsibilities under the Contract such as to design, suitability,quality and performances of this work, materials and goods

Contractor is to ensure all openings and recess are provided


as per M&E Approved Drawing

29-08-2022
1 To ensure K1F modules tally with overall Arch construction drawings. To reference Archi elevation drawings
Contractor is to ensure all openings and recess are provided 2 To ensure the sequence of the module installation tally with Archi construction drawings
as per M&E Approved Drawing 3 To do checking on site prior to installing of all K1F modules at the respective location
4 Setting out of all modules (height and width) to tally with construction
5 To obtain C&S comments/approval prior to fabrication

Please note that no further comments pertain only to compliance to architectural design intent. It does not release you from:
1. ensuring accurate dimensioning through thorough site measurement;
2. highlighting any deviation on shop drawings from the contract drawings if any;
3. highlighting any deviation on site from the shop drawings if any;
4. coordinating among other works and disciplines;
5. any other implied responsibility as the builder under this contract;
6. your obligations and responsibilities under the Contract such as to design,
suitability,quality and performances of this work, materials and goods

29-08-2022
d:
08-08-2022

Contractor is to ensure all openings and recess are provided


as per M&E Approved Drawing

1 To ensure proper coordination and setting out is done with regards to formliner and precast elements
2 To ensure formliner mould matches as per setting out
3 Gap between formliner modules to be kept consistent throughout.
4 To ensure alignment and fixing of formliners are kept consistant.
5 To ensure proper setting out is done prior to installation on site
6 To ensure proper coordination is done on the cutting list, all moulds for formliner are to be checked prior to overall fabrication of all formliners

Please note that no further comments pertain only to compliance to architectural design intent. It does not release you from:
1. ensuring accurate dimensioning through thorough site measurement;
2. highlighting any deviation on shop drawings from the contract drawings if any;
3. highlighting any deviation on site from the shop drawings if any;
4. coordinating among other works and disciplines;
5. any other implied responsibility as the builder under this contract;
6. your obligations and responsibilities under the Contract such as to design, suitability,quality and performances of this work, materials and goods
d:
08-08-2022

Contractor is to ensure all openings and recess are provided


as per M&E Approved Drawing

1 To ensure proper coordination and setting out is done with regards to formliner and precast elements
2 To ensure formliner mould matches as per setting out
3 Gap between formliner modules to be kept consistent throughout.
4 To ensure alignment and fixing of formliners are kept consistant.
5 To ensure proper setting out is done prior to installation on site
6 To ensure proper coordination is done on the cutting list, all moulds for formliner are to be checked prior to overall fabrication of all formliners

Please note that no further comments pertain only to compliance to architectural design intent. It does not release you from:
1. ensuring accurate dimensioning through thorough site measurement;
2. highlighting any deviation on shop drawings from the contract drawings if any;
3. highlighting any deviation on site from the shop drawings if any;
4. coordinating among other works and disciplines;
5. any other implied responsibility as the builder under this contract;
6. your obligations and responsibilities under the Contract such as to design, suitability,quality and performances of this work, materials and goods