MECON LIMITED

DAILY PROGRESS REPORT -- SRIKAKULAM - ANGUL PIPELINE PROJECT (PART-A)


Report Date : 23 March 2023 Progress Date : 22 March 2023

Section-I (M/s Corrtech International Section-II (M/s Advance Section-III (M/s Corrtech International Section-IV (M/s Ram Baran Singh Section-V (M/s Tolani Projects Pvt. Section-VI (M/s Ace Pipeline
Details of spread Cumulative Overall
Ltd.) Infrastructures Pvt. Ltd.) Ltd.) Apex Pvt. Ltd.) Ltd.) Contracts Pvt. Ltd)
24"x 86.5 KM (Ch. 0.00 to Ch. 86.5) 24" x 78.5 KM (Ch. 86.5 to Ch. 165.0) 18" x 64 KM (Ch. 165.0 to Ch. 229.0) 18" x 67 KM (Ch. 229.0 to 296.0) 18" x 61 KM (Ch. 296.0 to Ch. 357.0) 18" x 66 KM (Ch. 357.0 to Ch. 423.17)
Status
Date of award 30 June 2021 30 June 2021 30 June 2021 30 June 2021 30 June 2021 30 June 2021
Go-Ahead 13.12.2021 10.01.2022 10.01.2022 17.03.2022 21.05.2022 19.05.2022
Today Today Today Today Today Today
Cum. Till Progress Cum. Cum. Till Progress Cum. Cum. Till Progress Cum. Cum. Till Progress Cum. Cum. Till Progress Cum. Cum. Till Progress Cum. Total Previous Today Cum.
S. No Description UOM Scope Scope Scope Scope Scope Scope
Prev. Day Progress Prev. Day Progress Prev. Day Progress Prev. Day Progress Prev. Day Progress Prev. Day Progress Scope Progress progress Progress
22-03-2023 22-03-2023 22-03-2023 22-03-2023 22-03-2023 22-03-2023

1 Pre Construction Survey/ Construction survey Mtr 86500 86500.00 0.00 86500.00 79300.00 79300.00 0.00 79300.00 63500.00 63500.00 0.00 63500.00 66700.00 66700.00 0.00 66700.00 61000.00 61000.00 0.00 61000.00 66178.00 66178.00 0.00 66178.00 4,23,178 4,23,178 - 4,23,178.00

2 3 (1) Notification Mtr 86500 86500.00 0.00 86500.00 79300.00 79300.00 0.00 79300.00 63500.00 63500.00 0.00 63500.00 66700.00 66700.00 0.00 66700.00 61000.00 61000.00 0.00 61000.00 66178.00 66178.00 0.00 66178.00 4,23,178 4,23,178 - 4,23,178.00

3 6 (1) Notification Issued Mtr 86500 86500.00 0.00 86500.00 79300.00 79300.00 0.00 79300.00 63500.00 63500.00 0.00 63500.00 66700.00 66700.00 0.00 66700.00 61000.00 61000.00 0.00 61000.00 66178.00 66178.00 0.00 66178.00 4,23,178 4,23,178 - 4,23,178.00

4 PANCHNAMA Mtr 86500 69281.35 0.00 69281.35 79300.00 78280.00 0.00 78280.00 63500.00 62992.00 0.00 62992.00 66700.00 64752.00 0.00 64752.00 61000.00 61000.00 0.00 61000.00 66178.00 62112.06 0.00 62112.06 4,23,178 3,98,417 - 3,98,417.41

5 ROU Marking Mtr 86500 77957.00 500.00 78457.00 79300.00 77850.00 0.00 77850.00 63500.00 58967.00 200.00 59167.00 66700.00 66700.00 0.00 66700.00 61000.00 61000.00 0.00 61000.00 66178.00 61666.00 0.00 61666.00 4,23,178 4,04,140 700.00 4,04,840.00

ROU Clearing & Grading (Excluding HDD &


6 Mtr 81808 73649.00 60.00 73709.00 76332.61 77784.42 0.00 77784.42 62216.00 61293.00 200.00 61493.00 61830.00 50016.00 244.00 50260.00 58804.00 58804.00 0.00 58804.00 63528.00 60523.00 0.00 60523.00 4,04,519 3,82,069 504.00 3,82,573.42
Cased X-ing)

7 Line Pipe Received Mtr 86500 74047.23 0.00 74047.23 79300.00 76676.41 0.00 76676.41 63500.00 57112.00 315.00 57427.00 66700.00 55707.98 0.00 55707.98 61000.00 59996.90 0.00 59996.90 66178.00 63158.77 0.00 63158.77 4,23,178 3,86,699 315.00 3,87,014.29

8 Stringing Mtr 86500 73594.93 60.00 73654.93 79300.00 76654.68 0.00 76654.68 63500.00 57099.00 315.00 57414.00 66700.00 52986.52 244.00 53230.52 61000.00 59910.35 170.52 60080.87 66178.00 61748.07 60.75 61808.82 4,23,178 3,81,994 850.27 3,82,843.82

Cold Field bends fabrication Nos 230 230.00 0.00 230.00 110.00 105.00 0.00 105.00 69.00 66.00 0.00 66.00 95.00 85.00 0.00 85.00 52.00 25.00 3.00 28.00 147.00 107.00 0.00 107.00 703 618 3.00 621.00

9 Cold Field bends Installation Nos 230 155.00 0.00 155.00 110.00 105.00 0.00 105.00 69.00 45.00 0.00 45.00 95.00 0.00 0.00 0.00 52.00 25.00 3.00 28.00 147.00 94.00 0.00 94.00 703 424 3.00 427.00

Hot Bend Installation Nos 0.00 0.00 0.00 41.00 22.00 0.00 22.00 41.00 0.00 0.00 0.00 52.00 0.00 0.00 0.00 52.00 20.00 0.00 20.00 0.00 27.00 0.00 27.00 69 - 69.00

10 Concrete Coating of 3LPE Pipes Nos 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 33.00 0.00 33.00 33 - 33.00

Nos 6329 5475.00 0.00 5475.00 5672.00 5639.00 0.00 5639.00 4835.00 4313.00 26.00 4339.00 4972.00 3952.00 26.00 3978.00 4502.00 4604.00 10.00 4614.00 4797.00 4420.00 0.00 4420.00 31,107 28,403 62.00 28,465.00
11 Mainline Welding
Mtr 77776 65685.49 0.00 65685.49 68631.00 68897.93 0.00 68897.93 58503.00 51888.00 314.00 52202.00 59368.00 48238.40 317.20 48555.60 54760.00 57323.30 121.35 57444.65 59692.37 55317.44 0.00 55317.44 3,78,730 3,47,351 752.55 3,48,103.11

Free Tie in Nos 721 626.00 6.00 632.00 596.00 0.00 596.00 196.00 3.00 199.00 549.00 115.00 3.00 118.00 460.00 185.00 5.00 190.00 550.00 525.00 5.00 530.00 3,361 2,243 22.00 2,265.00
668.00 413.00
Free Tie / Tie-
12 Tie-In Nos 100 76.00 0.00 76.00 106.00 0.00 106.00 48.00 0.00 48.00 62.00 8.00 0.00 8.00 40.00 51.00 0.00 51.00 100.00 85.00 1.00 86.00 302 374 1.00 375.00
in Welding
Length Mtr 8724 7828.18 60.96 7889.14 10669.00 7713.45 0.00 7713.45 4997.00 3386.00 36.00 3422.00 7332.00 1140.80 24.40 1165.20 6240.00 2445.27 48.72 2493.99 6485.63 6425.37 60.26 6485.63 44,448 28,939 230.34 29,169.41

Nos 7150 6177.00 6.00 6183.00 6554.00 6341.00 0.00 6341.00 5248.00 4557.00 29.00 4586.00 5583.00 4075.00 29.00 4104.00 4962.00 4840.00 15.00 4855.00 5447.00 5030.00 6.00 5036.00 34,944 31,020 85.00 31,105.00
13 Total Welding
Mtr 86500 73513.67 60.96 73574.63 79300.00 76611.38 0.00 76611.38 63500.00 55274.00 350.00 55624.00 66700.00 49379.20 341.60 49720.80 61000.00 59768.57 170.07 59938.64 66178.00 61742.81 60.26 61803.07 4,23,178 3,76,290 982.89 3,77,272.51
14 Radiography & AUT

a Taken Nos 7150 6045.00 5.00 6050.00 6554.00 6319.00 0.00 6319.00 5248.00 3941.00 7.00 3948.00 5583.00 3864.00 48.00 3912.00 5002.00 4662.00 8.00 4670.00 5447.00 4846.00 4.00 4850.00 34,984 29,677 72.00 29,749.00

b Reviewed Nos 7150 6036.00 0.00 6036.00 6554.00 6306.00 0.00 6306.00 5248.00 3932.00 0.00 3932.00 5583.00 3784.00 50.00 3834.00 5002.00 4637.00 24.00 4661.00 5447.00 4850.00 7.00 4857.00 34,984 29,545 81.00 29,626.00

c Accepted Nos 7150 5069.00 0.00 5069.00 6554.00 5309.00 0.00 5309.00 5248.00 3381.00 0.00 3381.00 5583.00 3216.00 46.00 3262.00 5002.00 3866.00 19.00 3885.00 5447.00 4179.00 7.00 4186.00 34,984 25,020 72.00 25,092.00

d Repair Nos - 868.00 0.00 868.00 - 997.00 0.00 997.00 - 521.00 0.00 521.00 - 434.00 4.00 438.00 - 744.00 5.00 749.00 - 565.00 0.00 565.00 4,129 9.00 4,138.00

e Repair %age % - 14.38% 0.00% 14.35% - 15.81% 0.00% 15.78% - 13.25% 0.00% 13.20% - 11.47% 8.00% 11.20% - 16.04% 20.83% 16.04% - 11.65% 0.00% 11.65% 13.98% 11.11% 13.97%

f Repair Accepted Nos - 972.00 0.00 972.00 - 947.00 0.00 947.00 - 435.00 0.00 435.00 - 381.00 0.00 381.00 - 656.00 4.00 660.00 - 664.00 2.00 666.00 4,055 6.00 4,061.00

15 Joint Coating Nos 7150 5576.00 5.00 5581.00 6554.00 6068.00 7.00 6075.00 5248.00 3663.00 20.00 3683.00 5583.00 2816.00 44.00 2860.00 5002.00 4057.00 35.00 4092.00 5447.00 4806.00 23.00 4829.00 34,984 26,986 134.00 27,120.00

16 Trenching Mtr 82700 61944.91 148.00 62092.91 79300.00 70933.83 0.00 70933.83 62280.00 41257.00 150.00 41407.00 61530.00 29191.97 650.00 29841.97 58804.00 37914.00 180.00 38094.00 63528.00 49233.15 213.00 49446.15 4,08,142 2,90,475 1,341.00 2,91,815.86

Lowering & Holiday Testing (Excluding HDD


17 Mtr 82700 61852.20 0.00 61852.20 76589.45 67532.90 523.95 68056.85 62280.00 38725.06 195.00 38920.06 61530.00 26605.59 2254.60 28860.19 58804.00 38012.68 231.21 38243.89 63528.00 48123.12 1252.07 49375.19 4,05,431 2,80,852 4,456.83 2,85,308.38
& Crossing Length)

18 Total Lowering (incl. HDD, SHDD & Moling) Mtr 86500 62572.13 0.00 62572.13 79300.00 70230.90 523.95 70754.85 63500.00 39593.00 195.00 39788.00 66700.00 27069.92 2254.60 29324.52 61000.00 39251.68 231.21 39482.89 66178.00 50609.84 1252.07 51861.91 4,23,178 2,89,327 4,456.83 2,93,784.30

19 HDPE Duct Laying Mtr 82700 62572.13 0.00 62572.13 79300.00 70204.00 0.00 70204.00 63500.00 40442.00 200.00 40642.00 66700.00 23337.44 0.00 23337.44 61000.00 36015.00 1000.00 37015.00 66178.00 47418.00 100.00 47518.00 4,19,378 2,79,989 1,300.00 2,81,288.56

20 OFC Blowing Mtr 82700 0.00 0.00 0.00 79300.00 30445.00 1260.00 31705.00 63500.00 0.00 0.00 0.00 66700.00 0.00 0.00 0.00 61000.00 13585.00 0.00 13585.00 66178.00 22274.00 1389.00 23663.00 4,19,378 66,304 2,649.00 68,953.00

21 Back filling Mtr 82700 60380.44 548.00 60928.44 76589.45 67604.76 0.00 67604.76 62280.00 36433.00 450.00 36883.00 61530.00 22121.00 1000.00 23121.00 58804.00 34767.34 170.00 34937.34 63528.00 40958.00 170.00 41128.00 4,05,431 2,62,265 2,338.00 2,64,602.54
Major Crossings of (River,Railway, NH, SH,
22
Water body Crossing etc..)
A BY HDD

a River Crossing Nos 7 0.00 0.00 0.00 2.00 2.00 0.00 2.00 0.00 0.00 0.00 0.00 6.00 1.00 0.00 1.00 1.00 1.00 0.00 1.00 1.00 1.00 0.00 1.00 17 5 - 5.00

b Railway Crossing Nos 2 0.00 0.00 0.00 1.00 1.00 0.00 1.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2.00 2.00 0.00 2.00 5 3 - 3.00

c National Highway Crossing Nos 2.00 1.00 0.00 1.00 1.00 1.00 0.00 1.00 0.00 0.00 0.00 0.00 1.00 0.00 0.00 0.00 1.00 0.00 0.00 0.00 1.00 1.00 0.00 1.00 6 3 - 3.00

d State Highways Crossing Nos 2.00 0.00 0.00 0.00 2.00 1.00 0.00 1.00 3.00 3.00 0.00 3.00 2.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 9 4 - 4.00

e Canal / Nala / Drain Crossings/ POND Nos 0.00 0.00 0.00 0.00 5.00 5.00 0.00 5.00 2.00 1.00 0.00 1.00 5.00 0.00 0.00 0.00 7.00 5.00 0.00 5.00 5.00 4.00 0.00 4.00 24 15 - 15.00

f Other major Roads Nos 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1.00 0.00 0.00 0.00 1.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2 - - -

g Utility Crossings Nos 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 - - - -

Nos 13.00 1.00 0.00 1.00 11.00 10.00 0.00 10.00 5.00 4.00 0.00 4.00 15.00 1.00 0.00 1.00 10.00 6.00 0.00 6.00 9.00 8.00 0.00 8.00 63 30 - 30.00
h HDD CROSSINGS
Mtr 3700.00 161.93 0.00 161.93 2710.55 2453.16 0.000 2453.16 860.00 667.44 0.00 667.44 4810.00 312.33 0.00 312.33 2150.00 1184.00 0.00 1184.00 2500.00 2411.72 0.00 2411.72 16,731 7,191 - 7,190.58

B. K. Das
Sr. Manager
Page 1 of 13 MECON Limited
MECON LIMITED
DAILY PROGRESS REPORT -- SRIKAKULAM - ANGUL PIPELINE PROJECT (PART-A)
Report Date : 23 March 2023 Progress Date : 22 March 2023

Section-I (M/s Corrtech International Section-II (M/s Advance Section-III (M/s Corrtech International Section-IV (M/s Ram Baran Singh Section-V (M/s Tolani Projects Pvt. Section-VI (M/s Ace Pipeline
Details of spread Cumulative Overall
Ltd.) Infrastructures Pvt. Ltd.) Ltd.) Apex Pvt. Ltd.) Ltd.) Contracts Pvt. Ltd)
24"x 86.5 KM (Ch. 0.00 to Ch. 86.5) 24" x 78.5 KM (Ch. 86.5 to Ch. 165.0) 18" x 64 KM (Ch. 165.0 to Ch. 229.0) 18" x 67 KM (Ch. 229.0 to 296.0) 18" x 61 KM (Ch. 296.0 to Ch. 357.0) 18" x 66 KM (Ch. 357.0 to Ch. 423.17)
Status
Date of award 30 June 2021 30 June 2021 30 June 2021 30 June 2021 30 June 2021 30 June 2021
Go-Ahead 13.12.2021 10.01.2022 10.01.2022 17.03.2022 21.05.2022 19.05.2022
Today Today Today Today Today Today
Cum. Till Progress Cum. Cum. Till Progress Cum. Cum. Till Progress Cum. Cum. Till Progress Cum. Cum. Till Progress Cum. Cum. Till Progress Cum. Total Previous Today Cum.
S. No Description UOM Scope Scope Scope Scope Scope Scope
Prev. Day Progress Prev. Day Progress Prev. Day Progress Prev. Day Progress Prev. Day Progress Prev. Day Progress Scope Progress progress Progress
22-03-2023 22-03-2023 22-03-2023 22-03-2023 22-03-2023 22-03-2023

B BY SHDD
Pre Construction Survey/ Construction survey
a Major Road/Asphalted Roads/ Cart Track etc. Nos 3.00 2.00 0.00 2.00 2.00 0.00 0.00 0.00 8.00 5.00 0.00 5.00 6.00 3.00 0.00 3.00 1.00 2.00 0.00 2.00 0.00 0.00 0.00 0.00 20 12 - 12.00

b Canal / Nala / Drain Crossings Nos 1 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3 - - -

c SHDD length Mtr 174 96.00 0.00 96.00 30.00 0.00 0.00 0.00 240.00 114.00 0.00 114.00 240.00 108.00 0.00 108.00 16.00 32.00 0.00 32.00 0.00 0.00 0.00 0.00 700 350 - 350.00

C BY MOLING

a Major Road/Asphalted Roads/ Cart Track etc. Nos 27.00 27.00 0.00 27.00 20.00 15.00 0.00 15.00 9.00 4.00 0.00 4.00 6.00 4.00 0.00 4.00 2.00 2.00 0.00 2.00 8.00 6.00 0.00 6.00 72 58 - 58.00

b Canal / Nala / Drain Crossings Nos 4 1.00 0.00 1.00 3.00 3.00 0.00 3.00 0.00 0.00 0.00 0.00 1.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 8 4 - 4.00

c Moling length Mtr 464 462.00 0.00 462.00 226.84 244.84 0.00 244.84 120.00 86.50 0.00 86.50 120.00 44.00 0.00 44.00 30.00 23.00 0.00 23.00 150.00 75.00 0.00 75.00 1,111 935 - 935.34

D BY OPEN CUT

a Major Road/Asphalted Roads/ Cart Track etc. Nos 43 31.00 0.00 31.00 54.00 43.00 0.00 43.00 50.00 25.00 0.00 25.00 23.00 3.00 0.00 3.00 31.00 15.00 0.00 15.00 60.00 19.00 0.00 19.00 261 136 - 136.00

b Canal/ Nala/ Drain Crossings Nos 23 17.00 0.00 17.00 24.00 19.00 0.00 19.00 7.00 0.00 0.00 0.00 20.00 0.00 0.00 0.00 38.00 16.00 0.00 16.00 148.00 73.00 0.00 73.00 260 125 - 125.00

c Open Cut Length Mtr 528 454.04 0.00 454.04 616.00 957.00 0.00 957.00 684.00 377.00 0.00 377.00 516.00 21.00 0.00 21.00 700.00 162.00 0.00 162.00 1534.00 1079.92 0.00 1079.92 4,578 - 3,050.96

23 CP Work

a Soil Resistivity Survey Mtrs 82700 82700.00 0.00 82700.00 76500.00 76500.00 0.00 76500.00 62280.00 62216.00 0.00 62216.00 66700.00 66700.00 0.00 66700.00 61000.00 61000.00 0.00 61000.00 66178.00 66178.00 0.00 66178.00 4,15,358 4,15,294 - 4,15,294.00

b Mg. Anode-3-5 Kg Installation Nos 83 67.00 0.00 67.00 0.00 43.00 1.00 44.00 64.00 26.00 0.00 26.00 67.00 0.00 0.00 0.00 65.00 17.00 2.00 19.00 0.00 37.00 1.00 38.00 279 190 4.00 194.00

c Mg. Anode-5-10 Kg / 5 M Installation Nos 30 3.00 0.00 3.00 80.00 0.00 0.00 0.00 10.00 4.00 0.00 4.00 12.00 0.00 0.00 0.00 10.00 0.00 0.00 0.00 0.00 4.00 0.00 4.00 142 11 - 11.00

d Zn. Anode-20 Kg/ M Installation Nos 34 19.00 0.00 19.00 0.00 4.00 0.00 4.00 18.00 9.00 0.00 9.00 30.00 0.00 0.00 0.00 12.00 4.00 0.00 4.00 0.00 9.00 0.00 9.00 94 45 - 45.00

e Thermit Welding Nos 155.00 0.00 155.00 80.00 140.00 2.00 142.00 184.00 71.00 0.00 71.00 218.00 0.00 0.00 0.00 174.00 34.00 4.00 38.00 0.00 125.00 2.00 127.00 525 8.00 533.00

f TLP Installation Nos 64.00 0.00 64.00 89.00 64.00 1.00 65.00 92.00 39.00 0.00 39.00 109.00 0.00 0.00 0.00 87.00 0.00 0.00 0.00 0.00 44.00 1.00 45.00 211 2.00 213.00

g TCP Commissioning Nos 0.00 0.00 0.00 0.00 0.00 0.00 0.00 92.00 0.00 0.00 0.00 109.00 0.00 0.00 0.00 84.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 - - -

24 Cleaning & Guaging Mtr 82700 0.00 0.00 0.00 78500.00 0.00 0.00 0.00 63500.00 0.00 0.00 0.00 66700.00 0.00 0.00 0.00 61000.00 0.00 0.00 0.00 66178.00 12727.48 0.00 12727.48 4,18,578 12,727 - 12,727.48

25 Hydrotesting Mtr 82700 0.00 0.00 0.00 78500.00 0.00 0.00 0.00 63500.00 0.00 0.00 0.00 66700.00 0.00 0.00 0.00 61000.00 0.00 0.00 0.00 66178.00 12727.48 0.00 12727.48 4,18,578 12,727 - 12,727.48

26 Marker Installation

a Direction Marker Mtr 245 0.00 0.00 0.00 0.00 0.00 0.00 0.00 220.00 0.00 0.00 0.00 156.00 0.00 0.00 0.00 174.00 0.00 0.00 0.00 256.00 34.00 0.00 34.00 1,051 34 - 34.00

b Pipeline Warning Signs Nos. 150 0.00 0.00 0.00 0.00 0.00 0.00 0.00 100.00 0.00 0.00 0.00 150.00 0.00 0.00 0.00 120.00 0.00 0.00 0.00 259.00 17.00 0.00 17.00 779 17 - 17.00

c Kilo Meter Posts Nos. 87 0.00 0.00 0.00 0.00 0.00 0.00 0.00 64.00 0.00 0.00 0.00 67.00 0.00 0.00 0.00 61.00 0.00 0.00 0.00 54.00 3.00 0.00 3.00 333 3 - 3.00

d Aerial Marker Nos. 87 0.00 0.00 0.00 0.00 0.00 0.00 0.00 64.00 0.00 0.00 0.00 67.00 0.00 0.00 0.00 61.00 0.00 0.00 0.00 13.00 0.00 0.00 0.00 292 - - -

e Navigable Waterway Marker Nos. 4 0.00 0.00 0.00 0.00 0.00 0.00 0.00 4.00 0.00 0.00 0.00 4.00 0.00 0.00 0.00 4.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 16 - - -

f ROU Boundary Marker Mtrs 700 0.00 0.00 0.00 0.00 0.00 0.00 0.00 520.00 0.00 0.00 0.00 540.00 0.00 0.00 0.00 500.00 0.00 0.00 0.00 732.00 0.00 0.00 0.00 2,992 - - -

g Clean up & Restoration Nos. 82700 0.00 0.00 0.00 78500.00 0.00 0.00 0.00 63500.00 0.00 0.00 0.00 66700.00 0.00 0.00 0.00 61000.00 0.00 0.00 0.00 66178.00 0.00 0.00 0.00 4,18,578 - - -

27 MAHANADI PROGRESS

M/s TRENCHLESS ENGINEERING SERVICES PVT. LTD.


Rig Mobilization & Execution status (Srikkakulam
ROU STATUS (ANGUL SIDE) ROU STATUS (SRIKAKULAM SIDE) Topographical & Geotechnical survey status Profile Drawing status Rig Mobilization & Execution status (Angul side)
side)
* Handed over on 22.04.2022. * Handed over on 22.04.2022. * Topographical Survey completed on 15.09.2022. * Initial Profile Drawing was Approved on * 36" reaming completed. * 36" reaming completed. Welding of 24"
* Compensation has been paid on 14.05.2022. * Compensation has been paid on 14.05.2022. * Geotechnical Survey completed on 05.06.2022. 19.04.2022,However , as per latest inputs from * All casing has been retracted. * 310 nos coating completed. Product Pipe
3815.93 0 3815.93
(Scope: 3800
* Bathymetric survey completed on 24.08.2022. Geo-techsurvey, revised profile submitted on * Pre-hydro test completed. * Clean Pass stopped.
MAHANADI
meter)
Report submitted to MECON on 29.08.2022. 20.06.2022 for Mecon approval. Revised profile * During clean pass, after pulling out of 50
RT accepted (314
approved on 21.09.2022. drilling pipes from angul side, drilling pipes got 280 0 280

PROGRESS
Joints)
unattached and 71 pipes from angul side & 274
6" Piloting (3800
pipes from Srikkakulam side along with 36" 3821.85 0 3821.85
meters)
reamer barrel stuck inside. Process for pulling
24" Piloting (3800
out the stucked drilling pipes is in progress. meters)
3800 0 3800

36" Reaming (3800


3800 0 3800
meters)

Site Constraints : SECTION-I SECTION-II SECTION-III SECTION-IV SECTION-V SECTION-VI


1. Presently 4 rigs deployed at site, and additional 3 rigs Expediting supply of other BO items like electrical, 1. 1500 coatings sleeves are available and another lot of 1. Presently 3 HDD rigs are available, additional Expediting supply of other BO items like electrical, Expediting supply of other BO items like electrical,
to be deployed. Instrumentation & Fire fighting by the Contractor. 1500 sleeves will be available at site by 16.03.2023. deployment of 2 HDD rigs to be done. Instrumentation & Fire fighting by the Contractor. Instrumentation & Fire fighting by the Contractor.
2. Deployment of 25-30 manpower for each stations at 2. One rig for SHDD to be deployed. 2. Expediting supply of BO items like electrical,
SV-2 & SV-4 to be done. No work in last 20 days at SV-1. 3. Additional 25-30 manpower to be deployed for Instrumentation & Fire fighting by the Contractor.
3. Additional deploymeny of 3 excavators for mainline boundary wall works in each of SV-8 & 9. Work has not 3. Earth filling IP-3 to be done.
works to be done. been started at SV-9. 5. Work not started at SV-12 till now.
4. Expediting supply of OFC & other BO items like 4. Presently 12 excavators are deployed dditional 3
electrical, Instrumentation & Fire fighting by the excavators are required to be deployed.
Contractor. 5. Expediting supply of OFC & other BO items like
electrical, Instrumentation & Fire fighting by the
Contractor. 6. Earth filling in SV-8, SV-9 & SV-10 to be
done

B. K. Das
Sr. Manager
Page 2 of 13 MECON Limited
MECON LIMITED
DAILY PROGRESS REPORT --SRIKAKULAM - ANGUL PIPELINE PROJECT (PART-A) (HDD)
Report Date : 23 March 2023 Progress Date : 22 March 2023
Status of HDD
TYPE OF Crossing Approved Present
Contractors Sl.No. DESCRIPTION Listed / Unlisted Profile Drawing Remarks
CROSSING Chainage Length (Mtrs) Status
Approval

Asphalted Road (Dasmania to Captive


ASPHALTED ROAD 01+339.52
Power Plant)

EAST COAST RAILWAY LINE (TALCHER HINDRANCE :-ROU OF


1 RS TO ANGUL RS) WITH ASPHALTED RAILWAY Un-listed Approved 269.84 Not Started
01+409.58 GODMARA VILLAGE
ROAD (DASMANIA O CAPTIVR POWER CROSSING
PLANT ) AT CH: 01+339.52 AND POND
Nala Crossing NALA 01+559.99
Section-I (M/s Corrtech International Ltd.)

NATIONAL HIGHWAY -149 (CHAINPAL


Punchanama of High BMV.
2 TO BANARPAL, BETWEEN KMS-81 & NH 04+317.15 Un-listed Approved 200.51 Not Started
KMS-82) 12.4 mm pipe from mecon
EAST COAST RAILWAY
RAILWAY Railway permission yet to
3 LINE(BURHAPANKA RS TO CAPTIVE 07+601.14 Un-listed Approved 193.82 Not Started
POWER PLANT)
CROSSING receive
NATIONAL HIGHWAY -55 Pulling completed on
4 NH 09+368.10 Un-listed Approved 161.93
(NARENDRAPUR TO BANARPAL) 09.01.2023

140T rig deployed. due to


breakdown pump rod work not
5 NIGRA NADI RIVER 17+145.45 Listed Approved 382.69 22" reaming in progress
started for last 15 DAYS. Work
resumed on 21.03.2023.
RIVER 33+080.72 Rig setup done. Due to
BARHA JOR RIVER & ASPHALTED
6
ROAD
Listed Approved 333.36 Rig Mobilized unavailability of bentonite
ASPHALTED ROAD 33+142.20
work not started yet.
7 SAPUA NADI RIVER 45+943.40 Listed Yet to submit rerouting 3(1) under progress
8 SAPUA NADI RIVER 47+524.03 Listed Approved 312.76 36" reaming is in progress
9 SAPUA NADI RIVER 55+729.63 Listed Approved 319.16 Not Started Rig not mobilized yet.
10 SAPUA NADI RIVER 58+667.13 Listed Approved 298.74 Piloting is in progress
12.4 mm pipe yet to receive from
11 SAPUA NADI RIVER 64+785.86 Listed Approved 324.97 Not started
mecon
STATE HIGHWAY-65 (DERSHANPUR TO
12 SUSAGARI, BETWEEN KMS-21 & KMS- SH 68+221.17 Un-listed Approved 177.83 Not started Rig yet to mibilize
22)
STATE HIGHWAY-65 (PAOCHAGAN TO
13 SASAGARI, BETWEEN KMS-25 & KMS- SH 70+458.88 Un-listed Approved 181.43 Not Started Rig yet to mibilize
24)

1 CHANDRAPA NALA NALA 87+836.45 Un-listed Approved 239.424 Completed on 08.10.2022


uctures Pvt. Ltd.)

2 POND POND 88+461.97 Un-listed Approved 209.534 Completed on 21.10.2022

State Haighway -48 (Simor to gobindpur,


3 SH 102+141.76 Un-listed Approved 209.179 Completed on 28.11.2022
between kms-4 & kms-5

4 HARHA NALA NALA 114+165.71 Un-listed Approved 210 Completed on 06.02.2023

B. K. DAS
Sr. Manager
Page 3 of 13 MECON LIMITED
MECON LIMITED
DAILY PROGRESS REPORT --SRIKAKULAM - ANGUL PIPELINE PROJECT (PART-A) (HDD)
Ltd.) Infrastructures Pvt. Ltd.)

Report Date : 23 March 2023 Progress Date : 22 March 2023


Status of HDD
TYPE OF Crossing Approved Present
Contractors Sl.No. DESCRIPTION Listed / Unlisted Profile Drawing Remarks
CROSSING Chainage Length (Mtrs) Status
Approval

114+924.75
01+339.52
5 HARHA NALA NALA+ROAD 115+055.44 Un-listed Approved 215 Completed on 09.02.2023
115+017.37 HINDRANCE :-ROU OF
1 Un-listed Approved 269.84 Not Started
Raliway Line(RAJSUNAKHALA RS TO GODMARA VILLAGE
6 RAILWAY 131+384.10 Un-listed Approved 223.885 Completed on 02.11.2022
NAYAGARH TOWN RS)
NH-57
NH
(M/s Advance

7 132+582.06 Un-listed Approved 189.067 Completed on 16.08.2022


(KHURDA TO NAYAGARH)

Kusumi Nadi RIVER 138+336.57


International

8 Listed Approved 394.17 Completed on 11.08.2022


VILLAGE ROAD (SUNANATI TO
VILLAGE ROAD 138+254.20
SARAPARHA )
Pipes issued. Go-ahead for string
STATE HIGHWAY - 21 (MACHIPARA TO
SH preparation has been given to
Section-II

9 147+160.22 Un-listed Approved 153.351 Not started


HARIHARAPUR)
Contractor by GAIL.
158+899.60
Kusumi Nadi RIVER+NALA
Section-I (M/s Corrtech

10 Listed Approved 339.68 Completed


158+975.4

11 ROAD AND NALA ROAD+NALA 164+290 Un-listed Approved 327.265 16" reaming is in progress
INTERNATIONAL PRIVATE

1 State Highway - 21 SH 177+198 Un-listed AAN 148.51 Completed on 15.09.2022

Rig demobilized from CH 202 and Another


M/s CORRTECH

2 PENDULA NALA NALA 197+552 Un-listed AAN 178.52 Not started


Rig shall be mobilized on 6.03.2023
Section-III:

LIMITED

3 STATE HIGHWAY - 33 SH 202+710 Un-listed AAN 154.44 Completed on 06.02.2023

4 BIG POND AND ASPHALTED ROAD POND 225+622 Un-listed Approved 213.25 Completed on 06.12.2022

5 STATE HIGHWAY - 30 SH 227+483 Un-listed AAN 149.73 Completed on 24.08.2022

RUSIKULYA RIVER AND ASPHALTED Pilot work in progress around work stopped and machine under repair for
1 RIVER 233+775.14 Listed AAN 686.5
ROAD
ingh Apex Pvt. Ltd.)

534m completed. more than 50 days and shall be demobilized

Work stopped. Rig breakdown due to mud


2 NATIONAL HIGHWAY - 59 NH-59 235+114.96 Un-listed Approved 16" reaming completed motor pump

6" conduit pulling completed


3 STATE HIGHWAY-36 AND NALA SH + NALA 240+704 Un-listed AAN 151.665

B. K. DAS
Sr. Manager
Page 4 of 13 MECON LIMITED
MECON LIMITED
DAILY PROGRESS REPORT --SRIKAKULAM - ANGUL PIPELINE PROJECT (PART-A) (HDD)
Baran Singh Apex Pvt. Ltd.)

Report Date : 23 March 2023 Progress Date : 22 March 2023


Status of HDD
TYPE OF Crossing Approved Present
Contractors Sl.No. DESCRIPTION Listed / Unlisted Profile Drawing Remarks
CROSSING Chainage Length (Mtrs) Status
Approval

NANDANI RIVER AND ASPHALTED Completed on 25.02.2023


4 RIVER 01+339.52
243+996.25 Listed Approved 312.332
ROAD

HINDRANCE :-ROU OF
1 GHORHARA RIVER AND ASPHALTED Un-listed Approved 269.84 NotisStarted
Piloting in progress
5 RIVER 248+404.12 Listed AAN 421 GODMARA VILLAGE
ROAD

6 KHARI NALA CROSSING NALA 249+574.34 Un-listed AAN 181.396


Ltd.)

RUSIKULYA CANAL AND ASPHALTED


(M/s Ram

7 CANAL 252+863.04 Un-listed AAN 162.147


ROAD
International

8 POND and ODR ROAD POND 262+580.37 Un-listed AAN 207.859

9 KANTAJURA NADI RIVER 269+104.48 Listed AAN 305.000


KANTAJURA NALA NALA
Section-IV

10 275+464.12 Un-listed Approved


11 BAHUDA RIVER RIVER 276+111.53 Listed U/S

12 BAGI NADI, CANAL AND VILLAGE ROAD RIVER 285+730.63 Listed AAN 247.979
Section-I (M/s Corrtech

13 POND POND 289+693.68 Un-listed


14 POND POND 291+701.39 Un-listed
15 NALA AND CART TRACK NALA 293+177.22 Un-listed

1 MAHENDRA TANYA RIVER RIVER 317+982 Listed AAN 330 Completed on 24.01.2023
Section-V (M/s Tolani Projects Pvt.

2 POND POND 303+341 Un-listed AAN 187 Completed on 28.11.2022

3 PADIGAM CANAL CANAL 315+454 Un-listed AAN 162.5 Completed on 07.01.2023

4 ROAD, NALA AND RETAINING WALL NALA 310+000 Un-listed AAN 151 Completed on 15.02.2023

5 MINOR CANAL CANAL 346+899 Un-listed AAN 160 Completed on 17.03.2023


Ltd.)

CART TRACK, BUMSIDHARA CANAL


6 CANAL+ POND 349+802 Un-listed AAN 192.5 Completed on 20.03.2023
AND POND
ROU not available
7 NATIONAL HIGHWAY-16 NH 352+668 Un-listed Approved 150 Not started

8 CART RACK AND BAMSIDHARA CANAL CANAL 356+928 Un-listed AAN -- Not Started

Submitted for
9 NALA NALA 337+265 Un-listed --
approval
Submitted for
10 NALA NALA 338+679 Un-listed --
approval
Pvt. Ltd)

1 BASHDHARA RIVER RIVER 411+369 Listed AAN 1003 Completed on 25.09.2022

B. K. DAS
Sr. Manager
Page 5 of 13 MECON LIMITED
MECON LIMITED
DAILY PROGRESS REPORT --SRIKAKULAM - ANGUL PIPELINE PROJECT (PART-A) (HDD)
Report Date : 23 March 2023 Progress Date : 22 March 2023
Status of HDD
TYPE OF Crossing Approved Present
Contractors Sl.No. DESCRIPTION Listed / Unlisted Profile Drawing Remarks
CROSSING Chainage Length (Mtrs) Status
Contracts Pvt. Ltd)

Approval

2 RAILWAY CROSSING RAILWAY 01+339.52


385+251 Un-listed Approved 210.821 Completed on 25.02.2023

HINDRANCE :-ROU OF
1
3 STATE HIGHWAY AND RAILWAY SH+RAILWAY 369+563 Un-listed
Un-listed Approved
AAN 269.84
194 Not Started
Completed on 30.12.2022
GODMARA VILLAGE

4 NATIONAL HIGHWAY-16 NH-16 406+259 Un-listed Approved 292 Completed on 06.12.2022


Ltd.)
Ace Pipeline

5 DRY CANAL CANAL 418+694 Un-listed AAN 250 10" reaming completed
International

POND 366+164
6 CANAL POND+CANAL 366+198 Un-listed AAN 215.936 Completed on 21.01.2023
CART TRACK 366+271

7 CANAL CANAL 390+181 Un-listed Approved 145.2 Completed on 27.02.2023


Corrtech(M/s

8 POND POND 406+835 Un-listed Approved 178 Completed on 13.02.2023


Section-VI

9 CANAL CANAL 407+422 Un-listed AAN 212 Completed on 19.01.2023

POND 421.39
Section-I (M/s

10 POND Un-listed Yet to submit -- Under HOLD/ Deleted


ROAD 421.43

B. K. DAS
Sr. Manager
Page 6 of 13 MECON LIMITED
MECON LIMITED
Report Date : March 23, 2023 DAILY PROGRESS REPORT -- SRIKAKULAM - ANGUL PIPELINE PROJECT (PART-A) Progress Date : March 22, 2023
PROGRESS STATUS OF STATIONS (RT, DT, SV & IP) - MAINLINE CONTRACTOR'S SCOPE

Land Handover Topographical Geotechnical


Section Contractor Stations Status of Civil Drawings Status of Mechanical Drawings Status of Architectural Drawings Status Electrical Drawings Status of Instrumentation Drawings Civil Constrcution Status Station Piping Status
Date Survey Survey

1. Civil drawing for Pipe and Valve support R-0 1. Plot plan R-0 issued on 22.06.2022. 1) Overall SLD R-0 issued on 17.02.2023. 1. Cable shedule issued on 06.01.2023. Only process area is under SAPL (Part-A): Work not
issued on 03.11.2022. Plot plan R-1 issued on 15.09.2022. 2. Cable layout issued on 06.01.2023. started yet.
DT 13.12.2021 NA NA 2. Piping GAD R-0 issued on 06.07.2022. -- --
Piping GAD R-1 issued on 01.10.2022.
1. Detail of Boundary wall R-0 issued on 1. Plot Plan R-0 issued on 10.10.2022. 1. Details of steel gate R-0 issued on 1. Outdoor lighting layout 24" R-0 issued on 06.01.2023. 1) Boundary wall footing excavation - 157/188 RM.
02.11.2022. Plot Plan R-1 issued on 23.11.2022. 14.10.2022. 2. Electrical cable rout diagram for 24" R-0 issued on 2) Boundary wall footing PCC - 159.02/188 RM.
2. Details of GAIL logo R-0 issued on 29.10.2022. 2. Piping GAD R-0 issued on 17.10.2022. Typical details of steel gates R-1 issued on 06.01.2023. 3) Boundary wall footing R.C.C - 96.2/186 RM.
3. Process area layout/ Sleeper layout R-0 issued Piping GAD R-1 issued on 23.11.2022. 04.02.2023. 3. Earthing and lightning protection for 24" R-0 issued on 4) Column up to beam B3 - 35/71 nos.
07.09.2022 09.09.2022 on 19.11.2022 2. Details of structural Cross over R-0 06.01.2023. 5) Boundary wall raft beam RCC - 96.02/186 Rmt.
issued on 14.10.2022. 4. Electrical cable schedule R-0 issued on 24.01.2022. 6) Boundary wall NGL beam RCC - 60/186 Rmt. Not Started
SV-1 17.08.2022 Report- Report- --
5. Typical cable tray layout IFC R-0 issued on
27.09.2022 27.09.2022
17.02.2023.
6. Typical electrical Equipment layout R-0 issued on
17.02.2023.
7. Typical Overall Electrical SLD R-0 issued on
17.02.2023.
1. Detail of Boundary wall R-0 issued on 1. Plot Plan R-0 issued on 09.01.2023. 1. Details of steel gate R-0 issued on 1. Electrical cable schedule R-0 issued on 24.01.2022. 1. Cable shedule issued on 06.01.2023. 1) Boundary wall area cleaning and vegetation - 2800/2800
09.01.2023. Plot Plan R-1 issued on 03.02.2023. 14.10.2022. 2. Typical cable tray layout IFC R-0 issued on 2. Cable layout issued on 06.01.2023. Sqm.
M/s CORRTECH INTERNATIONAL LTD.

05.12.2022 04.12.2022 2. Piping GAD R-0 issued on 09.01.2023. Typical details of steel gates R-1 issued on 17.02.2023. 2) Excavation for raft footings - 51/210 Rmt.
Not Started
SV-2 19.11.2022 Report- Report- 04.02.2023. 3. Typical electrical Equipment layout R-0 issued on 3) Footings PCC completed - 20/210 Rmt.
12.12.2022 12.12.2022 2. Details of structural Cross over R-0 17.02.2023.
issued on 14.10.2022. 4. Typical Overall Electrical SLD R-0 issued on
17.02.2023.
1. Detail of Boundary wall R-0 issued on 1. Plot Plan R-0 issued on 10.10.2022. 1. Details of steel gate R-0 issued 1. Outdoor lighting layout 24" R-0 issued on 06.01.2023 & Type-I Wall:
SECTION-1

11.11.2022. Plot Plan R-1 issued on 20.12.2022. on 14.10.2022. R-1 on 09.01.2023. 1) Boundary wall footing excavation - 72/72 Nos.
Details of Boundary Wall R-1 issued on 2. Piping GAD R-0 issued on 17.10.2022. Typical details of steel gates R-1 issued on 2. Electrical cable rout diagram for 24" R-0 issued on 2) Boundary wall footing PCC - 60/72 Nos.
28.12.2022. 04.02.2023. 06.01.2023 & R-1 on 09.01.2023. 3) Boundary wall footing R.C.C - 60/72 Nos.
2. Process area layout/ Sleeper layout R-0 issued 3. details of structural Cross over R-0 issued 3. Earthing and lightning protection for 24" R-0 issued on 4) Column up to NGL beam - 72/92 Nos.
on 08.12.2022 on 14.10.2022. 06.01.2023 & R-1 on 09.01.2023. 5) Column NGL to FGL - 72/92 Nos.
4. Typical cable tray layout IFC R-0 issued on 6) NGL beam casting - 200/220 Rmt.
23.09.2022 23.09.2022 17.02.2023. 7) FGL beam casting - 203/260 Rmt.
Not Started
SV-3 21.09.2022 Report- Report- 5. Typical electrical Equipment layout R-0 issued on -- 8) Brick work NGL to FGL - 203/260 Rmt.
17.02.2023. 9) Column FGL to Top beam bottom - 72/92 Nos.
03.10.2022 03.10.2022
6. Typical Overall Electrical SLD R-0 issued on 10) Brick work FGL to Top beam bottom - 203/256 Rmt.
17.02.2023. TYPE-II Wall:
1) Retaining wall Raft excavation - 39/39 Rmt.
2) Retaining wall Raft PCC - 39/39 Rmt.
3) retaining wall Raft RCC - 39/39 Rtm.
4) Retaining wall up to NGL - 39/39 nos..
5) Main gate Portation beam - 4/4 completed.
1. Detail of Boundary Wall R-0 issued on 1. Plot Plan R-0 issued on 30.06.2022. 1. Details of steel gate R-0 issued on 1. Outdoor lighting layout 24" R-0 issued on 06.01.2023. 1. Cable shedule issued on 21.12.2022. Type-1 Wall (Single footings):
13.07.2022. 2. Piping GAD R-0 issued on 12.07.2022. 14.10.2022. 2. Electrical cable rout diagram for 24" R-0 issued on 2. Cable layout issued on 21.12.2022. 1) Boundary wall footing excavation - 22/58 nos.
2. Layout Plan & Detail of Pipe support & Typical details of steel gates R-1 issued on 06.01.2023. 2) Boundary wall footing PCC - 19/58 nos.
12.05.2022 Valve support R-0 issued on 03.09.2022. 04.02.2023. 3. Earthing and lightning protection for 24" R-0 issued on 3) Boundary wall footing RCC - 19/58 nos.
30-05-2022 25.05.2022 3. Details of GAIL logo R-0 issued on 29.10.2022. 2. details of structural Cross over R-0 issued 06.01.2023. Type-II Wall (Single footings):
on 14.10.2022. 4. Electrical cable schedule R-0 issued on 24.01.2022. Not Started
SV-4 24.04.2022 06.06.2022 Report- 1) Excavation (Single footing) - 19/19.
5. Typical cable tray layout IFC R-0 issued on 3) Boundary wall footing PCC - 19/19 nos.
08.06.2022 08.06.2022
17.02.2023. 4) Boundary wall footing RCC - 16/19 nos.
24.06.2022 6. Typical electrical Equipment layout R-0 issued on 5) Column up to NGL - 17/19 nos.
17.02.2023.
7. Typical Overall Electrical SLD R-0 issued on
17.02.2023.
1. Detail of Boundary Wall R-0 issued on 1. Plot Plan R-0 issued on 06.07.2022. 1. Details of steel gate R-0 issued on 1. Outdoor lighting layout 24" R-0 issued on 30.12.2022. 1. Cable shedule issued on 19.12.2022. 1) Boundary wall footing excavation - 97/97 Nos.
04.08.2022. 2. Piping GAD R-0 issued on 05.09.2022. 03.09.2022. 2. Electrical cable rout diagram for 24" R-0 issued on 2. Cable layout issued on 19.12.2022. 2)Combined footing Excavation - 37/37 mtr.
2. Process area layout/ Sleeper layout R-0 issued 2. details of structural Cross over R-0 issued 30.12.2022. 3) Boundary wall footing PCC - 97/97 Nos.
4) Boundary wall footing R.C.C - 97/97 Nos.
on 19.11.2022 on 03.09.2022. 3. Earthing and lightning protection for 24" R-0 issued on
5). Boundary wall Column up to Tie Beam Bottom- 117/117 Nos.
30.12.2022. 6). Boundary wall tie Beam Casting- 295/295 RM
4. Typical Overall electrical SLD drawing R-0 issued on 7). Column up to Tie Beam Top to Middle Beam Bottom- 117/117 nos
17.02.2023. 8)Combined footing P.C.C - 37/37 rm.
24.03.2022 5. Typical Electrical Equipment layout plan R-0 issued on 9) . Brick Work up to Tie Beam Top Middle Beam Bottom- 295/295 RM
IP-1 02.06.2022 29.06.2022 Report- 17.02.2023. 10)Combined footing R.C.C - 37/37 rm. Not Started
6. Typical Electrical Cable Tray Layout R-0 issued on 11)Middle beam casting - 295/295 Rm
29.06.2022 12) Retaining wall casting (700mm height) - 37/37 Rm.
17.02.2023.
13) Retaining wall casting (700mm 2nd lift height) - 37/37 Rm.
14) Retaining wall casting (700mm 3rd lift height) - 37/37 Rm.
15) Retaining wall casting (600mm 3rd lift height) - 37/37 Rm.
16) Column upto b2 bottom - 98/ 117 nos.
17)Brick Work up to Tie Beam Top top Beam Bottom- 138/295 RM

1. Detail of Boundary Wall R-0 issued on 1. Plot Plan R-0 issued on 10.10.2022. 1. Details of steel gate R-0 issued on 1. Outdoor lighting layout 24" R-0 issued on 30.12.2022. 1)Boundary wall footing excavation - 78/78 Nos.
21.10.2022. 2. Piping GAD R-0 issued on 17.10.2022. 03.09.2022. 2. Electrical cable rout diagram for 24" R-0 issued on 2) Boundary wall footing PCC - 78/78 Nos.
2. Process area layout/ Sleeper layout R-0 issued 2. details of structural Cross over R-0 issued 30.12.2022. 3) Boundary Wall Footing RCC - 75/78 Nos.
on 08.12.2022 on 03.09.2022. 3. Earthing and lightning protection for 24" R-0 issued on 4) Boundary wall column upto b3 bottom - 76/83 Nos.
16.09.2022 30.12.2022. 5) Plinth beam - 216/230 Rm
4. Electrical cable schedule R-0 issued on 24.01.2022. 6) Boundary wall column upto b2 bottom - 72/83 Nos.
SV-5 01.10.2022 03.10.2022 Report- -- Not started
5. Typical Overall electrical SLD drawing R-0 issued on 7) Boundary wall brick wall upto b2 bottom - 183/230 Rm
04.10.2022
17.02.2023. 8) Middle Beam - 112/230 Rm
M/s ADVANCE INFRASTRUCTURE PVT. LTD.

6. Typical Electrical Equipment layout plan R-0 issued on


17.02.2023.
7. Typical Electrical Cable Tray Layout R-0 issued on
17.02.2023.
1. Plot Plan R-0 issued on 27.02.2023. 1. Details of steel gate R-0 issued on 1. Outdoor lighting layout 24" R-0 issued on 04.03.2023.
03.09.2022. 2. Electrical cable rout diagram for 24" R-0 issued on
2. details of structural Cross over R-0 issued 04.03.2023.
SECTION-2

on 03.09.2022. 3. Earthing and lightning protection for 24" R-0 issued on


14.02.2023 11.02.2023 04.03.2023.
SV-6 31.01.2023 Report- Report- -- 4. Typical Overall electrical SLD drawing R-0 issued on -- Work not started Not Started
24.02.2023 24.02.2023 17.02.2023.
5. Typical Electrical Equipment layout plan R-0 issued on
17.02.2023.
6. Typical Electrical Cable Tray Layout R-0 issued on
17.02.2023.

B. K. DAS
Sr. Manager
Page 7 of 13 MECON LIMITED
M/s ADVANCE INFRASTRUCTURE PVT. LTD.

MECON LIMITED
Report Date : March 23, 2023 DAILY PROGRESS REPORT -- SRIKAKULAM - ANGUL PIPELINE PROJECT (PART-A) Progress Date : March 22, 2023
SECTION-2

PROGRESS STATUS OF STATIONS (RT, DT, SV & IP) - MAINLINE CONTRACTOR'S SCOPE

Land Handover Topographical Geotechnical


Section Contractor Stations Status of Civil Drawings Status of Mechanical Drawings Status of Architectural Drawings Status Electrical Drawings Status of Instrumentation Drawings Civil Constrcution Status Station Piping Status
Date Survey Survey

1. Detail of Boundary Wall R-0 issued on 1. Plot Plan R-0 issued on 25.08.2022. 1. Details of steel gate R-0 issued on 1. Outdoor lighting layout 24" R-0 issued on 30.12.2022. 1)Boundary wall footing excavation - 40/48 Nos.
14.10.2022. 2. Piping GAD R-0 issued on 29.08.2022. 03.09.2022. 2. Electrical cable rout diagram for 24" R-0 issued on 2) Combined footing Excavation - 115/115 mtr.
2. Layout Plan & Detail of Pipe & Valve 2. Details of structural Cross over R-0 issued 30.12.2022. 3)Boundary wall footing p.c.c - 40/48 Nos.
support R-0 issued on 20.09.2022. on 03.09.2022. 3. Earthing and lightning protection for 24" R-0 issued on 4) Combined footing p.c.c - 115/115 mtr.
19.07.2022 14.09.2022 30.12.2022. 5)Combined footing R.c.c - 115/115 mtr.
4. Electrical cable schedule R-0 issued on 24.01.2022. 6).Boundary wall Footing RCC- 40/48 Nos.
SV-7 28.07.2022 10.08.2022 Report- -- Not Started
5. Typical Overall electrical SLD drawing R-0 issued on 7) Boundary wall Column up to Tie Beam Bottom- 27/93 Nos.
12.10.2022 27.09.2022
17.02.2023. 8) Retaining wall RCC (1200mm)- 108/115
6. Typical Electrical Equipment layout plan R-0 issued on 9) Retaining wall RCC (1200mm 2nd lift)- 56/115
17.02.2023.
7. Typical Electrical Cable Tray Layout R-0 issued on
17.02.2023.
1. Boundary Wall details R-0 issued on 1. Plot Plan R-0 issued on 13.04.2022. 1. Details of steel gate R-0 issued on 1. Outdoor lighting layout 24" R-0 issued on 30.12.2022. 1. Boundary wall Footing Excavation- 115/115 Nos.
2. Boundary wall Footing PCC- 115/115 Nos.
30.04.2022. Plot Plan R-1 issued on 30.04.2022. 03.09.2022. 2. Electrical cable rout diagram for 24" R-0 issued on
3. Boundary wall Footing RCC- 115/115 Nos.
2. Boundary Wall Details R-1 issued on Plot Plan R-2 issued on 27.05.2022. 2. details of structural Cross over R-0 issued 30.12.2022. 4. Boundary wall Column up to Tie Beam Bottom- 122/122 Nos.
03.06.2022. Plot Plan R-3 issued on 22.06.2022. on 03.09.2022. 3. Earthing and lightning protection for 24" R-0 issued on 5. Boundary wall tie Beam Casting- 330/330 RM
3. Layout Plan of Process area Civil works R-0 Plot Plan R-4 issued on 27.07.2022. 30.12.2022. 6. Column up to Tie Beam Top to Middle Beam Bottom- 112/122 nos
issued on 20.09.2022. Plot Plan R-5 issued on 02.02.2023. 4. Typical Overall electrical SLD drawing R-0 issued on 7. Middle Beam - 330/330mtr
7. Brick Work up to Tie Beam Top Middle Beam Bottom- 320/330 RM
2. Piping GAD R-0 issued on 08.06.2022. 17.02.2023.
M/s CORRTECH INTERNATIONAL LTD.

8. Outer Plaster Tie Beam Bottom to Middle Beam Bottom- 78/330 RM


5. Typical Electrical Equipment layout plan R-0 issued on 9. Inner Plaster Tie Beam Bottom to Middle Beam Bottom- 78/330 RM
02.04.2022
IP-2 25.03.2022 24.03.2022 17.02.2023. -- 11. Column upto Top Beam Bottom(Height 1200mm): 114/122 Nos Completed Not Started
28.04.2022 6. Typical Electrical Cable Tray Layout R-0 issued on 12. Column upto Top Beam Bottom(Height above 1200mm): 114/122 Nos
Completed
17.02.2023.
13. Brick work upto b2 to b1 bottom (Height 1950 mm) - 325/330 MTR
14. Top beam casting - 318/330 Rmt.
SECTION-1

15. Copping Casting - 256/330 Rmt


16. Inner Plaster Middle Beam Bottom to copping top - 170/330 RM
17. Boundary wall inside soil filling continue.
18)Outer Plaster Middle Beam Bottom to copping top - 220/330 RM

1. Details of Boundary Wall R-0 issued 1. Plot Plan R-0 issued on 25.08.2022. 1. Details of steel gate R-0 issued on 1. Outdoor lighting layout 18" R-0 issued on 09.01.2023. 1. Excavation work for footing completed.
on 05.09.2022. 2. Piping GAD R-0 issued on 29.08.2022. 14.10.2022. 2. Electrical cable rout diagram for 18" R-0 issued on 2. PCC for footings completed.
2. Plan & Details of Pipe & Valve support Piping GAD R-1 issued on 11.11.2022. Typical details of steel gates R-1 issued on 09.01.2023. 3. Raft RCC casting completed.
R-0 issued on 20.09.2022. 04.02.2023. 3. Earthing and lightning protection for 18" R-0 issued on 4. Columns casting up to plinth bottom- 55/55 completed.
3. Details of GAIL logo R-0 issued on 2. details of structural Cross over R-0 issued 09.01.2023. 5. Retaining wall column and footing up to plinth bottom is in
28.07.2022 13.05.2022 29.10.2022. on 14.10.2022. 4. Electrical cable schedule R-0 issued on 24.01.2022. progress.
5. Typical cable tray layout IFC R-0 issued on 6. Beam B3 casting completed except retaining wall. Not Started
SV-8 07.08.2022 Report- Report- --
17.02.2023. 7. Column up to Beam B2 bottom completed for 26 nos of
23.08.2022 23.08.2022
6. Typical electrical Equipment layout R-0 issued on columns.
17.02.2023. 8. Beam B2 casting completed for 26 nos. of columns.
7. Typical Overall Electrical SLD R-0 issued on Brick work up to Beam B2 bottom completed for 26 nos. of
M/s CORRTECH INTERNATIONAL LTD.

17.02.2023. columns. Brick work in progress up to B1 beam bottom for 26


nos. of columns

1. Details of Boundary Wall R-0 issued 1. Plot Plan R-0 issued on 27.05.2022. 1. Details of steel gate R-0 issued on 1. Outdoor lighting layout 18" R-0 issued on 10.01.2023. 1. Footing excavation completed - 17/77 nos.
on 02.07.2022. Plot Plan R-1 issued on 22.06.2022. 14.10.2022. 2. Electrical cable rout diagram for 18" R-0 issued on
2. Plan & Details of Pipe & Valve support 2. Piping GAD R-0 issued on 24.06.2022. Typical details of steel gates R-1 issued on 10.01.2023.
SECTION-3

R-0 issued on 16.07.2022. Piping GAD R-1 issued on 11.11.2022. 04.02.2023. 3. Earthing and lightning protection for 18" R-0 issued on
24.04.2022 08.05.2022 3. Details of GAIL logo R-0 issued on 2. Details of structural Cross over R-0 issued 10.01.2023.
29.10.2022. on 14.10.2022. 4. Electrical cable schedule R-0 issued on 24.01.2022.
SV-9 14.03.2022 R-1 by Report- -- Not Started
5. Typical cable tray layout IFC R-0 issued on
05.06.2022 05.06.2022
17.02.2023.
6. Typical electrical Equipment layout R-0 issued on
17.02.2023.
7. Typical Overall Electrical SLD R-0 issued on
17.02.2023.
1. Detail of Boundary Wall R-0 issued on 1. Plot Plan R-0 issued on 27.05.2022. 1. Details of steel gate R-0 issued on 1. Outdoor lighting layout 18" R-0 issued on 09.01.2023. Cable schedule & Cable layout R-0 issued on All structural works completed except mainline Rou part. Top
10.06.2022. Plot Plan R-1 issued on 24.06.2022. 14.10.2022. 2. Electrical cable rout diagram for 18" R-0 issued on 11.07.2022. beam casting completed. Y angle fixing completed. Plastering
2. Details of Boundary Wall R-1 issued Plot Plan R-2 issued on 07.09.2022. Typical details of steel gates R-1 issued on 09.01.2023. work 60% completed.
on 09.09.2022. Plot Plan R-3 issued on 13.01.2023. 04.02.2023. 3. Earthing and lightning protection for 18" R-0 issued on
13.05.2022 13.05.2022 3. Plan & Details of Pipe & Valve support 2. Piping GAD R-0 issued on 24.06.2022. 2. Details of structural Cross over R-0 issued 09.01.2023.
R-0 issued on 19.07.2022. Piping GAD R-1 issued on 11.11.2022. on 14.10.2022. 4. Electrical cable schedule R-0 issued on 24.01.2022. Piping materials issued except assorted pipes. Fabrication not
SV-10 14.03.2022 05.06.2022 05.06.2022
4. Details of GAIL logo R-0 issued on 29.10.2022. Piping GAD R-2 issued on 13.01.2023. 5. Typical cable tray layout IFC R-0 issued on started yet.
24.04.2022 31.07.2022
17.02.2023.
6. Typical electrical Equipment layout R-0 issued on
17.02.2023.
7. Typical Overall Electrical SLD R-0 issued on
17.02.2023.
1. Details of boundary wall R-0 issued on 1. Plot Plan R-0 issued on 19.12.2022. 1. Details of steel gate R-0 issued on 1. Outdoor lighting layout 18" R-0 issued on 12.01.2023. 1) Footing excavation - 107/128 nos.
09.01.2023 Plot Plan R-1 issued on 04.01.2023. 18.10.2022. 2. Electrical cable rout diagram for 18" R-0 issued on 2) Footing PCC - 107/128 nos.
2. Plan & Details of Pipe & Valve support 2. Piping GAD R-0 issued on 18.01.2023. 2. details of structural Cross over R-0 issued 12.01.2023. 3) Footing RCC - 107/128 nos.
R-0 issued on 04.03.2023. Piping GAD R-1 issued on 27.02.2023. on 18.10.2022. 3. Earthing and lightning protection for 18" R-0 issued on 4) Column up to B2 beam bottom (1st lift) - 114/137 nos.
25.11.2022 26.11.2022 02.12.2022 12.01.2023. 5) Brick work B6 to B5 - 105.2/298.4 Rm.
IP-3 Registration done Repport- Report- 4. Typical Overall electrical SLD drawing R-0 issued on -- Not started
on 06.01.2023 03.12.2022 18.12.2022 17.02.2023.
5. Typical Electrical Equipment layout plan R-0 issued on
17.02.2023.
6. Typical Electrical Cable Tray Layout R-0 issued on
M/s RAM BARAN SINGH APEX PVT. LTD.

17.02.2023.
1. Plan & Details of Boundary Wall R-0 1. Plot Plan R-0 issued on 30.04.2022. 1. Details of steel gate R-0 issued on 1. Outdoor lighting layout 18" R-0 issued on 12.01.2023. 1) Boundary wall footing excavation - 69/71 Nos.
issued on 31.05.2022. Plot Plan R-1 issued on 27.05.2022. 18.10.2022. 2. Electrical cable rout diagram for 18" R-0 issued on 2) Boundary wall footing PCC - 69/71 Nos.
2. Plan & Details of Pipe & Valve support Plot Plan R-2 issued on 22.06.2022. 2. details of structural Cross over R-0 issued 12.01.2023. 3) Boundary wall footing RCC- 69/71 Nos.
R-0 issued on 18.07.2022. 2. Piping GAD R-0 issued on 08.06.2022. on 18.10.2022. 3. Earthing and lightning protection for 18" R-0 issued on 4) Column casting up to B-3 bottom- 71/77 Nos.
Piping GAD R-1 issued on 24.06.2022. 12.01.2023. 5) Beam B-3 RCC - 181.75/205.75 Mtr
SECTION-4

02.04.2022 Piping GAD R-2 issued on 11.11.2022. 4. Electrical cable schedule R-0 issued on 24.01.2022. 6) Brick work B3 to B2 - 161.35/182.65 Mtr
09.04.2022 5. Typical Overall electrical SLD drawing R-0 issued on 7) Plastering work B3 to B2 - 0/205.75 Mtr Not started
SV-11 14.03.2022 Report- --
Report-23.05.2022 17.02.2023. 8) Column casting B3 to B2- 71/77 Nos.
23.05.2022
6. Typical Electrical Equipment layout plan R-0 issued on 9) Beam B2 RCC- 170.1/205.75 Mtr
17.02.2023. 10) Brick work up to B2 beam bottom - 117.3/182.65 Mtr.
7. Typical Electrical Cable Tray Layout R-0 issued on 11) Column up to top beam - 25/77 nos.
17.02.2023. 12) Brick work up to top beam bottom - 32.4/ 182.65 Rmt.
13) Plot area Soil filling - 3500/4200 cum.

B. K. DAS
Sr. Manager
Page 8 of 13 MECON LIMITED
M/s RAM BARAN SINGH APEX PVT. LTD.

MECON LIMITED
SECTION-4

Report Date : March 23, 2023 DAILY PROGRESS REPORT -- SRIKAKULAM - ANGUL PIPELINE PROJECT (PART-A) Progress Date : March 22, 2023
PROGRESS STATUS OF STATIONS (RT, DT, SV & IP) - MAINLINE CONTRACTOR'S SCOPE

Land Handover Topographical Geotechnical


Section Contractor Stations Status of Civil Drawings Status of Mechanical Drawings Status of Architectural Drawings Status Electrical Drawings Status of Instrumentation Drawings Civil Constrcution Status Station Piping Status
Date Survey Survey

1. Plan & Details of Boundary Wall R-0 1. Plot Plan R-0 issued on 30.06.2022. 1. Details of steel gate R-0 issued on 1. Outdoor lighting layout 18" R-0 issued on 12.01.2023.
issued on 16.07.2022. 2. Piping GAD R-0 issued on 06.07.2022. 18.10.2022. 2. Electrical cable rout diagram for 18" R-0 issued on
2. Plan & Details of Pipe & Valve support Piping GAD R-1 issued on 11.11.2022. 2. details of structural Cross over R-0 issued 12.01.2023.
R-0 issued on 18.07.2022. on 18.10.2022. 3. Earthing and lightning protection for 18" R-0 issued on
12.01.2023.
26.05.2022 4. Electrical cable schedule R-0 issued on 24.01.2022. Not Started
SV-12 12.05.2022 17.05.2022 -- Work not started due to local villager's hidrance.
Report-13.06.2022 5. Typical Overall electrical SLD drawing R-0 issued on
17.02.2023.
6. Typical Electrical Equipment layout plan R-0 issued on
17.02.2023.
7. Typical Electrical Cable Tray Layout R-0 issued on
17.02.2023.
1. Plan & Details of Boundary Wall R-0 1. Plot Plan R-1 issued on 21.01.2023. 1. Details of steel gate R-0 issued on 1. Electrical Outdoor Lighting, Cable Route, Earthing & 1) Soil filling is in progress.
issued on 15.02.2023. 2. Piping GAD R-0 issued on 15.02.2023. 18.10.2022. Lightning prot. layout drawing R-0 issued on 14.02.2023. 2) Excavation for footings is in progress.
2. Layout Plan and details for pipes and valve Details of steel gate R-1 issued on 2. Typical Overall electrical SLD drawing R-0 issued on
11.01.2023 support R-0 issued on 16.02.2023. 04.02.2023. 17.02.2023.
SV-13 29.12.2022 05.01.2023 -- Not Started
Report- 19.01.2023 2. details of structural Cross over R-0 issued 3. Typical Electrical Equipment layout plan R-0 issued on
on 18.10.2022. 17.02.2023.
LTD.

4. Typical Electrical Cable Tray Layout R-0 issued on


17.02.2023.
INTERNATIONAL

1. Plan & Details of Boundary Wall R-0 1. Plot Plan R-0 issued on 01.12.2022. 1. Details of steel gate R-0 issued on 1. Outdoor lighting layout 18" R-0 issued on 17.01.2023. 1. Cable layout R-0 issued on 21.12.2022. 1) Excavation for Boundary wall - 201/201 Rmt.
issued on 23.12.2022. 2. Piping GAD R-0 issued on 17.12.2022. 18.10.2022. 2. Electrical cable rout diagram for 18" R-0 issued on 2. Cable schedule R-0 issued on 21.12.2022. 2) PCC for footings - 201/201 Rmt.
PVT. LTD.

2. Layout Plan and details for pipes and valve Details of steel gate R-1 issued on 17.01.2023. 3) RCC for footings - 183.34/201 Rmt.
support R-0 issued on 16.02.2023. 04.02.2023. 3. Earthing and lightning protection for 18" R-0 issued on 4) Soil Filling - 3055/6500 cum
SECTION-1

2. details of structural Cross over R-0 issued 17.01.2023. 5) RCC work for raft (Type-IV) - 00/29 rmt
31.10.2022 on 18.10.2022. 4. Electrical Cable Schedule R-0 issued on 24.01.2023. 6) RCC work for retaining wall (Type-III) - 00/97 rm
05.11.2022
Report-
PROJECTS

SV-14 5. Electrical cable schedule R-0 issued on 24.01.2022.


SECTION-5

26.10.2022 Report- Not Started


18.11.2022, 6. Typical Overall electrical SLD drawing R-0 issued on
M/s CORRTECH

23.11.2022
23.11.2022 17.02.2023.
7. Typical Electrical Equipment layout plan R-0 issued on
17.02.2023.
M/s TOLANI

8. Typical Electrical Cable Tray Layout R-0 issued on


17.02.2023.

1. Plan & Details of boundary wall R-1 issued on 1. Plot Plan R-0 issued on 15.02.2023. 1. Details of steel gate R-0 issued on 1. Typical Overall electrical SLD drawing R-0 issued on 1) Soil filling work completed.
03.02.2023. 2. Piping GAD R-0 issued on 17.02.2023. 18.10.2022. 17.02.2023. 2) Footing excavation completed - 380/1339 Rmt.
06.09.2022 16.10.2022 Details of steel gate R-1 issued on 2. Typical Electrical Equipment layout plan R-0 issued on 3) Raft casting is in progress.
IP-4 26.08.2022 -- Not Started
16.10.2022 Report-04.11.2022 04.02.2023. 17.02.2023.
2. details of structural Cross over R-0 issued 3. Typical Electrical Cable Tray Layout R-0 issued on
on 18.10.2022. 17.02.2023.
'1. Plan & Details of boundary wall R-0 issued on 1. Plot Plan R-1 issued on 10.02.2023. 1. Details of steel gate R-0 issued on 1. Typical Overall electrical SLD drawing R-0 issued on
18.01.2023 19.01.2023 18.03.2023. 2. Piping GAD R-0 issued on 15.02.2023. 18.10.2022. 17.02.2023.
Details of steel gate R-1 issued on 2. Typical Electrical Equipment layout plan R-0 issued on
SV-15 04.02.2023 Report- Report- -- Work not started Not Started
04.02.2023. 17.02.2023.
04.02.2023 04.02.2023 2. details of structural Cross over R-0 issued 3. Typical Electrical Cable Tray Layout R-0 issued on
on 18.10.2022. 17.02.2023.
1. Plan & Details of Boundary Wall R-0 issued on 1. Plot Plan R-0 issued on 21.10.2022. 1. Details of steel gate R-0 issued on 1. Outdoor lighting layout 18" R-0 issued on 17.01.2023. 1) Footing excavation completed- 71/71 nos.
08.12.2022. Plot Plan R-1 issued on 04.01.2023. 18.10.2022. 2. Electrical cable rout diagram for 18" R-0 issued on 2) Footing PCC completed - 71/71 nos.
'2. Plan & Details of Boundary Wall R-1 issued on 2. Piping GAD R-0 issued on 09.11.2022. 2. details of structural Cross over R-0 issued 17.01.2023. 3) Footing RCC completed - 71/71 nos.
17.01.2023. Piping GAD R-1 issued on 12.01.2023. on 18.10.2022. 3. Earthing and lightning protection for 18" R-0 issued on 4) Column up to ngl completed - 75/75 nos.
Plan & Details of boundary wall R-1 signed 17.01.2023. 5) Excavation - 204.72/204.72 Rm. Station piping materials issued. Fabrication/ welding & fitup
02.10.2022
03.11.2022 copy 4. Electrical cable schedule R-0 issued on 24.01.2022. 6) Beam B3 casting completed - 176.3/200 Rm work for pipe size 12", 6" and 2" is in progress.
SV16 15.09.2022 Report- --
M/s ACE PIPELINE CONTRACTS PVT. LTD.

Report- 03.12.2022 issued on 03.02.2023. 5. Typical Overall electrical SLD drawing R-0 issued on 7) Column casting B3 to B2 - 132.4/200 Rmt.
16.10.2022
3. Layout Plan and details for pipes and valve 17.02.2023. 8) Brick work between B3 and B2 - 8 m3. Civil work for process area is in progress.
support R-0 issued on 16.02.2023. 6. Typical Electrical Equipment layout plan R-0 issued on 9) Column from B2 to B1 - 19 nos.
17.02.2023. 8) Beam 2 casting is in progress. Brick work up to FGL in
7. Typical Electrical Cable Tray Layout R-0 issued on progress.
17.02.2023.
1. Plan & Details of Boundary Wall R-0 issued on 1. Plot Plan R-0 issued on 21.10.2022. 1. Details of steel gate R-0 issued on 1. Outdoor lighting layout 18" R-0 issued on 17.01.2023. 1) Excavation for footings 17 Mtr completed.
SECTION-6

03.02.2023. Plot Plan R-1 issued on 03.02.2023 18.10.2022. 2. Electrical cable rout diagram for 18" R-0 issued on
2. Layout Plan and details for pipes and valve Plot Plan R-2 issued on 04.03.2023. 2. details of structural Cross over R-0 issued 17.01.2023.
27.09.2022 support R-0 issued on 16.02.2023. 2. Piping GAD R-0 issued on 09.11.2022. on 18.10.2022. 3. Earthing and lightning protection for 18" R-0 issued on
Report- 08.11.2022 17.01.2023.
4. Electrical cable schedule R-0 issued on 24.01.2022. Station piping materials issued. Fabrication/ welding & fitup
SV-17 15.09.2022 19.10.2022 Report- --
5. Typical Overall electrical SLD drawing R-0 issued on work for pipe size 12", 6" and 2" is in progress.
Revised- 03.12.2022
17.02.2023.
22.02.2023 6. Typical Electrical Equipment layout plan R-0 issued on
17.02.2023.
7. Typical Electrical Cable Tray Layout R-0 issued on
17.02.2023.
1. Details of steel gate R-0 issued on 1. Typical Overall electrical SLD drawing R-0 issued on
18.10.2022. 17.02.2023.
2. details of structural Cross over R-0 issued 2. Typical Electrical Equipment layout plan R-0 issued on
RT Not Handed Over -- -- -- -- -- Work not started Not Started
on 18.10.2022. 17.02.2023.
3. Typical Electrical Cable Tray Layout R-0 issued on
17.02.2023.

B. K. DAS
Sr. Manager
Page 9 of 13 MECON LIMITED
MECON LIMITED
Report Date : March 23, 2023 DAILY PROGRESS REPORT -- SRIKAKULAM - ANGUL PIPELINE PROJECT (PART-A) Progress Date : March 22, 2023
PROGRESS STATUS OF STATIONS (RT, DT, SV & IP) - CIVIL CONTRACTOR'S SCOPE
Section Contractor Stations Plot Hand Over Status of Civil Drawings Status of Architectural Drawings Status Electrical Drawings Status of Instrumentation Drawings Constrcution Status
1. Plot plan R-0 issued on 27.12.2022. 1. Ground floor plan and elevation R-0 issued on
2. Shuttering and R/F details of foundation & Columns R-0 03.11.2022.
issued on 15.02.2023. 2. Roof floor plan, elevation, section and schedule of
3. Layout plan of plinth beam at +100 & details R-0 issued on finishes R-0 issues on 03.11.2022.
01.10.2022. 3. Elevations and sections R-0 issues on 03.11.2022.
CONTROL 4. Layout plan & R/f details of staircase R-0 issues on 4.Details and Elevation and section details of Door and Geo-technical survey yet to be submitted by laying
-- --
ROOM 01.10.2022. Windows R-0 issues on 03.11.2022. contractor.
5. Layout plan & F/F details of roof beam & slab R-0 issued
SV-2 18.11.2022
on 01.10.2022.
6. Layout plan & R/F details of Lintel R-0 issued on
01.10.2022.
7) Typical details of cat ladder R-0 issued on 24.02.2023.
1. Layout plan & R/F details of plinth beam, lintel, roof beam 1. Floor plan, schedule of finishes and openings R-0 issues 1). Typical Drawings for Indor lighting &
& slab R-0 issued on 29.09.2022. on 03.11.2022. Conduit layout R-0 issued on 17.03.2023. Geo-technical survey yet to be submitted by laying
GUARD ROOM 2. Shuttering and R/F details of foundation & Columns R-0 --
contractor.
issued on 15.02.2023.
1. Plot plan R-0 issued on 12.10.2022. 1. Ground floor plan and elevation R-0 issued on Excavation and PCC completed.
2. Layout plan, Shuttering and R/F details of column and 03.11.2022. Work stopped due to local issue.
foundation (Type-1A) R-0 issued on 12.10.2022. 2. Roof floor plan, elevation, section and schedule of
3. Layout plan of plinth beam at +100 & details R-0 issued on finishes R-0 issues on 03.11.2022.
01.10.2022. 3. Elevations and sections R-0 issues on 03.11.2022.
CONTROL 4. Layout plan & R/f details of staircase R-0 issues on 4.Details and Elevation and section details of Door and -- --
ROOM 01.10.2022. Windows R-0 issues on 03.11.2022.
5. Layout plan & F/F details of roof beam & slab R-0 issued
SV-4 09.09.2022 on 01.10.2022.
6. Layout plan & R/F details of Lintel R-0 issued on
01.10.2022.
M/s JPG ENGINEERING PVT. LTD

7) Typical details of cat ladder R-0 issued on 24.02.2023.


1. Layout plan and R/F details of column and foundation R-0 1. Floor plan, schedule of finishes and openings R-0 issues 1). Typical Drawings for Indor lighting & Excavation and PCC completed.
issued on 29.09.2022. on 03.11.2022. Conduit layout R-0 issued on 17.03.2023. Work stopped due to local issue.
GUARD ROOM '1. Layout plan & R/F details of plinth beam, lintel, roof beam
& slab R-0 issued on 29.09.2022.
GROUP-A

1. Plot plan R-0 issued on 14.09.2022.


2. Layout plan, shuttering and R/F details of foundation and
column (Type-2A) R-0 issued on 18.11.2022.
3. Layout plan and R/F details of plinth beam at +100 &
details (Type-2A) R-0 issued on 18.11.2022.
4. layout plan and R/F details of roof beam (Type-2A) R-0
CONTROL issued on 18.11.2022.
5. Layout plan and R/F details of roof slab (Type-2A) R-0 -- -- Survey work completed
ROOM
issued on 18.11.2022.
IP-1 09.09.2022 6. Layout plan and R/F details of staircase (Type-2A) R-0
issued on 18.11.2022.
7. Layout plan and R/F details of lintel (Type-2A) R-0 issued
on 18.11.2022.
8) Typical details of cat ladder R-0 issued on 24.02.2023.
1. Layout plan & R/F details of plinth beam, lintel, roof beam 1. Floor plan, schedule of finishes and openings R-0 issues 1). Typical Drawings for Indor lighting &
& slab R-0 issued on 29.09.2022. on 03.11.2022. Conduit layout R-0 issued on 17.03.2023.
GUARD ROOM 2. Layout plan, shuttering and R/F details of foundation and Excavation for footing completed
column R-0 issued on 29.09.2022.

1. Plot plan R-4 issued on 14.09.2022. Excavation & PCC for footings completed. Footing casting
CONTROL 2) Typical details of cat ladder R-0 issued on 24.02.2023. completed. Plinth beam work completed. Reinforcement
-- -- binding and column casting is in progress.
ROOM
IP-2 09.09.2022
1. Layout plan & R/F details of plinth beam, lintel, roof beam 1. Floor plan, schedule of finishes and openings R-0 issues 1). Typical Drawings for Indor lighting & Excavation & PCC for footings completed. Footing casting
& slab R-0 issued on 29.09.2022. on 03.11.2022. Conduit layout R-0 issued on 17.03.2023. completed. Plinth beam work completed. Column casting up to
GUARD ROOM 2. Layout plan, shuttering and R/F details of foundation and lintel level completed.
column R-0 issued on 29.09.2022.
1. Layout plan, reinforcement details of foundation and 1. Floor plan, schedule of finishes and openings R-0 issues 1). Typical Drawings for Indor lighting & Footing casting completed.
column R-0 issued on 13.10.2022. on 03.11.2022. Conduit layout R-0 issued on 17.03.2023. Column casting up to plinth beam completed. Plinth beam
SV-7 09.09.2022 GUARD ROOM '1. Layout plan & R/F details of plinth beam, lintel, roof beam -- casting completed.
& slab R-0 issued on 29.09.2022. Column casting up to roof level completed. Slab casting
completed. Parapet work is in progress.

B. K. DAS
Sr. Manager
10 of 13 MECON Limited
MECON LIMITED
Report Date : March 23, 2023 DAILY PROGRESS REPORT -- SRIKAKULAM - ANGUL PIPELINE PROJECT (PART-A) Progress Date : March 22, 2023
PROGRESS STATUS OF STATIONS (RT, DT, SV & IP) - CIVIL CONTRACTOR'S SCOPE
Section Contractor Stations Plot Hand Over Status of Civil Drawings Status of Architectural Drawings Status Electrical Drawings Status of Instrumentation Drawings Constrcution Status
1. Plot plan R-0 issued on 14.09.2022. 1. Ground floor plan and elevation R-0 issued on Excavation for footings completed. PCC for footings
2. Layout plan, Shuttering and R/F details of column and 03.11.2022. Completed. Reinforcement binding for footings and columns is
foundation (Type-1A) R-0 issued on 12.10.2022. 2. Roof floor plan, elevation, section and schedule of in progress.
3. Layout plan of plinth beam at +100 & details R-0 issued on finishes R-0 issues on 03.11.2022.
01.10.2022. 3. Elevations and sections R-0 issues on 03.11.2022.
CONTROL 4. Layout plan & R/f details of staircase R-0 issues on 4.Details and Elevation and section details of Door and
ROOM 01.10.2022. Windows R-0 issues on 03.11.2022.
5. Layout plan & F/F details of roof beam & slab R-0 issued
SV-2 18.11.2022
SV-8 09.09.2022 on 01.10.2022.
6. Layout plan & R/F details of Lintel R-0 issued on
01.10.2022.
7) Typical details of cat ladder R-0 issued on 24.02.2023.
1. Layout plan and R/F details of column and foundation R-0 1. Floor plan, schedule of finishes and openings R-0 issues 1). Typical Drawings for Indor lighting & Layout demarcation is in progress.
issued on 29.09.2022. on 03.11.2022. Conduit layout R-0 issued on 17.03.2023.
GUARD ROOM '1. Layout plan & R/F details of plinth beam, lintel, roof beam --
& slab R-0 issued on 29.09.2022.

1. Plot plan R-1 issued on 14.09.2022. 1. Floor plan, schedule of finishes and openings R-0 issues Excavation & PCC work for footing completed.
2. Layout plan, Shuttering and R/F details of column and on 03.11.2022. Footing casting completed. Soil filling completed. PCC for
PCP CUM foundation (Type-3A) R-0 issued on 01.10.2022. 2. Elevations and sections R-0 issues on 03.11.2022. plinth beam is in progress. Reinforcement work for plinth beam
SV-9 09.09.2022
GUARD ROOM 3. Layout plan & R/F details of plinth beam lintel, roof beam & is in progress.
slab R-0 issued on 01.10.2022.
4) Typical details of cat ladder R-0 issued on 24.02.2023.
1. Plot Plan R-2 issued on 14.09.2022. 1. Ground floor plan and elevation R-0 issued on Excavation & soil dressing for PCC work completed. Footing &
2. Layout plan, Shuttering and R/F details of column and 03.11.2022. column reinforcement binding work completed. Footing casting
LTD.

foundation (Type-1A) R-0 issued on 12.10.2022. 2. Roof floor plan, elevation, section and schedule of completed. Column casting in progress.
3. Layout plan of plinth beam at +100 & details R-0 issued on finishes R-0 issues on 03.11.2022.
LTD
PVT.

01.10.2022. 3. Elevations and sections R-0 issues on 03.11.2022.


CONTROL 4. Layout plan & R/f details of staircase R-0 issues on 4.Details and Elevation and section details of Door and
PVT.

ROOM 01.10.2022. Windows R-0 issues on 03.11.2022.


ENGINEERING
GROUP-A

5. Layout plan & F/F details of roof beam & slab R-0 issued
ENGINEERING

SV-10 on 01.10.2022.
GROUP-A

09.09.2022
6. Layout plan & R/F details of Lintel R-0 issued on
01.10.2022.
8) Typical details of cat ladder R-0 issued on 24.02.2023.
1. Layout plan and R/F details of column and foundation R-0 1. Floor plan, schedule of finishes and openings R-0 issues 1). Typical Drawings for Indor lighting & Excavation & soil dressing for PCC for footings is in progress.
JPG

issued on 29.09.2022. on 03.11.2022. Conduit layout R-0 issued on 17.03.2023.


GUARD ROOM 2. Layout plan & R/F details of plinth beam, lintel, roof beam
JPG

--
M/sM/S

& slab R-0 issued on 29.09.2022.

1. Plot plan R-2 issued on 14.09.2022. 1. Floor plan, schedule of finishes and openings R-0 issues Footing excavation completed.
2. layout plan, shuttering & reinforcement details of on 03.11.2022.
PCP CUM foundation and column (Type-3B), R-0 isssued on 2. Elevations and sections R-0 issues on 03.11.2022.
SV-11 09.09.2022
GUARD ROOM 01.10.2022.
3. Layout plan & R/F details of plinth beam lintel, roof beam &
slab R-0 issued on 01.10.2022.
6) Typical details of cat ladder R-0 issued on 24.02.2023.
1. Plot plan R-0 issued on 14.09.2022. 1. Ground floor plan and elevation R-0 issued on Work not started
2. Layout plan, Shuttering and R/F details of column and 03.11.2022.
foundation (Type-1A) R-0 issued on 12.10.2022. 2. Roof floor plan, elevation, section and schedule of
3. Layout plan of plinth beam at +100 & details R-0 issued on finishes R-0 issues on 03.11.2022.
01.10.2022. 3. Elevations and sections R-0 issues on 03.11.2022.
CONTROL 4. Layout plan & R/f details of staircase R-0 issues on 4.Details and Elevation and section details of Door and
ROOM 01.10.2022. Windows R-0 issues on 03.11.2022.
5. Layout plan & F/F details of roof beam & slab R-0 issued
SV-12 09.09.2022 on 01.10.2022.
5. Layout plan & R/F details of Lintel R-0 issued on
01.10.2022.
6) Typical details of cat ladder R-0 issued on 24.02.2023.
1. Layout plan & R/F details of plinth beam, lintel, roof beam 1. Floor plan, schedule of finishes and openings R-0 issues 1). Typical Drawings for Indor lighting & Work not started
& slab R-0 issued on 29.09.2022. on 03.11.2022. Conduit layout R-0 issued on 17.03.2023.
GUARD ROOM --

B. K. DAS
Sr. Manager
11 of 13 MECON Limited
MECON LIMITED
Report Date : March 23, 2023 DAILY PROGRESS REPORT -- SRIKAKULAM - ANGUL PIPELINE PROJECT (PART-A) Progress Date : March 22, 2023
PROGRESS STATUS OF STATIONS (RT, DT, SV & IP) - CIVIL CONTRACTOR'S SCOPE
Section Contractor Stations Plot Hand Over Status of Civil Drawings Status of Architectural Drawings Status Electrical Drawings Status of Instrumentation Drawings Constrcution Status

1. Layout plan & R/F details of plinth beam, lintel, roof beam 1. Floor plan & schedules of finishes and openings R-0 1) Typical Internal lighting & typical conduit All works completed up to plinth beam Bottom . Plinth
& slab R-0 issued on 05.12.2022. issues on 03.11.2022. layout R-0 issued on 21.02.2023. beam casting completed.
PCP CUM
SV-1 09.09.2022 2) Typical details of cat ladder R-0 issued on 24.02.2023. 2. Elevations and sections R-0 issued on 03.11.2022. -- Column up to lintel beam beam casting completed.
GUARD ROOM 3) Typical details for saptic tank & soak pit R-0 issued on Back filling up to plinth beam bottom completed. Plinth Beam
24.02.2023. Casting Completed. Column casting above plinth is in
progress.
1. Layout plan and R/F details of column and foundation R-0 1. Floor plans, schedules of finishes and openings R-0 1) Typical Internal lighting & typical conduit Footing excavation & PCC completed. Column casting up to
SV-2 18.11.2022 issued on 30.09.2022. issued on 03.11.2022. layout R-0 issued on 21.02.2023. plinth bottom completed.
SV-3 09.09.2022 GUARD ROOM 2) Typical details of cat ladder R-0 issued on 24.02.2023.
3) Typical details for saptic tank & soak pit R-0 issued on
24.02.2023.
1. layout plan, shuttering & reinforcement details of 1. Floor plan & schedules of finishes and openings R-0 1) Typical Internal lighting & typical conduit Excavation , PCC, Footing casting completed.
foundation and columns R-0 issued on 21.01.2022. issues on 03.11.2022. layout R-0 issued on 21.02.2023. Column casting up to plinth beam bottom completed.
PCP CUM 2. Layout plan & R/F details of plinth beam, lintel, roof beam 2. Elevations and sections R-0 issued on 03.11.2022. Plinth beam casting completed. column
SV-5 21.10.2022 --
GUARD ROOM & slab R-0 issued on 01.10.2022. casting completed up to roof beam bottom .Roof slab casting
3) Typical details of cat ladder R-0 issued on 24.02.2023. completed.
4) Typical details for saptic tank & soak pit R-0 issued on
24.02.2023.
1. Layout plan of plinth beam at +100 and details R-0 issued 1. Groud floor plan & elevation R-0 issued on 03.11.2022. 1) Typical Internal lighting & typical conduit
on 01.10.2022. 2. Roof floor plan & elevation, sections and schedule of layout R-0 issued on 21.02.2023.
2. Layout plan & R/f details of roof beam R-0 issues on finishes R-0 issued on 03.11.2022.
01.10.2022. 3. Elevations and sections R-0 issued on 03.11.2022
CONTROL 3. Layout plan & R/f details of roof slab R-0 issues on 4. Door and window elevation R-0 issued on 03.11.2022.
01.10.2022. 5. Section details of Door and Windows and details R-0 --
ROOM
4. Layout plan, shuttering & R/f details of lintel R-0 issues on issued on 03.11.2022.
01.10.2022.
SV-6 31.01.2023 5. Layout plan & R/f details of staircase R-0 issues on
LTD.LTD

01.10.2022.
6) Typical details of cat ladder R-0 issued on 24.02.2023.
APEX PVT.PVT.

1) Typical details for saptic tank & soak pit R-0 issued on 1. Floor plans, schedules of finishes and openings R-0 1) Typical Internal lighting & typical conduit
24.02.2023. issued on 03.11.2022. layout R-0 issued on 21.02.2023.
ENGINEERING

GUARD ROOM
GROUP-A
PART-B

M/s RBS

1. Layout Plan & R/F details of footings & Columns R-0 1) Typical Internal lighting & typical conduit Excavation for footings completed. PCC for footing completed.
issued on 06.02.2023. layout R-0 issued on 21.02.2023. Reinforcement for footing is in progress.
M/s JPG

2. Layout plan and R/F details of plinth beam at +100 &


details (Type-2A) R-0 issued on 18.11.2022.
3. layout plan and R/F details of roof beam (Type-2A) R-0
issued on 18.11.2022.
CONTROL 4. Layout plan and R/F details of roof slab (Type-2A) R-0
ROOM issued on 18.11.2022.
5. Layout plan and R/F details of staircase (Type-2A) R-0
issued on 18.11.2022.
IP-3 25.11.2022 6. Layout plan and R/F details of lintel (Type-2A) R-0 issued
on 18.11.2022.
7) Typical details of cat ladder R-0 issued on 24.02.2023.
8) Ground Floor & roof plan & Elevation and sections R-0
issued on Plan
1. Layout 20.02.2023.
& R/F details of footings & Columns R-0 1. Floor plans, schedules of finishes and openings R-0 1) Typical Internal lighting & typical conduit Excavation for footings completed.
issued on 06.02.2023. issued on 03.11.2022. layout R-0 issued on 21.02.2023. PCC & RCC for footing completed.
2) Typical details for saptic tank & soak pit R-0 issued on Plinth beam casting completed.
GUARD ROOM --
24.02.2023. Column casting up to lintel completed.

1) Typical details of cat ladder R-0 issued on 24.02.2023. 1) Typical Internal lighting & typical conduit Work not started
CONTROL layout R-0 issued on 21.02.2023.
ROOM

SV-13 04.02.2023 1. Layout Plan & R/F details of footings & Columns R-0 1) Typical Internal lighting & typical conduit Work not started
issued on 10.02.2023. layout R-0 issued on 21.02.2023.
GUARD ROOM 2) Typical details for saptic tank & soak pit R-0 issued on --
24.02.2023.

B. K. DAS
Sr. Manager
12 of 13 MECON Limited
MECON LIMITED
Report Date : March 23, 2023 DAILY PROGRESS REPORT -- SRIKAKULAM - ANGUL PIPELINE PROJECT (PART-A) Progress Date : March 22, 2023
PROGRESS STATUS OF STATIONS (RT, DT, SV & IP) - CIVIL CONTRACTOR'S SCOPE
Section Contractor Stations Plot Hand Over Status of Civil Drawings Status of Architectural Drawings Status Electrical Drawings Status of Instrumentation Drawings Constrcution Status
1. Plot plan R-0 issued on 26.12.2022. 1. Groud floor plan & elevation R-0 issued on 03.11.2022. 1) Typical Internal lighting & typical conduit Excavation for footings completed. PCC & RCC work for
2. Layout plan & R/F details of foundation and columns R-0 2. Roof floor plan & elevation, sections and schedule of layout R-0 issued on 21.02.2023. footings completed. Tie beam casting completed. Column
issued on 03.01.2023. finishes R-0 issued on 03.11.2022. casting up to plinth completed.
3. Layout plan & details of tie-beam at -2500 (Type-1A) R-0 3. Elevations and sections R-0 issued on 03.11.2022 Reinforment work in progress for plinth beam under progress.
issued on 07.01.2023. 4. Door and window elevation R-0 issued on 03.11.2022.
3. Layout plan of plinth beam at +100 and details R-0 issued 5. Section details of Door and Windows and details R-0
on 01.10.2022. issued on 03.11.2022.
CONTROL 4. Layout plan & R/f details of roof beam R-0 issues on
SV-2 18.11.2022 ROOM 01.10.2022.
5. Layout plan & R/f details of roof slab R-0 issues on
SV-14 26.10.2022 01.10.2022.
6. Layout plan, shuttering & R/f details of lintel R-0 issues on
01.10.2022.
7. Layout plan & R/f details of staircase R-0 issues on
01.10.2022.
8) Layout
1. Typical plan
details of cat
& R/F ladder
details of R-0 issued and
foundation on 24.02.2023.
columns R-0 1. Floor plans, schedules of finishes and openings R-0 1) Typical Internal lighting & typical conduit Footing excavation and PCC completed.
issued on 03.01.2023. issued on 03.11.2022. layout R-0 issued on 21.02.2023.
GUARD ROOM 2) Typical details for saptic tank & soak pit R-0 issued on --
24.02.2023.

1. Layout plan and R/F details of plinth beam at +100 & 1) Typical Internal lighting & typical conduit Work not started
details (Type-2A) R-0 issued on 18.11.2022. layout R-0 issued on 21.02.2023.
2. layout plan and R/F details of roof beam (Type-2A) R-0
issued on 18.11.2022.
3. Layout plan and R/F details of roof slab (Type-2A) R-0
CONTROL issued on 18.11.2022.
PVT. LTD. PVT. LTD

ROOM 4. Layout plan and R/F details of staircase (Type-2A) R-0


issued on 18.11.2022.
IP-4 26.08.2022 5. Layout plan and R/F details of lintel (Type-2A) R-0 issued
on 18.11.2022.
ENGINEERING

6) Typical details of cat ladder R-0 issued on 24.02.2023.


GROUP-A

7) Ground Floor & roof plan & Elevation and sections R-0
issued on 20.02.2023.
1) Typical details for saptic tank & soak pit R-0 issued on 1. Floor plans, schedules of finishes and openings R-0 1) Typical Internal lighting & typical conduit Work not started
PART-B

24.02.2023. issued on 03.11.2022. layout R-0 issued on 21.02.2023.


APEX

GUARD ROOM --
JPG
RBS

1) Typical details of cat ladder R-0 issued on 24.02.2023. 1) Typical Internal lighting & typical conduit Work not started
M/s

CONTROL layout R-0 issued on 21.02.2023.


M/s

ROOM
SV-15 04.02.2023
1) Typical details for saptic tank & soak pit R-0 issued on 1) Typical Internal lighting & typical conduit Work not started
24.02.2023. layout R-0 issued on 21.02.2023.
GUARD ROOM --

1. Plot plan R-0 issued on 26.12.2022. 1. Groud floor plan & elevation R-0 issued on 03.11.2022. 1) Typical Internal lighting & typical conduit Mobilization completed. Boudlers braking and removal
2. Layout plan, shuttering & reinforcement details of 2. Roof floor plan & elevation, sections and schedule of layout R-0 issued on 21.02.2023. completed. Footing excavation completed.
foundation and columns R-0 issued on 05.12.2022. finishes R-0 issued on 03.11.2022. PCC for footing completed.
3. Layout plan of plinth beam at +100 and details R-0 issued 3. Elevations and sections R-0 issued on 03.11.2022 Footing casting completed. column
on 01.10.2022. 4. Door and window elevation R-0 issued on 03.11.2022. completed up to plinth beam bottom . Plinth beam
4. Layout plan & R/f details of roof beam R-0 issues on 5. Section details of Door and Windows and details R-0 completed. Reinforcement binding for columns ubove plinth is
CONTROL 01.10.2022. issued on 03.11.2022. in progress.
ROOM 5. Layout plan & R/f details of roof slab R-0 issues on
SV-16 09.09.2022 01.10.2022.
6. Layout plan, shuttering & R/f details of lintel R-0 issues on
01.10.2022.
7. Layout plan & R/f details of staircase R-0 issues on
01.10.2022.
8) Typicalplan,
1. layout details of cat ladder
shuttering R-0 issued details
& reinforcement on 24.02.2023.
of 1. Floor plans, schedules of finishes and openings R-0 1) Typical Internal lighting & typical conduit Mobilization completed. Boudlers braking and removal
foundation and columns R-0 issued on 05.12.2022. issued on 03.11.2022. layout R-0 issued on 21.02.2023. completed. Footing excavation completed.
GUARD ROOM --
2) Typical details for saptic tank & soak pit R-0 issued on Raft for footing casting completed.
24.02.2023. Column casting up to plinth beam completed.
1. Plot plan R-0 issued on 26.12.2022. 1. Floor plan & schedules of finishes and openings R-0 1) Typical Internal lighting & typical conduit Work not started
2. Layout plan, Shuttering and R/F details of column and issues on 03.11.2022. layout R-0 issued on 21.02.2023.
foundation (Type-3A) R-0 issued on 21.10.2022. 2. Elevations and sections R-0 issued on 03.11.2022.
PCP CUM 3. Layout plan & R/F details of plinth beam, lintel, roof beam
SV-17 09.09.2022
GUARD ROOM & slab R-0 issued on 01.10.2022.
4) Typical details of cat ladder R-0 issued on 24.02.2023.
5) Typical details for saptic tank & soak pit R-0 issued on
24.02.2023.

B. K. DAS
Sr. Manager
13 of 13 MECON Limited