Question 1:

Specify the suitable Contract type for each of the following construction project:
a. Sewer and water lines projects b. Highways c. Hospitals d. Bridges e. Residential
Housing
Question 2:

Question3:

A contractor submitted a bid that included reinforcement concrete work, which was 3500
LE/m3. The contractor indicated that the variable price material are steel reinforcement,
cement, sand, and gravel. Calculate the adjusted unit price of reinforced concrete based the
following data: Cement price (900 L.E/ton), is used by (7 Sacks/m3)

Steel Reinforcement price (13,000 L.E./ton), is used by (120kg/m3)

Sand price (120 L.E/ton), is used by (0,4m3/m3)-

Gravel price (240 L.E/ton), is used by (0,8m3/m3)

Labor and equipment are estimated by 650 L.E./m3 (Non-adjustable prices).

Material Description Basic rate (points) New Rate (points)

Cement 152 161

Steel Reinforcement 227 235

Sand 98 101

Gravel 75 78

(1) Dr. Alaa Eddin Abd El-Razek, Asst. Prof.


Question 4:

A cost plus incentive fee (CPIF) contract has the following parameters in shown figure, calculate the final price if the project
was completed for an actual cost of OMR 400,000

Question 5:

Question 6:

In Fixed price inventive fee (FPIF) contract, the target cost is estimated at $100,000 and the
target fee is $15,000. The project is over, because the contractor’s cost came in higher than the
estimated costs, the owner shares in the added cost; 60% to the owner and 40% to the
contractor. The ceiling price is $125.000. Calculate the point of total assumption.

(2) Dr. Alaa Eddin Abd El-Razek , Asst. Prof.


Question 7:

(2) Dr. Alaa Eddin Abd El-Razek , Asst. Prof.