Professional Documents
Culture Documents
Note:
I) Column B - Compliance to technical requirements.
YES - Able to comply with the requirements
NO - Not able to comply with the requirements
(This column is mandatory to be filled in by the contractor and must be respond together with the proposal)
ii) Column C - To be filled in by the contractor if necessary. Please attach additional info in appendix if necessary.
COLUMN A COLUMN B COLUMN C
CONTRACTOR’S
REQUIREMENTS (YES/NO)
REMARKS
1. INTRODUCTION
Malaysia LNG Sdn Bhd (the “COMPANY”) intends to engage service (the “CONTRACTOR”) for PROVISION OF
MLNG TIGA ACID GAS INCINERATOR (AGI) + GAS TURBINE (GT) INTEGRATED STACK FEASIBILITY STUDY
(the “WORK”).
2. JOB/MATERIAL DESCRIPTIONS
CONTRACTOR shall carry out the Feasibility Study specifically for Incinerator
+ Gas Turbine Integrated Stack covering mechanical hardware modification
of Integrated Stack into two (2) separate individual stacks to meet single
equipment monitoring for Acid Gas Incinerator and Gas Turbine and hardware
modification of current individual Acid Incinerator (AGI) & Gas Turbine (GT)
sampling points to meet DOE CEMS guideline version 7 by maintaining AGI
and GT Integrated Stack configuration.
The CONTRACTOR shall attend to the COMPANY needs for any discussion.
5. RELATED EXPERIENCE
CONTRACTOR must have minimum one (1) past experience in conducting
feasibility study specifically for Acid Gas Incinerator + Gas Turbine Integrated
Stack covering both of the following:
1. Mechanical hardware modification of combined stack into new
individual stack
2. hardware modification of current sampling point to meet DOE CEMS
guideline version 7
7. OBLIGATIONS OF CONTRACTOR
Refer to ARTICLE 11 of Standard General Terms and Conditions
Payment shall be made within (30) days after receipt of undisputed invoice.
11. INSURANCES
Not Applicable.
Open
Page 2 of 3
PROVISION OF MLNG TIGA ACID GAS INCINERATOR (AGI) + GAS TURBINE (GT) INTEGRATED STACK FEASIBILITY STUDY
2. Commercial Proposal:
a) Cover letter for commercial proposal
b) EXHIBIT III - CONTRACT PRICE (Priced)
------------------------------------ ----------------------------
NAME :
DATE :
Open
Page 3 of 3
PROVISION OF MLNG TIGA ACID GAS INCINERATOR (AGI) + GAS TURBINE (GT) INTEGRATED STACK FEASIBILITY STUDY