You are on page 1of 3

Existing Connection Below 100 AMP Reference Code : 1778608

 Alter Existing Connection + Embedded Generation

LOCATION

Retailer
Energy Australia
NMI
41027455962
Land Title Type
Torrens
Street Number/RMB
33
Location Address
Bowman Street, Drummoyne, 2047
Land Zoning
Urban

APPLICANT

Applicant Type
Other On Behalf Of A Retail Customer Or Real Estate Developer
Full Name
Mr Partha Chowdhury
Email Address
connections@powerideas.com.au
ABN/ACN
23625803018
Company Name
Power Ideas
Unit/Shop Number
L2
Street Number/RMB
6
Applicant Address
Parkview Drive Sydney Olympic Park 2127
Phone Number
1300769371

CUSTOMER

Customer Type
Retail Customer
Full Name
Mr Robert Sealey
Email Address
rjbow@tpg.com.au
Phone Number
0297198427
Other Number
0410329242
LOAD DETAILS

INSTALLATION CHANGE
Connect A New Embedded Generation / Storage System
Yes

EMBEDDED GENERATION

How Do You Intend To Operate Your Embedded Generation With The Ausgrid Network?
Parallel
Embedded Generation Is Connected Via
Inverter

INVERTERS
NEW INVERTER
Energy Source Generation Kw Inverter Type
Pv Only 6.6 Grid Connect
Inverter Phase Phase A
Single 5

Inverters Generation Inverter kW Storage Other


kW (Phase A+ Phase B + Phase C) = Total kW Power kW

New 6.6 A: 5 + B: + C: = 5

Total 6.6 A: 5 + B: 0 + C: 0 = 5 0 0

EMBEDDED GENERATION SUMMARY


Premises Storage Other Generation Inverter kW Generation Generation
kW Power kW kW (A+ B + C) = Total kW (non- inverter) Total kW

0 0 6.6 A: 5 + B: 0 + C: 0 = 5 0 5

Total 0 0 6.6 A : 5 + B: 0 + C: 0 = 5 0 5

My Installation Is Part Of A Multi-Tenanted Premises Or Embedded Network That Has Existing Embedded Generation Installed.
No
Embedded Generation At Location
5

EMBEDDED GENERATION DECLARATION

I Have Made Efforts To Identify Any Other Premises With Embedded Generation That Share The Network Connection That This Application
Pertains To, And Have Provided Those Details (Where Relevant) Within This Application.
Yes
The Installer And Equipment Have Current Approval From The Australian Clean Energy Council (Cec).
Yes
Proposed Inverter(S) Complies With The Voltage Rise Requirements Of Nsw Service And Installation Rules
Yes
Proposed Inverter(S) Have Volt-Var And Volt-Watt Response Modes Enabled.
Yes
In Preparing This Application I Have Considered The Requirements Of Ns194 Connection Of Embedded Generators, And The Requirements
Of The Aemo Der Register Information Guidelines To Provide The Installed Generation Equipment Details To The Aemo Der Register Within
20 Business Days Of Commissioning
Yes
In Preparing This Application I Have Considered The Requirements Of The Service And Installation Rules Of Nsw
Yes
In Preparing This Application I Have Considered The Requirements Of The As/Nzs3000:2018 The Wiring Rules.
Yes
In Preparing This Application I Have Considered The Requirements Of The As/Nzs4777 Grid Connection Of Energy Systems Via Inverters
Yes

EXPEDITED CONNECTION

Do you want to expedite your connection offer for all premises?


Yes No

You can download the Basic Connection Services Offer Micro Embedded Generation Connections for your records here.

DECLARATION

Applicant Name
Mr Partha Chowdhury
Application Date
14-Mar-2023
Price Description Price Including GST
Micro Embedded Generation 1 x 21.43 AUD $21.43
Total Price AUD $21.43
Terms and Conditions:

In submitting this application you are engaging Ausgrid to provide you with a connection offer. Once submitted the fee
charged is consumed. Ausgrid will aim to provide you with a written response within 10 business days. If additional work
and/or fees are required, we will contact you to advise prior to providing the response.

Where this application requests an expedited connection, I declare that I have read and understood the terms and
conditions of the connection offer and agree that if the connection is expedited that a contract based on that offer will be
formed with Ausgrid on the date that Ausgrid receives the application. Where this application is being made on behalf of a
retail customer or real estate developer, I declare that I have obtained the authority of that person to make this
application of their behalf, including where applicable, making a request for expedition of the connection application.

ADVICE TO CONNECTING CUSTOMERS: additional connection-related service charges may be incurred after completion
of this connection offer, these can include - Site Establishment Fee (new connection), Site Alteration Fee (existing
connection) or NMI Extinction Fee (permanent disconnection). Any such applicable fee/s will be levied by your Retailer
on your electricity bill.

* I acknowledge the terms & conditions. 