MUMBAI METRO LINE 3 CONTRACT UGC-07

MONDAY, 6 JANUARY 2020


Ramp Programme

Shotcrete

Waler

MUMBAI METRO LINE 3 CONTRACT UGC-07


MONDAY, 6 JANUARY 2020
Ramp Programme
Dec’19 Dec ’19 Last week Last week Cumulative Next week Plan for
Activity UOM Scope Remarks
Plan achieved plan achieved Achieved plan Jan’20

Excavation
(Ramp portion Cum 50000 14000 9990 3500 2230 34190 3500 16000
Cut & cover)

Rock anchor (1st


Nos. 57 06 00 00 00 51 00 06
level) Once access
slope will
be
excavated
Rock anchor then only
waler bracket (1st Nos 59 07 00 00 00 52 00 07 balance
level) anchor will
be done
Rock anchor
Rmt 153 51 24 18 00 126.2 00 26.8
waler (1st level)

MUMBAI METRO LINE 3 CONTRACT UGC-07


MONDAY, 6 JANUARY 2020
Ramp Programme
Dec’19 Dec ’19 Last week Last week Cumulative Next week Plan for
Activity UOM Scope Remarks
Plan achieved plan achieved Achieved plan Jan’20

Rock anchor
Nos. 52 40 36 15 08 52 00 08 Completed
(2nd level)

Rock anchor
waler
Nos 53 53 43 04 00 43 04 02
bracket (2nd
level)
Rock anchor
waler (2nd Rmt 130 110 92 12 04 92 12 33
level)

Rock anchor
Nos. 27 10 07 10 07 07 06 19
(3rd level)

Rock anchor
waler
Nos 29 10 00 04 00 00 04 26
bracket (3rd
level)

MUMBAI METRO LINE 3 CONTRACT UGC-07


MONDAY, 6 JANUARY 2020
Ramp Programme
Dec’19 Dec ’19 Last week Last week Cumulative Next week Plan for
Activity UOM Scope Remarks
Plan achieved plan achieved Achieved plan Jan’20
Base slab (C
& C box Sqm 1875 00 00 00 00 00 00 172
tunnel)

MUMBAI METRO LINE 3 CONTRACT UGC-07


MONDAY, 6 JANUARY 2020
Ramp Programme (Temporary work)
Programme for Cut & Cover

Baseline Plan Actual/ Forecast Plan Current


Activity Name UOM Scope Delay
Planned Status
Start Finish Start Finish Duration
Duration
Hutment demolition Ls 1 30-Apr-19 07-May-19 7 30-Apr-19 07-May-19 7 0
Earthwork & levelling (if required) Ls 1 07-May-19 17-May-19 10 07-May-19 17-May-19 10 0
Retaining Structure
Secant Pile - South side (DL) Nos. 124 15-Apr-19 14-Jun-19 60 15-Apr-19 10-Aug-19 117 57
Capping beam (DL) Rmt 80 07-Jun-19 29-Jul-19 52 17-Aug-19 16-Oct-19 60 79
Nala Diversion (if required) Rmt 30 07-Jul-19 27-Jul-19 20 01-Oct-19 08-Oct-19 7 73
Excavation between Launching Shaft and C&C- Balance 15 m
Soil Excavation Cum 1500 26-Oct-19 02-Nov-19 7 26-Nov-19 17-Dec-19 21 45
Rock Excavation Cum 5700 05-Nov-19 20-Dec-19 45 21-Dec-19 07-Feb-20 48 49
Soil Excavation for remaining shaft (20 X 30 m)- Upto 2.5 m
Cum 1500 26-Oct-19 02-Nov-19 7 26-Nov-19 17-Dec-19 21 45
depth
Remove retaining support (6 diagonal strut at soldier pile and
Nos. 6 31-Oct-19 05-Nov-19 5 15-Dec-19 22-Dec-19 7 47
erect strut)
Rock excavation next 2.5 m Cum 1500 05-Nov-19 13-Nov-19 8 21-Dec-19 29-Dec-19 8 46

Remove retaining support (Destress rock anchor 2 layers) Ls 1 10-Nov-19 17-Nov-19 7 27-Dec-19 03-Jan-20 7 47

Rock excavation next 3 m Cum 1800 13-Nov-19 24-Nov-19 11 29-Dec-19 10-Jan-20 12 47

Remove balance rock anchors and all soldier piles Ls 1 21-Nov-19 03-Dec-19 12 07-Jan-20 14-Jan-20 7 42

Rock excavation next 4 m Cum 2400 03-Dec-19 20-Dec-19 17 14-Jan-20 07-Feb-20 24 49


Excavation at Cut & Cover
Excavation
Soil Excavation Cum 7100 07-Sep-19 12-Oct-19 36 29-Sep-19 12-Nov-19 44 30
Excavation
Rock Excavation Cum 9593 26-Sep-19 15-Dec-19 80 18-Oct-19 07-Feb-20 113 54
Rock bolt and shotcrete Ls 1 16-Jan-20 10-Feb-20
Rock anchoring at entire C&C Ramp
Rock anchor (1st level) Nos. 57 06-Oct-19 25-Oct-19 19 21-Oct-19 17-Dec-19 57 53
Fixing of waler Rmt 155 13-Oct-19 07-Nov-19 25 10-Nov-19 26-Dec-19 46 49
Rock anchor (2nd level) Nos. 52 21-Oct-19 09-Nov-19 26 19-Nov-19 27-Dec-19 38 48
Fixing of waler Rmt 132 28-Oct-19 18-Nov-19 21 26-Nov-19 05-Jan-20 40 48
Rock anchor (3rd level) Nos. 26 02-Nov-19 21-Nov-19 10 17-Dec-19 16-Jan-20 30 56
Fixing of waler Rmt 67 09-Nov-19 01-Dec-19 22 25-Dec-19 25-Jan-20 31 55

MUMBAI METRO LINE 3 CONTRACT UGC-07


MONDAY, 6 JANUARY 2020
Ramp Programme (Permanent work)
Programme for Cut & Cover

Baseline Plan Actual/ Forecast Plan Current


Activity Name UOM Scope Delay
Planned Status
Start Finish Start Finish Duration
Duration
Permanent Structural Works Launching Shaft
Base Slab Sqm 720 15-Dec-19 29-Jan-20 45 27-Dec-19 18-Mar-20 82 49
Upline side Sqm 360 27-Dec-19 21-Jan-20 25
Downline side Sqm 360 17-Feb-20 18-Mar-20 30
Sidewall (Upline side)- Box tunnel Sqm 495 03-Jan-20 31-Jan-20 28
Sidewall (Downline side)- Box tunnel Sqm 495 25-Feb-20 28-Mar-20 32
Side walls (with CP 26/27-03) Sqm 960 30-Dec-19 18-Feb-20 50 11-Jan-20 07-Apr-20 87 49
Roof Slab Sqm 720 29-Jan-20 28-Feb-20 40 13-Jan-20 09-Apr-20 87 41
Upline side Sqm 360 13-Jan-20 12-Feb-20 30
Downline side Sqm 360 03-Mar-20 09-Apr-20 37
Permanent Structural Works C&C area
Base Slab Sqm 688 15-Dec-19 29-Jan-20 45 04-Feb-20 25-Mar-20 50 56
Upline side Sqm 344 04-Feb-20 29-Feb-20 25
Downline side Sqm 344 24-Feb-20 25-Mar-20 30
Sidewall (Upline side)- Box tunnel Sqm 458 11-Feb-20 10-Mar-20 28
Sidewall (Downline side)- Box tunnel Sqm 458 05-Mar-20 06-Apr-20 32
Roof Slab Sqm 688 29-Jan-20 28-Feb-20 40 21-Feb-20 18-Apr-20 57 50
Upline side Sqm 344 21-Feb-20 22-Mar-20 30
Downline side Sqm 344 12-Mar-20 18-Apr-20 37

MUMBAI METRO LINE 3 CONTRACT UGC-07


MONDAY, 6 JANUARY 2020
Site Progress

MUMBAI METRO LINE 3 CONTRACT UGC-07


MONDAY, 6 JANUARY 2020
CP-13 progress and Programme

Heading

Benching

Waterproofing
completed PCC completed

Side and overt Waterproofing in progress

Completed invert part

MUMBAI METRO LINE 3 CONTRACT UGC-07


MONDAY, 6 JANUARY 2020
CP-13 progress and Programme
CP-13 (9.47 m) Planned
Cumulative
Actual/Expected dates as of 02-Jan-20
Scope Days
Completed
Sl. No. Description of work Unit Start Finish Days Start Finish

1 Erection of Ring beams (DL side) nos 3 5 20-Jul-19 24-Jul-19 Completed 5 20-Jul-19 24-Jul-19

2 Window core cutting LS 1 5 25-Jul-19 29-Jul-19 Completed 5 25-Jul-19 29-Jul-19

3 Backup gantry drag out nos 3 4 28-Aug-19 01-Sep-19 Completed 19 09-Sep-19 27-Sep-19

4 Erection of Ring beams (UL side) nos 3 5 05-Sep-19 09-Sep-19 11 08-Nov-19 18-Nov-19

Heading: 9.47 m
5 Excavation and Primary lining RM 9.47 51 30-Jul-19 19-Sep-19 131 05-Aug-19 13-Dec-19
Benching- 9.47 m

6 Steel 'Jamb frame' erection and PCC Nos 2 5 20-Sep-19 24-Sep-19 3 15-Dec-19 17-Dec-19

7 Water proofing - Invert Sq.M 2 25-Sep-19 26-Sep-19 3 20-Dec-19 27-Dec-19

8 Rebar fixing - Invert MT 2 3 27-Sep-19 29-Sep-19 3 27-Dec-19 29-Dec-19

9 Shuttering & concreting - Invert cum 2 30-Sep-19 01-Oct-19 2 29-Dec-19 30-Dec-20

10 Water proofing - Sides & overt Sq.M 3 02-Oct-19 04-Oct-19 3 02-Jan-20 04-Jan-20

11 Rebar fixing - Walls & crown MT 3 05-Oct-19 07-Oct-19 3 05-Jan-20 07-Jan-20

12 Shuttering & concreting - Overhead cum 5 08-Oct-19 12-Oct-19 5 07-Jan-20 -Jan-20

MUMBAI METRO LINE 3 CONTRACT UGC-07


MONDAY, 6 JANUARY 2020
CP-12 progress and Programme
Breakout done from
haeding

Completed excavation

MUMBAI METRO LINE 3 CONTRACT UGC-07


MONDAY, 6 JANUARY 2020
CP-12 progress and Programme
Actual/Expected dates as of 02-Jan-
CP-12 (9.00 Mtr) Planned Cumulative 20 Remarks
Completed
Sl. No. Description of work Unit Scope Days Start Finish Duration Start Finish
1 Erection of Steel Ring beams nos 3 12 01-Oct-19 13-Oct-19 3 12 01-Oct-19 13-Oct-19
2 Probing and ground treatment (if any) Ls 1 3 14-Oct-19 17-Oct-19 1 6 17-Oct-19 23-Oct-19
3 Window core cutting Nos 64 4 17-Oct-19 21-Oct-19 28 18 26-Oct-19 13-Nov-19

Heading- 9 m * 0.8 m/day either heading or


4 Excavation and Primary lining RM 9 35 21-Oct-19 25-Nov-19 70 29-Oct-19 07-Jan-20
Benching-5 m benching
5 Laying of DI pipe with trenching RM 3.91 6 25-Nov-19 01-Dec-19 5 07-Jan-20 12-Jan-20
6 Permanenet 'Jamb frame' erection Nos 4.76 3 30-Nov-19 03-Dec-19 2 11-Jan-20 13-Jan-20
7 PCC for collar invert Rm 2.00 1 14-Jan-20 15-Jan-20
8 Water proofing - Invert Rm 3.00 2 17-Jan-20 19-Jan-20
9 Rebar fixing for collar Ls 1.00 2 19-Jan-20 21-Jan-20
10 Shuttering and concreting Ls 1.00 4 21-Jan-20 25-Jan-20
11 Sump excavation Cum 71.65 15 05-Jan-20 20-Jan-20 15 27-Jan-20 11-Feb-20
12 PCC level course for Invert slab Cum 6.41 2 03-Dec-19 05-Dec-19 2 12-Feb-20 14-Feb-20
13 Water proofing - Sump base & walls Sq.M 2 20-Jan-20 22-Jan-20 2 14-Feb-20 16-Feb-20
14 Water proofing - Invert Sq.M 3 06-Dec-19 09-Dec-19 3 15-Feb-20 18-Feb-20
15 Rebar fixing - Sump base & walls MT 8 22-Jan-20 30-Jan-20 4 16-Feb-20 20-Feb-20
16 Rebar fixing, shuttering & concreting - Invert & sump MT 7 11-Dec-19 18-Dec-19 4 19-Feb-20 23-Feb-20
17 Water proofing - Sides & crown Sq.M 3 19-Dec-19 22-Dec-19 3 24-Feb-20 27-Feb-20
18 Rebar fixing - Walls & crown MT 7 22-Dec-19 29-Dec-19 6 27-Feb-20 04-Mar-20
19 Shuttering & concreting - Walls & crown Cum 7 29-Dec-19 05-Jan-20 5 04-Mar-20 09-Mar-20

MUMBAI METRO LINE 3 CONTRACT UGC-07


MONDAY, 6 JANUARY 2020
Cross Passage Progress Photos

CP 13

MUMBAI METRO LINE 3 CONTRACT UGC-07


MONDAY, 6 JANUARY 2020
Cross Passage Progress Photos

CP 12

MUMBAI METRO LINE 3 CONTRACT UGC-07


MONDAY, 6 JANUARY 2020
MUMBAI METRO LINE 3 CONTRACT UGC-07
MONDAY, 6 JANUARY 2020