Shotcrete
Waler
Excavation
(Ramp portion Cum 50000 14000 9990 3500 2230 34190 3500 16000
Cut & cover)
Rock anchor
Nos. 52 40 36 15 08 52 00 08 Completed
(2nd level)
Rock anchor
waler
Nos 53 53 43 04 00 43 04 02
bracket (2nd
level)
Rock anchor
waler (2nd Rmt 130 110 92 12 04 92 12 33
level)
Rock anchor
Nos. 27 10 07 10 07 07 06 19
(3rd level)
Rock anchor
waler
Nos 29 10 00 04 00 00 04 26
bracket (3rd
level)
Remove retaining support (Destress rock anchor 2 layers) Ls 1 10-Nov-19 17-Nov-19 7 27-Dec-19 03-Jan-20 7 47
Remove balance rock anchors and all soldier piles Ls 1 21-Nov-19 03-Dec-19 12 07-Jan-20 14-Jan-20 7 42
Heading
Benching
Waterproofing
completed PCC completed
1 Erection of Ring beams (DL side) nos 3 5 20-Jul-19 24-Jul-19 Completed 5 20-Jul-19 24-Jul-19
3 Backup gantry drag out nos 3 4 28-Aug-19 01-Sep-19 Completed 19 09-Sep-19 27-Sep-19
4 Erection of Ring beams (UL side) nos 3 5 05-Sep-19 09-Sep-19 11 08-Nov-19 18-Nov-19
Heading: 9.47 m
5 Excavation and Primary lining RM 9.47 51 30-Jul-19 19-Sep-19 131 05-Aug-19 13-Dec-19
Benching- 9.47 m
6 Steel 'Jamb frame' erection and PCC Nos 2 5 20-Sep-19 24-Sep-19 3 15-Dec-19 17-Dec-19
10 Water proofing - Sides & overt Sq.M 3 02-Oct-19 04-Oct-19 3 02-Jan-20 04-Jan-20
Completed excavation
CP 13
CP 12